Factors affecting thin coal seam shearer drum coal-loading ...
Presentation fot Coal Loading Operation
-
Upload
adi-sumanto -
Category
Documents
-
view
61 -
download
7
Transcript of Presentation fot Coal Loading Operation
Coal Loading Operation from Pit Stock Pile through hauling road and dump to Pelindo Stock Pile and Loading to Barge
BLACK GOLD ENERGY INDONESIA MINING OPERATION AT RENGAT
INDRAGIRI HULURIAU-INDONESIA
Coal getting
Pit Stock Pile 80km Hauling
Pelindo stock pile
Stocking and crushing
Dolphin Arrangement of Jetty
Dolphin to Accommodate 7000
DWT Barge
Effective operating hours coal getting to pit stock pile receciving = 360 hours
Effective operating hours loading to DT at pit stock pile = 360 hours
Effective operating hauling from pit stock pile to Pelindo = 360 hours
Hauling distance from Primanusa to Pelindo is 80 Km Coal charasteristics : Bulk density : 0,85T/M3 Boulder size : 400 to 300 mm Crush Coal size : 0-50 mm Stock Pile requirements Pit Stock Pile estimate for 7 days minimum Pelindo stock pile expected to received 60,000 mt as Standby Stock Pile. Loading operational 4 hours/ each 7,000 DWT barges Working hours 20 hours/day
Jetty Operational
River SURVEY /BED – BASIC ENGINEERING DESIGN Bathy metri, 35 km a long of river from Kuala Cenaku to Tembilhan Monitoring of water level at three points of area for 15 days Hydrometrics – Check water elevation Current meter Sedimentation check Weather Station – measure wind speed and rain leverages Cross section of river surrounding of loading jetty Hydrology Loading Jetty/Stock Pile and Coal Handling System – Sub structure – Basic
Engineering Design Topography for 12 Ha of area Bathymetry Survey Soil Investigation : deep bore hole and sondir and laboratories test for soil for total of 12
point Conceptual design – Civil- for Sub structure and Loading Jetty, mechanical refer to Coal
Handling Design Utilities building Reclamation and soil improvement study and calculation for Pressure load of stock pile
up to 60,000 MT Barging Study from Kuala Cenaku up to Mother Vessel
Survey and Engineering Study
Coal loading onto 10 DT at Pit Stock pile
10 Tons DT through 80 km hauling road to Pelindo stock pile
Coal Dump at Pelindo Stock Pile
From stock pile coal to be crush,and load to barge with conveyor
Loading operation to the barge
Pelindo Stock Pile and Laoding Facility
MESS,OFFICE AND HOUSING AT PELINDO STOCK PILE
Flow of coal Laoding at Pelindo Stock Pile
1 2
3 4
Weight bridge
Stockpile no.1
Stockpile no.2
Hauling truck entering Pelindo
stock pile
Raw Coal number 1 and 2 with
30,000 MT Capacity/each
total of 60,000 MT
Conveyor No. 2
Conveyor No. 1
Raw Coal then load to chain feeder and
crushing
Existing Jetty Indragiri River
Raw Coal load onto feeder breaker and
roller crusher then through
tranfer conveyor load
to loading conveyor
2000t/hours
1234
5
6
Conveyor Parts :1. Feeder
Breaker2. Chain feeder3. Vibrating
Screen4. Roller
Crusher5. Transfer
Conveyor6. Hopper7. Loading
Conveyor
Stockpile No.2
Stockpile No.1
Dol
phin
Indragiri River
Existing Jetty
Laoding to 7,000 mt barge with loading
conveyor 2000 t/hours capacity
Land clearing and dozing 11 ha area to be used – Pelindo or BGEReclamation and soil stabilization for stock pile – Pelindo or BGEFencing all Pelindo property Pelindo or BGEPermit for Constrction for Jetty/CHF Pelindo or BGEIf new Amdal need to be donePelindo or BGEConstruction of all facilities,stock pile,CHF,JettySoil protection at edges of river
Scope of Responsibility for Pelindo Stock Pile Development
Autocad drawing by : Ir. Aan Pujiandi Animation by : Robby Kurniawan
S.Kom
Flow diagram by : Ir.Adi Sumanto
Thanks for viewing this presentation
Presented By BGE Construction Team