8/3/2019 Presentation SE
1/33
-
8/3/2019 Presentation SE
2/33
USER
REQUIREMENTS:
Prepared By:
SAQIB SIKANDER
SAIF-UR-REHMAN
SAQIB JAVAID
USMAN AFTAB
For
Mr. MUKHTAR
INVENTORY AND PROCUREMENT SYSTEM (IPS)
-
8/3/2019 Presentation SE
3/33
It is responsible administrative and management work
assisting the Purchasing Department Director by
insuring the effective and efficient operation of
Purchasing Department procurement and inventory
automation systems. Work is performed withconsiderable independent judgment, discretion and
initiative.
An employee in a position allocated to this class is
responsible for planning, coordinating and
implementing Department/Countywide procurement
and inventory automation systems. This position reports
to the Purchasing Department Director.Work isevaluated based on quality and quantity of results
obtained and observation of overall effectiveness.
OVERVIEW
-
8/3/2019 Presentation SE
4/33
3.4 Non-Functional Requirements
3.4.1 Requisition Process3.4.2 Procurement
3.4.3 Inventory
3.4.4 Disposal
3.1 Functional Requirements
3.1.1 Initiate Requisition
3.1.2 Validate Requisition
3.1.3 Pre-Procurement Process3.1.4 Procurement
3.1.5 Purchase Goods & Services
3.1.6 Invoice Processing/Billing
3.1.7 Inventory Description
3.1.8 Inventory Issuance
3.1.9 Goods Return
3.1.10 Sale & Disposal of Stock3.1.11 Reports
-
8/3/2019 Presentation SE
5/33
3.1.1 Initiate Requisition
3.1.2 Validate Requisition
3.1.3 Pre-Procurement Process3.1.4 Procurement
3.1.5 Purchase Goods & Services
3.1.6 Invoice Processing/Billing
3.1.7 Inventory Description3.1.8 Inventory Issuance
3.1.9 Goods Return
3.1.10Sale & Disposal of Stock
3.1.11Reports
3.1 Functional Requirements
-
8/3/2019 Presentation SE
6/33
3.1.1 INITIATE REQUISITION
Objectives/Overview of Process:
1. To initiate the Requisition process in different departments of Ministry.
2. Requisitions will be project-based (Development Requisition).
3. Annual or Normal Requisition (Non-Development Requisition).
4. The process will provide a Requisition template.
5. The Requisitions will be generated by selecting items from the
inventory (project / Non-Development) and submitted to SO (G), SO (Admin).
6. The Requisition (Development, Non-Development) will be prepared (in high
authority section) by low authority staff like Stenographer, approval
from respective personal assistant in the office will be requiredbefore submission to SO (G) and SO (Admin).
7. A procurement case will be prepared and forwarded to higher
authorities by using Internal Communication module.
8. The system will provide support to save, edit and iterate
Requisition to assist MIT employees.3.
1F
unc
tionalRe
quirements
-
8/3/2019 Presentation SE
7/33
PROCESS CYCLE ( INITIATE REQUISITION)
Prepare Development Requisition
001. Select Project002. Add / Edit Items and Quantities003. Save Requisition004. View User Owned Requisition005. Edit Requisition006. Submit Requisition
Prepare Non-Development Requisition
001. Add / Edit Items and Quantities002. Save Requisition003. View User Owned Requisition004. Edit Requisition005. Submit Requisition
Prepare Annual Requisition
001. Edit Items and Quantities002. View Annual Statistics003. Save Requisition004. View User Owned Requisition005. Edit Requisition006. Approval Cycle
Local Approval Cycle
3.
1F
unc
tionalRe
quirements
-
8/3/2019 Presentation SE
8/33
3.1.2 VALIDATE REQUISTION
Objectives/Overview of Process:
1. The objective of this process is to validate the Requisition and to take an
appropriate action for issuance of fresh Procurement.
2. The validation of Requisition will take multiple policies, logic and decision
making into account before approval or rejection of Requisition.
3. Requisitions fulfilling the criteria of authorization, rules and regulation
are entertained. The Requisitions will be entertained either from
inventory or a new procurement process will be initiated under the rulesof General Financial Rules (G.F.R).
4. The Requisitions that will contain items of different account heads will be
broken to their respective account heads.
