Mining for the Future. Appendix B: Mine Closure Working Paper
Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility...
Transcript of Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility...
![Page 1: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/1.jpg)
Pre-Feasibility Report of the ESI Closure Working Group June 2014
![Page 2: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/2.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 2
Table of Contents
Table of Contents .................................................................................................................................. 2
List of Figures ........................................................................................................................................ 3
List of Tables ......................................................................................................................................... 3
1 Executive Summary ....................................................................................................................... 4
1.1 Overview ................................................................................................................................ 4
1.2 Standardized Closure Criteria for Mine Site Relinquishment ................................................... 4
1.3 Passive Systems to Reduce / Eliminate the Effects of ARD .................................................... 4
1.4 Project Selection and Risk Assessment .................................................................................. 5
2 Introduction .................................................................................................................................... 5
2.1 Background ............................................................................................................................ 5
2.2 Project Involvement ................................................................................................................ 6
2.3 Project Schedule .................................................................................................................... 7
2.4 Project Selection Workshop .................................................................................................... 7
3 Pre-feasibility Study Objectives .................................................................................................... 8
4 Problem Statements ...................................................................................................................... 8
4.1 Standardized Criteria for Mine Site Relinquishment ................................................................ 8
4.2 Passive Systems for Acid Rock Drainage ............................................................................... 9
5 Standardized Closure Framework for Relinquishment .............................................................. 10
5.1 Overview .............................................................................................................................. 10
5.2 Saskatchewan ...................................................................................................................... 10
5.3 Québec ................................................................................................................................ 13
5.4 Ontario ................................................................................................................................. 15
5.5 British Columbia ................................................................................................................... 16
5.6 Alberta ................................................................................................................................. 17
5.7 Gaps in Current Practice ...................................................................................................... 21
5.8 Conclusion ........................................................................................................................... 24
6 Passive Treatment Systems for Acid Rock Drainage ................................................................. 24
6.1 Existing Systems .................................................................................................................. 24
6.2 Advancement in Technology and Development .................................................................... 42
6.3 Gaps in Technology and Research ....................................................................................... 47
7 Project Selection Workshop ........................................................................................................ 50
7.1 Overview .............................................................................................................................. 50
7.2 Risk Assessment .................................................................................................................. 51
7.3 Assessment Criteria ............................................................................................................. 54
7.4 Conclusions / Recommendations.......................................................................................... 54
8 References ................................................................................................................................... 55
![Page 3: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/3.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 3
List of Figures
Figure 1 – Typical Alberta well site ........................................................................................................ 19
Figure 2 – Stages of Closure Planning .................................................................................................. 22
Figure 3 – General Selection Process for ARD Passive Treatment Systems.......................................... 26
Figure 4 – Selection Criteria for Passive Treatment Technologies ......................................................... 27
Figure 5 – Free Water Surface Constructed Wetland............................................................................. 28
Figure 6 – Constructed Wetland Cells Showing Potential Flow Paths .................................................... 29
Figure 7 – Anaerobic Wetland Treatment System.................................................................................. 31
Figure 8 – Anaerobic Wetland Treatment System.................................................................................. 31
Figure 9 – General Schematic of a Vertical Flow Wetland System ......................................................... 32
Figure 10 – Sulfate-reducing Bioreactor System .................................................................................... 33
Figure 11 – Schematic of Anoxic Limestone Drains ............................................................................... 35
Figure 12 – Schematic View of a Limestone Diversion Well ................................................................... 36
Figure 13 – Limestone Leach Bed Treatment System ........................................................................... 37
Figure 14 – Slag Leach Bed Treatment System .................................................................................... 37
Figure 15 – Cross-Sectional of a Permeable Reactive Barrier ............................................................... 38
Figure 16 – Microbial Fuel Cell for ARD ................................................................................................ 43
Figure 17 – Schematic of Microbial Fuel Cell for ARD ........................................................................... 43
Figure 18 – GaRDS Bioreactor (Taylor et al. 2005: 31). ......................................................................... 44
Figure 19 – Installation of Low Permeability Well and Drainage system. ................................................ 45
Figure 20 – Risk Assessment Components ........................................................................................... 51
Figure 21 – Likelihood-Consequence Risk Matrix .................................................................................. 52
List of Tables
Table 1 – Closure Working Group Members ............................................................................................ 7
Table 2 – CEMA Proposed Reclamation Criteria ................................................................................... 20
Table 3 – Phytoremediation Technologies ............................................................................................. 39
Table 4 – Risk Assessment Results for the Standardized Closure Criteria for Relinquishment ............... 53
![Page 4: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/4.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 4
1 Executive Summary
1.1 Overview
This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three
working groups of the Environmental Stewardship Initiative (ESI) of the Canada Mining Innovation Council
(CMIC).
The objective of the report is to determine the initial feasibility of two project concepts:
1. Standardized closure criteria for mine site relinquishment
2. Passive systems to reduce / eliminate the effects of acid rock drainage (ARD)
1.2 Standardized Closure Criteria for Mine Site Relinquishment
Mine closure is an amorphous concept with no defined end point in many instances, which is often
related to the environmental regulatory environment and the application by regulators. The lack of
defined relinquishment criteria can lead to the management of sites in perpetuity. Should the company
dissolve or mineral rights leases and/or permits expire, the responsibility for closure and rehabilitation
would then revert to the Crown.
The development of standardized closure criteria will provide a clear path to achieving the end-goal
of relinquishment. In turn, this will provide certainty for operators and stakeholders regarding mine
closure, will allow for more progressive rehabilitation planning and implementation, and will help reduce
the incidence of abandoned mines accruing to the Crown.
All jurisdictions provide for the return of mine sites to the Crown, although the legislation and
regulations differ across jurisdictions. Some jurisdictions (e.g. Saskatchewan) have comprehensive
programs for relinquishment, while most others have brief stipulations in environmental legislation. The
legislation / regulations differ based on liability, specific requirements, and financial assurances (among
others). However, despite most jurisdictions having de jure stipulations for relinquishment, very few
recently closed mines have been returned to the Crown. One jurisdiction – Alberta – has developed
standardized criteria and associated indicators for the return of oil sands sites to the Crown.
The main gaps related to achieving mine site relinquishment fall under two general categories:
Legislative / regulatory; and, Technical in mining, reclamation, and closure practices.
1.3 Passive Systems to Reduce / Eliminate the Effects of ARD
ARD has the potential to be one of the costliest environmental effects affecting the mining industry.
The greatest potential risk of ARD to the receiving environment is the sulphate and metal contamination
associated with the low pH leaving operational and closed sites and entering surface water and ground
water.
![Page 5: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/5.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 5
Practices to stop / treat ARD are typically divided into either ‘active’ or ‘passive / semi-passive’
treatment. Passive systems are generally considered attractive to stop / treat ARD due to their lower costs
of construction, operation, and maintenance, as well as their ability to operate at remote locations with
limited operational requirements (MEND 1999: 1).
Some 15 predominant passive / semi-passive systems were identified and recent advancements
related to ARD management were also presented. Additionally, some of the major gaps related to the
operation of the above systems across Canada were identified, including:
Existing reliance on treatment in perpetuity;
System performance in cold / winter climates; and
Long-term performance and maintenance.
The CWG determined that there were outstanding issues uncovered as part of the pre-feasibility
research (including the gaps outlined above). These issues need to be further addressed before an
appropriate risk assessment is possible.
Accordingly, the ESI plans to work in conjunction with a graduate student under the guidance of a
professor specializing in passive systems for ARD. Once the research is completed, it is anticipated that a
more thorough risk assessment would be conducted that will enable the group to make a
recommendation as to whether or not the project should be taken to the feasibility level.
1.4 Project Selection and Risk Assessment
A project selection workshop was held to assess the two project concepts and determine which
should be taken to the feasibility level. As part of the workshop, a risk assessment was conducted for the
closure criteria project, which uncovered some risks that may prevent the project from succeeding.
Management responses were formulated to mitigate these risks.
Based on the results of the workshop, the Closure Working Group made a recommendation that a
feasibility study should be conducted for the standardized closure criteria project. The study will being in
June 2014 and should be completed by end-2014.
2 Introduction
2.1 Background
The Environmental Stewardship Initiative (ESI) of the Canada Mining Innovation Council (CMIC) is
an industry-led consortium comprised of approximately 25 members from industry and government.
Initiated in early 2012, the ESI’s mandate is to develop – through step-change technological innovation,
project development, and multi-stakeholder collaboration – solutions to some of the myriad
environmental, sustainability, and competiveness issues facing the Canadian mining industry.
![Page 6: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/6.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 6
The first phase of the ESI’s work was for Hatch Ltd to complete a scoping study outlining some
potential areas where environmental research, development, and innovation are required.1 Several multi-
stakeholder surveys were also conducted in September 2012 to ascertain stakeholder needs and priorities
in terms of research and innovation. Based on the results of the studies and ongoing collaboration through
CMIC workshops, the following concepts were selected for project development under the aegis of three
ESI working groups:
Water Working Group (WWG)
Integrated remote sensor for surface / groundwater quality and quantity monitoring,
including baseline, operations, and post-closure monitoring;
Database / repository of water resources information (i.e. physical, chemical, and
biological properties);
Tailings Working Group (TWG)
Production of benign tailings (i.e. stabilization or removal of contaminants prior to
placement);
In situ stabilization / remediation of contaminants within existing tailings;
Closure Working Group (CWG)
Development of a standardized framework for closure criteria; and,
Reduction / elimination of the effects of acid rock drainage.
The following pre-feasibility study represents the second phase of project development for the CWG.
2.2 Project Involvement
The pre-feasibility study reports for each working group were prepared by an individual, independent
consultant of CMIC in collaboration with the above working groups. In-kind contributions were provided
by the members of the ESI as members of the respective working groups, including document review and
input, meetings, and workshop participation. The composition of the closure working group is presented
in Table 1 below.
1 http://www.cmic-ccim.org/wp-content/uploads/2013/07/HatchScopingReport1.pdf
![Page 7: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/7.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 7
TABLE 1 – CLOSURE WORKING GROUP MEMBERS
MEMBER ORGANIZATION
Robert Holmes (Chair) Government of Yukon
Mark Thorpe (ESI Chair) Golden Star Resources
Scott Davidson New Gold
Mike Aziz Goldcorp
Heather MacDonald CH2M HILL
Karen Chovan Independent
Robert Reisinger CH2M HILL
Bryan Schreiner Saskatchewan Research Council
Ian Wilson Saskatchewan Research Council
Heli Aatelma Government of Yukon
2.3 Project Schedule
The pre-feasibility work started in January 2014 following some initial work in late 2013 and was
conducted over the course of approximately four months. Ongoing meetings / workshops were conducted
among ESI members (typically monthly) and among the individual working groups beginning in 2013. An
in-person workshop was conducted in early March 2014 in Toronto to review preliminary pre-feasibility
work towards completion of the pre-feasibility studies. Culminating workshops involving working group
members were held in May 2014 to assess the results of the studies and to select projects for further
project development.
It is planned that the feasibility study will be conducted immediately following the completion of the
pre-feasibility study and should be completed within 2014. Additional project development activities will
be outlined as part of this work.
2.4 Project Selection Workshop
A culminating, in-person workshop was held among the members of the CWG in Vancouver on 13
May 2014. The primary purpose of the workshop was to finalize the results of the pre-feasibility study,
which enabled the group to make a decision as to the initial feasibility of the project concepts. To do so,
the workshop was organized around two primary exercises:
1) Conducting a risk assessment of the projects
2) Screening the projects against assessment criteria to allow for prioritisation
In turn, the workshop enabled the group to determine the preliminary elements of the subsequent
feasibility studies. A summary of the workshop is presented in Section 7.
![Page 8: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/8.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 8
3 Pre-feasibility Study Objectives
The objectives of the pre-feasibility study are as follows:
Introduce the selected subjects; Identify associated challenges and risks; Determine optimal pathways for future activities; and, Select projects that will provide accessible step changes in the mining business.
The selected projects will then undergo feasibility analyses. These analyses will allow the ESI to
further prioritize its focus areas with the aim of developing a comprehensive development program
directed by industry through CMIC.
Lastly, the studies will serve as a basis for attracting stakeholder support and funding for the ESI’s
ongoing project development activities, including support from industry, government, and academia
(among others).
4 Problem Statements
4.1 Standardized Criteria for Mine Site Relinquishment
Mine closure involves decommissioning and rehabilitation activities that are conducted – typically
progressively – in preparation for the cessation of mining and processing activities at a particular site.
These activities are carried out in accordance with mine closure plans, which are required by most
jurisdictions before the start of mine development activities. Mine closure and asset retirement
obligations are updated as mining proceeds. Mine closure plans aim to ensure that sites are restored to a
suitable post-mining land-use in which the risks to the receiving environment and human health and
safety are minimized. Financial assurances are usually required by governments with the aim of ensuring
that funding is available for the associated costs of the closure and rehabilitation activities.
Although all mining companies are engaged in such activities, mine closure and rehabilitation remains
an amorphous concept with no defined end in many instances. This is often related to environmental
legislation. Detailed closure planning and the associated implementation activities are also often deferred
by operators to later in the operational life of the mine. The lack of a defined end can lead to management
of the sites in perpetuity, and, should the company dissolve or mineral rights leases and/or permits expire,
the responsibility for closure and rehabilitation reverts to the Crown. Evidence of this can be seen in the
number of abandoned and orphaned mine sites across all jurisdictions in Canada (i.e. 10,000+) (NOAMI
2010: 2).
Based on the lack of certainty that sites can be relinquished in many jurisdictions, CMIC members
prioritized the development of a closure and rehabilitation criteria framework with the end goal of
rehabilitated site relinquishment to the Crown. All jurisdictions allow for relinquishment to take place
(nine through a legislative act), although in reality this is rarely achieved. For example, in Ontario, no mine
site has been relinquished under the current regulatory framework (a review process is now underway).
In Saskatchewan, there is an Institutional Control Program (ICP) for mine and mill site relinquishment that
![Page 9: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/9.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 9
has been effectively used for the relinquishment of five uranium mine sites and one gold mine site. The
Saskatchewan program may serve as a model for the development of the proposed closure and
rehabilitation framework.
