  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    SAMPLE PROJECT - ROADS & INFRASTRUCTURE 312 01-Feb-14 31-Jan-15 0%GENERAL 312 01-Feb-14 31-Jan-15 0%

    Project Start 0 01-Feb-14 0%Mobilisation 30 01-Feb-14 06-Mar-14 0%Project Finish 0 31-Jan-15 0%

    AUTHORITY APPROVALS (PRELIMINARY) 70 06-Feb-14 28-Apr-14 0%Approval from Muncipal Authorities, (To be arranged by Client) 70 06-Feb-14 28-Apr-14 0%Approval from SCECO, (To be arranged by Client) 70 06-Feb-14 28-Apr-14 0%Approval from Water supply Authorities (To be arranged by Client) 70 06-Feb-14 28-Apr-14 0%Approval from Civil Defence Authorities, (To be arranged by Client) 70 06-Feb-14 28-Apr-14 0%Approval from District Cooling system (To be arranged by Client) 70 06-Feb-14 28-Apr-14 0%Approval of Environment Clearence (To be arranged by Client) 70 06-Feb-14 28-Apr-14 0%Approval from STC Authorities, (To be arranged by Client) 70 06-Feb-14 28-Apr-14 0%

    ENGINEERING & PROCUREMENT 210 01-Feb-14 02-Oct-14 0%ENGINEERING 132 01-Feb-14 03-Jul-14 0%

    DELIVERABLES 75 01-Feb-14 28-Apr-14 0%Receipt of All IFC Drawings from Client 10 01-Feb-14 11-Feb-14 0%100% Design & Spec from Client 5 01-Feb-14 05-Feb-14 0%Subcontractors Finalisation & Approval 75 01-Feb-14 28-Apr-14 0%Submission/Approval of Health & Safety Plans 10 06-Feb-14 17-Feb-14 0%Submission/Approval of QA/QC plan 20 06-Feb-14 01-Mar-14 0%Submission/Approval of Methodology 10 06-Feb-14 17-Feb-14 0%Submission/Approval of Construction Programme 10 06-Feb-14 17-Feb-14 0%Submission of Insurance Certificates 15 12-Feb-14 01-Mar-14 0%

    SHOP DWG PREPARATION & SUBMISSION 108 12-Feb-14 17-Jun-14 0%ROADS 42 12-Feb-14 01-Apr-14 0%

    Road layout and Profile 18 12-Feb-14 04-Mar-14 0%Road C/S 18 20-Feb-14 12-Mar-14 0%Alignment control plan 18 26-Feb-14 18-Mar-14 0%Spot Lvl along with Centerlines 18 04-Mar-14 24-Mar-14 0%Signage and Road Marking 18 12-Mar-14 01-Apr-14 0%

    INFRASTRUCTURE 108 12-Feb-14 17-Jun-14 0%Sewer Network & Lifting Stn 28 12-Feb-14 16-Mar-14 0%Storm Water Network 28 24-Feb-14 27-Mar-14 0%Fire Network & Pumping Stn 28 08-Mar-14 08-Apr-14 0%District Cooling Network 28 19-Mar-14 20-Apr-14 0%Water Network 28 31-Mar-14 01-May-14 0%Spare Ducts & Electricity 28 12-Apr-14 13-May-14 0%Irrigation Network & Pumping Stn 28 12-Apr-14 13-May-14 0%Telecommunication Network 28 23-Apr-14 25-May-14 0%Gas sleeve Network 28 05-May-14 05-Jun-14 0%Street Lighting 28 17-May-14 17-Jun-14 0%

    SHOP DWG REVIEW & APPROVAL BY CONSULTANT 104 05-Mar-14 03-Jul-14 0%ROADS 38 05-Mar-14 17-Apr-14 0%

    Road layout and Profile 14 05-Mar-14 20-Mar-14 0%Road C/S 14 13-Mar-14 29-Mar-14 0%Alignment control plan 14 19-Mar-14 03-Apr-14 0%Spot Lvl along with Centerlines 14 25-Mar-14 09-Apr-14 0%Signage and Road Marking 14 02-Apr-14 17-Apr-14 0%

    INFRASTRUCTURE 94 17-Mar-14 03-Jul-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    06-Mar-14

    28-Apr-1428-Apr-1428-Apr-1428-Apr-1428-Apr-1428-Apr-1428-Apr-14

    11-Feb-1405-Feb-14

    28-Apr-1417-Feb-14

    01-Mar-1417-Feb-1417-Feb-14

    01-Mar-14

    04-Mar-1412-Mar-14

    18-Mar-1424-Mar-14

    01-Apr-14

    16-Mar-1427-Mar-14

    08-Apr-1420-Apr-14

    01-May-1413-May-1413-May-14

    25-May-1405-Jun-14

    17-Jun-14

    20-Mar-1429-Mar-14

    03-Apr-1409-Apr-14

    17-Apr-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 1 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Sewer Network & Lifting Stn 14 17-Mar-14 01-Apr-14 0%Storm Water Network 14 29-Mar-14 13-Apr-14 0%Fire Network & Pumping Stn 14 09-Apr-14 24-Apr-14 0%District Cooling Network 14 21-Apr-14 06-May-14 0%Water Network 14 03-May-14 18-May-14 0%Spare Ducts & Electricity 14 14-May-14 29-May-14 0%Irrigation Network & Pumping Stn 14 14-May-14 29-May-14 0%Telecommunication Network 14 26-May-14 10-Jun-14 0%Gas sleeve Network 14 07-Jun-14 22-Jun-14 0%Street Lighting 14 18-Jun-14 03-Jul-14 0%

    PROCUREMENT 185 02-Mar-14 02-Oct-14 0%MATERIAL SUBMITTAL & APPROVAL 90 02-Mar-14 14-Jun-14 0%

    CIVIL & MEP 90 02-Mar-14 14-Jun-14 0%Civil Material Submittals & Approvals 75 02-Mar-14 27-May-14 0%MEP Material Submittals & Approvals 90 02-Mar-14 14-Jun-14 0%

    MATERIAL ORDER & DELIVERY 180 08-Mar-14 02-Oct-14 0%MEP SERVICES 180 08-Mar-14 02-Oct-14 0%

    SEWARAGE 105 08-Mar-14 07-Jul-14 0%VC Pipes 28 08-Mar-14 08-Apr-14 0%Ductile Castiron Pipes 40 19-Mar-14 04-May-14 0%Sewerage Pumps 90 25-Mar-14 07-Jul-14 0%

    STORM WATER 35 13-Mar-14 22-Apr-14 0%RC Pipes and Fittings 35 13-Mar-14 22-Apr-14 0%

    FIRE WATER 100 09-Jun-14 02-Oct-14 0%HDPE Pipes Fittings & Valves 30 09-Jun-14 13-Jul-14 0%Fire Hydrant 45 15-Jun-14 05-Aug-14 0%Fire Pumps 90 21-Jun-14 02-Oct-14 0%

    PORTABLE WATER 50 11-May-14 07-Jul-14 0%HDPE Pipes and Fittings 30 11-May-14 14-Jun-14 0%Ductile Iron Pipes and Fittings 45 17-May-14 07-Jul-14 0%Valves 14 22-May-14 07-Jun-14 0%

    IRRIGATION WATER 95 28-May-14 15-Sep-14 0%UPVC Pipes Fittings & Valves 14 28-May-14 12-Jun-14 0%Irrigation Pumps 90 03-Jun-14 15-Sep-14 0%

    ELECTRICAL 28 31-Mar-14 01-May-14 0%UPVC Electrical Ducts 28 31-Mar-14 01-May-14 0%Electrical Cables 21 06-Apr-14 29-Apr-14 0%

    TELECOM 28 05-May-14 05-Jun-14 0%UPVC Electrical Ducts 28 05-May-14 05-Jun-14 0%

    GAS LINES 28 08-Jul-14 09-Aug-14 0%UPVC Ducts 28 08-Jul-14 09-Aug-14 0%

    STREET LIGHTING 70 12-Apr-14 01-Jul-14 0%UPVC Electrical Ducts 28 12-Apr-14 13-May-14 0%Street light poles & Luminaries 60 17-Apr-14 25-Jun-14 0%Feeder Pillar 60 23-Apr-14 01-Jul-14 0%Electrical Cables 28 29-Apr-14 31-May-14 0%

    SPARE DUCTS 18 26-Jun-14 16-Jul-14 0%UPVC Ducts 18 26-Jun-14 16-Jul-14 0%

    CONSTRUCTION 307 06-Feb-14 31-Jan-15 0%AREA-G 199 06-Feb-14 27-Sep-14 0%

    TRIAL HOLES & WORK PERMITS 35 06-Feb-14 18-Mar-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    01-Apr-1413-Apr-14

    24-Apr-1406-May-14

    18-May-1429-May-1429-May-14

    10-Jun-1422-Jun-14

    03-Jul-14

    27-May-1414-Jun-14

    08-Apr-1404-May-14

    07-Jul-14

    22-Apr-14

    13-Jul-1405-Aug-14

    02-Oct-14

    14-Jun-1407-Jul-14

    07-Jun-14

    12-Jun-1415-Sep-14

    01-May-1429-Apr-14

    05-Jun-14

    09-Aug-14

    13-May-1425-Jun-14

    01-Jul-1431-May-14

    16-Jul-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 2 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Survey & Setting out the Layout 30 06-Feb-14 12-Mar-14 0%Trail pits for the existing services 10 18-Feb-14 01-Mar-14 0%Submission and approval of trialhole data to start protection 15 24-Feb-14 12-Mar-14 0%Protection / Diversion of Existing services (variation) 15 02-Mar-14 18-Mar-14 0%

    PHASE 1 - G18 - G02 199 06-Feb-14 27-Sep-14 0%ROAD WORKS 199 06-Feb-14 27-Sep-14 0%

    Surface rough Grading 10 06-Feb-14 17-Feb-14 0%INITIAL STAGE 58 05-Mar-14 11-May-14 0%

    Setting out for Road works 10 05-Mar-14 16-Mar-14 0%1st Stage Excavation upto Formation level 15 17-Apr-14 04-May-14 0%Stocking/Disposal/Filling in embankments of Lagoon 16 23-Apr-14 11-May-14 0%

    FINAL STAGE 38 13-Aug-14 27-Sep-14 0%Sub base 18 13-Aug-14 03-Sep-14 0%Aggregate base course 12 19-Aug-14 02-Sep-14 0%Kerbs 10 25-Aug-14 06-Sep-14 0%Asphalt Base course 13 31-Aug-14 15-Sep-14 0%Wearing course 10 06-Sep-14 17-Sep-14 0%Road marking 7 15-Sep-14 23-Sep-14 0%Road furniture 8 17-Sep-14 27-Sep-14 0%

    MEP SERVICES 169 06-Feb-14 23-Aug-14 0%Surface rough Grading 10 06-Feb-14 17-Feb-14 0%SEWERAGE WORKS 54 29-Apr-14 30-Jun-14 0%

    Setting out for MEP network 10 29-Apr-14 10-May-14 0%Establishing Temp Dewatering System 10 29-Apr-14 10-May-14 0%Excavation 20 29-Apr-14 21-May-14 0%Bedding 20 05-May-14 27-May-14 0%Pipe Laying 16 22-May-14 09-Jun-14 0%Construction of Manholes 16 22-May-14 09-Jun-14 0%Inspection & Approval to Backfill 14 09-Jun-14 24-Jun-14 0%Backfilling & Removal of Dewatering 14 09-Jun-14 24-Jun-14 0%Precommissioning 10 19-Jun-14 30-Jun-14 0%