5. A procurement case will be prepared if the items are not presented in
inventory. If multiple Requisitions of the same account head will beraised, a single procurement case will be prepared for all of them.
3.
1F
unc
tionalRe
quirements
-
8/3/2019 Presentation SE
9/33
PROCESS CYCLE ( VALIDATE REQUISITION)
Process Requisition001. View Requisitions List
002. View Requisition Details
003. Verify Requisition
004. Decision on Requisition
005. Generate Issuance Request
Prepare Procurement Case
001. Break/Merge Requisitions on account head
002. Approximate Costing
003. Verify from Budget
004. Decision on Procurement
Approval
001. Approval / Rejection
002. Approval Cycle
3.
1F
unc
tionalRe
quirements
-
8/3/2019 Presentation SE
10/33
1.3.3 PRE-PROCUREMENT PROCESS
Objectives/Overview of Process:
1. Pre-Procurement process will be used for establishing the groundwork for
purchasing items against procurement cases.
2. Procurement process will be triggered after the approval of
method/strategy set in this process.
3. Rules and policies will be defined for procurement methods i.e. direct
purchase/petty purchase, quotations and Tenders. In few exceptional
cases, a No Objection Certificate (NOC) will be obtained before Tendering.
4. After the approval of Tender or quotation, subsequent process of
procurement will be initiated.
3.
1F
unc
tionalRe
quirements
References Chapter 8 of G.F.R.
Sample Quotations
Sample Tenders
Functionality Specification document
-
8/3/2019 Presentation SE
11/33
PROCESS CYCLE ( PRE-PROCUREMENT REQUISITION)
Select Policy for Purchase Order flow
001. Amount based Procurement Policy setup
002. View Approved Procurement Cases
003. Select Procurement Method
Process Quotation
001. Generate RFQ (Request for Quotation)
002. Input Received Quotation
003.View Quotations004. Local Verification of Quotations
Process Tender
001. Generate Tender
002. Iterate for Tender Approval
Process Tender after NOC
001. Generate Tender
002. Attach documents with Tender
003. Store NOC Details
Reject Tender
001. Reject Tender
3.
1F
unc
tionalRe
quirements
-
8/3/2019 Presentation SE
12/33
1.3.4 Procurement
Objectives/Overview of Process:1. This process will be used for the selection of Supplier for the current Tender or
Quotation.
2. It consist of several subtasks like evaluation committee formation, preparation of
evaluation criteria, input bids received, bidder evaluation, recording of Minutes of
Meeting till a comparative analysis report will be generated for items and
Suppliers.
3. There will be no restrictions on the number of member in Technical Committee.
4. In most cases SO (G), SO (Admin) or Project Coordinator will be the only members.
Similarly in most cases only one evaluation criteria i.e. cost will be considered.
5. Multiple Suppliers will be selected for a single procurement case.
6. A formal contract will be prepared for the selected Supplier.
7. The contract will not be compulsory but will be required in few cases.
8. The contract will entail all the terms and conditions for the Supplier to agree. If the
Supplier isnot be agreed on terms, next Supplier in comparative analysis will be
given a chance, SO (G), SO (Admin) and Project Coordinator will have the
authority to re-Tender in exceptional circumstances like this.
9. Output of this process will be the Purchase Order for the successful
Suppliers/bidders.3.
1F
unc
tionalRe
quirements
-
8/3/2019 Presentation SE
13/33
PROCESS CYCLE (PROCUREMENT REQUISITION)
Formulation of Technical Committee
001. Select Procurement Case
002. Show Members list
003. Add Member
Evaluation
001. Evaluation Criteria
002. Input Received Bids
003. Evaluate Bidders
004. Minutes of Meeting
005. Generate Comparative Analysis Report
006. Local Verification of Evaluation
Supplier Approval Cycle
001. View Tender/Quotation
002. Send report to appropriate Member for approval
003. View Request for approval004. Approve/Reject
005. Contract Supplier
Generate P.O.
001. Generate Purchase Order
3.
1F
unc
tionalRe
quirements
-
8/3/2019 Presentation SE
14/33
1.3.5 Purchase goodsandservices
Objectives/Overview of Process:
1. The objective of this process is to receive the goods from Supplier in areliable and crystal clear method.
2. To support the cause a Technical Committee will be formulated that will
inspect these goods. There will be no restrictions on the number of members
in Technical Committee.
3. In most cases SO (G), SO (Admin) or Project Coordinator will be the only
member. After inspection a certificate of valid items received will input tosystem.
4. After inspection a certificate of valid items received will input to system. In
case of bad or partial delivery the committee will send the notification to
Supplier for clarification and the bad items back.
5. The Supplier will send a new schedule for delivery. The delivery will berecorded in the system against the Purchase Order.
6. In case of successful completion of delivery a Delivery Challan will be sent to
Supplier by the SO (G), SO (Admin) or Project Coordinator.
7. . If any fraud will be found or the Supplier fails to deliver the items in
schedule SO (G), SO (Admin), Project Coordinator will block the Suppliertemporarily or permanently by Blacklisting the Supplier.
References Chapter 8 of G.F .R
Functionality Specification document
3.
1F
unc
tionalRe
quirements
-
8/3/2019 Presentation SE
15/33
Inspection
Process
001. Technical Committee
002. Goods Evaluation Criteria
003. Issuance of certificate
004. Notification to Supplier
005. Update Delivery Schedule
Process
Received
Goods
001. Update Stock
002. Delivery Challan Receipt
003 Blacklist Supplier
PROCESS CYCLE (PURCHASE GOODS & SERVICES)
Basic Function Breakdown
ID Sub-Functionality
3.
1F
unc
tionalRe
quirements
-
8/3/2019 Presentation SE
16/33
1.3.6 Invoice Processing / Billing
Objectives/Overviews of Process:
1. The purpose of this module is to record and process the invoice provided bythe Supplier.
2. The invoice details (items, quantity, price, discounts) will be inputs and the
scanned image of the invoice sent by Supplier will be kept in the system.
3. SO (G), SO (Admin), Project Coordinator will prepare a case by attaching
relevant documents of procurement that might be useful for Finance Section.
4. The Invoice will be sanctioned and forwarded to Finance Department.
5. The users will use the module to view the invoices and there status of processing.
6. Details of invoice with consolidated documents that generate the invoice
(Requisition, Quotation, Tender, Purchase Order, Delivery Challan and Invoice
details) can be viewed.
7. The module will be coupled with Finance module. Any objection / clarification on
the invoice will be sent by Finance Officer.
8. SO (G), SO (Admin), Project Coordinator will resubmit the invoice by providing
clarification and attaching documents to the invoice case.
9. The module will use Internal Communication to derive the workflows.3.
1F
unc
tionalRe
quirements
-
8/3/2019 Presentation SE
17/33
PROCESS CYCLE (INVOICE PROCESSING/BILLING)
Record
Invoice001. Record Invoice Details
002. Sanction and Submit Invoice
Process
Invoice
001. View Invoices List
002. View Invoice Details
003. Resubmit Invoice
Basic Function Breakdown
ID Sub-Functionality
3.
1F
unc
tionalRe
quirements
-
8/3/2019 Presentation SE
18/33
1.3.7 Inventory Description
Objectives/Overview of Process:
1. The objective of this process is to manage the stock. This process will also
maintain the Suppliers record.
2. The inventory administrator will perform operations. e.g. adding, editing
and deleting items and their specifications under different account
heads/category.
3. Inventory Administrator will also set an upper and lower threshold level and
depreciation of each item.
4. Stock in charge keeps track of the health of items. Inspections will be made
by SO (G), SO (Admin) or Project Coordinator.
5. The inspection result about the health of items will be recorded in the
system.
6. The Inventory Administrator can add, delete, edit and search a Suppliers
record.
7. The Inventory Administrator will also provide the information regarding the
Supplier to item link.
8. Report can also be viewed against Supplier/s.
References Functional Specification document
3.
1F
unc
tionalRe
quirements
-
8/3/2019 Presentation SE
19/33
PROCESS CYCLE (INVENTORY DESCRIPTION)
Manage
Inventory
001. Define Items (Data
Dictionary)
002. Inventory Inspection
Define
Suppliers
001. Add / Edit Supplier
002. Search Supplier
Basic Function Breakdown
ID Sub-Functionality
3.