Critical to achieving an accepted framework is greater front-end emphasis on mine closure and
rehabilitation. Specifically, a major implementation gap identified in preliminary work was limited
consideration – including technical, financial2, and operational – for mine closure and rehabilitation in the
early stages of mine development evaluation (i.e. preliminary economic assessments, feasibility studies,
etc.). Doing so would allow for an increased understanding of rehabilitation and closure needs and
requirements (including costs) resulting in a more accurate assessment of project economics and long-
term project viability. In turn, costly, unforeseen events related to rehabilitation and closure can be better
accounted for and more effectively managed.
Ultimately, the overriding goals of developing the proposed standardized framework are a reduction
in environmental and socioeconomic risks and associated costs, a reduction in adverse environmental
effects (including costly, unforeseen liabilities), a more secure investment environment, and the
promotion of stakeholder / public confidence for mining.
The overall objectives of mine closure are to:
Prevent or minimise risks to human health and safety;
Minimise adverse long-term environmental, physical, social, and economic impacts;
Achieve water quality objectives;
Create a stable landform suitable for some agreed-upon subsequent land use;
Develop a site that is suitable for return to the Crown.
4.2 Passive Systems for Acid Rock Drainage
Acid rock drainage (ARD) has the potential to be one of the costliest and most severe environmental
impacts associated with a mine’s development, operation, and closure. The cost of ARD remediation at
mine sites in North America has been estimated in the tens of billions of dollars with many individual
mines facing post-closure ARD liabilities upwards of tens of millions of dollars (GARD Guide n.d.). The
greatest potential risk of ARD to the receiving environment is the sulphate and metal contamination
associated with the low pH leaving operational and closed sites and entering surface water and ground
water.
ARD has the potential to continue indefinitely. In fact, many Roman-era mines continue to produce
ARD to this day. Thus, there is the possibility of ARD-affected water requiring treatment in perpetuity,
which inevitably entails high financial costs associated with the work required to remove the potential
contaminants.
2 For example, a reliance on discounted cash flow return on investment (DCFROI) may encourage the postponement of reclamation and closure costs, thereby discouraging progressive reclamation.
![Page 10: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/10.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 10
Accordingly, industry best practice for the management of ARD has an initial focus on avoidance and
prevention. Where avoidance is not possible, and where it is deemed that the processes can be managed
such that the environmental attenuation limit will not be exceeded, a variety of treatment / mitigation
practices have been developed.
Typically, these practices are divided into either ‘active’ or ‘passive / semi-passive’ treatment; active
treatment typically involves the addition of alkaline chemicals to neutralize the acidity, whereas passive /
semi-passive treatment involves reliance on biological, geochemical, and gravitational processes (Zipper
et al. 2011).
The focus of the following study will be on passive treatment systems. These systems are generally
considered attractive to stop / treat ARD due to their lower costs of construction, operation, and
maintenance, as well as their ability to operate at remote locations with limited operational requirements
(MEND 1999: 1). In a survey conducted by MEND (Zinck and Griffith 2013: 13-17), passive treatment
systems were found to have the lowest associated capital expenditures among the ARD treatment
systems that are used across Canadian mining sites. Lastly, consideration will be given to technologies
that promote walkaway / relinquishment closure scenarios, which will tie in with the first component of
this pre-feasibility work (i.e. standardized framework / criteria for closure).
5 Standardized Closure Framework for Relinquishment
5.1 Overview
Many jurisdictions around the world – including all jurisdictions in Canada – allow for the return of
mining lands to the Crown after a site has been closed out. However, very few of these jurisdictions have
an established regulatory framework for achieving this. As mentioned, an exception to this is
Saskatchewan’s ICP. This program, as well as additional examples from other Canadian and world
jurisdictions, may serve as models for the development of the proposed framework. By understanding the
criteria through which particular sites were able to be returned to the Crown (or relevant body), it is
desired that standardized criteria and hand-over mechanisms can be developed that can be applied to all
Canadian jurisdictions.
The following sections outline the legislation and associated processes for mine site relinquishment
for the major mining jurisdictions in Canada. A specific focus is given to the Saskatchewan ICP given its
comprehensiveness.
5.2 Saskatchewan
Overview of Legislation
The Reclaimed Industrial Sites Act (RISA) and its associated regulations were enacted in 2007 to
“establish a uniform framework for returning Crown land held under surface lease back to the Province
when industrial activities have been completed” (Saskatchewan Ministry of Energy and Resources (MoER),
2012: ii). The development of the act and regulations involved extensive consultation with various
![Page 11: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/11.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 11
stakeholders, including the Canadian Nuclear Safety Commission (CNSC), the mining industry, Aboriginal
organizations, and the communities in the major mining regions of the province. According to the MoER
(2012: ii), the program was initiated to ensure the “health, safety, and well-being of future generations,
provide greater certainty and closure for the mining industry, [and to] recognize past-stated […] provincial,
national, and international obligations for the storage of radioactive materials”.
To date, six sites have been accepted into the ICP, including five former uranium mine sites and one
former gold operation (all in 2009). From 2012-2017, the MoER expects that two more sites will make
applications for acceptance into the program.
Primary Components
The two primary components of the ICP are the Institutional Control Registry (ICR) and the
Institutional Control Funds (ICFs). The ICR maintains a formal record of closed sites, manages the ICFs, and
performs any required monitoring and maintenance work. This is in accordance with federal and
provincial obligations under the International Atomic Energy Agency (IAEA) Joint Convention on the Safety
of Spent Fuel Management (MoER 2009: 6). There are two separate funds comprising the ICF, namely the
Institutional Control Monitoring and Maintenance Fund (ICMMF) and the Institutional Control Unforeseen
Events Fund (ICUEF). The former is the primary funding mechanism for the ICP, while the latter covers
events such as the failure of a containment dyke, collapse of a pit wall, shaft cover degradation, or a
change in regulatory requirements.
Regulatory Process for Relinquishment
In the context of rehabilitation, closure, and decommissioning activities, mining operations in
Saskatchewan are subject to similar environmental regulations as other Canadian jurisdictions.
Specifically, project proponents are required to submit a conceptual decommissioning and reclamation
plan as part of their initial environmental assessment to the MoER, which may require federal review
under the Canadian Environmental Assessment Act (CEAA). Once the proponent receives federal and
Ministry approval for the project, a detailed decommissioning and closure plan is submitted for review
and approval by the Minister. Financial assurances are also required, as are detailed reviews of the plans
(typically every 5 years, or, 12 months preceding the closure of a facility) (MoER, 2009: 4).
After the cessation of mining and processing activities, and upon completion of the approved
decommissioning and reclamation activities, the site enters a period of ‘transition phase monitoring’,
during which the operator is required to continue monitoring the site at their own expense. The operator
is also required to post financial assurances sufficient to cover the cost of any outstanding obligations, as
well as a contingency for any unexpected occurrences. During this phase, the operator “remains fully liable
for any impacts the site may have on the environment, surrounding communities, and public safety”
(MoER, 2009: 5).
If the site performs in accordance with the decommissioning and reclamation plan, and achieves the
predicted stability (i.e. chemical, biological, and physical stability) during the transition phase, the
operator may make an Application for a Release from Decommissioning and Reclamation. This releases
![Page 12: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/12.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 12
the company from monitoring and maintenance responsibilities and from the obligation to maintain
financial assurances (although not entirely). Upon approval of the release, the operator may then apply
for a release from its surface lease, which allows for the transfer of custodial responsibility for the property
to the ICP (MoER, 2009: 5). At that time, should the site holder also own the mineral rights associated
with the closed site, the site holder also surrenders those rights to the Minister (MoER 2009: 8).
The federal Canada Nuclear Safety Commission (CNSC) oversees the process for uranium mine sites,
as much of the jurisdiction regarding uranium regulations falls under the purview of the federal
government. This includes regular monitoring of the site activities during the transition phase as well as a
requirement that the CNSC approve the site for acceptance into the ICP by ceasing to regulate the
property.
A site holder cannot be granted complete absolution for site responsibility. The Environmental
Management and Protection Act (EMPA) “provides for absolute liability of a person for a discharge to
continue indefinitely” (MoER 2009: 11). No authority to grant such absolution is provided for in this or any
other relevant provincial legislation. Furthermore, should the site require additional remediation work
that was not accounted for in the plans, additional funds will be required to be posted (CNSC 2013b: 11-
12).
Lastly, planned revisions to the Act and Regulations will allow for the transfer of custodial
responsibility from the ICP to a new company, thereby transferring all current and future liabilities
associated with the site (MoER 2009: 16).
Discussion
A driving force behind the establishment of the ICP was Canada’s international obligations as a
“Contracting Party” to the International Atomic Energy Agency (IAEA) Joint Convention on the Safety of
Spent Fuel Management and on the Safety of Radioactive Waste Management. As the MoER states, as a
Contracting Party to the Convention, “Canada is required to take the steps to ensure that an appropriate
institutional control framework is in place to address the long-term management of decommissioned
uranium mine / mill facilities in Saskatchewan” (MoER 2009: 6).
Furthermore, the history of uranium mining in Saskatchewan may have provided a further incentive
for the establishment of such a program. Historically, a large portion of uranium mining in Saskatchewan
was conducted by Eldorado Mining and Refining Limited (Eldorado).3 Eldorado operated as a federal
Crown corporation beginning in 1943 and continued mining uranium – mostly in Saskatchewan – until
1982. In 1988, Eldorado merged with the provincially Crown-owned Saskatchewan Mining Development
Corporation (SMDC) to become Cameco, which is now the province’s largest uranium producer. As part
of the asset-transfer agreement, the federal government retained financial liability for environmental
impacts at the Beaverlodge sites through a newly-formed Crown corporation, Canada Eldor Inc. Through
3 The company became known as Eldorado Nuclear Limited in 1965.
![Page 13: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/13.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 13
a licensing agreement, Cameco became responsible for carrying out reclamation and monitoring activities
at the sites (Webster & Hockley 2013: 3).
Of the six total mine sites that have been accepted to the ICP, five of them are former uranium sites
that were operated by Eldorado at its Beaverlodge properties.4 Moreover, many of the sites that are slated
to apply for acceptance to the program are former Eldorado sites (Webster & Hockley 2013). Because the
federal government retained liability for many sites, this may have provided some impetus for the
establishment of the ICP. This is supported by the fact that, although industry may develop a framework
for relinquishment, the driver behind accepting it is, ultimately, governments (i.e. the Crown). The number
of abandoned / orphaned mine sites in Saskatchewan is also small as compared to other Canadian
jurisdictions (i.e. British Columbia, Ontario, and Quebec), which may have enabled the government’s
capacity to manage the incoming mine sites.
Furthermore, the uranium sites that have been accepted are relatively benign (Webster and Hockley
2013: 5). The gold mine site that was accepted to the ICP is also relatively small (i.e. production of
190,000 ounces over a four year mine life from 1994-98).5
5.3 Québec
Overview of Legislation
In Québec, mine operators may apply for a ‘certificate of release’, which releases a company from
any further reclamation, closure, and post-closure obligations. This is provided for under Division III
(Protective Measures and Rehabilitation Measures) of the Québec Mining Act. Specifically, section 232.10
states:
The Minister may release any person from his obligations under sections 232.1 to 232.7 and issue to
him a certificate to that effect,
(1) if the Minister is satisfied that the rehabilitation and restoration work has been completed
in accordance with the rehabilitation and restoration plan approved by the Minister, and if no
sum of money is due to the Minister with respect to the performance of the work; and
(2) if the Minister is satisfied that the condition of the land affected by the mining activities no
longer poses a risk for the environment or for human health and safety and, in particular, poses
no risk of acid mine drainage.
The Minister may also release a person from the obligations set out in sections 232.1 to 232.7 and
issue a certificate to that effect if the Minister agrees to let a third person assume the obligations.
4 There are 68 additional Beaverlodge sites that have not been admitted to the program. Additionally, the gold mine site that was accepted into the program was the Contact Lake gold mine, which was operated by the SMDC. 5 The sum that was posted to cover the monitoring was CAD$30,000.
![Page 14: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/14.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 14
Additionally, under Section 232.12, the operator will still be responsible for any environmental
liabilities associated with the site. Specifically,
Nothing in sections 232.1 to 232.11 shall affect or restrict the application of the Environment
Quality Act (chapter Q-2).
Discussion
The above legislation has only been in force since early 2014 following amendments made to the
Québec Mining Act in late 2013 that included amendments to the process through which the operator of
a mine may be granted a certificate of release. The new legislation is stricter than the previous version of
the Mining Act, which read as follows:
232.10. The Minister may release any person from his obligations under sections 232.1 to 232.7
and issue to him a certificate to that effect,
(1) where he agrees to letting a third person assume the obligations;
(2) where, in his opinion, the rehabilitation and restoration work has been carried out in
accordance with the rehabilitation and restoration plan approved by him and no sum of money
is due to him with respect to the performance of the work and, where there are tailings, they
no longer present any risk of acid mine drainage. 1991, c. 23, s. 65.
Under the previous legislation, approximately 11 sites were relinquished to the Québec Crown
(Bienvenu 2014: personal communication). The relinquishments took place prior to 1985 and, since then,
no sites have been relinquished. In fact, no applications have been made to the Crown to do so since 1985,
likely because acceptance conditions under the legislation are not close to being met (Ibid).
In the new legislation, Section 232.10 (2) was added and is the biggest change related to
relinquishment. The language in the paragraph, specifically that, “the condition of the land affected by
the mining activities no longer poses a risk for the environment or for human health and safety”, appears
to be rather restrictive. The new legislation also stipulates that for a site to receive a certificate of release
the site “must not pose a risk of acid mine drainage” rather than just the tailings site not posing a risk, as
stipulated by the previous legislation.
It is too early to discern how the legislation will affect future applications for a certificate of release,
as the act was passed in December 2013, although it may be more difficult to obtain the certificate (Gagne
and Kazaz 2009).6 This makes the possibility of obtaining a certificate of release problematic in Québec
given that under the previous legislation, few sites actually obtained a certificate. Reference was only
6 Reference is made to a 2009 publication by lawyers of Fasken Martineau, despite the amendments to the bill being passed in late 2013. This is because the changes to the legislation regarding relinquishment are the exact same as those proposed in 2009 by the Liberal Government. Those amendments failed to pass in the National Assembly although they did pass as part of Bill 70 on 9 December 2013.