    STORM WATER WORKS 78 05-May-14 04-Aug-14 0%Setting out for MEP network 8 05-May-14 13-May-14 0%Establishing temporary dewatering system 10 19-May-14 31-May-14 0%Excavation 20 25-May-14 17-Jun-14 0%Bedding 20 31-May-14 23-Jun-14 0%Piple laying 20 17-Jun-14 10-Jul-14 0%Construction of chambers 20 17-Jun-14 10-Jul-14 0%Construction of thurst blocks 15 23-Jun-14 10-Jul-14 0%Inspection and approval to backfill 15 05-Jul-14 22-Jul-14 0%Backfilling and removal of Dewatering 17 09-Jul-14 29-Jul-14 0%Precommissioning 10 23-Jul-14 04-Aug-14 0%

    FIRE WATER WORKS 73 11-May-14 04-Aug-14 0%Setting out for MEP network 8 11-May-14 19-May-14 0%Establishing temporary dewatering system 10 19-May-14 31-May-14 0%Excavation 17 05-Jun-14 25-Jun-14 0%Bedding 17 11-Jun-14 01-Jul-14 0%Piple laying 17 17-Jun-14 07-Jul-14 0%Construction of chambers 20 17-Jun-14 10-Jul-14 0%Construction of thurst blocks 15 23-Jun-14 10-Jul-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    12-Mar-1401-Mar-14

    12-Mar-1418-Mar-14

    17-Feb-14

    16-Mar-1404-May-14

    11-May-14

    03-Sep-1402-Sep-14

    06-Sep-1415-Sep-1417-Sep-14

    23-Sep-1427-Sep-14

    17-Feb-14

    10-May-1410-May-14

    21-May-1427-May-14

    09-Jun-1409-Jun-14

    24-Jun-1424-Jun-14

    30-Jun-14

    13-May-1431-May-14

    17-Jun-1423-Jun-14

    10-Jul-1410-Jul-1410-Jul-14

    22-Jul-1429-Jul-14

    04-Aug-14

    19-May-1431-May-14

    25-Jun-1401-Jul-14

    07-Jul-1410-Jul-1410-Jul-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 3 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Inspection and approval to backfill 15 05-Jul-14 22-Jul-14 0%Backfilling and removal of Dewatering 17 09-Jul-14 29-Jul-14 0%Precommissioning 10 23-Jul-14 04-Aug-14 0%

    DISTRICT COOLING WATER WORKS (SCOPE NOT DEFINED) 56 11-May-14 15-Jul-14 0%Setting out for MEP network 10 11-May-14 21-May-14 0%Establishing temporary dewatering system 10 19-May-14 31-May-14 0%Excavation in R/C 15 05-Jun-14 23-Jun-14 0%Bedding in R/C 15 11-Jun-14 29-Jun-14 0%Piple laying in Road crossings R/C 13 17-Jun-14 02-Jul-14 0%Inspection and approval to backfill 13 23-Jun-14 08-Jul-14 0%Backfilling and removal of Dewatering 15 28-Jun-14 15-Jul-14 0%

    POTABLE WATER WORKS 84 17-May-14 23-Aug-14 0%Setting out for MEP network 8 17-May-14 25-May-14 0%Establishing temporary dewatering system 10 31-May-14 11-Jun-14 0%Excavation 15 11-Jun-14 29-Jun-14 0%Bedding 15 17-Jun-14 05-Jul-14 0%Piple laying 18 23-Jun-14 14-Jul-14 0%Construction of chambers 20 23-Jun-14 16-Jul-14 0%Construction of thurst blocks 15 15-Jul-14 02-Aug-14 0%Inspection and approval to backfill 15 21-Jul-14 07-Aug-14 0%Backfilling and removal of Dewatering 18 27-Jul-14 17-Aug-14 0%Precommissioning 10 11-Aug-14 23-Aug-14 0%

    IRRIGATION WATER WORKS 66 22-May-14 06-Aug-14 0%Setting out for MEP network 8 22-May-14 31-May-14 0%Establishing temporary dewatering system 10 31-May-14 11-Jun-14 0%Excavation 12 17-Jun-14 01-Jul-14 0%Bedding 12 23-Jun-14 07-Jul-14 0%Piple laying 15 29-Jun-14 16-Jul-14 0%Construction of chambers 13 29-Jun-14 14-Jul-14 0%Construction of thurst blocks 10 07-Jul-14 19-Jul-14 0%Inspection and approval to backfill 13 16-Jul-14 31-Jul-14 0%Backfilling and removal of Dewatering 13 16-Jul-14 31-Jul-14 0%Precommissioning 10 26-Jul-14 06-Aug-14 0%

    ELECTRIAL 67 01-Jun-14 18-Aug-14 0%Setting out 10 01-Jun-14 11-Jun-14 0%Excavation 10 17-Jul-14 29-Jul-14 0%Sand Bedding 15 23-Jul-14 10-Aug-14 0%Cable laying 17 29-Jul-14 18-Aug-14 0%Inspection 10 29-Jul-14 10-Aug-14 0%Backfilling 10 04-Aug-14 16-Aug-14 0%

    TELECOM 63 07-Jun-14 19-Aug-14 0%Setting out 10 07-Jun-14 17-Jun-14 0%Excavation 10 17-Jul-14 29-Jul-14 0%Bedding 15 23-Jul-14 10-Aug-14 0%Ducts and Chambers 18 29-Jul-14 19-Aug-14 0%Inspection 10 29-Jul-14 10-Aug-14 0%Backfilling 10 04-Aug-14 16-Aug-14 0%

    GAS LINES 54 18-Jun-14 20-Aug-14 0%Setting out 10 18-Jun-14 29-Jun-14 0%Excavation 10 23-Jul-14 04-Aug-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    22-Jul-1429-Jul-14

    04-Aug-14

    21-May-1431-May-14

    23-Jun-1429-Jun-14

    02-Jul-1408-Jul-14

    15-Jul-14

    25-May-1411-Jun-14

    29-Jun-1405-Jul-14

    14-Jul-1416-Jul-14

    02-Aug-1407-Aug-14

    17-Aug-1423-Aug-14

    31-May-1411-Jun-14

    01-Jul-1407-Jul-14

    16-Jul-1414-Jul-14

    19-Jul-1431-Jul-1431-Jul-14

    06-Aug-14

    11-Jun-1429-Jul-14

    10-Aug-1418-Aug-14

    10-Aug-1416-Aug-14

    17-Jun-1429-Jul-14

    10-Aug-1419-Aug-14

    10-Aug-1416-Aug-14

    29-Jun-1404-Aug-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 4 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Bedding 15 29-Jul-14 16-Aug-14 0%Ducts/Gas lines and Chambers 13 04-Aug-14 19-Aug-14 0%Inspection 10 06-Aug-14 18-Aug-14 0%Backfilling 10 09-Aug-14 20-Aug-14 0%

    STREET LIGHTING 52 18-Jun-14 18-Aug-14 0%Setting out 10 18-Jun-14 29-Jun-14 0%Excavation 10 23-Jul-14 04-Aug-14 0%Sand Bedding 10 29-Jul-14 10-Aug-14 0%Cable laying 15 29-Jul-14 16-Aug-14 0%Foundation for street lighting 10 29-Jul-14 10-Aug-14 0%Inspection 10 04-Aug-14 16-Aug-14 0%Backfilling 10 05-Aug-14 17-Aug-14 0%Erection of high masts 8 06-Aug-14 16-Aug-14 0%Testing and commisioning 10 06-Aug-14 18-Aug-14 0%

    SPARE DUCTS 51 17-May-14 15-Jul-14 0%Setting out for MEP network 10 17-May-14 27-May-14 0%Establishing temporary dewatering system 10 19-May-14 31-May-14 0%Excavation in R/C 15 05-Jun-14 23-Jun-14 0%Bedding in R/C 15 11-Jun-14 29-Jun-14 0%Piple laying in Road crossings R/C 13 17-Jun-14 02-Jul-14 0%Inspection and approval to backfill 13 23-Jun-14 08-Jul-14 0%Backfilling and removal of Dewatering 15 28-Jun-14 15-Jul-14 0%

    PHASE 2 - G22 to 21, BSC1 G 48 to GSC1 G 51,G36 to 37 & G32 135 12-Feb-14 20-Jul-14 0%ROAD WORKS 135 12-Feb-14 20-Jul-14 0%

    Surface rough Grading 10 12-Feb-14 23-Feb-14 0%INITIAL STAGE 31 13-Feb-14 20-Mar-14 0%

    Setting out for Road works 10 13-Feb-14 24-Feb-14 0%1st Stage Excavation upto Formation level 15 25-Feb-14 13-Mar-14 0%Stocking/Disposal/Filling in embankments of Lagoon 16 03-Mar-14 20-Mar-14 0%

    FINAL STAGE 38 05-Jun-14 20-Jul-14 0%Sub base 18 05-Jun-14 26-Jun-14 0%Aggregate base course 12 11-Jun-14 25-Jun-14 0%Kerbs 10 17-Jun-14 29-Jun-14 0%Asphalt Base course 13 23-Jun-14 08-Jul-14 0%Wearing course 10 29-Jun-14 10-Jul-14 0%Road marking 7 08-Jul-14 16-Jul-14 0%Road furniture 8 10-Jul-14 20-Jul-14 0%

    MEP SERVICES 105 12-Feb-14 15-Jun-14 0%Surface rough Grading 10 12-Feb-14 23-Feb-14 0%SEWERAGE WORKS 64 19-Feb-14 04-May-14 0%

    Setting out for MEP network 10 19-Feb-14 02-Mar-14 0%Establishing Temp Dewatering System 10 19-Feb-14 02-Mar-14 0%Excavation 20 03-Mar-14 25-Mar-14 0%Bedding 20 09-Mar-14 31-Mar-14 0%Pipe Laying 16 26-Mar-14 13-Apr-14 0%Construction of Manholes 16 26-Mar-14 13-Apr-14 0%Inspection & Approval to Backfill 14 13-Apr-14 28-Apr-14 0%Backfilling & Removal of Dewatering 14 13-Apr-14 28-Apr-14 0%Precommissioning 10 23-Apr-14 04-May-14 0%

    STORM WATER WORKS 78 25-Feb-14 27-May-14 0%Setting out for MEP network 8 25-Feb-14 05-Mar-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    16-Aug-1419-Aug-1418-Aug-1420-Aug-14

    29-Jun-1404-Aug-14

    10-Aug-1416-Aug-14

    10-Aug-1416-Aug-1417-Aug-1416-Aug-1418-Aug-14

    27-May-1431-May-14

    23-Jun-1429-Jun-14

    02-Jul-1408-Jul-14

    15-Jul-14

    23-Feb-14

    24-Feb-1413-Mar-14

    20-Mar-14

    26-Jun-1425-Jun-14

    29-Jun-1408-Jul-1410-Jul-14

    16-Jul-1420-Jul-14

    23-Feb-14

    02-Mar-1402-Mar-14

    25-Mar-1431-Mar-14

    13-Apr-1413-Apr-14

    28-Apr-1428-Apr-14

    04-May-14

    05-Mar-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 5 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Establishing temporary dewatering system 10 11-Mar-14 23-Mar-14 0%Excavation 20 17-Mar-14 09-Apr-14 0%Bedding 20 23-Mar-14 15-Apr-14 0%Piple laying 20 09-Apr-14 03-May-14 0%Construction of chambers 20 09-Apr-14 03-May-14 0%Construction of thurst blocks 15 15-Apr-14 03-May-14 0%Inspection and approval to backfill 15 27-Apr-14 14-May-14 0%Backfilling and removal of Dewatering 17 01-May-14 21-May-14 0%Precommissioning 10 15-May-14 27-May-14 0%

    FIRE WATER WORKS 73 03-Mar-14 27-May-14 0%Setting out for MEP network 8 03-Mar-14 11-Mar-14 0%Establishing temporary dewatering system 10 11-Mar-14 23-Mar-14 0%Excavation 17 29-Mar-14 17-Apr-14 0%Bedding 17 03-Apr-14 23-Apr-14 0%Piple laying 17 09-Apr-14 29-Apr-14 0%Construction of chambers 20 09-Apr-14 03-May-14 0%Construction of thurst blocks 15 15-Apr-14 03-May-14 0%Inspection and approval to backfill 15 27-Apr-14 14-May-14 0%Backfilling and removal of Dewatering 17 01-May-14 21-May-14 0%Precommissioning 10 15-May-14 27-May-14 0%