1F
unctionalRe
quirements
-
8/3/2019 Presentation SE
20/33
1.3.8 Inventory Issuance
Objectives/Overview of Process:
1. This process will cover inventory issuance to the Requestor.
2. Requestor will be the person who raised the Requisition or a contractor etc.
3. SO (G) will generate the issue request and submit it to the stock in charge for
issuance.
4. Issue request will be generated from SO (G) in different cases one at the time
when Requisition will be raised and stock will be available and second after the
procurement of item against the Requisition and goods received; means orderfulfilled.
5. Third in case the Requestor raises Requisition for the replacement of item and
item is available.
6. Once the request is raised, it will be submitted to Stock Incharge and Stock
Incharge will generate the Delivery Receipt for the request and issue goods to
Request Initiator together with delivery receipt that will be signed off by theRequestor after accepting the goods.
7. Stock Incharge will be able to view all the delivery receipts that have been issued
and accepted/signed off by the Requestor for his information. The items can also
be issued from Non-Development to Development department.
8. Items can also be issued to the contractor as per the rule. The contractor has to
pay the recovery rate and other charges.
References Sample Copies of Register maintained in MoIT
3.
1F
unctionalRe
quirements
-
8/3/2019 Presentation SE
21/33
Receive
Issuance
Request
001. View Issuance Request
002. View Issuance Details
Process
Issuance
001. Issue Items
002. Update Stock
PROCESS CYCLE (INVENTORY ISSUANCE)
Basic Function Breakdown
ID Sub-Functionality
3.
1F
unctionalRe
quirements
-
8/3/2019 Presentation SE
22/33
1.3.9 Goods Return
Objectives/Overview of Process:
1. This process aims to maintain the stock record when goods will be
returned when a request is put up for replacement.
2. The SO (G), SO (Admin), Project Coordinator will check the reason to
replace the items and has authority to approve or reject the request.
3. On approval the goods return case will be sent to Stock Incharge. The Stock
Incharge will update the stock for returned items and will enter the status
of returned items i.e. Serviceable or Damaged.
4. If items will need to be replaced, Stock Incharge will generate a Delivery
Goods Receipt and send it to the Request Initiator.
5. The Store Incharge will record the signed receipt. The Request Initiator canview the status of request during the process.
References Sample copies of Register maintained at MoIT
3.
1F
unctionalRe
quiremen
ts
-
8/3/2019 Presentation SE
23/33
PROCESS CYCLE (GOOD RETURN)
Goods
Return
Request
001. Return Goods Request
002. View request status
003. Replacement approval
Update
Stock
001. View Return Goods List
002. Record Returned Items
003. Record Damaged Items
Deliver
Items
001. Delivery goods receipt002. View delivery receipt
Basic Function Breakdown
ID Sub-Functionality
3.
1F
unctionalRe
quiremen
ts
-
8/3/2019 Presentation SE
24/33
1.3.10 Sale and DisposalofStock
Objectives/Overview of Process:
1. The purpose of this module is to record and take an appropriate action on
inventory that will need to be disposed.
2. SO (G), SO (Admin) or project coordinator will develop a case for the items
that will be reported to be obsolete, surplus or unserviceable. The disposalcase will be prepared and sent to the Competent Officer with rights to write
off a loss.
3. Competent Officer will take a decision on the method of disposing the stock
i.e. by auction, sale to officer, other department, or any other decision like
donation, permanently purging the stock.
4. The Competent Officer will sanction the disposal by sale or other wise.
5. The sale and disposal will be recorded and inventory will be issued against
the request submitted.
References Chapter 8 of G.F.R.
3.
1F
unctionalRe
quiremen
ts
-
8/3/2019 Presentation SE
25/33
PROCESS CYCLE (SALE & DISPOSAL OF STOCK)
Basic Function Breakdown
ID Sub-Functionality
Prepare
Disposal
Case
001. View Disposable Stock
002. Generate Disposal request
003. Local Verification of Disposal
Case
004. Submit Request to
Competent Authority
Sanction
Disposal
001. View Disposal Requests
002. View Disposal Request
Content
003. Disposal Decision
Process
Disposal
001. Disposal Action
002. Sales of Surplus to Private
persons of Store003. Sales by Auction
004. to other departments or
authority
005. Other decision taken
Release /
Issue Order
001. Inventory Issue
3.
1F
unctionalRe
quiremen
ts
-
8/3/2019 Presentation SE
26/33
1.3.11 Reports
Objectives/Overview of Process:
1. In order to assist management and decision
makers summarized reports can be displayed.