![Page 15: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/15.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 15
found to two sites, namely the Iron Ore Company of Canada’s Schefferville mine site and Adventure
Mining’s Lucien Beliveau gold mine site.
5.4 Ontario
Overview of Legislation
Ontario provides for the return of mining lands and / or rights under Section 149 (Surrender by
Agreement) of the Ontario Mining Act. Specifically,
The Minister may refuse to accept a voluntary surrender of mining lands or mining rights under
section 183 if he or she has reasonable grounds for believing that a proponent has failed to
rehabilitate the site in accordance with a filed closure plan or, if no closure plan has been filed,
in accordance with the prescribed standards for site rehabilitation.
Furthermore, under Section 149 (1),
The Minister may accept a surrender of mining lands from a proponent on the conditions
specified by the Minister if,
(a) the project relating to the mining lands is closed out; or
(b) the project relating to the mining lands is not closed out only because it is subject to long-
term maintenance and monitoring by the proponent.
The act provides for a special purpose account that the Minister may use to conduct any
necessary rehabilitation and / or monitoring work that is required. Lastly, under Section 149
(4),
Despite subsections 7 (1) and 8 (1) and sections 12, 18, 43, and 44 of the Environmental
Protection Act, a proponent who surrenders mining lands under the section is not liable under
these provisions.
Discussion
A mine site or mine lease has yet to be surrendered to the Ontario Crown under the above provisions,
despite the provisions coming into force partially in 1996 and fully in 2001. A Ministry of Northern
Development and Mines (MNDM) review process began in 2010, although this process has yet to be
completed (NOAMI 2013: 18). However, details of a MNDM draft policy have been made available to
NOAMI. The draft policy highlights general criteria that should be met for an operator to be released from
a site / lease. Specifically,
“The surrendering [of a mining site or lease] is predicated on the fact that these lands have
been rehabilitated as per an accepted closure plan. The closure plan has as its main goals the
removal of human health and safety hazards, the removal or securing of environmental
contamination and mine wastes, the long-term protection of the environment, and the return
of lands to some productive land use. If a proponent has met the requirement of their closure
![Page 16: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/16.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 16
plan and is willing to compensate the Crown sufficiently for those items requiring long-term or
perpetual maintenance on the site, then the Ministry will consider the issuance of an exit
ticket.” (NOAMI 2013: 17)
The draft policy also highlighted Section 149 (4) of the act regarding “no liability” after surrender.
The draft policy states, “It is this permanent shift of environmental responsibility from the private owner
to the public that ultimately the Crown must be concerned” (NOAMI 2013: 18). This provision is evidently
a major roadblock to successful surrender of mining lands / leases. One can reasonably assume that for a
site to be surrendered, the operator would have to demonstrate with a very high level of confidence that
the risks posed by the site – to human beings, ecosystems, and the environment – are nearly zero.
Otherwise, the Crown, and ultimately taxpayers, would become liable for the potential deleterious
impacts of these risks, in contrast to the liability stipulations in other jurisdictions in Canada.
5.5 British Columbia
Overview of Legislation
The British Columbia Mines Act establishes the Health, Safety, and Reclamation Code (HSR Code),
which has as one of its main components the key rehabilitation, decommissioning, and closure
requirements of mining companies. The HSR Code contains a provision for the “release of obligations”
under the Mines Act. This is the closest example of mine site relinquishment / lease surrender to the
Crown. Section 10.7.31 of the HSR Code states:
If all conditions of the act, code and permit have been fulfilled to the satisfaction of the chief
inspector and there are no on-going inspection, monitoring, mitigation or maintenance
requirements, the owner, agent or manager will be released from all further obligations under
the Mines Act.
Under provincial legislation, responsible parties (RPs) (i.e. mine owners and mine operators) are
“absolutely, retroactively, and jointly and severally liable for clean-up costs” (Packee and Bandopadhyay
2001: 184, quoting Overholt 1996). Thus, all RPs are financially responsible for all environmental
degradation following closure “regardless of whether the original mining remediation activity complied
with the laws of the day or with permits held at the time of the activity” (Ibid). Absolute liability also
precludes due diligence defenses. Given these stipulations, it follows that a closed mine in British
Columbia is never a closed mine for liability purposes (Ibid).
Discussion
No examples of a company being released from any of their environmental obligations were
uncovered as part of the research for the study. This is likely due to the policy and legislative environment
in British Columbia, which does not appear to be conducive to the practice despite a formal stipulation in
the legislation.
As stated in the legislation, a site must not have “on-going inspection, monitoring, mitigation or
maintenance requirements”. However, most, if not all mine sites will have, at the very least, some
![Page 17: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/17.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 17
inspection, monitoring, mitigation, and / or maintenance requirements. To be eligible, it appears that a
site would have to be a literal ‘walk-away’ site, namely one that, aside from an initial monitoring period,
would not require further attention. Current rehabilitation and closure activities may not be at a stage
whereby a walk-away scenario can be achieved except perhaps for marginally affected sites.
Furthermore, as Packee and Bandopadhyay (2001: 183-4) note, the long-term liability requirements
outlined in the previous section are the strictest among all Canadian jurisdictions. In fact, they are among
the strictest of the major mining jurisdictions in the world at the time of the survey.
5.6 Alberta
Overview of Legislation
The Alberta Government introduced reclamation certificates in 1963 to promote reclamation of
privately disturbed lands and in 1978, the program was expanded to include public lands. In 2003, the
program was revised to its current form (Alberta Government 2013).
Under the provincial Environmental Protection and Enhancement Act, 2000 (EPEA, 2000), all
industrial operators are required to conserve and reclaim disturbed land and obtain a reclamation
certificate (EPEA 2000: Section 137(1)).7 There are different classes of reclamation certificates, although
in order for a site to be released or surrendered to the Crown, a site must be “certified reclaimed” (EPEA
2000: Section 144(1)) (Alberta Government 2009).
The EPEA is underpinned by the Conservation and Reclamation Regulation (CRR 1993, 2013). The CRR
defines the overarching aim of reclamation activities, namely to obtain “equivalent land capability”, which
is defined as:
“the ability of the land to support various land uses after conservation and reclamation is
similar to the ability that existed prior to an activity being conducted on the land, but that the
individual land uses will not necessarily be identical.”
The Government of Alberta – through the Alberta Energy Regulator – has also established the
Enhanced Approval Process (EAP) Integrated Standards and Guidelines, which are given effect under the
EEAP. Under the EAP, reclamation outcomes are delineated that are to be met for the issuance of a
reclamation certificate. These are:
Return disturbed land to equivalent capability;
Promote prompt re-vegetation of disturbed lands;
Re-vegetate disturbed land to target the establishment of a self-sustaining, ecologically
suitable species, integrated with the surrounding area;
Conserve soils and minimize loss of land productivity; and,
Re-establish the original landform and drainage.
7 There are a few minor exceptions to this under Section 15.1(1) of the CRR. However, these exceptions are immaterial to this study.
![Page 18: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/18.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 18
Given the second bullet above, and given that oil sands mining occurs primarily in complex wetland
ecosystems of boreal swamps, bogs, and peatland fens, specific wetland guidelines have also been
established by the Government of Alberta. In the Provincial Wetland Restoration Compensation Guide
(2007), restoration is defined as the “re-establishment of a naturally occurring wetland with a functioning
natural ecosystem whose characteristics are as close as possible to conditions prior to drainage or other
alteration.”
The CRR also defines the liability stipulations after the issuance of a reclamation certificate.
Specifically, industry is liable for all surface reclamation issues (e.g. topography, vegetation, soil texture,
drainage, etc.) for the first 25 years following the issuance of a certificate and industry is required to
resolve any reclamation issues that arise within that period. Once the 25-year period has expired, liability
reverts to the government, although liability for contamination issues remains with the company in
perpetuity (Alberta Government 2013).8
Lastly, reclamation certificates that have been granted are subject to amendment and / or
cancellation. Specifically, under Section 139 of the EPEA:
(1) The Director or an inspector may
(a) amend a term or condition of, add a term or condition to or delete a term or condition from
a reclamation certificate if the Director or the inspector considers it appropriate to do so,
(b) cancel a reclamation certificate issued in error,
(c) cancel a reclamation certificate where no reclamation inquiry was conducted prior to the
issuance of the certificate and the Director or the inspector is of the opinion that further work
may be necessary to conserve and reclaim the specified land to which the certificate relates, or
(d) correct a clerical error in a reclamation certificate.
(2) The Director or the inspector shall promptly give notice of any amendment, addition,
deletion or cancellation to the same persons to whom a copy of the original reclamation
certificate was given under section 145.
(3) Where a reclamation certificate is cancelled under this section, then for the purposes of this
Part it is considered never to have been issued.
Discussion
No case of a metal mine obtaining a certificate of release was uncovered as part of the research for
this study nor was an example of a coal mine site. The closest site to obtaining one is the Gregg River
Mine, although it is estimated that reclamation objectives will take another 10-15 years to complete
(Cowan 2013: 32). The greatest number of sites that have obtained a reclamation certificate are upstream
8 The relevant section of the CRR is Section 15(1-3).
![Page 19: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/19.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 19
oil and gas well sites9, although these have marginal reclamation and rehabilitation requirements as
compared with mining operations (see Figure 1). These sites are also administered under a separate
program.
FIGURE 1 – TYPICAL ALBERTA WELL SITE (McIntosh 2014)
In 2008, Syncrude’s Gateway Hill site – a 1.04 km2 former overburden dump – became the first oil
sands site to be certified reclaimed and issued a full reclamation certificate by the Government of Alberta.
One of the biggest challenges identified in achieving reclamation goals in Alberta – and ultimately
obtaining a reclamation certificate from the government – is that the criteria for doing so are unclear
(Purdy & Richens 2011). In response to this, the Cumulative Environmental Management Association
(CEMA), a multi-stakeholder research group based in the Regional Municipality of Wood Buffalo and
comprised of 50+ members from industry, regulatory agencies, Aboriginal communities, and non-
governmental organizations (among others), developed the Criteria and Indicators Framework for Oil
Sands Mine Reclamation Certification.
The framework outlines 16 criteria and 44 corresponding indicators that are recommended for use
in determining whether a reclamation certificate should be issued. The criteria are divided amongst three
overarching reclamation objectives, which are as follows:
Objective 1: Reclaimed landscapes are established that support natural ecosystem
functions
9 Hundreds of these sites have received the certificates.
![Page 20: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/20.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 20
Objective 2: Natural ecosystem functions are established on the reclaimed landscape
Objective 3: Reclaimed landscapes support an equivalent land capability appropriate to
the approved end land uses
Based on these objectives, the following criteria were agreed upon:10
TABLE 2 – CEMA PROPOSED RECLAMATION CRITERIA
CEMA PROPOSED RECLAMATION CRITERIA
1.1 The landforms are integrated within and across lease boundaries.
1.2 The landforms have a natural appearance.
1.3 The landscape and its landforms incorporate watershed features such as surface drainage, lakes and wetlands.
1.4 The landforms have geotechnical stability.
1.5 Reclamation materials are placed appropriate to the landform.
1.6 Terrestrial and aquatic vegetation common to the boreal forest is established.
2.1 The reclaimed landforms have the required water quality.
2.2 The reclaimed landforms have the required water quantity.
2.3 Nutrient cycling is established on the reclaimed landscape.
2.4 Ecosystem productivity is established on the reclaimed landscape.
2.5 Reclaimed ecosystems display characteristics of resilience to natural disturbances.
3.1 The reclaimed landscape provides for biodiversity.
3.2 The reclaimed landscape provides commercial forests.
3.3 The reclaimed landscape provides for fish and wildlife habitat.
3.4 The reclaimed landscape provides opportunities for traditional uses.
3.5 The reclaimed landscape provides opportunities for recreational uses.
According the CEMA website, the organization is a “key advisor” to the provincial and federal
governments, with a role of “producing recommendations and management frameworks pertaining to
the cumulative impact of oil sands development in northeastern Alberta, which are, once complete,
forwarded to the Provincial and Federal regulators”. It is unknown what the response is to these
recommendations and whether the Government of Alberta plans on incorporating them into the
regulatory frameworks outlined above.
Another challenge in achieving reclamation goals and reclamation certificates is the stipulation that
ecosystems are to be reclaimed to a self-sustaining state. As mentioned, oil sands mining occurs primarily
in complex wetland ecosystems of boreal swamps, bogs, and peatland fens that were formed over the
course of thousands of years and harbor a large amount of biodiversity. The challenge of restoring
peatland fens is of particular importance given the size of the losses (Rooney et al. 2011) and given the
fact that there is little to no direct precedent for restoring peatland fens (Struzik 2014, quoting Suncor
officials; Purdy & Richens 2011). Until recently, it was thought that recreating peatland fens was
10 The criteria are numbered according the numbered objective.
![Page 21: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/21.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 21
impossible (Struzik 2014). Pilot projects are being undertaken, which have showed promising initial
results, although estimates for wetland reclamation range between CAD$3 billion and CAD$14 billion
(Struzik 2014, quoting Foote).
5.7 Gaps in Current Practice
As evidenced by the above research, a gap in regards to mine site relinquishment in Canada is the
gap in the legislative and regulatory process. Despite all Canadian jurisdictions having de jure stipulations
for relinquishment, very few mine sites have actually been returned to the Crown.
Relevant legislation regarding mine site relinquishment oscillates between two extreme across
Canadian jurisdictions, from ‘strict’ in British Columbia to ‘lenient’ in Ontario.11 In British Columbia, for an
operator to be released from their obligations under the Mines Act, the site must not have “on-going
inspection, monitoring, mitigation or maintenance requirements”. Furthermore, all jurisdictions – with
the exception of Ontario – still stipulate that liability will continue even upon surrender of the mine site
to the Crown, usually in perpetuity. Rather, the provincial government will merely monitor the site and
carry out necessary (likely minimal) reclamation efforts whose costs have been provided for through
appropriate financial mechanisms.
Conversely, under the relevant legislation in Ontario, all liability associated with a mine site will revert
to the Crown upon the site’s relinquishment. This was acknowledged by the Ontario government itself as
a major roadblock to achieving relinquishment (Cowan 2013: 17-18).
In Alberta, where a more comprehensive legislative and policy framework is in place,12 technical gaps
exist that must be overcome before the provincial government will be in a position to accept the return
of mine sites on a larger scale. This notion can be generalized across jurisdictions. Some jurisdictions, such
as Saskatchewan, will not accept sites if active water treatment is required, for example. Another example
is Quebec, where mines must not present a risk of ARD. Thus, closure and rehabilitation practices – which
encompass the associated technologies, operational controls, and current mining methods (among many
other factors) – are likely not at a stage whereby corresponding closure scenarios are acceptable to the
risk appetite of governments such that they would be willing to take the majority of mine sites back.
Notwithstanding this, it is anticipated that the development of the standardized criteria will help to drive
the development of these technologies towards regulatory acceptance for relinquishment.
Another gap that exists is the lack of reliability of closure models / scenarios, although this is rarely
stated or recognized (Maest et al. 2005: 41). The lack of reliability is due to myriad factors, including, but
not limited to, the level of detail available for closure planning (ICMM 2006; see Figure 2), changing
regulatory requirements, and the ability (or lack thereof) to accurately capture uncertainties. On this latter
point, Goodbody (2013: 45, quoting Weeks) notes,
11 ‘Strict’ and ‘lenient’ are used loosely to describe liability stipulations. 12 To be sure, many regulatory gaps still exist, such as the development of closure and reclamation criteria that were outlined above. As mentioned, it is unknown if these criteria have been accepted and operationalized by the government, although it does not appear to be the case.
![Page 22: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/22.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 22
“especially in closure, where there can be pressure to make predictions for periods of time
that are far beyond what is seen in most other areas of engineering practice, there is often a
lack of understanding of the variance or error in model outputs. These may be much greater
than realised by some model users, and could make some model outputs so unreliable as to
be redundant”.
Given these difficulties, it becomes similarly difficult to accurately assess long-term closure costs,
including after a site is closed out. In turn, this affects the ability to accurately provide funding for
reclamation and closure activities. Struizk (2014, quoting Bayley) uses the Environmental Protection
Security Fund in Alberta to illustrate this. To date, the fund has US$875M in bonded assets for more than
70,000 ha of disturbed land; however, other estimates calculate the reclamation and closure costs at over
US$14B. This gap likely reduces the willingness of governments and stakeholders to accept relinquishment
on a large scale.
FIGURE 2 - STAGES OF CLOSURE PLANNING (Starke 2008)
![Page 23: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/23.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 23
Another gap that exists is the lack of emphasis on comprehensive, up-front closure planning activities
(i.e. closure planning early in the mine life development cycle). This includes incorporating detailed closure
planning and costs into pre-operations activities (i.e. preliminary economic assessments (PEAs), pre-
feasibility studies, detailed feasibility studies, etc.). To be sure, closure planning has become more
integrated into the early stages of mine design and development, as evidenced by the “design for closure”
approach introduced in the 1980s. However, a paradigm shift is perhaps needed towards, to borrow
Cowan’s (2013: vi) phrase, “design for relinquishment”. The development of the criteria will help to fill
this gap given that there will be a defined end that practitioners and managers can work towards; by
knowing the end goal, mine design and management can be tailored towards achieving it.
Similarly, up-front (i.e. baseline) data collection is also critical to achieving successful mine closure
and ultimately relinquishment, especially for biodiversity and ecosystem rehabilitation, which are
becoming ever-important components of mine reclamation and closure (e.g. the Albertan regulations
described above). As the CMIC / Hatch scoping study (2013: 31) notes, “achieving objectives and targets
for biodiversity in closure are dependent on baseline information and datasets collected from project pre-
development”. The report (quoting Lloyd 2002 and ICMM 2006: 30) also notes general challenges
associated with biodiversity data. Specifically,
“one of the major constraints to the effective management of biodiversity is the scarcity of existing
scientific data regarding the way biodiversity changes in response to disturbance. To date, much of
the potentially useful information from large-scale management activities taking place during
operations of a mining project has been rendered unusable due to a lack of formal experimental
design such as a lack of controls and replication, changes in techniques and technologies over time,
and a lack of basic before and after monitoring datasets”.
The sentiment of the importance of early data collection and corresponding closure planning is
echoed by Mulvey et al. (2012) in their analysis of the only mine in Australia to be successfully relinquished
to the a state government13, namely the Mary Kathleen uranium mine. Successful relinquishment was
possible for the mine,
“due to the development of a conceptual model using real data to predict the long term geological
behaviour of the mine waste, and confirming the model projections with real-time calibration
throughout the life of the mine. Consistent integration of the closure plan into mine operations was
essential. Final landform of waste rock dumps and tailings was undertaken during mine operations.”
To summarize, the biggest gaps that were uncovered fall into two general categories:
Legislative and policy framework Technical in mining, reclamation, and closure practices.
13 This was the only mine that was relinquished at the time. Since, another mine – Barrick Gold’s Timbarra mine in New South Wales – was also successfully relinquished.
![Page 24: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/24.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 24
5.8 Conclusion
The gaps outlined above are likely impeding the successful relinquishment of mine sites to the
respective Crown agencies in Canada. Additionally, there is currently little impetus for mine operators to
work towards a ‘walk-away’ / relinquishment scenario given that there is no clear path / course (i.e.
criteria) that can be used to achieve this aim.
Accordingly, it is anticipated that the development of the standardized criteria for mine closure will
aid in driving the regulations, technology, and corresponding management practices towards the
achievement of mine site relinquishment. The standardized criteria may not result in relinquishment
straightaway; however, it will aid in kick-starting the process towards the ensuing realization of
relinquishment.
In turn, the following closure activities can be enhanced to help achieve a walk-away / relinquishment
scenario, including but not limited to the following:
Refined regulations / legislation that facilitates relinquishment;
Greater accuracy in closure cost models;
Development of tools for early integration of closure into the mine life cycle;
Facilitating the use of passive systems for reclamation and rehabilitation, thereby
reducing longer-term management obligations; and,
Improving the understanding of biological, geochemical, geomorphological, and surface
/ sub-surface soil and water interaction impacts to better enable the re-establishment
of near-natural conditions.
6 Passive Treatment Systems for Acid Rock Drainage
6.1 Existing Systems
Overview
Systems for managing ARD are typically grouped into ‘active’ and ‘passive / semi-passive’ treatment
options. Active treatments systems for ARD are characterized as such due to the active dosing of the ARD
with an alkaline reagent such as lime, caustic soda, soda ash, or ammonia, and collecting the floc in ponds
(Skousen et al. 2005, quoting Environmental Protection Agency 1983, Skousen & Ziemkiwwicz 1996, and
Skousen et al. 2000). These systems require regular maintenance to sustain chemical supplies, power,
pumps, and the floc handling system, and are generally considered reliable and effective. Another
predominant active treatment system is the use of membranes (e.g. reverse osmosis). However, as with
active dosing regimens, high costs, power, and maintenance requirements render them “impractical for
most remote [and] abandoned mines” (Skousen et al. 2005).
A variety of passive treatment systems have been developed as an alternative to active treatment
systems. Gusek (2002) defines passive treatment as,
![Page 25: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/25.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 25
“a process of sequentially removing contaminants and / or acidity in a natural-looking, man-
made bio-system that capitalizes on ecological, and / or geochemical reactions coupled with
physical sequestration. The process does not require [significant] power or chemical [inputs]
after construction, and [can last] for decades with minimal human help.”
The predominant types of passive treatment systems are as follows:
Aerobic wetlands;
Alkalinity producing covers;
Anaerobic wetlands;
Anoxic limestone drains;
Bioreactors;
Limestone diversion wells;
Limestone leach beds;
Open limestone channels;
Permeable reactive barriers;
Phytoremediation.
Slag leach beds;
Vertical flow systems / SALPs / RAPs;
Water covers;
Dry and wet soil covers; and,
Synthetic barriers.
Ultimately, the choice of treatment systems – whether passive or active – will pivot on a variety of
technical factors, including, but not limited to, acidity levels, flows, the types and concentrations of metals
in the water, the rate and degree of chemical treatment needed, and water quality requirements
(Faulkner et al. 1996). Economic factors, such as prices of reagents, costs of labour, machinery, and
equipment, treatment timeframes, interest rates, and risk factors, will also determine the suitability of
the selected option. Site-specific characteristics may also preclude the use of passive treatment systems
(e.g. geographical location, topography, climate, etc.).
Most of the above treatment options are used concurrently or sequentially to achieve the desired
outcomes based on the intervening technical and economic factors. Figure 3 and Figure 4 below provide
schematic overviews of the general selection process for various passive treatment systems given various
site-specific conditions.
![Page 26: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/26.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 26
FIGURE 3 – GENERAL SELECTION PROCESS FOR ARD PASSIVE TREATMENT SYSTEMS (Ford 2003: 9, adapted from Hedin at al. 1994 and Skousen 2001)
![Page 27: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/27.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 27
FIGURE 4 – SELECTION CRITERIA FOR PASSIVE TREATMENT TECHNOLOGIES (Ibid)
Constructed Wetlands
6.1.2.1 Overview
Wetlands are composite ecological systems in which a variety of physical, chemical, microbial, and
plant-mediated processes occur that can effect significant changes in the water chemistry of mine-
impacted water through processes of oxidation, reduction, precipitation, chelation, adsorption,
complexation, sedimentation, filtration, active plant uptake and microbial mechanisms (MEND 1999: 19).
As with other passive treatment systems, these processes are designed to mimic and optimize natural
processes, namely those that occur in natural wetlands.
Wetlands can be divided into two primary types, namely aerobic and anaerobic. Metals are removed
in aerobic cells (or zones) via precipitation, chelation, and exchange reactions, whereas neutralization is
achieved in anaerobic zones by the activity of sulphate reducing bacteria (Ibid). Passive treatment systems
typically incorporate both aerobic and anaerobic zones to carry out both microbial and abiotic reactions
(Ibid).
6.1.2.2 Aerobic Wetlands
Aerobic wetlands are the simplest type of passive treatment system (Zipper et al. 2011: 3). These
wetlands, are comprised of shallow ponds that are 0.15 m to 1 m deep. They are typically planted with
various wetland plants (i.e. macrophytes), including cattails (Typha sp.), Juncus, and Scirpus sp. (Skousen
2005: 2), which translocate oxygen to the subsurface through their roots, thereby facilitating the oxidation
of metals (Zipper et al. 2011: 3). As Zipper et al. (2011: 3) note, “the aquatic plants also help to prevent
channelization of the waters flowing through the wetland, slowing water velocities and aiding solid-phase
metal removal via sedimentation.”
The primary function of aerobic wetlands is to provide sufficient residence time and aeration to allow
metal oxidation reactions and hydrolysis, which, in turn, facilitate the precipitation and physical retention
![Page 28: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/28.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 28
of mostly iron, aluminum, and manganese hydroxides (Skousen et al. 1998: 106). Once sufficient residence
time and aeration are allowed for, the influent ARD is drained by gravity though the wetland, thereby
progressively undergoing metal removal / neutralization (See Figure 5).
FIGURE 5 - FREE WATER SURFACE CONSTRUCTED WETLAND14
The pH and net acidity/alkalinity of the water are important because pH influences both the solubility
of metal hydroxide precipitates and the kinetics of metal oxidation and hydrolysis (GARD Guide n.d.:
Chapter 7). Thus, aerobic wetlands are generally constructed to treat mine-impacted waters that are net
alkaline.
Another key remedial process that occurs in aerobic wetlands is the removal of arsenic, which is
highly toxic even at trace levels. Typically, arsenic in mine-impacted waters originates from the oxidative
dissolution of arsenopyrite (FeAsS) that may be present in mine waste. Soluble arsenic may be removed
via absorption onto positively charged ferric iron colloids and, in theory, by the formation of scorodite
(FeAsO4). Novel strains of Thiomonas-like bacteria that oxidizes arsenic (III) to arsenic (V), have been
isolated from mine waters (Johnson & Hallberg 2005: 9, quoting Battaglia-Brunet et al. 2002 and Coupland
et al. 2003). Other trace metals that will co-precipitate with iron to some degree are cadmium, copper,
lead, and zinc.
Aerobic wetlands can also be characterized by their potential flow paths, namely surface and
subsurface flows. Treatment systems may be designed such that different cells in the system utilize
alternative flows. Figure 6 provides an illustration of these different types.
14 Retrieved from: http://www.prp.cses.vt.edu/Research_Results/SAPS.html
![Page 29: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/29.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 29
FIGURE 6 – CONSTRUCTED WETLAND CELLS SHOWING POTENTIAL FLOW PATHS (MEND 1999: 31)
6.1.2.3 Anaerobic Wetlands
In contrast to aerobic wetlands that are designed to maximize the effectiveness of oxidisation
reactions, anaerobic wetlands rely on the lack of oxygen and the promotion of chemical and microbial
processes to precipitate metals as well as to generate net alkalinity and biogenic sulfide (MEND 1999: 3;
Johnson & Hallberg 2005: 10). These systems rely on thick, water-permeable, and organic-rich substrates
that become anaerobic due to high biological oxygen demand (Gard Guide n.d.: Chapter 7). A layer of
limestone may be added to the bottom of the wetland or it may be mixed among the organic matter.
![Page 30: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/30.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 30
Limestone dissolution and the metabolic products of sulfate-reducing bacteria (e.g. Desulfovibrioa,
Desulfotomaculum, etc.) raise pH and precipitate metals as sulfides, hydroxides, and / or carbonates
(Skousen & Ziemkiewicz 2005: 3, quoting Henrot and Wieder 1990).
The most common form of sulfide reduction generates H2S and bicarbonate alkalinity. As Zipper et
al. (2005) note, sulfate-reducing bacteria utilize the oxygen that enters the anoxic environment as a
component of sulfate (SO42-) for metabolic processing of biodegradable organics.
General guidelines for construction of anaerobic wetlands suggest utilizing a 30-60 cm layer of
organic matter over a 15-30 cm bed of limestone, or placing a mixture of organic matter and limestone to
a depth of 50-100 cm. Crucially, the organic matter must be permeable and biodegradable (Zipper et al.
2005a: 5). Common animal manure from browsing animals like cows, sheep, or goats are preferred,
although wood chips, crushed limestone, plant residue, grass cuttings, hay, straw, manure, and compost
are used as well (GARD Guide n.d.: Chapter 7). Myriad innovative substrates are now being tested as part
of laboratory and bench-scale studies, including alfalfa hay, walnut / pecan shells, and mussel shells
(among many others) (Lee at al. 2014; Trumm and Ball 2014). The design depth of the water over the
substrate varies, with some designs maintaining water depths of 10-30 cm, while others are deeper (Ibid).
The sulfate-reducing bacteria (e.g. Desulfovibrioa, Desulfotomaculum, Desulfobulbus) function best
in the pH range of pH 6 to pH 9 (Skousen 1999: 109, quoting Widdle 1988), although they have limited
function down to pH 5 (Skousen 1999: 109). For treatment, optimal aerobic wetland performance is
expected when the pH is pH 6.0 or above and when the water is net alkaline (Skousen & Ziemkiewicz
2005: 6).
Figure 7 and Figure 8 show the systems in practice. The site in Figure 7 contains six cells, of which the
first three are seen. The first red pond collects the seepage from the hillside. The water is then routed
through these anaerobic cells through spillway berms. Figure 8 shows a longer, narrower system (Skousen
& Ziemkiewicz 2005).
![Page 31: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/31.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 31
FIGURE 7 – ANAEROBIC WETLAND TREATMENT SYSTEM (Skousen et al. 2005: 1112)
FIGURE 8 – ANAEROBIC WETLAND TREATMENT SYSTEM (Skousen et al. 2005: 1110)
![Page 32: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/32.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 32
6.1.2.4 Vertical Flow Wetland Systems
Vertical flow wetland (VFW) systems15 combine the treatment mechanisms of anaerobic wetlands
and ALDs in an attempt to compensate for the limitations of both (Zipper et al. 2005: 8, quoting Hendricks
1991, Duddleston et al. 1992; Kepler & McCleary 1994). In this system, water flows downward through a
layer of organic matter, then through a bed of limestone, before flowing out through a drainage system
(Skousen 1999: 117).
VFWs are similar to AWLs, although the addition of a drainage system to force the ARD into direct
contact with the alkalinity-producing substrate is what differentiates the two (Zipper et al. 2005: 8).
Furthermore, the ARD must pass vertically through the organic matter and the limestone to exit the
system through a standpipe. The associated alkalinity is generated, like anaerobic systems, through sulfate
reduction and limestone dissolution. Metal removal is also possible, mostly through precipitation in the
settling pond that receives the discharge waters.
Similar to anaerobic wetlands, VFWs are used to treat net-acidic mine waters, although they have
been shown to treat higher concentrations of metal contaminants due to the addition of a settling pond,
which facilitates the precipitation. Furthermore, due to the forced contact of the ARD with the limestone,
acid neutralization is more rapid in VFWs. Consequently, VFWs require shorter residence times and
smaller surface areas (Zipper et al. 2005: 10). Figure 9 presents a general schematic of a VFW (or SAPS).
FIGURE 9 – GENERAL SCHEMATIC OF A VERTICAL FLOW WETLAND SYSTEM16
15 These systems are also sometimes referred to as “reducing and alkalinity producing systems” (RAPS) or “successive alkalinity producing systems “SAPS”. 16 Retrieved from http://www.prp.cses.vt.edu/Research_Results/SAPS.html
![Page 33: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/33.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 33
Passive Bioreactors
Passive bioreactor systems rely on sulfate-reducing bacteria (SRB) – coupled with a biodegradable
carbon source – to increase pH and water alkalinity as well as to immobilize dissolved metals by
precipitating them as metal sulfides (Neculita et al. 2007a: 1-2).
Bioreactors are analogous to anaerobic wetlands in that the acidic drainage is directed / flows
through organic materials. These systems may be very small – often in one or a series of tanks / barrels –
or they may be very large (see Figure 10). The systems are particularly useful for remote mine sites and
sites with extreme weather conditions (Zagury et al. 2007: 1439-1440).
Anaerobic “wetland” systems are sometimes referred to as “compost bioreactors” given that, in
some installations, the systems are enclosed entirely below ground level and do not support any
macrophytes; thus, they are not wetlands per se (Johnson & Hallberg 2005: 9-10). Some designers
encourage using deeper waters and no vegetation at all, supposing that the translocation of oxygen to
substrates through the roots of the macrophytes hinders anoxic conditions, and thus, substrate functions
that are critical to performance (Zipper et al. 2005: 5-6).
In the last 20 years, passive bioreactors have successfully treated ARD-contaminated waters in both
pilot and full-scale projects (Neculita et al. 2007a). However, reactive mixture composition, ARD load, and
metal toxicity have limited the efficacy of some systems (Neculita et al. 2007b). Furthermore, additional
research is needed to properly assess the long-term efficacy of reactive mixtures and the associated metal
removal mechanisms (Ibid). Lastly, as Neculita et al. (2007b) note, “metal speciation and ecotoxicological
assessments of treated effluent from on-site passive bioreactors have yet to be performed”.
FIGURE 10 – SULFATE-REDUCING BIOREACTOR SYSTEM (Cavanagh et al. 2010)
Anoxic Limestone Drains
Anoxic limestone drains (ALDs) are a form of alkalinity addition for ARD that has a net acidity (MEND
1999: 7). ALDs are constructed trenches filled with high-quality, crushed limestone that is sealed under
geotechnical fabric or layer (i.e. clay) and covered with soil. Plastic is sometimes placed between the
limestone and clay to act as an additional gas barrier (GARD Guide n.d.: Chapter 7.5.2.3). As with anaerobic
wetlands, the systems rely on the exclusion of dissolved oxygen in the water; if dissolved oxygen is
present, iron and aluminum hydroxides clog the system, which will cause failure (Ford 2003: 13).
![Page 34: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/34.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 34
Thus, similar to anaerobic wetlands, the limestone produces bicarbonate alkalinity through
dissolution (Zipper et al. 2005: 6).
The sole function of an ALD is to convert net acidic mine-impacted water to net-alkaline water by
adding the bicarbonate alkalinity. The removal of metals is not intended because metal hydroxide
precipitation within an ALD will retard water flow and the permeability of the drain resulting in premature
failure (Skousen 1999: 114-5). This will typically occur when pH 4.5 or above is reached (Zipper et al. 2005:
7). Thus, ALDs are not a stand-alone treatment of ARD but rather form part of a series of cells (MEND
1999: 13).
The majority of ALDs that have been implemented have been used for the mine-impacted waters of
coal mines. This is also true of research surrounding ALDs (MEND 1999: 7). Furthermore, MEND (1999:
12-13) posits that ALDs may only have limited applicability to Canadian mines given the strict influent
stipulations that are required for ALDs to be effective. Specifically, dissolved oxygen, ferric iron, and
aluminum concentrations typically must be <1mg/L and sulphate concentrations typically must be below
2,000 mg/L. Given that most ARD sites in Canada do not meet these influent requirements, ALDs may only
have limited long-term application to Canadian mines. This is not to say that ALDs are less effective in a
more extreme northern climate (MEND 1999: 13), although this is a general gap in regards to passive
treatment systems (see Section 6.3.2).
![Page 35: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/35.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 35
FIGURE 11 – SCHEMATIC OF ANOXIC LIMESTONE DRAINS (GARD Guide n.d.: Chapter 7.5.2.3)
Open Limestone Channels
Open limestone channels (OLC) are open-air analogues to ALDs. They are open channels or ditches
with limestone placed along their sides and in the bottom of culverts, diversions, ditches, and / or stream
channels (Ford 2003: 5). Water flows down a steep slope through the limestone riprap and is conveyed to
a discharge point (Ford 2003: 6; GARD Guide n.d.: Section 7.5.2.5). Thus, these systems are employed
where ARD must be conveyed over some distance prior to or during treatment.
Alkalinity is introduced via the dissolution of the exposed limestone, which dissolves in the bottom
and side of a limestone drain. OLCs can be effective as one element of a passive treatment system,
although they are not typically relied on as a stand-alone system; rather, they usually form part of a larger
ARD treatment strategy (Zipper et al. 2005: 8, quoting Ziemkiewicz et al. 1997; Skousen et al. 2000).
Specifically, OLCs are typically useful as the stage that fulfills the requirement of conveying the ARD over
some distance.
![Page 36: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/36.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 36
Limestone Diversion Wells
Limestone diversion wells (LDWs) consist of a well in the form of an in-ground metal or concrete tank
that contains crushed limestone aggregate. Part of a fast-flowing stream is diverted, often via a pipeline,
into the well. The hydraulic force of the flow causes the limestone to turbulently mix and abrade into fine
particles and prevent armoring. The water flows upward and overflows the well at which point it is
diverted back into the stream.
LDWs are typically viewed as passive treatment systems, although significant maintenance is
required. Because limestone can only be added to the well in small amounts, frequent refilling is required
(Taylor et al. 2005: 19). Hopper feed systems can be installed to enable automatic refilling, which reduces
the amount of maintenance required. However, regular maintenance to remove leaves and other debris
will still be required to avoid blocking (Ibid).
Figure 12 provides a schematic overview of a LDW.
FIGURE 12 – SCHEMATIC VIEW OF A LIMESTONE DIVERSION WELL17
Limestone / Slag Leach Beds
Limestone leach beds (LLBs) consist of a cell or a series of cells that are filled with limestone to varying
degrees, and receive water that has little or no alkalinity or dissolved metals (Skousen & Ziemkiewicz 2005:
8; Black et al. 1999). The water slowly dissolves the limestone and the associated alkalinity concentration
that is generated ranges from 50 – 80 mg/L of CaCO3 (Black et al. 1999: 8), which helps to buffer streams
against acidity downstream (Skousen & Ziemkiewicz 2005: 4).
Slag leach beds (SLB) are a more recent development as compared with the other options presented
in this study. This system utilizes a bed of steel slag fines (-⅛ in.) to treat water that does not contain iron,
manganese, or aluminum (Skousen & Ziemkiewicz 2005: 4, quoting Simmons et al. 2002). The steel slag
contains high levels of alkalinity that are released into the water, with some pilot studies noting alkalinities
17 Retrieved from http://www.ei.lehigh.edu/envirosci/enviroissue/amd/links/passive4.html
![Page 37: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/37.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 37
in water as high as 2,000 mg/L. However, as the GARD Guide (n.d.: Section 7.5.2.7) notes, sites in which
these high alkalinities are generated must be carefully selected since water that is too alkaline can be
highly toxic to aquatic life.
Manganese oxidation beds (MOBs) are similar to limestone and slag leach beds. The MOBs support
the growth of a bacterial / algal consortium, which enables the precipitation of manganese oxides and /
or similar compounds. However, MOBs are positioned as a final step in a treatment system. This is because
they are only effective once all iron has been removed, as dissolved Fe2+ chemically reduces manganese,
which causes it to dissolve. Figure 13 below shows a LLB treatment system. Figure 14 presents a slag leach
bed system.
FIGURE 13 – LIMESTONE LEACH BED TREATMENT SYSTEM (Cavanagh et al. 2010)
FIGURE 14 – SLAG LEACH BED TREATMENT SYSTEM (Ibid)
![Page 38: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/38.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 38
Permeable Reactive Barriers
As Johnson and Hallberg (2005: 10) note, permeable reactive barriers (PRBs) are increasingly being
used to treat a wide range of polluted ground-waters. The systems are constructed for the reduction of
organic and inorganic contaminants, especially chlorinated solvents, fuels, heavy metals, metalloids,
nutrients, and radioactive materials (Sasaki et al. 2008: 835).
The PRBs operate on the same basic principles as compost bioreactors. However, their construction
involves digging a trench or pit in the flow path of contaminated groundwater and filling the void with
reactive materials (i.e. mixture of organic solids, limestone gravel, etc.). The void must be filled with
materials that are sufficiently permeable to allow unimpeded flow of the groundwater. Reductive
microbiological processes within the PRB generate alkalinity and remove metals as sulfides, hydroxides,
and carbonates (Johnson and Hallberg 2005: 10-11). Figure 15 below illustrates a typical PRB system
(USEPA 2014: 34).
FIGURE 15 – CROSS-SECTIONAL OF A PERMEABLE REACTIVE BARRIER18
Phytoremediation19
Phytoremediation technologies use plants to treat and / or capture contaminants in various media
Furthermore, these technologies generate minimal air emissions, water discharge, and secondary wastes,
and improve air quality by sequestering greenhouse gases (USEPA 2014: 31). There are six general
phytoremediation processes, which are summarized in the following table (adapted from Thangavel et al.
2013: 78-79).
18 Retrieved from http://www.geochem.geos.vt.edu/fluids/projects.shtml 19 These processes simultaneously occur in many of the additional passive treatment systems described above. However, they are often grouped as a separate suite of technologies in the literature.
![Page 39: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/39.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 39
TABLE 3 – PHYTOREMEDIATION TECHNOLOGIES
TECHNOLOGY CLUSTER DESCRIPTION
Phytostabilization
Applicable to the cleanup of both organic and inorganic contaminants Utilizes certain plant species to immobilize contaminants in the soil,
sediments, and groundwater through their absorption / accumulation onto the roots, or precipitation / immobilization within the root zone
Rhizodegradation
Alternate terms: phytostimulation, rhizosphere biodegradation, plant-assisted bioremediation
Based on the breakdown of contaminants in the soil through the bioactivity that exists in the rhizosphere
Phytodegradation
Also termed phytotransformation Refers to the uptake of organic contaminants from soil, sediments, and
water with a subsequent transformation by the plant Plants transform the organic contaminants through various internal,
metabolic processes that help catalyze degradation Contaminants are degraded in the plant with the breakdown products
subsequently stored in the vacuole or incorporated in plant tissues
Phytovitalization
Uptake / transpiration of a contaminant by a plant with the release of the contaminant or a modified form to the atmosphere
Occurs as growing trees and other plants take up water and organic contaminants
Some contaminants pass through the plants to the leaves and volatize at comparatively low concentrations
Phytoextraction
Also termed phytoaccumulation Refers to use of metal- or salt-accumulating plants that translocate and
concentrate these soil contaminants into their roots and above-ground shoots or leaves
Emphasis on “hyperaccumulators” that absorb comparatively large amounts of metals
Phytohydraulics Refers to ability of plants to capture, evaporate, and transpire water If water is able to percolate below the root zone, groundwater can be
recharged
Water Covers
As per the GARD Guide (n.d.: Section 6.6.7), the “disposal of acid generating materials below a water
cover is one of the most effective ways of limiting ARD generation” because the contact between the
minerals and dissolved oxygen is greatly limited. Specifically, the maximum concentration of dissolved
oxygen is approximately 30 times less than in the atmosphere and the diffusive transfer of oxygen in water
is approximately 10,000 times slower than in air.
Water covers can take the form of natural water bodies, which takes advantages of physically stable,
depositional environments (GARD Guide n.d.: Section 6.6.7). Engineered structures, such as tailings
![Page 40: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/40.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 40
storage facilities and man-made lakes, are often used for the subaqueous disposal of sulphide materials,
as are mined out pits / mine voids.
Key considerations for the use of these methods are water balance, water availability, wave action,
and the extent of rainfall / drought. Regulatory requirements may also preclude some types of disposal
mechanisms; for example, under Canadian regulations there are few instances where disposal in “fish-
bearing water bodies” is permitted.
The effectiveness of water covers may be improved by covering the waste material with a layer of
sediment or organic material, which provides additional protection against re-suspension due to the
effects of wind and waves (Johnson and Hallberg 2005: 5). Purpose-built wetland / bog covers are
examples of this system.
Water covers are in use throughout Canada, although mostly south of the 60th parallel north.
Examples include the Louvicourt Mine in Quebec, Voisey’s Bay nickel mine in Labrador, and Vale’s
Thompson Mine in Manitoba. As such, there is a need for additional research on the performance of water
covers in cold regions (MEND 2009). This is especially important given climate change considerations,
including: reduced temperatures; ice formation, scouring, and breakup; permafrost thawing; and,
changing snow cover (MEND 2011).
Dry Covers
Dry covers are typically earthen, organic, and / or synthetic materials that are placed over mine waste
materials (GARD Guide n.d.: Section 6.6.6.2). Cover materials are typically grouped into the following
categories:
Soil;
Alkaline;
Organic; and,
Synthetic.
The materials can be used in conjunction with one another; cover systems typically incorporate
several layers to help achieve the following objectives (Rykaart and Caldwell 2006), in addition to
achieving the overarching objective of stabilizing ARD and ML:
Vegetation support;
Erosion resistance;
Percolation control;
Moisture retention;
System foundation; and,
Reinforcement.
6.1.11.1 Soil Covers
Soil cover layers are constructed with natural earth materials, often including mine rock. The barriers
are typically used to achieve the following objectives (GARD Guide n.d.: Section 6.6.6.2.1):
![Page 41: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/41.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 41
Dust and erosion control;
Impeding oxygen and water ingress;
Contaminant release control; and,
Provision of a growth medium for vegetation.
The barriers can achieve substantial reductions in water flow through piles, although they generally
do not control ARD completely (Skousen et al. 1998: 45-6). Additionally, single soil layers have been used
in North America but are generally ineffective. Thus, soil covers are often multi-layered, with organic and
synthetic materials also used (GARD Guide n.d.: Section 6.6.6.2).
Soil store and release covers perform best in climates with high potential evaporation equal to two
to three times the precipitation.
6.1.11.2 Alkaline Covers
Alkaline cover materials (e.g. limestone) can be placed over acid-producing mine waste to increase
alkalinity, thereby providing pH control (GARD Guide n.d.: Section 6.6.6.2.2). Using alkaline materials
allows for rainfall infiltration to take up alkalinity and dissolved silicate as water seeps through the cover
material (Li et al. 2011). The alkalinity released from the covers can react with acid and metallic salts along
preferential flow pathways to create inert, precipitate-coated channels that inhibit further acid release
(Taylor et al. 2006).
As Taylor et al. (2006) note, the effectiveness of alkaline covers is limited under most climactic
conditions “as a result of the low solubility and slow dissolution rates of limestone in near-neutral
rainwater”. To be successful at more mine sites, alternative reagents will be necessary, such as fly ash,
seawater-neutralized red mud, and / or conventional caustic magnesia (Ibid). However, climactic
conditions may still preclude their use, given that system efficacy requires very high rainfall (Ibid).
6.1.11.3 Organic Covers
Mixing organic materials with acid-producing wastes helps to consume oxygen and promote metal
reduction in an anoxic environment (GARD Guide n.d.: Section 6.6.4.4). There are myriad examples of
these materials, such as pulp and paper residues, sewage sludge, bark, sawdust, sanding dust, fiberboard,
pulpwood, deinking residues, peat, compost and carbonaceous matter. Mine waste materials rich in
organic matter are also used (Ibid).
Limitations associated with organic matter include availability (especially at remotes sites), resistance
to decomposition with time, and climate (i.e. to maintain anaerobic conditions in the organic medium,
humid climates may be required). These challenges may preclude widespread application to Canadian
mine sites.
6.1.11.4 Synthetic Covers
Synthetic liners are used to encapsulate mine waste and reduce infiltration (GARD Guide n.d.: Section
6.6.6.2.5). Examples of these include:
Polyethylene (PE);
High density polyethylene (HDPE);
Chlorinated polyethylene (CPE);
![Page 42: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/42.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 42
Chlorosulphanated polyethylene (HYPALON);
Polyvinyl chloride (PVC);
Linear low density polyethylene (LLDPE);
Geo-synthetic clay liners (GCL); and,
Geo-membranes impregnated with bitumen.
A bedding material layer (e.g. sand) must be laid in advance to prevent puncturing by underlying
rock. A multi-layer soil cover is also required before adding the final growth substrate to prevent further
fracturing, especially if the cover soil contains a significant coarse fraction (Ibid; SRK 2013: 15).
The above covers have been shown to effectively eliminate oxygen and water ingress with relatively
low environmental risk in the long term. However, the liners have a finite life; manufacturers typically
guarantee the liners for 20-40 years and closure plans may have to allow for complete liner replacement
every 100 to 200 years (SRK 2013: 15). Synthetic liners are also one of the most expensive cover options
available.
Notwithstanding these challenges, geo-synthetic liners / covers are the least susceptible to the direct
effects of climate change, including but not limited to: changes in precipitation patterns,
evapotranspiration, and temperature as well as permafrost degradation (MEND 2011: 38).
6.2 Advancement in Technology and Development
Microbial Fuel Cells
Microbial fuel cell (MFC) architecture is being used to develop ARD fuel cells that are capable of
abiotic electricity generation. What differentiates MFCs from conventional chemical fuel cells is that the
anodes are “alive” (Lefebvre et al. 2011: 5841). The ARD fuel cells simultaneously generate electricity and
treat wastewater through the bacterial oxidation of organic matter, such as acetate, glucose, and
domestic wastewaters as well as inorganic matter (e.g. sulfides) (Cheng at al. 2007: 8149).
Researchers based at the University of Pennsylvania developed a prototype of an ARD fuel cell (see
Figure 16 and Figure 17 below) that was constructed from two plastic containers separated by an anion
exchange membrane, with carbon anodes and cathodes at either end of the chamber.
Ideally, the MFCs will be placed remotely at sites to treat water and generate electricity (e.g. for
operating pumps). Thus, the systems can be seen as a hybrid between passive and active treatment
systems.
The development of the technology is still in its infancy and is not yet at a stage for commercialisation
(Yadav 2012: 126). Nevertheless, synergistic processes such as these likely represent the way forward in
research and development.
![Page 43: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/43.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 43
FIGURE 16 – MICROBIAL FUEL CELL FOR ARD (American Chemical Society 2007)
FIGURE 17 – SCHEMATIC OF MICROBIAL FUEL CELL FOR ARD (Cheng et al. 200: 8149)
Gas Redox and Displacement Systems
Gas redox and displacement systems (GaRDS) is a relatively new approach to passively prevent the
formation of ARD in underground mines (Taylor and Waring 2012: 2). The approach was developed jointly
by Earth Systems and the Australian Nuclear Science and Technology Organization (ANSTO). The system
is one, if not the only, passive treatment system for ARD treatment in underground mines (Taylor et al.
2005: 31).
The system utilizes reducing gas mixtures generated by anaerobic bacterial activity to displace oxygen
without impeding drainage from the underground mine workings. The gas mixtures retard sulphide
![Page 44: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/44.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 44
oxidation and acid generation as well as precipitate secondary sulfides from the accumulated drainage
water (Taylor et al. 2005: 30).
The GaRDS technique has many advantages for mine operators who wish to temporarily close a mine
and retain the option of reopening the mine if metal prices increase. The systems can serve as a substitute
for the flooding of mine workings, which is the key method for limiting sulfide oxidation upon
underground mine closure. This alternative has many potential benefits, as flooding entails high costs and
the risk of catastrophic failure.
Taylor and Waring (2012: 6) outline several of the systems’ advantages:
Long term minimisation or prevention of acid drainage from underground workings;
No large scale pre-feasibility investigation required;
Rapid and low-cost to install;
Very low recurrent costs, especially relative to conventional chemical treatment systems;
Can be applied to all underground workings or portions thereof that cannot be flooded;
Only a small mass of degrading solid organic matter is required to fill (non-floodable)
airspace (i.e. adit + shaft + fracture volume) due to solid to gas conversion;
In some cases, the GaRDS approach could be combined with sewage disposal strategies for
some towns;
Re-precipitation of metal sulphides likely at some sites; and,
Performance of the system can be judged by the quality of the water emanating from the
workings (e.g. total acidity over time will decrease).
Figure 18 shows a GaRDS bioreactor that generates CO2 and CH4 gases, which displaces oxygen from
the underground mine. Figure 19 shows the installation of a low permeability well and drainage system
at the main adit opening.
FIGURE 18 – GARDS BIOREACTOR (Taylor et al. 2005: 31).
![Page 45: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/45.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 45
FIGURE 19 – INSTALLATION OF LOW PERMEABILITY WELL AND DRAINAGE SYSTEM (Taylor et al. 2005: 31).
Development of Innovative Substrates
The use of innovative materials as substrates in passive treatment systems is a burgeoning research
and development topic among researchers, mine operators, and governments (among others). This is
evidenced by the myriad research on the topic in the literature surrounding ARD and passive treatment
systems.
The substrates – including both chemical and organic materials – act as key sources of carbon. There
are many examples of substrates, with experimentation and development occurring with substances
ranging from wood chips and fly ash to mussel shells and crab shell chitin. Additional research regarding
the use of mine-specific wastes – including synergistically with other materials – may be beneficial to
reduce costs, optimize waste management practices, and enhance overall sustainability.
Other innovative materials that are the focus of research are zeolites (Motsi 2010), silicates to coat
sulfide minerals (Bell and Donnelly 2006: 405), microcrystalline silica (Marisco et al. 2010), and
serpentinite (Bernier 2005; Kamal and Sulaiman 2009).
Co-treatment of ARD with Municipal Waste Water
Co-treatment of ARD with municipal wastewater (MWW) is an emerging synergistic treatment
approach that blends aspects of passive ARD treatment with conventional active MMW treatment
![Page 46: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/46.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 46
(Strosnider et al. 2012: 26). The process offers potential savings in materials, proprietary chemicals, and
energy inputs and is a viable approach to ARD and MWW treatment in developed as well as remote,
resource-poor, and / or developing regions (Ibid: 28).
As with other passive treatment systems, the removal of acidity, metals, and sulfates is accomplished
by generating alkalinity either abiotically via passive dissolution of limestone or biotically via bacterial
sulfate reduction, which raises pH and aids in the dissolution of metals by precipitation and / or absorption
(Hughes and Gray 2013: 170). In conventional active MWW treatment using the activated sludge process,
organic compounds and nutrients are primarily removed via bacterial oxidation and assimilation
(Strosnider 2013: 26-7). Combining the two processes takes advantage of the natural alkalinity of MWW
and the absorptive properties of MWW particulates, as well as the activated sludge biomass, to remove
acidity and metals by precipitation and absorption (Ibid).
The technology is still in the research and development phase, with few systems actually constructed
to simultaneously co-treat ARD and MWW. However, small-scale testing has shown promising results
(Strosnider et al. 2012: 27). For example, one study documented the removal of aluminum, arsenic,
cadmium, iron, manganese, lead, and zinc by 99%, 88%, 98%, 99%, 14%, 88%, and 73%, respectively.
Orthophosphate has been shown to decrease below detection limits with ammonium decreasing 46%. A
near 100% reduction in total Coliforms, fecal Coliforms, E. coli, and fecal Streptococci has also been noted.
These studies have demonstrated ARD generally considered too high-strength for passive treatment could
be successfully and passively co-treated with MWW, as can the application of the conventional sludge
process (Ibid: 27-8). Strosnider et al. (2012: 28) outline multiple lines of research that should be
conducted, which, in turn, will help to enable the system to become a design option.
Recovery of Marketable Products
Active and passive treatment systems are often useful only in the context of actual treatment. A
development in the mining industry as a whole is a trend towards developing processes whereby
marketable products can be recovered from mine waste. Such products are currently able to be recovered
from passive treatment systems and can help to reduce costs.
Hedin (2012) notes that that are two conventional uses for mine drainage solids. One is iron oxide
solids have high pigmentary characteristics and thus can be used as pigments that are used in paint, stains,
concrete, and plastics.
A second general application is the use of iron-rich solids as sorbents for oxyanions, such as arsenate,
selenite, and phosphate given the high sorption capacity of iron oxides. Iron oxide is also a good sorbent
of lead, cadmium, copper, and zinc. These are particularly useful for contaminated soils, where sorption
onto the solid can decrease metals concentrations to safe levels and mitigate the need for costly soil
removal and / or disposal (Hedin 2012).
Another metal-bearing solid produced as a by-product of ARD passive treatment is a manganese-
bearing material that is used for pottery glaze (Denholm et al. 2008). The material was produced at a
former coal mine in Pennsylvania. Other industrial uses of the material are now being investigated (Ibid).
![Page 47: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/47.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 47
Although mine drainage iron oxide products are purer and more valuable than mined iron oxides,
they cannot match the purity of synthetically produced iron oxide (Ibid). However, volume reduction of
the mine drainage solids has not yet been explored (Ibid). Furthermore, the market for iron oxides is
already highly competitive.
A South African company – Earth Metallurgical Works – has demonstrated many innovative
possibilities in this area. The company has converted ARD-treated water and the by-products of the
treatment process into potable water (van der Merwe 2010a), stabilisers used in emulsion explosives (in
conjunction with African Explosives Limited (AEL)) (van der Merwe 2010b), and metal nitrates that are
converted into thermal salts, which can be used for storage in concentrated solar power plants (Creamer
2011). The company has also extracted ammonium sulphate, which is used as an industrial chemical (e.g.
in the vanadium industry) (Hannah 2011).
6.3 Gaps in Technology and Research
Emphasis on Treatment in Perpetuity
In 2012, MEND (2013) conducted a survey of mines producing precious and base metals, coal, and
uranium. Respectively, these mines accounted for 46%, 23%, 7%, and 5% of the mines surveyed, with the
remaining 19% classified as others. The primary purpose of the survey was to ascertain what treatment
and management options were being used in relation to ARD and sludge management. Roughly two-thirds
of the sites are based in Canada, although sites were also included from the USA (roughly 25%), the UK,
Australia, Mexico, Peru, China, South Africa, Germany, Brazil, New Zealand, and Hungary.
The survey found that the most common methods used to treat ARD were active treatment methods,
including: 1) basic neutralization through active addition of chemical / biological reagents; and, 2)
flocculation. Passive treatment systems were found to be the least utilized treatment process out of the
12 different suites of technologies. The alternative technology suites in order of their prevalence of use
are as follows:
High-density sludge;
Basic neutralization;
Other;
Reactors;
Iron sulfates;
Aeration;
Membrane separation;
Acidification;
Sludge recycle; and,
Mechanical solid / liquid separation.
In fact, the survey (2013: 5-6) found that most sites (46%) expected to treat ARD and sludge
management in perpetuity, with another 6% expecting treatment to take 50-200 years. Another 25%
expected treatment to take 10-50 years, while the least likely scenario was a 0-10 year timeframe (23%).
![Page 48: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/48.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 48
Thus, additional development of passive treatment systems, particularly those that strive towards walk-
away scenarios, would be beneficial to the Canadian mining industry at large.
System Performance in Northern Climates
Crucially, the design and operation of passive treatment systems must take into account seasonal
variation, especially cold climate winter conditions. This is true under conditions of a complete freeze or
a partial thaw (MEND 1999: 13).
As the GARD Guide (n.d.: Section 7.5.2.10) notes, “all biochemical and microbial reaction rates
decrease as temperatures drop”. In some instances, extreme cold temperatures can kill the treatment
organisms off altogether, thereby reducing the effectiveness of the system or causing it to fail outright
(Ford 2003: 11). This is especially true of wetland systems relying on sulfate reduction given that they are
biologically based (Ibid: 11-12).
Furthermore, snowmelt in the spring poses additional challenges for passive treatment systems given
the increased water volumes as well as the corresponding, increased trafficability of effluent runoff. This
also leads to reduced hydraulic retention time, which will inevitably reduce system effectiveness when
compared to lower flow regimes.
Some passive treatment technologies are currently better suited to harsh winter operational
conditions. For example, anoxic limestone drains and RAPs are better suited than constructed wetlands
and phytoremediation technologies. This is because the former are able to insulate the treatment against
the extremes of winter temperatures (GARD Guide n.d.: Section 7.5.2.10).
Many of the leading passive treatment technologies that have been developed have been
implemented in the Appalachia region of the United States, particularly the coal-mining states of West
Virginia and Pennsylvania. Consequently, additional applied research is required to understand how these
technologies can be adapted to suit the climatic conditions facing the Canadian mining industry.
Technology adaptation and development as it relates to ARD in other cold climates (e.g. northern Europe)
will be useful in this respect.
Lastly, system design for cold winter climates may become more important given the potential effects
of climate change (MEND 2011: 11-12), particularly the increased likelihood of more extreme seasonal
variation and weather events, which will exacerbate the challenges outlined above. Moreover, certain
systems may rely on permafrost for stability, which may reduce performance or cause them to fail. Thus,
permafrost degradation will become an increasingly important concern for system design (MEND 2011:
14).
Long-term Performance and Maintenance
As Price (2003: 5) notes, because ARD assessment and mitigation are relatively new endeavors that
have only come into being within the last few decades, there is little long-term operating experience with
respect to ARD treatment, including passive systems. In turn, there is a lack of representative data that
can be used to assess potential options. This is more true of certain systems over others; for example,
![Page 49: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/49.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 49
given that constructed wetlands have been utilized for a greater period of time, more information is
available as compared with biochemical reactors, for example (ITRC n.d.: Biochemical Reactors).
Consequently, additional long-term, laboratory, and field performance data are needed to address
gaps in the knowledge base. Bench testing, laboratory simulations, and small-scale (i.e. pilot) testing will
assist in filling these knowledge gaps.
Similarly, although passive treatment systems are designed with the intention of having to conduct
limited maintenance, this is often not the case. Periodic monitoring and maintenance is to be expected,
as no passive / semi-passive treatment system is wholly a ‘walk-away’ one. However, long-term
maintenance costs of passive treatment systems is a major design challenge, as many implemented
systems have experienced unanticipated maintenance activities and associated costs (Gusek 2002: 945).
Development of Innovative Substrates
The use of innovative substrates in passive treatment systems is a burgeoning research and
development topic among researchers, mine operators, and governments. Additional research is required
into how different substrates will perform under the varying climactic conditions across Canada,
particularly in areas with cold winters. A related challenge is the sourcing of local materials, including local
waste materials. In the case of steel slag leach beds, they were developed and are primarily used for ARD
treatment of coal mine-impacted water in West Virginia and Pennsylvania. Due to the proximity of steel
production activities (i.e. Pennsylvania), the process is optimized. An additional avenue for further
research would be to determine the possibility of using mine wastes as part of these systems, whether it
be processing waste or waste from another mining-related activity.
Developing synergistic processes with other waste treatment is optimal. There are many rapidly-
emerging technologies in this area. One of the most promising is the co-treatment of ARD with MWW that
was identified above.
Recovery of Marketable Products
The recovery of saleable / marketable products from mine waste is a growing trend within the mining
industry, and the extractives industry more generally. The process can help to offset remediation costs or
may actually create a revenue stream for the company. The process also helps to deal with the by-
products of ARD-treated water, which can be highly problematic themselves. Specifically, the brine and /
or sludge that is generated as part of many treatment processes will likely need to be stored in brine
ponds and / or sludge dams. This is an increasingly important concern given space limitations (See Section
6.3.8).
Currently, the process is more developed for mine waste types other than ARD materials, with one
of the most prevalent examples being the re-processing of metals from tailings storage facilities.
Additional development in this area would be beneficial to the industry and overall sustainability.
![Page 50: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/50.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 50
Focus on Coal Mining
Another gap that was uncovered as part of the pre-feasibility research is that a greater focus on the
passive treatment of ARD is geared towards treating ARD in waters impacted by coal mines rather than
metal mines. This is partly due to the relative scale of the ARD problem; for example, in 1995, the EPA
reported that over 80% of ARD contamination originated from abandoned underground coal workings
(Skousen and Ziemkiewicz 2005: 1). Although this report was from 20 years ago, it is anticipated that the
scale of the problem is of a similar nature.
Nevertheless, as Gusek (2009) notes, in the last two decades the scope of passive treatment has
expanded to more fully incorporate precious and base metals mines, uranium mines, and even gravel pits.
Thus, there is potential for passive treatment systems related to coal mine environments to be adapted
to other mining environments. Much knowledge, best practice, and technology development have
developed that could be transferred to these sites or, at a minimum, their applicability could be examined.
Secondary Effects
A corollary of limited long-term experience with passive treatment systems is the risk of secondary
and / or unintended effects of the systems. While a treatment process may produce a desired result – for
example, a reduction in sulfates – other, perhaps unintended, consequences may develop, such as the
formation of undesirable precipitates. This may ultimately reduce water quality (Gillow et al. 2014) and
the system may become counterproductive to meeting design goals (e.g. regulatory water quality
requirements).
There are numerous examples of passive treatment systems that have done more harm than good
(Sobolewski n.d.). This often involves trade-offs; thus, prioritizing the end-goal of a passive treatment
system is critical, which suitable design mechanisms will enable.
Space Limitations
Open spaces available for constructing passive treatment systems will likely become more restricted
(Gusek 2002: 945). This is less of a concern in Canada as compared with other jurisdictions, although
reduced environmental footprints are increasingly expected by stakeholders and regulators. Thus,
evolving system design will tend towards shrinking the treatment systems into tighter spaces. Gusek (Ibid)
posits several potential solutions including stacking, installation of the systems in underground mine voids
through boreholes, and hybrid systems that use industrial organic wastes as nutrient feed stock. This latter
solution has already become a burgeoning research topic in the literature.
7 Project Selection Workshop
7.1 Overview
A project selection workshop was held on 13 May 2014 in Vancouver that included the working group
members, the ESI Chair, and the consultant that helped prepare the pre-feasibility studies.
![Page 51: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/51.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 51
The primary objectives of the workshop were to assess the initial feasibility of the proposed projects
and to provide a recommendation as to which project(s) should be taken to the feasibility level. To achieve
these objectives, the workshop was structured around two main exercises:
1) Conducting a risk assessment of the projects; and,
2) Screening the projects against assessment criteria to allow for prioritization.
Feasibility study preparation and planning also took place as part of the workshop.
A risk assessment was conducted for the standardized closure criteria project. The group chose to
forego conducting a risk assessment on the passive treatment systems for ARD project as it was
determined that there were outstanding issues that were uncovered as part of the pre-feasibility research
that needed to be further addressed before an appropriate risk assessment could take place (see Section
7.4.2).
7.2 Risk Assessment
Overview
A high-level risk management exercise developed by Shepherd (1997) was used to identify, assess /
analyze, and plan for potential risks associated with the projects. An overview of these components is
presented in Figure 20.
FIGURE 20 – RISK ASSESSMENT COMPONENTS (Shepherd 1997)
![Page 52: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/52.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 52
The identified risks were assessed according to the likelihood of the risk and the magnitude of the
associated consequences. The risks were then placed on a likelihood-consequence matrix (presented in
Figure 21), which enabled the group to determine the scenarios that presented a high risk to impeding
project success. If a risk placed on the ‘high’ end of the matrix, a management response would be required
to control, reduce, or eliminate the risk. If a management response was not available, the project would
be deemed infeasible. The results of the risk assessment for the standardized closure criteria project are
presented in Table 4.
FIGURE 21 – LIKELIHOOD-CONSEQUENCE RISK MATRIX (Shepherd 1997)
![Page 53: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/53.jpg)
C L O S U R E W O R K I N G G R O U P P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 53
TABLE 4 – RISK ASSESSMENT RESULTS FOR THE STANDARDIZED CLOSURE CRITERIA FOR RELINQUISHMENT
RISK LIKELIHOOD CONSEQUENCE RANKING COMMENTS
Unable to obtain stakeholder acceptance / consensus
4 3 Medium
It is highly likely that consensus will not be obtained from all stakeholders given the diverse range of stakeholders that will be impacted by the process (e.g. governments, regulatory agencies, industry, local communities, etc.). Stakeholders across the different jurisdictions will also have different expectations and risk appetites. However, it is anticipated that sufficient buy-in from a range of stakeholders will be viable given the benefits that will accrue to stakeholders once a more robust relinquishment process is implemented.
Governments oppose approach to criteria for relinquishment
3 5 High
Some governments will likely oppose the approach to the criteria given that they are risk-averse, yet without a framework to relinquish mine sites, there is a strong likelihood that abandoned mine sites will continue to accrue to the Crown. The consequence of the governments of the major mining jurisdictions opposing the approach is that relinquishment would be precluded, perhaps entirely. To mitigate this risk, government champions will be needed to advocate for the project who can aid in obtaining buy-in from other jurisdictions.
Technology risk – criteria cannot be achieved
2 4 Medium There is a low likelihood that the criteria will not be achieved due to technology risk. Rather, the criteria will be a significant driver of the development of the technology to achieve the closure objectives given that there is a defined end / goal that must be met. Though unlikely, this risk could impede project success by making relinquishment unattainable.
Unable to define acceptable criteria and risk scenarios
1 4 Low It is unlikely that the project will be unable to define acceptable criteria and risk scenarios given that the risk of not doing so will likely result in the continuing accrual of abandoned mine sites to the Crown (and ultimately the public). Additionally, criteria frameworks have previously been developed (i.e. Alberta (see Section 5.6)) that can serve as a model for criteria development.
Risk of extensive change of expectations with time
3 2 Medium It is likely that stakeholder expectations will change with time given the development of new technologies, greater understanding of environmental impacts, and more robust management practices to achieve closure objectives (among other factors). The risk can be mitigated by ensuring that the criteria evolves with time to incorporate changing expectations. Continual improvement will be a cornerstone of the criteria framework.
Unable to obtain funding / partners
1 4 Low It is anticipated that industry, consulting, and mining organizations (e.g. MAC) will support the development of the criteria. Thus, it is unlikely that the project will be unable to establish partnerships and obtain funding. Though unlikely, the lack of partners / funding could represent an unacceptable risk to the project. Thus, a primary component of future project development activities will be exploring funding opportunities and arrangements.
Unacceptable cost increase to achieve relinquishment (existing projects)
3 2 Medium For existing projects, achieving a relinquishment scenario will likely entail increased closure costs. It is likely that these costs will be unacceptable to mine operators, especially given the increasing cost pressures across the industry. However, the long-term costs and liabilities associated with mine closure will decrease. Thus, the consequences of this risk are considered low.
Unacceptable cost increase to achieve relinquishment (new projects)
3 4 Medium For new projects, it is likely that the additional costs of achieving relinquishment will be unacceptable. Specifically, some projects may not be viable – as compared with not working towards relinquishment – and may not be developed. To mitigate this risk, mine operators may continue to design for closure such that they are not required to relinquish a particular site to the Crown.
Unacceptable time to succeed (>5 years)
2 3 Low There is a low likelihood that the criteria cannot be developed within five years. Although CMIC endeavors to create a national framework, the relinquishment criteria that was developed in Alberta was developed over a 2-3 year timeframe. This process may serve as a model for the project. The consequences of this risk are moderate given that, at a minimum, the foundation of a framework will be laid.
![Page 54: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/54.jpg)
C L O S U R E W O R K I N G G R O U P P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 54
7.3 Assessment Criteria
The project selection workshop was initially organized such that, following the risk assessments, the
projects would be screened against selection criteria, compared against each other, and prioritized based
on the results. However, because an initial risk assessment for the passive treatment for ARD project was
deemed premature – thereby deferring the project subject to further research – it was deemed
unnecessary to do so.
However, assessment criteria were formulated and ranked so as to provide direction for future
project development activities, including any feasibility work. The selection criteria are as follows (in order
of importance):
Reduces stakeholder and operations risk;
Affects all mining projects in Canada (legacy and current);
Reduces health and safety risks;
Saves time and money;
Promotes stakeholder buy-in and project sustainability;
Likelihood exists that the concept would succeed if CMIC was not involved;
Facilitates a step-change improvement in the mining business;
Encourages applications beyond mining;
Profitability of the concept; and,
Options exist for a quick win (e.g. possibly applications from other industries, availability
of a staged approach to project development).
7.4 Conclusions / Recommendations
Standardized Closure Criteria for Relinquishment
The risk assessment established that there were few risks that would prevent the project from
succeeding. For risks that did present such a scenario, management responses were developed that could
mitigate, reduce, or eliminate the risk.
Accordingly, the group made a recommendation to take the project to the feasibility level. Key
components of the feasibility-level analysis were formulated based on the results of the risk assessment.
The feasibility study will incorporate risk tracking to ensure that the identified risks are managed
prudently. The assessment criteria that were developed will also help guide the study. The major
components of the feasibility study will be organized into a terms of reference (ToR) and work plan.
It is planned that the feasibility study work will take place over 6 months and would be completed
before end 2014.
![Page 55: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/55.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 55
Passive Systems for ARD
The working group determined that there were outstanding issues that were uncovered as part of
the pre-feasibility research that needed to be further addressed before an appropriate risk assessment
could take place. This includes but is not limited to the following:
Lack of passive system use throughout mining operations in Canada;
Performance of the systems in winter climates, especially given sub-optimal temperatures and
spring run-off complications;
Successes and failures throughout Canada; and
Scalability.
To help delineate these issues, CMIC plans to work in conjunction with a graduate-level student under
the guidance of a professor specializing in passive systems for ARD / ML. CMIC intends to sponsor a portion
of the student’s financial requirements for the duration of their thesis work, which is planned to begin in
September 2014.
The research will enable the group to further define the initial scope of the potential project. One
option that may ensue is grouping the passive systems for ARD project with the work of the tailings
working group given the potential synergies that exist. This determination will be made after further
review.
Once the research is completed, it is anticipated that a more thorough risk assessment can be
conducted that will enable the group to make a recommendation as to whether or not the project should
be taken to the feasibility level.
8 References
2012 Institutional Control Report. (2012). Saskatchewan Ministry of Energy and Resources.
Alberta Conservation and Reclamation Regulation. (1993, 2013 (amendments)).
Alberta Environmental Protection and Enhancement Act. (2000).
American Chemical Society. (2007). New Fuel Cell Cleans Up Pollution and Produces Electricity.
ScienceDaily (4 December 2007).
Bernier, L.R. (2005). The Potential Use of Serpentinite in the Passive Treatment of Acid Mine Drainage:
Batch Experiments.
Cavanagh, J.E., Pope, J., Harding, J.S., Trumm, D., Craw, D., Buxton, R., Rait, R., Champeau, O., Clemens,
A, Niyogi, D., & Greig, H. (2010). A Framework for Predicting and Managing Water Quality Impacts of
Mining on Streams: A User’s Guide. CRL Energy Institute.
Cheng, S., Liu, H., & Logan, B. (2008). Increased Power Generation in a Continuous Flow MFC with
Adjective Flow Through the Porous Anode and Reduced Electrode Spacing.
![Page 56: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/56.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 56
Cowan, W.R., Mackasey, W.O., & Robertson, J.G.A. (2010). The Policy Framework in Canada for Mine
Closure and Management of Long-term Liabilities: A Guidance Document. National Orphaned /
Abandoned Mines Initiative (NOAMI).
Cowan, W.R., Mackasey, W.O., & Robertson, J.G.A. (2013). Case Studies and Decision Making Process
for the Relinquishment of Closed Mine Sites. National Orphaned / Abandoned Mines Initiative (NOAMI).
Creamer, M. (2011). South Africa’s AMD / Wasterwater is ‘mineable’ – Turton. Mining Weekly (20
January 2011).
Denholm, C., T. Danehy, S. Bulsler, R. Dolance, & M. Dunn. (2008). Presentation at the National Meeting
of the American Society of Mining and Reclamation, June.
Faulkner, B.B. & Skousen, J. (1996). Treatment of Acid Mine Drainage by Passive Treatment Systems.
In Acid Mine Drainage: Control and Treatment, J. G. Skousen, and P. F. Ziemkiewicz, eds. (Morgantown,
WV: West Virginia University and the National Mine Land Reclamation Center).
Ford, K.L. (2003). Passive Treatment Systems for Acid Mine Drainage. U.S. Bureau of Land Management
Papers.
Gillow, J., Hay, M., Horst, J. (2014). In Situ Sulfate Mine Water Treatment – Practical Engineering in the
Field. Paper presented to the INAP Workshop of Sulfate Mine Water Treatment (Salt Lake City, UT).
Global Acid Rock Drainage Guide. International Network for Acid Prevention.
Goodbody, A. (2014). Mine Design and Closure: Closing the Deal. Mining Magazine (14 January 2014).
Gusek, J.J. (2002). Sulfate-reducing Bioreactor Design and Operating Issues: Is this the Passive
Treatment Technology for your Mine Drainage. Paper presented at the National Association of Abandoned
Mine Land Programs.
Gusek, J., Conroy, K., & Rutkowski, T. (2008). Past, Present, and Future for Treating Selenium-Impacted
Water. Paper present at the 2008 Annual Meeting of the West Virginia Mine Drainage Task Force.
Hannah, J. (2011). Solutions Needed for By-Products from AMD Treatment. Mining Weekly (29 April
2011).
Hedin, R.S., (2012). Advances in the Production of Marketable Products from Mine Water Treatment
Systems. Iron Oxide Recovery Inc.
Hughes, T.A. & Gray, N.F. (2013). Removal of Metals and Acidity from Acid Mine Drainage Using
Municipal Wastewater and Activated Sludge. Mine Water and the Environment 32: 170-184.
Institutional Control Program: Post Closure Management of Decommissioned Mine / Mill Properties
Located on Crown Land in Saskatchewan. (2009). Saskatchewan Ministry of Energy and Resources.
Johnson, D.B. & Hallberg, K.B. (2005). Acid Mine Drainage Remediation Options: A Review. Science of
the Total Environment 338: 3-14.
![Page 57: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/57.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 57
Kamal, N.M. & Sulaiman, S.K. (2014). Passive Treatment of Acid Mine Drainage with Limestone,
Calcareous Rock and Septentinite. In From Sources to Solution: Proceedings of the International
Conference on Envroonemtnal Forensics 2013. (Singapore: Springer).
Lefebvre, O., Shen, Y., Tan, Z., Arnaud, U., Change I.S., Ng, H.Y. (2011). Full-loop Operation and Cathodic
Acidification of a Microbial Fuel Cell Operated on Domestic Wastewater. Bioresource Technology.
Li, J., Kawashima, N., Schumann, S., Hughes, A., Hutchison, B., Kent, S., Kaplun, K., Ciccarelli, J., Smart,
R. (2011). Assessment of Alkaline Cover Performance for Abatement of ARD from waste Rock Dumps at
Savage River Mine. Paper presented to the Australian Workship on Acid and Metalliferous Drainage: 241-
253.
Maest, A.S., Kuipers, J.R., Travers, C.L., and Atkins, D.A. (2005). Predicting Water Quality at Hardrock
Mines: Methods and Models, Uncertainties, and State-of-the-Art.
Marisco, L.V., Orellana, D., & Tubino, R.J.C. (2010). Possibility of Removing Metals from Acid Mine
Drainage Using Industry Waste Processing Agates as Absorbent. Paper presented to International Mine
Water Association, 2010.
McIntosh, A. (2014). We Have a Reclamation Certificate but is it Enough? It’s Our Nature to Know Blog
(Alberta Biodiversity Monitoring Institute).
Mine Environment Neutral Drainage Program (2011). Climate Change and Acid Rock Drainage – Risks
for the Canadian Mining Sector.
Mine Environment Neutral Drainage Program (2012). Cold Regions Cover System Design.
Moncur, M.C. (2006). Acid Mine Drainage: Past, Present…Future? WAT on Earth. Available Online at:
https://uwaterloo.ca/wat-on-earth/news/acid-mine-drainage-past-presentfuture
Motsi, T. (2010). Remediation of Acid Mine Drainage Using Natural Zeolite. PhD Thesis at University of
Birmingham.
Mulvey, P. Baker, A., Scott, P. (2013). Mine Closure and Waste: Responsibilities and Liabilities.
Packee, E.C. & Bandopadhay, S. (2001). Linking Long-term Environmental Liability and Closure: A
Necessary Development Towards Walk-Away Closure. Paper presented to the International Mining
Congress and Exhibition of Turkey.
Provincial Wetland Restoration / Compensation Guide. (2007). Government of Alberta.
Planning for Integrated Mine Closure: Toolkit. (2006). International Council on Mining and Metals
(ICMM).
Poscente, M. and Charette, T. (2012). Criteria and Indicators Framework for Oil Sands Mine
Reclamation Certification. Cumulative Environment Management Association.
Purdy, B. & Richens, T. Conservation and Reclamation at Alberta’s Mineable Oil Sands. (2012).
Government of Alberta.
![Page 58: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/58.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 58
Price, W.A. (2003). Challenges Posed by Metal Leaching and Acid Rock Drainage at Closed Mine Sites.
Quebec Mining Act. (2013).
Review of Passive Systems for Treatment of Acid Mine Drainage. Mine Environment Neutral Drainage
(MEND). (1999). Report No. 3.14.1.
Rooney, R.C., Bayley, S.E., & Schindler, D.W. (2012). Oil Sands Mining and Reclamation Cause Massive
Loss of Peatland and Stored Carbon. Paper presented to the National Academy of Sciences of the United
States of America.
Rykaart, M. & Caldwell, J. (2006). State of the Art Review: Covers. Infomine.
Rykaart, M. & Hockley D. (2009). Mine Waster Covers in Cold Regions. Mine Environment Neutral
Drainage Program (2009).
Sasaki, K., Nukina, S., Wilopo, W., Hirajima, T. (2008). Removal of Arsenate in Acid Mine Drainage by a
Permeable Reactive Barrier Bearing Granulated Blast Furnace Slag: Column Study. Materials Transactions
49(4): 835-844.
Shepherd, B. (1997). Managing Risk. Paper presented to the Project Management Insitute 28th Annual
Seminars and Symposium (Chicago, IL: 29 September – 1 October 1997).
Starke, L. (2008). Planning for Integrated Mine Closure: Toolkit. International Council on Mining and
Metals (ICMM).
Struzik, E. (2014). On Ravaged Tar Sands Lands, Big Challenges for Reclamation. Yale Environment 360
(Yale School of Forestry and Environmental Studies).
Skousen, J. and Ziemkiwwicz, P. (2005). Performance of 116 Passive Treatment Systems for Acid Mine
Drainage. Paper presented at the 2005 National Meeting of the American Society of Mining and
Reclamation.
SRK Consulting (2013). Scoping Level Cover Assessment for Minto Closure Covers. Available Online at:
http://www.emr.gov.yk.ca/mining/pdf/mml_minto_phase_iv_rcp_version_4_app_e.pdf
Strosnieder, W.H.J., Hughes, T.A., Peer, R.A.M., Winfrey, B.K., Gray, N.F., Nairn, R.W. (2012). Co-
treatment if Acid Mine Drainage with Municipal Wastewater: A Promising New Approach. American
Society of Mining and Reclamation.
Taylor, J., Pape, S., Murphy, N. (2005). A Summary of Passive and Active Treatment Technologies for
Acid and Metalliferous Drainage (AMD). Australian Centre for Minerals Extension and Research (ACMER).
Taylor, J., Guthrie, B., Murphy, N., and Waters, J. (2006). Alkalinity Producing Cover Materials for
Providing Sustained Improvement in Water Quality from Waste Rock Piles. Paper presented to the 7th
ICARD (St. Louis, MO: 26-30 March 2006).
Taylor, J., & Waring, C. (2012). The Passive Prevention of ARD in Underground Mines by Displacement
of Air with a Reducing Gas Mixture: GaRDS. Mine Water and the Environment.
![Page 59: Pre-Feasibility Report of the ESI Closure Working Group ...This report presents the pre-feasibility work of the Closure Working Group (CWG) – one of three working groups of the Environmental](https://reader033.fdocuments.in/reader033/viewer/2022042110/5e8adf7634f17807751116fb/html5/thumbnails/59.jpg)
C L O S U R E W O R K I N G G R O U P | P R E - F E A S I B I L I T Y S T U D Y R E P O R T
CM I C E S I CW G | P R E - F E A S I B I L I T Y S T U D Y R E P O R T 59
Thangavel, P., