Prepared by- Er. Dipesh Pandey December 2014. CONTENTS Introduction Activities in Road Construction...
-
Upload
joella-kelley -
Category
Documents
-
view
219 -
download
0
Transcript of Prepared by- Er. Dipesh Pandey December 2014. CONTENTS Introduction Activities in Road Construction...
Prepared by- Er. Dipesh Pandey
December 2014
CONTENTSIntroduction
Activities in Road Construction
Tools, Equipment and Plant
Earthwork
Mass Haul Diagram
Definition
Activities to change existing ground to designed shape, grade and provide necessary facilities for
smooth, safe and efficient traffic operation,
including reconstruction of existing road.
Activities in Road ConstructionEarthworksite clearance, E/W in filling, E/W in excavation,Excavation for borrow pit,Excavation for foundation,Disposal of surplus
Drainage Work
Side drains, Culverts, Sub surface
drain, Causeway Minor bridge
Structural WorkEarth retaining str, Gully control works,Land slide
stabilization,River training works,Bridge protection
worksPavement WorkSub grade
preparation,Sub-base, Base course andWearing course
Miscellaneous Work
Road Ancillaries
Traffic sign/signal, markings
Boi-engineering works
Tools, Equipment and PlantToolsHand shovel, Chisel, Peak, Spade, Hand Rammer, Brushes, Trowel, Wheel Borrow
Compaction Equipmentsmooth wheel roller, vibrating roller, pneumatic roller, sheep foot roller, different capacity rammers
EquipmentEarth Moving
EquipmentDozer, Scraper, Loader, Excavator, Backhoe, Dragline, Clamshell, Trench diggerLeveling Equipment
Motor GraderPaving Equipment
Binder storage tank with heating device, binder spreader, aggregate spreader, cement concrete mixture, bituminous mechanical paver, cement concrete paver
Cont.…
Miscellaneous Equipment
Rock driller, Core Cutter, Edge cutter
Transporting EquipmentDumping trucks, Flat body trucks, mini dumper
Lifting EquipmentLoader, Backhoe, Different capacity
crane Leveling EquipmentMotor Grader
Paving EquipmentBinder storage tank with
heating device, binder spreader, aggregate spreader, cement concrete mixture, bituminous mechanical paver, cement concrete paver
Plants Cement concrete plant, Asphalt concrete plant, cold mix plant, Aggregate crushing plant, Screening plant,
Cont.….
EarthworkProcess to prepare sub grade level bringing it to
design grade and shape
may be in embankment and filling
Quantity based on longitudinal and cross section
Mass haul diagram necessary to decide economic haul
E/W quantities are estimate based on L and X sections
Site ClearanceStarted just after survey works and before any
construction works
Clearing of grass, weeds, bushes, shrubs
Removal of existing trees, stumps and roots along the road alignment
Removal of existing structures along right of way
Earthwork in FillingNecessary when we have to raise the sub-
grade from existing ground level
Reasons:To keep sub-grade high from ground water
table
To prevent damage due to surface and capillary rise
To maintain vertical alignment
Design elements:Height, Fill material, Settlement, Stability of foundation, Stability of slope
Equipment: Grader, Roller, Tripper and water tanker or
manually for small project
Construction steps:Laying layer by layerGrading each layerAttaining desired density before next layer is
placedThe thickness of the layers may vary between
10 to 30 cm depending on various factors such as soil type, equipment, specifications etc.
Quality ControlChecking of suitability of filling materialChecking of field moisture and dry density of each
layer (> 93 % for below and > 95% for above)Proper finishing of formation slope as per design
E/W in Excavation
In the process of cutting or loosening and removing earth including rock from its original position, transporting and dumping it as a fill or spoil bank.
Also includes excavation for side drains
Earth excavation work may be divided as excavation or cutting, grading and compaction.
Design ElementsDepth, Stability of foundation, Stability of slopes, Accommodation of road side drain
•Equipment Grader, roller, tipper and water tanker
Construction StepsExcavation Grading of sub-grade layerCompaction with roller
• Quality Control Fixing reference pegs Checking field moisture and dry density Proper finishing of formation slopes
Field Control of compaction Measurement of moisture content Measurement of max. dry density
corresponding to optimum moisture content
Planning of E/WMass haul DiagramEarthwork for a highway project involves cuts
and fills.
The most balanced design is one which utilizes the cut volumes in the adjacent fills.
This is achieved by a mass haul diagram which is a graphical representation of amount of cut and the fill and the manner in which the earth is to be hauled from cut to fill.
Planning of E/W Mass haul Diagram
The ordinate at any station along the MHD indicates the earthwork quantity accumulated up to that point, and is the summation of the differences between cut and fill.
The maximum (+) ordinate indicates a change from cut to fill (D) and the minimum (-) ordinate indicates from fill to cut (A and G).
Upward sloping curves indicate (rising left to right) indicate a cut
Downward sloping (falling left to right) curves occur in a fill section
peaks indicate a change from cut to fill and valleys occur when the earthwork changes from fill to cut
If the curve has steep slope it indicates heavy cuts or high fills. Flat slopes indicate small earthwork quantities.
The balance point is defined as a point where the volume in excavation balances the volume in embankment.
Any line drawn parallel to the base line and intersecting two points within the same curve indicates a balance of cut and fill between these two points ( C and D). Such a line (HJ) is called a balancing line.
Haul: it has dual meaning. Distance over which material is moved and also the volume distance of material used.
Free haul: The certain amount of haulage is included in the earthwork rate itself and the contractor is expected to carry earth over this haulage within his quoted rate.
Over haul: the haulage over the free haul distance paid for extra rate called over haul.
Economic over haul: the economic over haul distance can be determined by equating the cost of roadway excavation plus overhaul and tipping in embankment with the cost of borrow pit material plus excavation, haul and wasting of roadway material within the free haul distancea= cost of roadway excavation per cu. m.b= cost of overhaul and tipping per cu. m. c = cost of borrow material per cu. M.L= economic overhaul distance in stationsa + b x L = c + a
L= c/b
Thank you