    DISTRICT COOLING WATER WORKS (SCOPE NOT DEFINED) 56 03-Mar-14 07-May-14 0%Setting out for MEP network 10 03-Mar-14 13-Mar-14 0%Establishing temporary dewatering system 10 11-Mar-14 23-Mar-14 0%Excavation in R/C 15 29-Mar-14 15-Apr-14 0%Bedding in R/C 15 03-Apr-14 21-Apr-14 0%Piple laying in Road crossings R/C 13 09-Apr-14 24-Apr-14 0%Inspection and approval to backfill 13 15-Apr-14 30-Apr-14 0%Backfilling and removal of Dewatering 15 20-Apr-14 07-May-14 0%

    POTABLE WATER WORKS 84 09-Mar-14 15-Jun-14 0%Setting out for MEP network 8 09-Mar-14 17-Mar-14 0%Establishing temporary dewatering system 10 23-Mar-14 03-Apr-14 0%Excavation 15 03-Apr-14 21-Apr-14 0%Bedding 15 09-Apr-14 27-Apr-14 0%Piple laying 18 15-Apr-14 06-May-14 0%Construction of chambers 20 15-Apr-14 08-May-14 0%Construction of thurst blocks 15 07-May-14 25-May-14 0%Inspection and approval to backfill 15 13-May-14 31-May-14 0%Backfilling and removal of Dewatering 18 19-May-14 09-Jun-14 0%Precommissioning 10 03-Jun-14 15-Jun-14 0%

    IRRIGATION WATER WORKS 68 15-Mar-14 01-Jun-14 0%Setting out for MEP network 8 15-Mar-14 23-Mar-14 0%Establishing temporary dewatering system 10 23-Mar-14 03-Apr-14 0%Excavation 12 13-Apr-14 26-Apr-14 0%Bedding 12 19-Apr-14 01-May-14 0%Piple laying 15 24-Apr-14 11-May-14 0%Construction of chambers 13 24-Apr-14 08-May-14 0%Construction of thurst blocks 10 03-May-14 13-May-14 0%Inspection and approval to backfill 13 12-May-14 26-May-14 0%Backfilling and removal of Dewatering 13 12-May-14 26-May-14 0%Precommissioning 10 21-May-14 01-Jun-14 0%

    ELECTRIAL 67 24-Mar-14 10-Jun-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    23-Mar-1409-Apr-14

    15-Apr-1403-May-1403-May-1403-May-14

    14-May-1421-May-14

    27-May-14

    11-Mar-1423-Mar-14

    17-Apr-1423-Apr-14

    29-Apr-1403-May-1403-May-14

    14-May-1421-May-14

    27-May-14

    13-Mar-1423-Mar-14

    15-Apr-1421-Apr-14

    24-Apr-1430-Apr-14

    07-May-14

    17-Mar-1403-Apr-14

    21-Apr-1427-Apr-14

    06-May-1408-May-14

    25-May-1431-May-14

    09-Jun-1415-Jun-14

    23-Mar-1403-Apr-14

    26-Apr-1401-May-14

    11-May-1408-May-14

    13-May-1426-May-1426-May-14

    01-Jun-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 6 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Setting out 10 24-Mar-14 03-Apr-14 0%Excavation 10 10-May-14 21-May-14 0%Sand Bedding 15 15-May-14 02-Jun-14 0%Cable laying 17 21-May-14 10-Jun-14 0%Inspection 10 21-May-14 02-Jun-14 0%Backfilling 10 27-May-14 08-Jun-14 0%

    TELECOM 63 30-Mar-14 11-Jun-14 0%Setting out 10 30-Mar-14 09-Apr-14 0%Excavation 10 10-May-14 21-May-14 0%Bedding 15 15-May-14 02-Jun-14 0%Ducts and Chambers 18 21-May-14 11-Jun-14 0%Inspection 10 21-May-14 02-Jun-14 0%Backfilling 10 27-May-14 08-Jun-14 0%

    GAS LINES 54 10-Apr-14 12-Jun-14 0%Setting out 10 10-Apr-14 21-Apr-14 0%Excavation 10 15-May-14 27-May-14 0%Bedding 15 21-May-14 08-Jun-14 0%Ducts/Gas lines and Chambers 13 27-May-14 11-Jun-14 0%Inspection 10 29-May-14 10-Jun-14 0%Backfilling 10 01-Jun-14 12-Jun-14 0%

    STREET LIGHTING 51 10-Apr-14 09-Jun-14 0%Setting out 10 10-Apr-14 21-Apr-14 0%Excavation 10 15-May-14 27-May-14 0%Foundation for street lighting 10 15-May-14 27-May-14 0%Sand Bedding 10 21-May-14 02-Jun-14 0%Cable laying 15 21-May-14 08-Jun-14 0%Erection of high masts 8 24-May-14 02-Jun-14 0%Inspection 10 27-May-14 08-Jun-14 0%Backfilling 10 28-May-14 09-Jun-14 0%Testing and commisioning 10 28-May-14 09-Jun-14 0%

    SPARE DUCTS 51 09-Mar-14 07-May-14 0%Setting out for MEP network 10 09-Mar-14 19-Mar-14 0%Establishing temporary dewatering system 10 11-Mar-14 23-Mar-14 0%Excavation in R/C 15 29-Mar-14 15-Apr-14 0%Bedding in R/C 15 03-Apr-14 21-Apr-14 0%Piple laying in Road crossings R/C 13 09-Apr-14 24-Apr-14 0%Inspection and approval to backfill 13 15-Apr-14 30-Apr-14 0%Backfilling and removal of Dewatering 15 20-Apr-14 07-May-14 0%

    PHASE 3 - GP 5-7 141 18-Feb-14 02-Aug-14 0%ROAD WORKS 141 18-Feb-14 02-Aug-14 0%

    Surface rough Grading 10 18-Feb-14 01-Mar-14 0%INITIAL STAGE 31 19-Feb-14 26-Mar-14 0%

    Setting out for Road works 10 19-Feb-14 02-Mar-14 0%1st Stage Excavation upto Formation level 15 03-Mar-14 19-Mar-14 0%Stocking/Disposal/Filling in embankments of Lagoon 16 09-Mar-14 26-Mar-14 0%

    FINAL STAGE 44 11-Jun-14 02-Aug-14 0%Sub base 18 11-Jun-14 02-Jul-14 0%Aggregate base course 12 18-Jun-14 02-Jul-14 0%Kerbs 10 24-Jun-14 06-Jul-14 0%Asphalt Base course 13 02-Jul-14 17-Jul-14 0%Wearing course 10 12-Jul-14 23-Jul-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    03-Apr-1421-May-14

    02-Jun-1410-Jun-14

    02-Jun-1408-Jun-14

    09-Apr-1421-May-14

    02-Jun-1411-Jun-14

    02-Jun-1408-Jun-14

    21-Apr-1427-May-14

    08-Jun-1411-Jun-1410-Jun-1412-Jun-14

    21-Apr-1427-May-1427-May-14

    02-Jun-1408-Jun-14

    02-Jun-1408-Jun-1409-Jun-1409-Jun-14

    19-Mar-1423-Mar-14

    15-Apr-1421-Apr-14

    24-Apr-1430-Apr-14

    07-May-14

    01-Mar-14

    02-Mar-1419-Mar-14

    26-Mar-14

    02-Jul-1402-Jul-14

    06-Jul-1417-Jul-14

    23-Jul-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 7 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Road marking 7 21-Jul-14 29-Jul-14 0%Road furniture 8 23-Jul-14 02-Aug-14 0%

    MEP SERVICES 107 18-Feb-14 23-Jun-14 0%Surface rough Grading 10 18-Feb-14 01-Mar-14 0%SEWERAGE WORKS 68 25-Feb-14 14-May-14 0%

    Setting out for MEP network 10 25-Feb-14 08-Mar-14 0%Establishing Temp Dewatering System 10 25-Feb-14 08-Mar-14 0%Excavation 20 09-Mar-14 31-Mar-14 0%Bedding 20 15-Mar-14 06-Apr-14 0%Pipe Laying 16 06-Apr-14 23-Apr-14 0%Construction of Manholes 16 06-Apr-14 23-Apr-14 0%Inspection & Approval to Backfill 14 23-Apr-14 08-May-14 0%Backfilling & Removal of Dewatering 14 23-Apr-14 08-May-14 0%Precommissioning 10 04-May-14 14-May-14 0%

    STORM WATER WORKS 78 03-Mar-14 02-Jun-14 0%Setting out for MEP network 8 03-Mar-14 11-Mar-14 0%Establishing temporary dewatering system 10 17-Mar-14 29-Mar-14 0%Excavation 20 23-Mar-14 15-Apr-14 0%Bedding 20 29-Mar-14 21-Apr-14 0%Piple laying 20 15-Apr-14 08-May-14 0%Construction of chambers 20 15-Apr-14 08-May-14 0%Construction of thurst blocks 15 21-Apr-14 08-May-14 0%Inspection and approval to backfill 15 03-May-14 20-May-14 0%Backfilling and removal of Dewatering 17 07-May-14 27-May-14 0%Precommissioning 10 21-May-14 02-Jun-14 0%

    FIRE WATER WORKS 73 09-Mar-14 02-Jun-14 0%Setting out for MEP network 8 09-Mar-14 17-Mar-14 0%Establishing temporary dewatering system 10 17-Mar-14 29-Mar-14 0%Excavation 17 03-Apr-14 23-Apr-14 0%Bedding 17 09-Apr-14 29-Apr-14 0%Piple laying 17 15-Apr-14 05-May-14 0%Construction of chambers 20 15-Apr-14 08-May-14 0%Construction of thurst blocks 15 21-Apr-14 08-May-14 0%Inspection and approval to backfill 15 03-May-14 20-May-14 0%Backfilling and removal of Dewatering 17 07-May-14 27-May-14 0%Precommissioning 10 21-May-14 02-Jun-14 0%

    DISTRICT COOLING WATER WORKS (SCOPE NOT DEFINED) 56 09-Mar-14 13-May-14 0%Setting out for MEP network 10 09-Mar-14 19-Mar-14 0%Establishing temporary dewatering system 10 17-Mar-14 29-Mar-14 0%Excavation in R/C 15 03-Apr-14 21-Apr-14 0%Bedding in R/C 15 09-Apr-14 27-Apr-14 0%Piple laying in Road crossings R/C 13 15-Apr-14 30-Apr-14 0%Inspection and approval to backfill 13 21-Apr-14 06-May-14 0%Backfilling and removal of Dewatering 15 26-Apr-14 13-May-14 0%

    POTABLE WATER WORKS 84 15-Mar-14 21-Jun-14 0%Setting out for MEP network 8 15-Mar-14 23-Mar-14 0%Establishing temporary dewatering system 10 29-Mar-14 09-Apr-14 0%Excavation 15 09-Apr-14 27-Apr-14 0%Bedding 15 15-Apr-14 03-May-14 0%Piple laying 18 21-Apr-14 12-May-14 0%Construction of chambers 20 21-Apr-14 14-May-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    29-Jul-1402-Aug-14

    01-Mar-14

    08-Mar-1408-Mar-14

    31-Mar-1406-Apr-14

    23-Apr-1423-Apr-14

    08-May-1408-May-14

    14-May-14

    11-Mar-1429-Mar-14

    15-Apr-1421-Apr-14

    08-May-1408-May-1408-May-14

    20-May-1427-May-14

    02-Jun-14

    17-Mar-1429-Mar-14

    23-Apr-1429-Apr-14

    05-May-1408-May-1408-May-14

    20-May-1427-May-14

    02-Jun-14

    19-Mar-1429-Mar-14

    21-Apr-1427-Apr-14

    30-Apr-1406-May-14

    13-May-14

    23-Mar-1409-Apr-14

    27-Apr-1403-May-14

    12-May-1414-May-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 8 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Construction of thurst blocks 15 13-May-14 31-May-14 0%Inspection and approval to backfill 15 19-May-14 05-Jun-14 0%Backfilling and removal of Dewatering 18 25-May-14 15-Jun-14 0%Precommissioning 10 09-Jun-14 21-Jun-14 0%

