Page 1: Presentasi Pemeriksaan Kapal Tanker

Joanne Song

Vetting & Clearance Superintendent

BP Marine Risk Assurance

INTERTANKO Vetting Seminar11 October 2011

Page 2: Presentasi Pemeriksaan Kapal Tanker

2

It is all about reducing the risk to BP

target

Develop a core fleet that will deliver for BP’s

asset requirements

objective

no accidents, no harm to people

no damage to the environment

Owned and TC spot

BP Shipping controls: improve global tanker standards in the

industry by influencing through:

pool of vessels used by BP

improve quality by

tankers used by BP

• oil majors

• ship owners

• legislation

• setting standards– age

– double hull policy

– operational requirements

– operating procedures

– manning training

• confirmed by– inspection

– management audit

– structural review

• design

• build

• operation

• procedures

• maintenance

• people

• deployment

• disposal

• T/C assurance

Page 3: Presentasi Pemeriksaan Kapal Tanker

3

Stephen Alexander USA

Tim AshbyEMEA

Andrew RayapanAspac

BP Shipping Vetting & Clearance Team

Patrick JosephManager – Global Vetting & Clearance

Page 4: Presentasi Pemeriksaan Kapal Tanker

4

Control quality to minimise risk

Strategic Operational Influencing

IMO

TSCFOCIMF

Flag/PortState

Legislation

Owned

Set standards-Audit-Vetting

Design-Operation-Audit

Shipping

policies

Balance riskreward

Voyage chartered

Time CharteredSet standards-Operations-Audit

Raise standards soBP quality control not req’d

Control of Shipping Risk

Page 5: Presentasi Pemeriksaan Kapal Tanker

5

SHIP INSPECTIONS

SIRE REPORTS

PSC INSPECTIONS

Company Assessment

OWNER REPUTATION

The Vetting Decision

YESNO

More inforequired

The Ship Vetting Decision

Page 6: Presentasi Pemeriksaan Kapal Tanker

6

BP Inspection and 3rd Party SIRE

SIRE INSPECTION REPORT REQUIREMENT

From 1 January 2012, when a vessel is proposed for BP employment, unless otherwise notified, the vessel must have:

a) a current SIRE inspection report i.e., one that is less than 6 months old; and

b) a BP SIRE inspection report that is less than 24 months for vessels that are less than 15 years old; or

c) a BP SIRE inspection report that is less than 12 months for vessels that are older than 15 years old.

Page 7: Presentasi Pemeriksaan Kapal Tanker

7

How do we look at a SIRE report

A report with a factual record of the vessel’s condition and standard of operation at the time of the inspectionand, in turn, allow an assessment of the risk that use of the vessel might pose.

What is in a SIRE report?

therefore . . .

Page 8: Presentasi Pemeriksaan Kapal Tanker

8

OWNER REPUTATION

SHIP INSPECTIONS

SIRE REPORTS

PSC INSPECTIONS

TERMINAL FEEDBACKS

CHARTER FEEDBACKS

CASUALTY DATA

Company Assessment

The Vetting Decision

YESNO

More inforequired

The Ship Vetting Decision

Page 9: Presentasi Pemeriksaan Kapal Tanker

9

Incident Notification and Investigation

No proper

investigation and Root

Cause analysis

[email protected]

All crew members’ fault

Planned/Un-planned

maintenance shut

down vs Incident

Master onboard did not give

a factual report about the

incident at the 1st place.

Delay in Notification

Page 10: Presentasi Pemeriksaan Kapal Tanker

10

OWNER REPUTATION

SHIP INSPECTIONS

SIRE REPORTS

PSC INSPECTIONS

TERMINAL FEEDBACKS

CHARTER FEEDBACKS

CASUALTY DATA

FLAG CHANGES

MANNING/MANAGEMENT CHANGES

CLASSIFICATION SOCIETY CHANGE

MARKET INTELLIGENCE

Company Assessment

The Vetting Decision

YESNO

More inforequired

STRUCTURAL ASSURANCE

The Ship Vetting Decision

Page 11: Presentasi Pemeriksaan Kapal Tanker

11

Structure Assessment - Criteria

Type Class documents CAP with

fatigue

CAIP

Vessel up to 15 years of age

Vessel greater than 15 years of age and less

than 20,000 dwt

Vessels greater than 15 years of age and

greater than or equal to 20,000 dwt

Vessels greater than 15 years of age and

greater than or equal to 20,000 dwt involved

in TAPS trade (USA)

LNG carriers, over 20yrs, CAP with critical

area inspection & Fatigue analysis

Barges

Page 12: Presentasi Pemeriksaan Kapal Tanker

12

We aim to ensure that ships fixed on BP Group business are maintained above the Class minimum requirements.

• Condition Assessment Program (CAP) Report

• CAIP USA select vessels ONLY

• IMO CAS (not in lieu of CAP but in addition to)

• Class reports including Enhanced Survey Programme (ESP) File, Survey Status, Special Survey, Docking Survey etc reports

• Structural drawings

• Owners PMS inspection reports, Photographs etc.

• UTM Reports

• Shipyard Steel Repair Reports

• Physical structural survey by Naval Architects

Structure Assessment - Tools

Page 13: Presentasi Pemeriksaan Kapal Tanker

13

• Close up survey report including colour photos

• Class status report and examination of historical records

• Thickness measurements records

• Structural Strength Calculations

• Fatigue analysis

CAP – What we are looking for . . .

Page 14: Presentasi Pemeriksaan Kapal Tanker

14

OWNER REPUTATION

SHIP INSPECTIONS

SIRE REPORTS

PSC INSPECTIONS

TERMINAL FEEDBACKS

CHARTER FEEDBACKS

CASUALTY DATA

FLAG CHANGES

MANNING/MANAGEMENT CHANGES

CLASSIFICATION SOCIETY CHANGE

MARKET INTELLIGENCE

Company Assessment

The Vetting Decision

YESNO

More inforequired

STRUCTURAL ASSURANCE

The Ship Vetting Decision

Page 15: Presentasi Pemeriksaan Kapal Tanker

15

Working together for a cleaner environment and safer shipping

Thank you !