Procedimiento Reparacion Tubo-placatubular
-
Upload
mau-ate-nas -
Category
Documents
-
view
224 -
download
0
Transcript of Procedimiento Reparacion Tubo-placatubular
-
7/25/2019 Procedimiento Reparacion Tubo-placatubular
1/14
-
7/25/2019 Procedimiento Reparacion Tubo-placatubular
2/14
ALSTOM Power Energy Recovery GmbH
34123 Kassel, Ellenbacher Str. 10
Germany
Repair Procedure
Dokument-Nr:Document-No.:
1 02 123-81-14-D4
Seite vonPage of2 14
Repair of tubes to tubesheet weld at inlet side and outlet side ofFire Tube Boiler
General
At the tube to tubesheet welds on the gas inlet and outlet side of the fire tube boiler
leakages occurred in the weld.
Grinding of surface and PT have been performed. Most likely location of pores is at
the welding end craters.
As conclusion it was decided that all welds shall be removed and rewelded acc. to this
procedure.
Repairing tools and repairing material are described in Appendix 3.
The work will be done acc. to NBIC, which will be used due to the fact that the boiler
was already in operation.
Preconditions
Tube sheet and tubes should be clean and dry. The tubes should be dried and cleaned
with compressed air.
The following tasks should be confirmed before the repair:
AI approval of repair procedure is mandatory
Tube sheet is clean and dry
All electrical equipment of boiler has connected with safety protectors.
Axial-flow fans have been installed on the inlet and outlet of the boiler and the
boiler is ventilated.
Kick-off meeting to the participants of each procedure. Work may proceed after
release from Outotec.
The required welders must have the satisfied TIG qualifications and the welding job
should be strictly done according to WPS A148Re offered by ALSTOM.
-
7/25/2019 Procedimiento Reparacion Tubo-placatubular
3/14
ALSTOM Power Energy Recovery GmbH
34123 Kassel, Ellenbacher Str. 10
Germany
Repair Procedure
Dokument-Nr:Document-No.:
1 02 123-81-14-D4
Seite vonPage of3 14
1. Preparation of the tube sheet for repairTwo different repair methods are applied for the repair of tube to tubesheet welds.
Para. 1 a. describes the procedure for a local area which was already repaired
whereas para 1 b. describes the repair for all other tube to tube sheet welds.
1. a. repair in the 2 areas which showed leakage during hydrotest on
9.9.11
- Both of the leaking tubes shall be cut for testing purposes. Detailed cutting
procedure still has to be agreed on. For repair please refer to 1 02 123-81-13-
D4-01.
Sketch 1: repaired area acc to procedure 1021213-81-13-D4
-
7/25/2019 Procedimiento Reparacion Tubo-placatubular
4/14
ALSTOM Power Energy Recovery GmbH
34123 Kassel, Ellenbacher Str. 10
Germany
Repair Procedure
Dokument-Nr:Document-No.:
1 02 123-81-14-D4
Seite vonPage of4 14
1. b. check and repair of all other welding seams
- Repair of tube sheet welds will be performed in clusters of 9 tubes each.
- Distance between clusters are maximized. The minimum distance between 2
clusters is 5 x tube pitch (see sketch 2 and 3)
- As maximum 4 clusters at one time will be ground and rewelded
- Remove inner layer of refractory at a length of 500 mm if needed for working
space of milling machine- Cut and remove Pos. no. 51 on drawing 102123-33-11-Z0-01
- Grind back the tube projection to 4,5 mm for tubes 60,3 x4,5 mm
- Grind back the tube projection to 6 mm for tubes 101,6 x 8 mm mm
- Grind back the total weld by using milling machine. Cutting tool should be used
to prepare the original J-groove acc. drawing no. 05685 (Fire tube boiler
details 1).
- After removing of welds 100% VT and 100% PT inspection should be done at the
machined area
-Welding of tube to tube sheet acc. drawing no 05685 and WPS A148Re.
-
7/25/2019 Procedimiento Reparacion Tubo-placatubular
5/14
ALSTOM Power Energy Recovery GmbH
34123 Kassel, Ellenbacher Str. 10
Germany
Repair Procedure
Dokument-Nr:Document-No.:
1 02 123-81-14-D4
Seite vonPage of5 14
Sketch 2: Repair - Clusters
-
7/25/2019 Procedimiento Reparacion Tubo-placatubular
6/14
ALSTOM Power Energy Recovery GmbH
34123 Kassel, Ellenbacher Str. 10
Germany
Repair Procedure
Dokument-Nr:Document-No.:
1 02 123-81-14-D4
Seite vonPage of6 14
Sketch 3: Repair - Clusters
-
7/25/2019 Procedimiento Reparacion Tubo-placatubular
7/14
ALSTOM Power Energy Recovery GmbH
34123 Kassel, Ellenbacher Str. 10
Germany
Repair Procedure
Dokument-Nr:Document-No.:
1 02 123-81-14-D4
Seite vonPage of7 14
2. Welding and Testing
- Preheating of a min. surface of 250 mm around the repair place at a
temperature of min. 150 C 220 C
- Root pass welding acc. to WPS A148Re
- Testing: 10% PT, 100% VT of root pass (only for the first 200 welds)
- Build up welding acc. to WPS A148Re
- Maximum interpass temperature is 232 C
- Testing 100% PT, 100% VT
- Referring NBIC, part 3, sect. 2 para. 2.5.3 and 2.5.3.1 the welding method
without PWHT will be applied
- Hydrotest: After completion of all welds
NOTE: after root pass testing of the first 200 welds it needs to be agreed if the
remaining welds can be welded completely without root pass testing.
3. (deleted, see 2)
4. Reinstallation of Pos. 51 and refractory
Reweld pos. no. 51 acc. To WPS A356
-
7/25/2019 Procedimiento Reparacion Tubo-placatubular
8/14
ALSTOM Power Energy Recovery GmbH
34123 Kassel, Ellenbacher Str. 10
Germany
Repair Procedure
Dokument-Nr:Document-No.:
1 02 123-81-14-D4
Seite vonPage of8 14
Appendix 1 WPS and PQR for Tube to Tubesheet Welding
-
7/25/2019 Procedimiento Reparacion Tubo-placatubular
9/14
ALSTOM Power Energy Recovery GmbH
34123 Kassel, Ellenbacher Str. 10
Germany
Repair Procedure
Dokument-Nr:Document-No.:
1 02 123-81-14-D4
Seite vonPage of9 14
-
7/25/2019 Procedimiento Reparacion Tubo-placatubular
10/14
ALSTOM Power Energy Recovery GmbH
34123 Kassel, Ellenbacher Str. 10
Germany
Repair Procedure
Dokument-Nr:Document-No.:
1 02 123-81-14-D4
Seite vonPage of10 14
-
7/25/2019 Procedimiento Reparacion Tubo-placatubular
11/14
ALSTOM Power Energy Recovery GmbH
34123 Kassel, Ellenbacher Str. 10
Germany
Repair Procedure
Dokument-Nr:Document-No.:
1 02 123-81-14-D4
Seite vonPage of11 14
Appendix 2: WPS and PQR for welding of Pos. No. 51
-
7/25/2019 Procedimiento Reparacion Tubo-placatubular
12/14
ALSTOM Power Energy Recovery GmbH
34123 Kassel, Ellenbacher Str. 10
Germany
Repair Procedure
Dokument-Nr:Document-No.:
1 02 123-81-14-D4
Seite vonPage of12 14
-
7/25/2019 Procedimiento Reparacion Tubo-placatubular
13/14
ALSTOM Power Energy Recovery GmbH
34123 Kassel, Ellenbacher Str. 10
Germany
Repair Procedure
Dokument-Nr:Document-No.:
1 02 123-81-14-D4
Seite vonPage of13 14
-
7/25/2019 Procedimiento Reparacion Tubo-placatubular
14/14
ALSTOM Power Energy Recovery GmbH
34123 Kassel, Ellenbacher Str. 10
Germany
Repair Procedure
Dokument-Nr:Document-No.:
1 02 123-81-14-D4
Seite vonPage of14 14
Appendix 3: Required Tools and Materials
Material
- TIG wire DMO IG 2,4 mm, 200 Kg- CM2- IG 2,4 mm, 4 Kg
Tools
-
1 x rolling machine for inner
51,3 mm (not planned, just as precaution)
- 1 x bevelling machine for inner 51,3 mm (not planned, just as precaution)
- 1 x drift punch outer 60 mm, inner 51,3 mm, length400 mm (not planned,
just as precaution)
- 2 x milling machine (rotary speed ~ 20.000 rpm) with 8 and 6 mm adaptor
- various milling cutter tree shape 8 mm
- 1 x hammer ~ 2.000 gr
- 2 x TIG welding machine with tungsten electrodes 2,4 mm
- 2 x argon 99,8%
- various nos. of cleaner
- 2 x grinding machine for grinding disc 115 mm
- various grinding discs 115 mm
- various cutting discs 115 mm
- various serrated grinder grain size 40
- various grinding paper grain size medium