Pre-Installation Instructions Check List · Pre-Installation Instructions & Check List ... Clamps...

8
200544 D Pre-Installation Instructions & Check List Note: You must complete and return the check list on the last page of these instructions in order to schedule set-up and training for your TD-100. Manufactured By: 6810 Kitimat Rd, unit 1 Mississauga, ON L5N-5M2 Phone: (800) 701-7450 Phone: (905) 826-6330 Fax: (905) 826-3288

Transcript of Pre-Installation Instructions Check List · Pre-Installation Instructions & Check List ... Clamps...

200544 D

Pre-Installation Instructions

&

Check List

Note: You must complete and return the check list on the last page of these instructions in order to schedule set-up and training for your TD-100.

Manufactured By:

6810 Kitimat Rd, unit 1

Mississauga, ON

L5N-5M2

Phone: (800) 701-7450

Phone: (905) 826-6330

Fax: (905) 826-3288

2 of 8 200544 D

Introduction

Before beginning this installation, make certain that you have read and understand

these instructions. If you are uncertain of any of these requirements please call

Customer Service at Phoenix Airmid Biomedical (800) 701-7450. This installation

should conform to your local building code requirements and be performed by

qualified personnel. Upon completing the Pre-Installation, send photos and

completed check list on the last page to Phoenix Airmid Biomedical.

CAUTION! Failure to follow the instructions could result in voiding

the warranty.

TD-100 Pre-Installation Kit is intended for use by building engineering to

prepare the room for the TD-100.

Space Planning

Your TD-100 is a floor standing unit that is secured to the wall using brackets that

are provided. Make sure to allow space beside and above the TD-100 as shown in

figures 1 and 2.

Figure 1. Typical Setup for the TD-100.

3 of 8 200544 D

The on/off switch, electrical and fluid connections are on the left side of the TD-

100 and will require at least 6” of clear space. Where possible the right side should

allow at least 6” for the probe connector bracket as shown in figure 1.

Figure 2. Mounting and space requirements.

If you plan to have additional equipment installed with your TD-100 please plan

for the additional space at this time.

Electrical Planning

A 20 Amp hospital grade GFCI receptacle is required near the TD-100. The TD-

100 comes with a 6’ cord that attaches near the top left side. The receptacle must

be within reach of the cord.

4 of 8 200544 D

Plumbing Planning – Water Supply

A high quality COLD potable water source that meets Federal Clean Water

Standards at the point of use is necessary. The water source must be regulated to

20-25 psi. The source must be within 8’ of the left side or 6’ of the right side of

the TD-100.

Plumbing Planning – Drain

The drain is one of the most important parts to the TD-100s fume management

system. The drain has two jobs to do with the TD-100, first is to carry off the

waste fluids and second is to help contain the smell of the disinfectant. The TD-

100, a trap, drain fitting with the drain filter having a direct connection to the riser

is the ideal setup.

Given practical limitations, the TD-100 may have to share a drain or connect to a

lateral. If TD-100 shares a drain connection the TD-100 should be after any shared

traps and the lowest connection on the shared drain line to prevent fumes from

escaping from the other drains. See figure 3.

“S” traps and good pitch may allow other drain configurations to work. Remember

that the key is not to allow the liquids from the TD-100 to accidentally run into

another trap that is open to the room.

Items included in Pre-Installation Kit

Match all the items in the kit with those on the list below. If any items are missing

or damaged, immediately contact CS Medical.

Item Part # Quantity Pre-Installation Instructions 200544 1

Drain Fitting 200498 1

Drain filter 200499 1

Quick Disconnect ¼” MNPT 200500 1

5 of 8 200544 D

Materials Required but not Supplied

Description Quantity P-Trap 1-1/2” (that will accept 1-1/2” PVC) 1

Water shut-off valve 1

Pressure Regulator (Watts 263A) ¼” NPT outlet 1

Pressure gauge for regulator (0-60 psi) 1

Assorted pipe As Req

Clamps to secure the plumbing installation As Req

Installation Step 1 – Install the GFCI Receptacle

A hospital grade GFCI receptacle is required where the TD-100

™ will be plugged

in. The receptacle should be located as close as possible to the TD-100™

(Six foot

power cord supplied with TD-100).

The following diagram is a typical installation. Please place items in Pre-

Installation Kit as needed to meet the installation requirements shown in the

diagram.

Figure 3. Electrical and Plumbing Locations.

6 of 8 200544 D

Installation Step 2 – Assemble the Drain Fitting

Assemble the 1½” drain and P-trap as shown below; making sure that the top of

the pipe is no higher than 18”. See figure 3. Cement (or attach with a Fernco

coupling or similar) the drain fitting PN 200498, supplied in Pre-Installation kit to

the P-trap as shown below.

Installation Step 3 – Place the Drain Filter on the Drain Fitting

Place the drain filter PN 200499 on top of the drain fitting as shown in below. DO

NOT CEMENT. This filter is intended to be replaced.

CAUTION! DO NOT BOND THE DRAIN FILTER IN PLACE. IT

IS INTENDED TO BE REPLACED.

Drain Fitting

P/N 200498

Drain Filter

P/N 200499

7 of 8 200544 D

Installation Step 4 – Regulated Water Supply

Install a water pressure regulator (Watts 263A recommended) to a high quality

potable COLD water supply (high quality potable water will meet the federal clean

water standards at the point of use) with a shut-off valve. Adjust regulator outlet

pressure to 20-25 psi static. Install the quick disconnect fitting (PN 200500). The

flow rate should be a minimum of 1gpm @ 20 psi.

Installation Step 5 – Schedule Set-up and Training

Email photos showing the completed area including the plumbing preparation

along with the completed check list for the TD-100 to [email protected] to

schedule your set-up and training.

You may also fax the completed Pre-Installation Check list to Phoenix Airmid

Biomedical to schedule your TD-100 set-up and training. FAX# (905) 826-3288.

Quick Disconnect

P/N 200500

8 of 8 200544 D

TD-100 PLUMBING & ELECTRICAL INSTALLATION CHECKLIST

MAINTENANCE /ENGINEERING CONTACT

FACILITY___________________________

NAME:______________________________

PHONE:_____________________________

VERIFY INSTALLATION REQUIREMENTS BY CHECKING THE BOXES

PLEASE CALL PHOENIX AIRMID BIOMEDICAL WITH ANY QUESTIONS

REGARDING THE INSTALLATION REQUIREMENTS. (800) 701-7450

CHECK

� Unit able to be positioned within 6’ of the drain and water supply from the

right side of the TD-100 or 8’ of drain and water supply from the left side of

the TD-100.

� 120 VAC, 20A, 60Hz hospital grade GFCI outlet within reach of 6’ cord.

� P-Trap installed according to Installation Step 2.

� Drain fitting (P/N 200498) installed on P-Trap.

� Drain vent filter (P/N 200499) installed on Drain Fitting.

� Shut-off valve installed on water line.

� Water pressure regulator installed and regulated to 20-25psi, with a

minimum flow of 1 gal/ min.

� Quick disconnect fitting (P/N 200500) installed.

� Email photos of completed area for the TD-100 including the plumbing and

electrical preparations to: [email protected]

Comments:

Fax completed checklist to Phoenix Airmid Biomedical (905-826-3288) to schedule set-up

and training for your TD-100.