    IRRIGATION WATER WORKS 72 20-Mar-14 11-Jun-14 0%Setting out for MEP network 8 20-Mar-14 29-Mar-14 0%Establishing temporary dewatering system 10 29-Mar-14 09-Apr-14 0%Excavation 12 23-Apr-14 06-May-14 0%Bedding 12 29-Apr-14 12-May-14 0%Piple laying 15 05-May-14 21-May-14 0%Construction of chambers 13 07-May-14 21-May-14 0%Construction of thurst blocks 10 13-May-14 24-May-14 0%Inspection and approval to backfill 13 22-May-14 05-Jun-14 0%Backfilling and removal of Dewatering 13 22-May-14 05-Jun-14 0%Precommissioning 10 01-Jun-14 11-Jun-14 0%

    ELECTRIAL 72 30-Mar-14 22-Jun-14 0%Setting out 10 30-Mar-14 09-Apr-14 0%Excavation 10 15-May-14 27-May-14 0%Sand Bedding 15 21-May-14 08-Jun-14 0%Cable laying 17 27-May-14 16-Jun-14 0%Inspection 10 04-Jun-14 16-Jun-14 0%Backfilling 10 10-Jun-14 22-Jun-14 0%

    TELECOM 68 05-Apr-14 23-Jun-14 0%Setting out 10 05-Apr-14 15-Apr-14 0%Excavation 10 15-May-14 27-May-14 0%Bedding 15 21-May-14 08-Jun-14 0%Ducts and Chambers 18 27-May-14 17-Jun-14 0%Inspection 10 05-Jun-14 17-Jun-14 0%Backfilling 10 11-Jun-14 23-Jun-14 0%

    GAS LINES 57 16-Apr-14 22-Jun-14 0%Setting out 10 16-Apr-14 27-Apr-14 0%Excavation 10 21-May-14 02-Jun-14 0%Bedding 15 27-May-14 14-Jun-14 0%Ducts/Gas lines and Chambers 13 02-Jun-14 17-Jun-14 0%Inspection 10 08-Jun-14 19-Jun-14 0%Backfilling 10 10-Jun-14 22-Jun-14 0%

    STREET LIGHTING 52 16-Apr-14 16-Jun-14 0%Setting out 10 16-Apr-14 27-Apr-14 0%Excavation 10 21-May-14 02-Jun-14 0%Sand Bedding 10 27-May-14 08-Jun-14 0%Cable laying 15 27-May-14 14-Jun-14 0%Foundation for street lighting 10 27-May-14 08-Jun-14 0%Inspection 10 02-Jun-14 14-Jun-14 0%Backfilling 10 03-Jun-14 15-Jun-14 0%Erection of high masts 8 04-Jun-14 14-Jun-14 0%Testing and commisioning 10 04-Jun-14 16-Jun-14 0%

    SPARE DUCTS 51 15-Mar-14 13-May-14 0%Setting out for MEP network 10 15-Mar-14 25-Mar-14 0%Establishing temporary dewatering system 10 17-Mar-14 29-Mar-14 0%Excavation in R/C 15 03-Apr-14 21-Apr-14 0%Bedding in R/C 15 09-Apr-14 27-Apr-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    31-May-1405-Jun-14

    15-Jun-1421-Jun-14

    29-Mar-1409-Apr-14

    06-May-1412-May-14

    21-May-1421-May-14

    24-May-1405-Jun-1405-Jun-14

    11-Jun-14

    09-Apr-1427-May-14

    08-Jun-1416-Jun-1416-Jun-14

    22-Jun-14

    15-Apr-1427-May-14

    08-Jun-1417-Jun-1417-Jun-14

    23-Jun-14

    27-Apr-1402-Jun-14

    14-Jun-1417-Jun-1419-Jun-14

    22-Jun-14

    27-Apr-1402-Jun-14

    08-Jun-1414-Jun-14

    08-Jun-1414-Jun-1415-Jun-1414-Jun-1416-Jun-14

    25-Mar-1429-Mar-14

    21-Apr-1427-Apr-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 9 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Piple laying in Road crossings R/C 13 15-Apr-14 30-Apr-14 0%Inspection and approval to backfill 13 21-Apr-14 06-May-14 0%Backfilling and removal of Dewatering 15 26-Apr-14 13-May-14 0%

    PHASE 4 - GP 44-47 145 24-Feb-14 12-Aug-14 0%ROAD WORKS 145 24-Feb-14 12-Aug-14 0%

    Surface rough Grading 10 24-Feb-14 06-Mar-14 0%INITIAL STAGE 31 25-Feb-14 01-Apr-14 0%

    Setting out for Road works 10 25-Feb-14 08-Mar-14 0%1st Stage Excavation upto Formation level 15 09-Mar-14 25-Mar-14 0%Stocking/Disposal/Filling in embankments of Lagoon 16 15-Mar-14 01-Apr-14 0%

    FINAL STAGE 38 29-Jun-14 12-Aug-14 0%Sub base 18 29-Jun-14 20-Jul-14 0%Aggregate base course 12 05-Jul-14 19-Jul-14 0%Kerbs 10 10-Jul-14 22-Jul-14 0%Asphalt Base course 13 16-Jul-14 31-Jul-14 0%Wearing course 10 22-Jul-14 03-Aug-14 0%Road marking 7 31-Jul-14 09-Aug-14 0%Road furniture 8 03-Aug-14 12-Aug-14 0%

    MEP SERVICES 100 13-Mar-14 08-Jul-14 0%Surface rough Grading 10 13-Mar-14 24-Mar-14 0%SEWERAGE WORKS 54 15-Mar-14 15-May-14 0%

    Setting out for MEP network 10 15-Mar-14 25-Mar-14 0%Establishing Temp Dewatering System 10 15-Mar-14 25-Mar-14 0%Excavation 20 15-Mar-14 06-Apr-14 0%Bedding 20 20-Mar-14 12-Apr-14 0%Pipe Laying 16 07-Apr-14 24-Apr-14 0%Construction of Manholes 16 07-Apr-14 24-Apr-14 0%Inspection & Approval to Backfill 14 24-Apr-14 10-May-14 0%Backfilling & Removal of Dewatering 14 24-Apr-14 10-May-14 0%Precommissioning 10 05-May-14 15-May-14 0%

    STORM WATER WORKS 78 20-Mar-14 19-Jun-14 0%Setting out for MEP network 8 20-Mar-14 29-Mar-14 0%Establishing temporary dewatering system 10 03-Apr-14 15-Apr-14 0%Excavation 20 09-Apr-14 03-May-14 0%Bedding 20 15-Apr-14 08-May-14 0%Piple laying 20 03-May-14 26-May-14 0%Construction of chambers 20 03-May-14 26-May-14 0%Construction of thurst blocks 15 08-May-14 26-May-14 0%Inspection and approval to backfill 15 20-May-14 07-Jun-14 0%Backfilling and removal of Dewatering 17 25-May-14 14-Jun-14 0%Precommissioning 10 08-Jun-14 19-Jun-14 0%

    FIRE WATER WORKS 73 26-Mar-14 19-Jun-14 0%Setting out for MEP network 8 26-Mar-14 03-Apr-14 0%Establishing temporary dewatering system 10 03-Apr-14 15-Apr-14 0%Excavation 17 21-Apr-14 11-May-14 0%Bedding 17 27-Apr-14 17-May-14 0%Piple laying 17 03-May-14 22-May-14 0%Construction of chambers 20 03-May-14 26-May-14 0%Construction of thurst blocks 15 08-May-14 26-May-14 0%Inspection and approval to backfill 15 20-May-14 07-Jun-14 0%Backfilling and removal of Dewatering 17 25-May-14 14-Jun-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    30-Apr-1406-May-14

    13-May-14

    06-Mar-14

    08-Mar-1425-Mar-14

    01-Apr-14

    20-Jul-1419-Jul-14

    22-Jul-1431-Jul-14

    03-Aug-1409-Aug-14

    12-Aug-14

    24-Mar-14

    25-Mar-1425-Mar-14

    06-Apr-1412-Apr-14

    24-Apr-1424-Apr-14

    10-May-1410-May-14

    15-May-14

    29-Mar-1415-Apr-14

    03-May-1408-May-14

    26-May-1426-May-1426-May-14

    07-Jun-1414-Jun-14

    19-Jun-14

    03-Apr-1415-Apr-14

    11-May-1417-May-14

    22-May-1426-May-1426-May-14

    07-Jun-1414-Jun-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 10 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Precommissioning 10 08-Jun-14 19-Jun-14 0%DISTRICT COOLING WATER WORKS (SCOPE NOT DEFINED) 56 26-Mar-14 31-May-14 0%

    Setting out for MEP network 10 26-Mar-14 06-Apr-14 0%Establishing temporary dewatering system 10 03-Apr-14 15-Apr-14 0%Excavation in R/C 15 21-Apr-14 08-May-14 0%Bedding in R/C 15 27-Apr-14 14-May-14 0%Piple laying in Road crossings R/C 13 03-May-14 18-May-14 0%Inspection and approval to backfill 13 08-May-14 24-May-14 0%Backfilling and removal of Dewatering 15 13-May-14 31-May-14 0%

    POTABLE WATER WORKS 84 01-Apr-14 08-Jul-14 0%Setting out for MEP network 8 01-Apr-14 09-Apr-14 0%Establishing temporary dewatering system 10 15-Apr-14 27-Apr-14 0%Excavation 15 27-Apr-14 14-May-14 0%Bedding 15 03-May-14 20-May-14 0%Piple laying 18 08-May-14 29-May-14 0%Construction of chambers 20 08-May-14 01-Jun-14 0%Construction of thurst blocks 15 31-May-14 17-Jun-14 0%Inspection and approval to backfill 15 05-Jun-14 23-Jun-14 0%Backfilling and removal of Dewatering 18 11-Jun-14 02-Jul-14 0%Precommissioning 10 26-Jun-14 08-Jul-14 0%

    IRRIGATION WATER WORKS 66 07-Apr-14 22-Jun-14 0%Setting out for MEP network 8 07-Apr-14 15-Apr-14 0%Establishing temporary dewatering system 10 15-Apr-14 27-Apr-14 0%Excavation 12 03-May-14 17-May-14 0%Bedding 12 08-May-14 22-May-14 0%Piple laying 15 14-May-14 01-Jun-14 0%Construction of chambers 13 14-May-14 29-May-14 0%Construction of thurst blocks 10 22-May-14 03-Jun-14 0%Inspection and approval to backfill 13 01-Jun-14 16-Jun-14 0%Backfilling and removal of Dewatering 13 01-Jun-14 16-Jun-14 0%Precommissioning 10 10-Jun-14 22-Jun-14 0%

    ELECTRIAL 65 16-Apr-14 01-Jul-14 0%Setting out 10 16-Apr-14 27-Apr-14 0%Excavation 10 31-May-14 11-Jun-14 0%Sand Bedding 15 05-Jun-14 23-Jun-14 0%Cable laying 17 11-Jun-14 01-Jul-14 0%Inspection 10 11-Jun-14 23-Jun-14 0%Backfilling 10 17-Jun-14 29-Jun-14 0%

    TELECOM 61 22-Apr-14 02-Jul-14 0%Setting out 10 22-Apr-14 03-May-14 0%Excavation 10 31-May-14 11-Jun-14 0%Bedding 15 05-Jun-14 23-Jun-14 0%Ducts and Chambers 18 11-Jun-14 02-Jul-14 0%Inspection 10 11-Jun-14 23-Jun-14 0%Backfilling 10 17-Jun-14 29-Jun-14 0%

    GAS LINES 52 04-May-14 03-Jul-14 0%Setting out 10 04-May-14 14-May-14 0%Excavation 10 05-Jun-14 17-Jun-14 0%Bedding 15 11-Jun-14 29-Jun-14 0%Ducts/Gas lines and Chambers 13 17-Jun-14 02-Jul-14 0%Inspection 10 19-Jun-14 01-Jul-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    19-Jun-14

    06-Apr-1415-Apr-14

    08-May-1414-May-14

    18-May-1424-May-14

    31-May-14

    09-Apr-1427-Apr-14

    14-May-1420-May-14

    29-May-1401-Jun-14

    17-Jun-1423-Jun-14

    02-Jul-1408-Jul-14

    15-Apr-1427-Apr-14

    17-May-1422-May-14

    01-Jun-1429-May-14

    03-Jun-1416-Jun-1416-Jun-14

    22-Jun-14

    27-Apr-1411-Jun-14

    23-Jun-1401-Jul-14

    23-Jun-1429-Jun-14

    03-May-1411-Jun-14

    23-Jun-1402-Jul-14

    23-Jun-1429-Jun-14

    14-May-1417-Jun-14

    29-Jun-1402-Jul-1401-Jul-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 11 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Backfilling 10 22-Jun-14 03-Jul-14 0%STREET LIGHTING 50 04-May-14 01-Jul-14 0%

    Setting out 10 04-May-14 14-May-14 0%Excavation 10 05-Jun-14 17-Jun-14 0%Sand Bedding 10 11-Jun-14 23-Jun-14 0%Cable laying 15 11-Jun-14 29-Jun-14 0%Foundation for street lighting 10 11-Jun-14 23-Jun-14 0%Inspection 10 17-Jun-14 29-Jun-14 0%Backfilling 10 18-Jun-14 30-Jun-14 0%Erection of high masts 8 19-Jun-14 29-Jun-14 0%Testing and commisioning 10 19-Jun-14 01-Jul-14 0%

    SPARE DUCTS 51 01-Apr-14 31-May-14 0%Setting out for MEP network 10 01-Apr-14 12-Apr-14 0%Establishing temporary dewatering system 10 03-Apr-14 15-Apr-14 0%Excavation in R/C 15 21-Apr-14 08-May-14 0%Bedding in R/C 15 27-Apr-14 14-May-14 0%Piple laying in Road crossings R/C 13 03-May-14 18-May-14 0%Inspection and approval to backfill 13 08-May-14 24-May-14 0%Backfilling and removal of Dewatering 15 13-May-14 31-May-14 0%

    PHASE 5 - G23-27 145 02-Mar-14 18-Aug-14 0%ROAD WORKS 145 02-Mar-14 18-Aug-14 0%

    Surface rough Grading 10 02-Mar-14 12-Mar-14 0%INITIAL STAGE 31 03-Mar-14 07-Apr-14 0%

    Setting out for Road works 10 03-Mar-14 13-Mar-14 0%1st Stage Excavation upto Formation level 15 15-Mar-14 31-Mar-14 0%Stocking/Disposal/Filling in embankments of Lagoon 16 20-Mar-14 07-Apr-14 0%

    FINAL STAGE 38 05-Jul-14 18-Aug-14 0%Sub base 18 05-Jul-14 26-Jul-14 0%Aggregate base course 12 10-Jul-14 24-Jul-14 0%Kerbs 10 16-Jul-14 28-Jul-14 0%Asphalt Base course 13 22-Jul-14 06-Aug-14 0%Wearing course 10 28-Jul-14 09-Aug-14 0%Road marking 7 06-Aug-14 14-Aug-14 0%Road furniture 8 09-Aug-14 18-Aug-14 0%

    MEP SERVICES 100 19-Mar-14 14-Jul-14 0%Surface rough Grading 10 19-Mar-14 30-Mar-14 0%SEWERAGE WORKS 54 20-Mar-14 21-May-14 0%

    Setting out for MEP network 10 20-Mar-14 31-Mar-14 0%Establishing Temp Dewatering System 10 20-Mar-14 31-Mar-14 0%Excavation 20 20-Mar-14 12-Apr-14 0%Bedding 20 26-Mar-14 17-Apr-14 0%Pipe Laying 16 13-Apr-14 30-Apr-14 0%Construction of Manholes 16 13-Apr-14 30-Apr-14 0%Inspection & Approval to Backfill 14 30-Apr-14 15-May-14 0%Backfilling & Removal of Dewatering 14 30-Apr-14 15-May-14 0%Precommissioning 10 11-May-14 21-May-14 0%

    STORM WATER WORKS 78 26-Mar-14 25-Jun-14 0%Setting out for MEP network 8 26-Mar-14 03-Apr-14 0%Establishing temporary dewatering system 10 09-Apr-14 21-Apr-14 0%Excavation 20 15-Apr-14 08-May-14 0%Bedding 20 21-Apr-14 14-May-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    03-Jul-14

    14-May-1417-Jun-14

    23-Jun-1429-Jun-14

    23-Jun-1429-Jun-1430-Jun-1429-Jun-1401-Jul-14

    12-Apr-1415-Apr-14

    08-May-1414-May-14

    18-May-1424-May-14

    31-May-14

    12-Mar-14

    13-Mar-1431-Mar-14

    07-Apr-14

    26-Jul-1424-Jul-14

    28-Jul-1406-Aug-14

    09-Aug-1414-Aug-14

    18-Aug-14

    30-Mar-14

    31-Mar-1431-Mar-14

    12-Apr-1417-Apr-14

    30-Apr-1430-Apr-14

    15-May-1415-May-14

    21-May-14

    03-Apr-1421-Apr-14

    08-May-1414-May-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 12 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Piple laying 20 08-May-14 01-Jun-14 0%Construction of chambers 20 08-May-14 01-Jun-14 0%Construction of thurst blocks 15 14-May-14 01-Jun-14 0%Inspection and approval to backfill 15 26-May-14 12-Jun-14 0%Backfilling and removal of Dewatering 17 31-May-14 19-Jun-14 0%Precommissioning 10 14-Jun-14 25-Jun-14 0%

    FIRE WATER WORKS 73 01-Apr-14 25-Jun-14 0%Setting out for MEP network 8 01-Apr-14 09-Apr-14 0%Establishing temporary dewatering system 10 09-Apr-14 21-Apr-14 0%Excavation 17 27-Apr-14 17-May-14 0%Bedding 17 03-May-14 22-May-14 0%Piple laying 17 08-May-14 28-May-14 0%Construction of chambers 20 08-May-14 01-Jun-14 0%Construction of thurst blocks 15 14-May-14 01-Jun-14 0%Inspection and approval to backfill 15 26-May-14 12-Jun-14 0%Backfilling and removal of Dewatering 17 31-May-14 19-Jun-14 0%Precommissioning 10 14-Jun-14 25-Jun-14 0%

    DISTRICT COOLING WATER WORKS (SCOPE NOT DEFINED) 56 01-Apr-14 05-Jun-14 0%Setting out for MEP network 10 01-Apr-14 12-Apr-14 0%Establishing temporary dewatering system 10 09-Apr-14 21-Apr-14 0%Excavation in R/C 15 27-Apr-14 14-May-14 0%Bedding in R/C 15 03-May-14 20-May-14 0%Piple laying in Road crossings R/C 13 08-May-14 24-May-14 0%Inspection and approval to backfill 13 14-May-14 29-May-14 0%Backfilling and removal of Dewatering 15 19-May-14 05-Jun-14 0%

    POTABLE WATER WORKS 84 07-Apr-14 14-Jul-14 0%Setting out for MEP network 8 07-Apr-14 15-Apr-14 0%Establishing temporary dewatering system 10 21-Apr-14 03-May-14 0%Excavation 15 03-May-14 20-May-14 0%Bedding 15 08-May-14 26-May-14 0%Piple laying 18 14-May-14 04-Jun-14 0%Construction of chambers 20 14-May-14 07-Jun-14 0%Construction of thurst blocks 15 05-Jun-14 23-Jun-14 0%Inspection and approval to backfill 15 11-Jun-14 29-Jun-14 0%Backfilling and removal of Dewatering 18 17-Jun-14 08-Jul-14 0%Precommissioning 10 02-Jul-14 14-Jul-14 0%

    IRRIGATION WATER WORKS 66 13-Apr-14 28-Jun-14 0%Setting out for MEP network 8 13-Apr-14 21-Apr-14 0%Establishing temporary dewatering system 10 21-Apr-14 03-May-14 0%Excavation 12 08-May-14 22-May-14 0%Bedding 12 14-May-14 28-May-14 0%Piple laying 15 20-May-14 07-Jun-14 0%Construction of chambers 13 20-May-14 04-Jun-14 0%Construction of thurst blocks 10 28-May-14 09-Jun-14 0%Inspection and approval to backfill 13 07-Jun-14 22-Jun-14 0%Backfilling and removal of Dewatering 13 07-Jun-14 22-Jun-14 0%Precommissioning 10 16-Jun-14 28-Jun-14 0%

    ELECTRIAL 65 22-Apr-14 07-Jul-14 0%Setting out 10 22-Apr-14 03-May-14 0%Excavation 10 05-Jun-14 17-Jun-14 0%Sand Bedding 15 11-Jun-14 29-Jun-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    01-Jun-1401-Jun-1401-Jun-14

    12-Jun-1419-Jun-14

    25-Jun-14

    09-Apr-1421-Apr-14

    17-May-1422-May-14

    28-May-1401-Jun-1401-Jun-14

    12-Jun-1419-Jun-14

    25-Jun-14

    12-Apr-1421-Apr-14

    14-May-1420-May-14

    24-May-1429-May-14

    05-Jun-14

    15-Apr-1403-May-14

    20-May-1426-May-14

    04-Jun-1407-Jun-14

    23-Jun-1429-Jun-14

    08-Jul-1414-Jul-14

    21-Apr-1403-May-14

    22-May-1428-May-14

    07-Jun-1404-Jun-14

    09-Jun-1422-Jun-1422-Jun-14

    28-Jun-14

    03-May-1417-Jun-14

    29-Jun-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 13 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Cable laying 17 17-Jun-14 07-Jul-14 0%Inspection 10 17-Jun-14 29-Jun-14 0%Backfilling 10 23-Jun-14 05-Jul-14 0%

    TELECOM 61 28-Apr-14 08-Jul-14 0%Setting out 10 28-Apr-14 08-May-14 0%Excavation 10 05-Jun-14 17-Jun-14 0%Bedding 15 11-Jun-14 29-Jun-14 0%Ducts and Chambers 18 17-Jun-14 08-Jul-14 0%Inspection 10 17-Jun-14 29-Jun-14 0%Backfilling 10 23-Jun-14 05-Jul-14 0%

    GAS LINES 52 10-May-14 09-Jul-14 0%Setting out 10 10-May-14 20-May-14 0%Excavation 10 11-Jun-14 23-Jun-14 0%Bedding 15 17-Jun-14 05-Jul-14 0%Ducts/Gas lines and Chambers 13 23-Jun-14 08-Jul-14 0%Inspection 10 25-Jun-14 07-Jul-14 0%Backfilling 10 28-Jun-14 09-Jul-14 0%

    STREET LIGHTING 50 10-May-14 07-Jul-14 0%Setting out 10 10-May-14 20-May-14 0%Excavation 10 11-Jun-14 23-Jun-14 0%Sand Bedding 10 17-Jun-14 29-Jun-14 0%Cable laying 15 17-Jun-14 05-Jul-14 0%Foundation for street lighting 10 17-Jun-14 29-Jun-14 0%Inspection 10 23-Jun-14 05-Jul-14 0%Backfilling 10 24-Jun-14 06-Jul-14 0%Erection of high masts 8 25-Jun-14 05-Jul-14 0%Testing and commisioning 10 25-Jun-14 07-Jul-14 0%