2. Reports will be generated for different areas
of procurement and inventory management.
3. By just a few clicks a report will be selected
and summarized information of area of
interest e.g. Requisitions, procurements,
Tenders, quotations, issuance etc. will be
displayed.
References Functionality Specification Document
3.
1F
unctionalRe
quiremen
ts
-
8/3/2019 Presentation SE
27/33
View Reports001. View Reports
PROCESS CYCLE (SALE & DISPOSAL OF STOCK)
Basic Function Breakdown
ID Sub-Functionality
3.
1F
unctionalRe
quiremen
ts
-
8/3/2019 Presentation SE
28/33
3.4 Non-Functional Requirements
3.4.1 Requisition Process
3.4.2 Procurement Process
3.4.3 Inventory Process
3.4.4 Disposal Process
-
8/3/2019 Presentation SE
29/33
1. REQUISITION PROCESS
1. Requisitions in development projects are made only against the Project
inventory. The inventory contains only those items that are enlisted in PC-
I document.
2. If any Requisition is raised by supporting staff for the section, it must be
verified by the authorized officer of respective section. e.g. a stenographer
in Secretary office raises Requisition for stationary. It must be verified by
Personal Assistant to Secretary before submission to SO (G), SO (Admin).
3. Partial Requisitions can be fulfilled. In case of partial Requisitions
issuance and procurement cases are generated.
4. Annual Requisitions are based on Stationary account head only. Howeverthe system supports addition of items from different account heads.
5. Procurement is based on the account head defined in FPBS. Therefore,
Requisitions containing items of different account heads must be separated
on the basis of item account heads. Items in Requisitions that belong to
common account head must be consolidated in one procurement case.
6. SO (G), SO (Admin) must be given an interface to finance planning and
budgeting system to verify the procurement.
7. Procurement cases are forwarded to competent officers for approvalaccording to the delegation of powers. The officer can take a decision if
he/she has the power of decision on amount in account head.
8. Approval cycle for the Procurement case can be postponed up-till the
process of Tender or quotation. Complete case will be submitted together
with Tender or quotation.
1.2
Non-Functiona
lRequirem
ents
-
8/3/2019 Presentation SE
30/33
2. PROCUREMENT PROCESS
1. Procurement cases are procured separately depending on the
approximate amounts i.e. for procurements less than Rs. 4000; aPurchase Order is generated directly. For amounts in range of Rs. 4000-
Rs. 40000 a quotation process is initiated. Amounts exceeding Rs. 40000
fall in Tender domain. For even higher amounts e.g. above Rs. 50000 or
any amount threshold set in delegation of power an NOC must be
obtained.
2. Officers (SO (G), SO (Admin) or Project Coordinator) can change the
default course of procurement described above by providing appropriate
reasons to adopt the methodology.3. There are no restrictions on members of Technical Committee i.e. SO
(G), SO (Admin), Project Coordinator. There can be single evaluation
criteria i.e. Cost of procurement. Cost of procurement must be the part
of evaluation criteria.
4. Competent authority has the rights to Reject the Tender initially or
after the selection of Supplier. Multiple Suppliers can be selected
against procurement.
5. In case of fraud or the Supplier is unable to deliver the goods, SO (G),SO (Admin), Project Coordinator can temporarily or permanently black
list a Supplier.
6. Invoices should be entertained with high priority and supporting
documents must be attached.
1.2
Non-Functiona
lRequirem
ents
-
8/3/2019 Presentation SE
31/33
3. INVENTORY PROCESS
1. Nominal issues of inventory must be recorded in the
system.
2. Items are issued to request initiator after he/shesigns the inventory delivery challan.
3. Goods can be issued to development project or any
other department of ministry but follows the same
principles of issuance and receipt.
1.2
Non-Functiona
lRequirem
ents
-
8/3/2019 Presentation SE
32/33
4. DISPOSAL PROCESS
1. Inventory marked as surplus, obsolete or unserviceable
can be disposed after permission of competent
authority who can write off all losses.
2. If surplus goods are to be sold to internal employeesthe officer must provide a reason / clarification to
perform this action.
1.2
Non-Functiona
lRequirem
ents
-
8/3/2019 Presentation SE
33/33