    SPARE DUCTS 51 07-Apr-14 05-Jun-14 0%Setting out for MEP network 10 07-Apr-14 17-Apr-14 0%Establishing temporary dewatering system 10 09-Apr-14 21-Apr-14 0%Excavation in R/C 15 27-Apr-14 14-May-14 0%Bedding in R/C 15 03-May-14 20-May-14 0%Piple laying in Road crossings R/C 13 08-May-14 24-May-14 0%Inspection and approval to backfill 13 14-May-14 29-May-14 0%Backfilling and removal of Dewatering 15 19-May-14 05-Jun-14 0%

    PHASE 6 - G27-32 145 08-Mar-14 24-Aug-14 0%ROAD WORKS 145 08-Mar-14 24-Aug-14 0%

    Surface rough Grading 10 08-Mar-14 18-Mar-14 0%INITIAL STAGE 31 09-Mar-14 13-Apr-14 0%

    Setting out for Road works 10 09-Mar-14 19-Mar-14 0%1st Stage Excavation upto Formation level 15 20-Mar-14 06-Apr-14 0%Stocking/Disposal/Filling in embankments of Lagoon 16 26-Mar-14 13-Apr-14 0%

    FINAL STAGE 38 10-Jul-14 24-Aug-14 0%Sub base 18 10-Jul-14 31-Jul-14 0%Aggregate base course 12 16-Jul-14 30-Jul-14 0%Kerbs 10 22-Jul-14 03-Aug-14 0%Asphalt Base course 13 28-Jul-14 12-Aug-14 0%Wearing course 10 03-Aug-14 14-Aug-14 0%Road marking 7 12-Aug-14 20-Aug-14 0%Road furniture 8 14-Aug-14 24-Aug-14 0%

    MEP SERVICES 100 25-Mar-14 20-Jul-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    07-Jul-1429-Jun-14

    05-Jul-14

    08-May-1417-Jun-14

    29-Jun-1408-Jul-14

    29-Jun-1405-Jul-14

    20-May-1423-Jun-14

    05-Jul-1408-Jul-1407-Jul-1409-Jul-14

    20-May-1423-Jun-14

    29-Jun-1405-Jul-14

    29-Jun-1405-Jul-1406-Jul-1405-Jul-1407-Jul-14

    17-Apr-1421-Apr-14

    14-May-1420-May-14

    24-May-1429-May-14

    05-Jun-14

    18-Mar-14

    19-Mar-1406-Apr-14

    13-Apr-14

    31-Jul-1430-Jul-14

    03-Aug-1412-Aug-1414-Aug-14

    20-Aug-1424-Aug-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 14 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Surface rough Grading 10 25-Mar-14 05-Apr-14 0%SEWERAGE WORKS 54 26-Mar-14 27-May-14 0%

    Setting out for MEP network 10 26-Mar-14 06-Apr-14 0%Establishing Temp Dewatering System 10 26-Mar-14 06-Apr-14 0%Excavation 20 26-Mar-14 17-Apr-14 0%Bedding 20 01-Apr-14 23-Apr-14 0%Pipe Laying 16 19-Apr-14 06-May-14 0%Construction of Manholes 16 19-Apr-14 06-May-14 0%Inspection & Approval to Backfill 14 06-May-14 21-May-14 0%Backfilling & Removal of Dewatering 14 06-May-14 21-May-14 0%Precommissioning 10 17-May-14 27-May-14 0%

    STORM WATER WORKS 78 01-Apr-14 01-Jul-14 0%Setting out for MEP network 8 01-Apr-14 09-Apr-14 0%Establishing temporary dewatering system 10 15-Apr-14 27-Apr-14 0%Excavation 20 21-Apr-14 14-May-14 0%Bedding 20 27-Apr-14 20-May-14 0%Piple laying 20 14-May-14 07-Jun-14 0%Construction of chambers 20 14-May-14 07-Jun-14 0%Construction of thurst blocks 15 20-May-14 07-Jun-14 0%Inspection and approval to backfill 15 01-Jun-14 18-Jun-14 0%Backfilling and removal of Dewatering 17 05-Jun-14 25-Jun-14 0%Precommissioning 10 19-Jun-14 01-Jul-14 0%

    FIRE WATER WORKS 73 07-Apr-14 01-Jul-14 0%Setting out for MEP network 8 07-Apr-14 15-Apr-14 0%Establishing temporary dewatering system 10 15-Apr-14 27-Apr-14 0%Excavation 17 03-May-14 22-May-14 0%Bedding 17 08-May-14 28-May-14 0%Piple laying 17 14-May-14 03-Jun-14 0%Construction of chambers 20 14-May-14 07-Jun-14 0%Construction of thurst blocks 15 20-May-14 07-Jun-14 0%Inspection and approval to backfill 15 01-Jun-14 18-Jun-14 0%Backfilling and removal of Dewatering 17 05-Jun-14 25-Jun-14 0%Precommissioning 10 19-Jun-14 01-Jul-14 0%

    DISTRICT COOLING WATER WORKS (SCOPE NOT DEFINED) 56 07-Apr-14 11-Jun-14 0%Setting out for MEP network 10 07-Apr-14 17-Apr-14 0%Establishing temporary dewatering system 10 15-Apr-14 27-Apr-14 0%Excavation in R/C 15 03-May-14 20-May-14 0%Bedding in R/C 15 08-May-14 26-May-14 0%Piple laying in Road crossings R/C 13 14-May-14 29-May-14 0%Inspection and approval to backfill 13 20-May-14 04-Jun-14 0%Backfilling and removal of Dewatering 15 25-May-14 11-Jun-14 0%

    POTABLE WATER WORKS 84 13-Apr-14 20-Jul-14 0%Setting out for MEP network 8 13-Apr-14 21-Apr-14 0%Establishing temporary dewatering system 10 27-Apr-14 08-May-14 0%Excavation 15 08-May-14 26-May-14 0%Bedding 15 14-May-14 01-Jun-14 0%Piple laying 18 20-May-14 10-Jun-14 0%Construction of chambers 20 20-May-14 12-Jun-14 0%Construction of thurst blocks 15 11-Jun-14 29-Jun-14 0%Inspection and approval to backfill 15 17-Jun-14 05-Jul-14 0%Backfilling and removal of Dewatering 18 23-Jun-14 14-Jul-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    05-Apr-14

    06-Apr-1406-Apr-14

    17-Apr-1423-Apr-14

    06-May-1406-May-14

    21-May-1421-May-14

    27-May-14

    09-Apr-1427-Apr-14

    14-May-1420-May-14

    07-Jun-1407-Jun-1407-Jun-14

    18-Jun-1425-Jun-14

    01-Jul-14

    15-Apr-1427-Apr-14

    22-May-1428-May-14

    03-Jun-1407-Jun-1407-Jun-14

    18-Jun-1425-Jun-14

    01-Jul-14

    17-Apr-1427-Apr-14

    20-May-1426-May-14

    29-May-1404-Jun-14

    11-Jun-14

    21-Apr-1408-May-14

    26-May-1401-Jun-14

    10-Jun-1412-Jun-14

    29-Jun-1405-Jul-14

    14-Jul-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 15 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Precommissioning 10 08-Jul-14 20-Jul-14 0%IRRIGATION WATER WORKS 66 19-Apr-14 03-Jul-14 0%

    Setting out for MEP network 8 19-Apr-14 27-Apr-14 0%Establishing temporary dewatering system 10 27-Apr-14 08-May-14 0%Excavation 12 14-May-14 28-May-14 0%Bedding 12 20-May-14 03-Jun-14 0%Piple laying 15 26-May-14 12-Jun-14 0%Construction of chambers 13 26-May-14 10-Jun-14 0%Construction of thurst blocks 10 03-Jun-14 15-Jun-14 0%Inspection and approval to backfill 13 12-Jun-14 28-Jun-14 0%Backfilling and removal of Dewatering 13 12-Jun-14 28-Jun-14 0%Precommissioning 10 22-Jun-14 03-Jul-14 0%

    ELECTRIAL 67 28-Apr-14 15-Jul-14 0%Setting out 10 28-Apr-14 08-May-14 0%Excavation 10 14-Jun-14 25-Jun-14 0%Sand Bedding 15 19-Jun-14 07-Jul-14 0%Cable laying 17 25-Jun-14 15-Jul-14 0%Inspection 10 25-Jun-14 07-Jul-14 0%Backfilling 10 01-Jul-14 13-Jul-14 0%

    TELECOM 63 04-May-14 16-Jul-14 0%Setting out 10 04-May-14 14-May-14 0%Excavation 10 14-Jun-14 25-Jun-14 0%Bedding 15 19-Jun-14 07-Jul-14 0%Ducts and Chambers 18 25-Jun-14 16-Jul-14 0%Inspection 10 25-Jun-14 07-Jul-14 0%Backfilling 10 01-Jul-14 13-Jul-14 0%

    GAS LINES 54 15-May-14 17-Jul-14 0%Setting out 10 15-May-14 26-May-14 0%Excavation 10 19-Jun-14 01-Jul-14 0%Bedding 15 25-Jun-14 13-Jul-14 0%Ducts/Gas lines and Chambers 13 01-Jul-14 16-Jul-14 0%Inspection 10 03-Jul-14 15-Jul-14 0%Backfilling 10 06-Jul-14 17-Jul-14 0%

    STREET LIGHTING 52 15-May-14 15-Jul-14 0%Setting out 10 15-May-14 26-May-14 0%Excavation 10 19-Jun-14 01-Jul-14 0%Sand Bedding 10 25-Jun-14 07-Jul-14 0%Cable laying 15 25-Jun-14 13-Jul-14 0%Foundation for street lighting 10 25-Jun-14 07-Jul-14 0%Inspection 10 01-Jul-14 13-Jul-14 0%Backfilling 10 02-Jul-14 14-Jul-14 0%Erection of high masts 8 03-Jul-14 13-Jul-14 0%Testing and commisioning 10 03-Jul-14 15-Jul-14 0%

    SPARE DUCTS 51 13-Apr-14 11-Jun-14 0%Setting out for MEP network 10 13-Apr-14 23-Apr-14 0%Establishing temporary dewatering system 10 15-Apr-14 27-Apr-14 0%Excavation in R/C 15 03-May-14 20-May-14 0%Bedding in R/C 15 08-May-14 26-May-14 0%Piple laying in Road crossings R/C 13 14-May-14 29-May-14 0%Inspection and approval to backfill 13 20-May-14 04-Jun-14 0%Backfilling and removal of Dewatering 15 25-May-14 11-Jun-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    20-Jul-14

    27-Apr-1408-May-14

    28-May-1403-Jun-14

    12-Jun-1410-Jun-14

    15-Jun-1428-Jun-1428-Jun-14

    03-Jul-14

    08-May-1425-Jun-14

    07-Jul-1415-Jul-14

    07-Jul-1413-Jul-14

    14-May-1425-Jun-14

    07-Jul-1416-Jul-14

    07-Jul-1413-Jul-14

    26-May-1401-Jul-14

    13-Jul-1416-Jul-1415-Jul-1417-Jul-14

    26-May-1401-Jul-14

    07-Jul-1413-Jul-14

    07-Jul-1413-Jul-1414-Jul-1413-Jul-1415-Jul-14

    23-Apr-1427-Apr-14

    20-May-1426-May-14

    29-May-1404-Jun-14

    11-Jun-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 16 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    PHASE 7 - VERTICAL ALIGNMENT 145 13-Mar-14 30-Aug-14 0%ROAD WORKS 145 13-Mar-14 30-Aug-14 0%

    Surface rough Grading 10 13-Mar-14 24-Mar-14 0%INITIAL STAGE 31 15-Mar-14 19-Apr-14 0%

    Setting out for Road works 10 15-Mar-14 25-Mar-14 0%1st Stage Excavation upto Formation level 15 26-Mar-14 12-Apr-14 0%Stocking/Disposal/Filling in embankments of Lagoon 16 01-Apr-14 19-Apr-14 0%

    FINAL STAGE 38 16-Jul-14 30-Aug-14 0%Sub base 18 16-Jul-14 06-Aug-14 0%Aggregate base course 12 22-Jul-14 05-Aug-14 0%Kerbs 10 28-Jul-14 09-Aug-14 0%Asphalt Base course 13 03-Aug-14 18-Aug-14 0%Wearing course 10 09-Aug-14 20-Aug-14 0%Road marking 7 18-Aug-14 26-Aug-14 0%Road furniture 8 20-Aug-14 30-Aug-14 0%

    MEP SERVICES 100 31-Mar-14 26-Jul-14 0%Surface rough Grading 10 31-Mar-14 10-Apr-14 0%SEWERAGE WORKS 54 01-Apr-14 02-Jun-14 0%

    Setting out for MEP network 10 01-Apr-14 12-Apr-14 0%Establishing Temp Dewatering System 10 01-Apr-14 12-Apr-14 0%Excavation 20 01-Apr-14 23-Apr-14 0%Bedding 20 07-Apr-14 29-Apr-14 0%Pipe Laying 16 24-Apr-14 12-May-14 0%Construction of Manholes 16 24-Apr-14 12-May-14 0%Inspection & Approval to Backfill 14 12-May-14 27-May-14 0%Backfilling & Removal of Dewatering 14 12-May-14 27-May-14 0%Precommissioning 10 22-May-14 02-Jun-14 0%

    STORM WATER WORKS 78 07-Apr-14 07-Jul-14 0%Setting out for MEP network 8 07-Apr-14 15-Apr-14 0%Establishing temporary dewatering system 10 21-Apr-14 03-May-14 0%Excavation 20 27-Apr-14 20-May-14 0%Bedding 20 03-May-14 26-May-14 0%Piple laying 20 20-May-14 12-Jun-14 0%Construction of chambers 20 20-May-14 12-Jun-14 0%Construction of thurst blocks 15 26-May-14 12-Jun-14 0%Inspection and approval to backfill 15 07-Jun-14 24-Jun-14 0%Backfilling and removal of Dewatering 17 11-Jun-14 01-Jul-14 0%Precommissioning 10 25-Jun-14 07-Jul-14 0%

    FIRE WATER WORKS 73 13-Apr-14 07-Jul-14 0%Setting out for MEP network 8 13-Apr-14 21-Apr-14 0%Establishing temporary dewatering system 10 21-Apr-14 03-May-14 0%Excavation 17 08-May-14 28-May-14 0%Bedding 17 14-May-14 03-Jun-14 0%Piple laying 17 20-May-14 09-Jun-14 0%Construction of chambers 20 20-May-14 12-Jun-14 0%Construction of thurst blocks 15 26-May-14 12-Jun-14 0%Inspection and approval to backfill 15 07-Jun-14 24-Jun-14 0%Backfilling and removal of Dewatering 17 11-Jun-14 01-Jul-14 0%Precommissioning 10 25-Jun-14 07-Jul-14 0%

    DISTRICT COOLING WATER WORKS (SCOPE NOT DEFINED) 56 13-Apr-14 17-Jun-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    24-Mar-14

    25-Mar-1412-Apr-14

    19-Apr-14

    06-Aug-1405-Aug-14

    09-Aug-1418-Aug-1420-Aug-14

    26-Aug-1430-Aug-14

    10-Apr-14

    12-Apr-1412-Apr-14

    23-Apr-1429-Apr-14

    12-May-1412-May-14

    27-May-1427-May-14

    02-Jun-14

    15-Apr-1403-May-14

    20-May-1426-May-14

    12-Jun-1412-Jun-1412-Jun-14

    24-Jun-1401-Jul-14

    07-Jul-14

    21-Apr-1403-May-14

    28-May-1403-Jun-14

    09-Jun-1412-Jun-14

    12-Jun-1424-Jun-14

    01-Jul-1407-Jul-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 17 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Setting out for MEP network 10 13-Apr-14 23-Apr-14 0%Establishing temporary dewatering system 10 21-Apr-14 03-May-14 0%Excavation in R/C 15 08-May-14 26-May-14 0%Bedding in R/C 15 14-May-14 01-Jun-14 0%Piple laying in Road crossings R/C 13 20-May-14 04-Jun-14 0%Inspection and approval to backfill 13 26-May-14 10-Jun-14 0%Backfilling and removal of Dewatering 15 31-May-14 17-Jun-14 0%

    POTABLE WATER WORKS 84 19-Apr-14 26-Jul-14 0%Setting out for MEP network 8 19-Apr-14 27-Apr-14 0%Establishing temporary dewatering system 10 03-May-14 14-May-14 0%Excavation 15 14-May-14 01-Jun-14 0%Bedding 15 20-May-14 07-Jun-14 0%Piple laying 18 26-May-14 16-Jun-14 0%Construction of chambers 20 26-May-14 18-Jun-14 0%Construction of thurst blocks 15 17-Jun-14 05-Jul-14 0%Inspection and approval to backfill 15 23-Jun-14 10-Jul-14 0%Backfilling and removal of Dewatering 18 29-Jun-14 20-Jul-14 0%Precommissioning 10 14-Jul-14 26-Jul-14 0%

    IRRIGATION WATER WORKS 66 24-Apr-14 09-Jul-14 0%Setting out for MEP network 8 24-Apr-14 03-May-14 0%Establishing temporary dewatering system 10 03-May-14 14-May-14 0%Excavation 12 20-May-14 03-Jun-14 0%Bedding 12 26-May-14 09-Jun-14 0%Piple laying 15 01-Jun-14 18-Jun-14 0%Construction of chambers 13 01-Jun-14 16-Jun-14 0%Construction of thurst blocks 10 09-Jun-14 21-Jun-14 0%Inspection and approval to backfill 13 18-Jun-14 03-Jul-14 0%Backfilling and removal of Dewatering 13 18-Jun-14 03-Jul-14 0%Precommissioning 10 28-Jun-14 09-Jul-14 0%

    ELECTRIAL 65 04-May-14 19-Jul-14 0%Setting out 10 04-May-14 14-May-14 0%Excavation 10 17-Jun-14 29-Jun-14 0%Sand Bedding 15 23-Jun-14 10-Jul-14 0%Cable laying 17 29-Jun-14 19-Jul-14 0%Inspection 10 29-Jun-14 10-Jul-14 0%Backfilling 10 05-Jul-14 16-Jul-14 0%

    TELECOM 61 10-May-14 20-Jul-14 0%Setting out 10 10-May-14 20-May-14 0%Excavation 10 17-Jun-14 29-Jun-14 0%Bedding 15 23-Jun-14 10-Jul-14 0%Ducts and Chambers 18 29-Jun-14 20-Jul-14 0%Inspection 10 29-Jun-14 10-Jul-14 0%Backfilling 10 05-Jul-14 16-Jul-14 0%

    GAS LINES 52 21-May-14 21-Jul-14 0%Setting out 10 21-May-14 01-Jun-14 0%Excavation 10 23-Jun-14 05-Jul-14 0%Bedding 15 29-Jun-14 16-Jul-14 0%Ducts/Gas lines and Chambers 13 05-Jul-14 20-Jul-14 0%Inspection 10 07-Jul-14 19-Jul-14 0%Backfilling 10 09-Jul-14 21-Jul-14 0%

    STREET LIGHTING 50 21-May-14 19-Jul-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    23-Apr-1403-May-14

    26-May-1401-Jun-14

    04-Jun-1410-Jun-14

    17-Jun-14

    27-Apr-1414-May-14

    01-Jun-1407-Jun-14

    16-Jun-1418-Jun-14

    05-Jul-1410-Jul-14

    20-Jul-1426-Jul-14

    03-May-1414-May-14

    03-Jun-1409-Jun-14

    18-Jun-1416-Jun-14

    21-Jun-1403-Jul-1403-Jul-14

    09-Jul-14

    14-May-1429-Jun-14

    10-Jul-1419-Jul-14

    10-Jul-1416-Jul-14

    20-May-1429-Jun-14

    10-Jul-1420-Jul-14

    10-Jul-1416-Jul-14

    01-Jun-1405-Jul-14

    16-Jul-1420-Jul-1419-Jul-1421-Jul-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 18 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Setting out 10 21-May-14 01-Jun-14 0%Excavation 10 23-Jun-14 05-Jul-14 0%Sand Bedding 10 29-Jun-14 10-Jul-14 0%Cable laying 15 29-Jun-14 16-Jul-14 0%Foundation for street lighting 10 29-Jun-14 10-Jul-14 0%Inspection 10 05-Jul-14 16-Jul-14 0%Backfilling 10 06-Jul-14 17-Jul-14 0%Erection of high masts 8 07-Jul-14 16-Jul-14 0%Testing and commisioning 10 07-Jul-14 19-Jul-14 0%

    SPARE DUCTS 51 19-Apr-14 17-Jun-14 0%Setting out for MEP network 10 19-Apr-14 29-Apr-14 0%Establishing temporary dewatering system 10 21-Apr-14 03-May-14 0%Excavation in R/C 15 08-May-14 26-May-14 0%Bedding in R/C 15 14-May-14 01-Jun-14 0%Piple laying in Road crossings R/C 13 20-May-14 04-Jun-14 0%Inspection and approval to backfill 13 26-May-14 10-Jun-14 0%Backfilling and removal of Dewatering 15 31-May-14 17-Jun-14 0%

    EAST WEST TRUNK ROAD AREAS 284 02-Mar-14 26-Jan-15 0%TRIAL HOLES & WORK PERMITS 30 02-Mar-14 05-Apr-14 0%

    Survey & Setting out the Layout 30 02-Mar-14 05-Apr-14 0%Trail pits for the existing services 10 08-Mar-14 18-Mar-14 0%Submission and approval of trialhole data to start protection 15 11-Mar-14 27-Mar-14 0%Protection / Diversion of Existing services (variation) 15 12-Mar-14 29-Mar-14 0%

    ROAD WORKS 284 02-Mar-14 26-Jan-15 0%Surface rough Grading 10 02-Mar-14 12-Mar-14 0%INITIAL STAGE 114 08-Mar-14 17-Jul-14 0%

    Setting out for Road works 50 08-Mar-14 04-May-14 0%1st Stage Excavation upto Formation level 90 30-Mar-14 12-Jul-14 0%Stocking/Disposal/Filling in embankments of Lagoon 90 05-Apr-14 17-Jul-14 0%

    FINAL STAGE 140 16-Aug-14 26-Jan-15 0%Sub base 90 16-Aug-14 29-Nov-14 0%Aggregate base course 90 27-Aug-14 10-Dec-14 0%Kerbs 100 08-Sep-14 03-Jan-15 0%Asphalt Base course 100 14-Sep-14 08-Jan-15 0%Wearing course 90 20-Sep-14 03-Jan-15 0%Road furniture 60 17-Nov-14 26-Jan-15 0%Road marking 30 10-Dec-14 14-Jan-15 0%

    MEP SERVICES 280 02-Mar-14 21-Jan-15 0%Surface rough Grading 10 02-Mar-14 12-Mar-14 0%SEWERAGE WORKS 159 13-Mar-14 14-Sep-14 0%

    Setting out for MEP network 45 13-Mar-14 04-May-14 0%Establishing Temp Dewatering System 60 13-Mar-14 21-May-14 0%Excavation 90 05-Apr-14 17-Jul-14 0%Bedding 90 22-Apr-14 04-Aug-14 0%Pipe Laying 100 10-May-14 02-Sep-14 0%Construction of Manholes 90 10-May-14 21-Aug-14 0%Inspection & Approval to Backfill 90 27-May-14 08-Sep-14 0%Backfilling & Removal of Dewatering 90 27-May-14 08-Sep-14 0%Precommissioning 60 07-Jul-14 14-Sep-14 0%

    STORM WATER WORKS 181 19-Mar-14 16-Oct-14 0%Setting out for MEP network 45 19-Mar-14 10-May-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    01-Jun-1405-Jul-14

    10-Jul-1416-Jul-14

    10-Jul-1416-Jul-1417-Jul-1416-Jul-14

    19-Jul-14

    29-Apr-1403-May-14

    26-May-1401-Jun-14

    04-Jun-1410-Jun-14

    17-Jun-14

    05-Apr-1418-Mar-14

    27-Mar-1429-Mar-14

    12-Mar-14

    04-May-1412-Jul-14

    17-Jul-14

    29-Nov-1410-Dec-14

    03-Jan-1508-Jan-15

    03-Jan-1526-Jan-15

    14-Jan-15

    12-Mar-14

    04-May-1421-May-14

    17-Jul-1404-Aug-14

    02-Sep-1421-Aug-14

    08-Sep-1408-Sep-14

    14-Sep-14

    10-May-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 19 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Establishing temporary dewatering system 60 02-Apr-14 11-Jun-14 0%Excavation 90 20-Apr-14 03-Aug-14 0%Bedding 90 07-May-14 20-Aug-14 0%Piple laying 100 25-May-14 18-Sep-14 0%Construction of chambers 90 25-May-14 07-Sep-14 0%Construction of thurst blocks 90 16-Jun-14 29-Sep-14 0%Inspection and approval to backfill 90 22-Jun-14 05-Oct-14 0%Backfilling and removal of Dewatering 90 28-Jun-14 11-Oct-14 0%Precommissioning 60 07-Aug-14 16-Oct-14 0%

    FIRE WATER WORKS 199 25-Mar-14 11-Nov-14 0%Setting out for MEP network 45 25-Mar-14 15-May-14 0%Establishing temporary dewatering system 60 02-Apr-14 11-Jun-14 0%Excavation 90 28-Apr-14 11-Aug-14 0%Bedding 90 15-May-14 28-Aug-14 0%Construction of chambers 90 09-Jun-14 21-Sep-14 0%Piple laying 100 09-Jun-14 02-Oct-14 0%Construction of thurst blocks 90 30-Jun-14 13-Oct-14 0%Inspection and approval to backfill 90 06-Jul-14 19-Oct-14 0%Backfilling and removal of Dewatering 100 12-Jul-14 05-Nov-14 0%Precommissioning 60 02-Sep-14 11-Nov-14 0%

    DISTRICT COOLING WATER WORKS 149 31-Mar-14 20-Sep-14 0%Setting out for MEP network 30 31-Mar-14 04-May-14 0%Establishing temporary dewatering system 30 02-Apr-14 07-May-14 0%Excavation 60 06-May-14 15-Jul-14 0%Bedding 60 24-May-14 02-Aug-14 0%Piple laying 50 21-Jun-14 17-Aug-14 0%Inspection and approval to backfill 45 08-Jul-14 28-Aug-14 0%Backfilling and removal of Dewatering 50 23-Jul-14 20-Sep-14 0%

    POTABLE WATER WORKS 162 06-Apr-14 12-Oct-14 0%Setting out for MEP network 45 06-Apr-14 27-May-14 0%Establishing temporary dewatering system 60 12-Apr-14 19-Jun-14 0%Excavation 90 14-May-14 27-Aug-14 0%Bedding 90 20-May-14 02-Sep-14 0%Piple laying 100 26-May-14 20-Sep-14 0%Construction of chambers 90 26-May-14 08-Sep-14 0%Construction of thurst blocks 90 01-Jun-14 14-Sep-14 0%Inspection and approval to backfill 90 07-Jun-14 20-Sep-14 0%Backfilling and removal of Dewatering 100 11-Jun-14 06-Oct-14 0%Precommissioning 60 03-Aug-14 12-Oct-14 0%

    IRRIGATION WATER WORKS 179 12-Apr-14 05-Nov-14 0%Establishing temporary dewatering system 60 12-Apr-14 19-Jun-14 0%Setting out for MEP network 45 12-Apr-14 02-Jun-14 0%Excavation 75 20-May-14 16-Aug-14 0%Bedding 75 07-Jun-14 02-Sep-14 0%Piple laying 80 24-Jun-14 25-Sep-14 0%Construction of chambers 90 24-Jun-14 07-Oct-14 0%Construction of thurst blocks 90 30-Jun-14 13-Oct-14 0%Inspection and approval to backfill 90 06-Jul-14 19-Oct-14 0%Backfilling and removal of Dewatering 100 06-Jul-14 30-Oct-14 0%Precommissioning 60 27-Aug-14 05-Nov-14 0%

    ELECTRIAL 141 03-Jun-14 15-Nov-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    11-Jun-1403-Aug-14

    20-Aug-1418-Sep-14

    07-Sep-1429-Sep-14

    05-Oct-1411-Oct-14

    16-Oct-14

    15-May-1411-Jun-14

    11-Aug-1428-Aug-14

    21-Sep-1402-Oct-14

    13-Oct-1419-Oct-14

    05-Nov-1411-Nov-14

    04-May-1407-May-14

    15-Jul-1402-Aug-14

    17-Aug-1428-Aug-14

    20-Sep-14

    27-May-1419-Jun-14

    27-Aug-1402-Sep-14

    20-Sep-1408-Sep-14

    14-Sep-1420-Sep-14

    06-Oct-1412-Oct-14

    19-Jun-1402-Jun-14

    16-Aug-1402-Sep-14

    25-Sep-1407-Oct-14

    13-Oct-1419-Oct-14

    30-Oct-1405-Nov-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 20 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Setting out 45 03-Jun-14 24-Jul-14 0%Excavation 75 03-Jul-14 29-Sep-14 0%Sand Bedding 75 21-Jul-14 16-Oct-14 0%Cable laying 90 02-Aug-14 15-Nov-14 0%Inspection 60 02-Aug-14 11-Oct-14 0%Backfilling 75 07-Aug-14 03-Nov-14 0%

    TELECOM 141 09-Jun-14 20-Nov-14 0%Setting out 45 09-Jun-14 30-Jul-14 0%Excavation 75 09-Jul-14 05-Oct-14 0%Bedding 75 21-Jul-14 16-Oct-14 0%Ducts and Chambers 90 07-Aug-14 20-Nov-14 0%Inspection 60 07-Aug-14 16-Oct-14 0%Backfilling 75 13-Aug-14 09-Nov-14 0%

    GAS LINES 141 15-Jun-14 26-Nov-14 0%Setting out 45 15-Jun-14 05-Aug-14 0%Excavation 60 15-Jul-14 23-Sep-14 0%Bedding 60 27-Jul-14 05-Oct-14 0%Ducts/Gas lines and Chambers 90 13-Aug-14 26-Nov-14 0%Inspection 60 13-Aug-14 22-Oct-14 0%Backfilling 75 13-Aug-14 09-Nov-14 0%

    STREET LIGHTING 185 21-Jun-14 21-Jan-15 0%Setting out 45 21-Jun-14 11-Aug-14 0%Foundation for street lighting 75 31-Jul-14 26-Oct-14 0%Excavation 60 12-Aug-14 20-Oct-14 0%Sand Bedding 60 18-Aug-14 26-Oct-14 0%Cable laying 90 18-Aug-14 30-Nov-14 0%Inspection 60 24-Aug-14 01-Nov-14 0%Backfilling 75 30-Aug-14 24-Nov-14 0%Erection of high masts 60 04-Sep-14 12-Nov-14 0%Testing and commisioning 45 01-Dec-14 21-Jan-15 0%

    SPARE DUCTS 154 31-Mar-14 25-Sep-14 0%Setting out for MEP network 30 31-Mar-14 04-May-14 0%Establishing temporary dewatering system 30 02-Apr-14 07-May-14 0%Excavation 60 06-May-14 15-Jul-14 0%Bedding 60 24-May-14 02-Aug-14 0%Piple laying 50 26-Jun-14 23-Aug-14 0%Inspection and approval to backfill 45 14-Jul-14 03-Sep-14 0%Backfilling and removal of Dewatering 50 29-Jul-14 25-Sep-14 0%

    BUILDING WORKS 237 28-Apr-14 31-Jan-15 0%ELEC POCKET SUBSTATIONS - 10 211 29-Apr-14 30-Dec-14 0%

    Survey & setout 15 29-Apr-14 15-May-14 0%Excavation & Substructure 30 17-May-14 19-Jun-14 0%Structure 90 21-Jun-14 02-Oct-14 0%Building Envelope incdg. Roofing 75 08-Jul-14 02-Oct-14 0%Interior Services & Finishes 90 26-Jul-14 06-Nov-14 0%External Works 45 04-Oct-14 24-Nov-14 0%Install Transformers & Switchgear 46 08-Nov-14 30-Dec-14 0%Test & Commission 31 25-Nov-14 30-Dec-14 0%

    SEWAGE- LIFTING STATIONS 333 28-Apr-14 20-Jan-15 0%Construction of wet well and Manhole 150 28-Apr-14 26-Aug-14 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    24-Jul-1429-Sep-14

    16-Oct-1415-Nov-14

    11-Oct-1403-Nov-14

    30-Jul-1405-Oct-14

    16-Oct-1420-Nov-14

    16-Oct-1409-Nov-14

    05-Aug-1423-Sep-14

    05-Oct-1426-Nov-14

    22-Oct-1409-Nov-14

    11-Aug-1426-Oct-14

    20-Oct-1426-Oct-14

    30-Nov-1401-Nov-14

    24-Nov-1412-Nov-14

    21-Jan-15

    04-May-1407-May-14

    15-Jul-1402-Aug-14

    23-Aug-1403-Sep-14

    25-Sep-14

    15-May-1419-Jun-14

    02-Oct-1402-Oct-14

    06-Nov-1424-Nov-14

    30-Dec-1430-Dec-14

    26-Aug-14

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 21 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP

  • Activity Name OriginalDuration

    Start Finish Performance% Complete

    Construction of valve camber room 30 02-Aug-14 26-Aug-14 0%Piping and Pumps 95 02-Aug-14 17-Oct-14 0%Construction of MCC room 75 26-Aug-14 25-Oct-14 0%External Works 75 25-Oct-14 24-Dec-14 0%Testing and Commsioning 33 24-Dec-14 20-Jan-15 0%

    IRRIGATION- PUMPING STATION 288 22-May-14 08-Jan-15 0%Construction of U/G water tank 60 22-May-14 09-Jul-14 0%Construction of Pump room 60 09-Jul-14 26-Aug-14 0%Construction of MCC room 75 26-Aug-14 25-Oct-14 0%Piping and Pumps 95 26-Aug-14 10-Nov-14 0%External Works 60 25-Oct-14 12-Dec-14 0%Testing and Commsioning 33 12-Dec-14 08-Jan-15 0%

    FIRE- LIFT/PUMPING STATIONS 282 19-Jun-14 31-Jan-15 0%Construction of U/G water tank 60 19-Jun-14 06-Aug-14 0%Construction of Pump room 60 06-Aug-14 23-Sep-14 0%Construction of MCC room 75 23-Sep-14 22-Nov-14 0%Piping and Pumps 95 23-Sep-14 08-Dec-14 0%External Works 60 22-Nov-14 09-Jan-15 0%Testing and Commsioning 33 05-Jan-15 31-Jan-15 0%

    HANDING OVER 48 06-Dec-14 31-Jan-15 0%Final Testing & Commissioning of MEP services 48 06-Dec-14 31-Jan-15 0%

    03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015

    26-Aug-1417-Oct-14

    25-Oct-1424-Dec-14

    20-Jan-15

    09-Jul-1426-Aug-14

    25-Oct-1410-Nov-14

    12-Dec-1408-Jan-15

    06-Aug-1423-Sep-14

    22-Nov-1408-Dec-14

    09-Jan-15

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Summary Page 22 of 22 Date Revision Checked Approved05-Mar-14 REV 00 PCP PCP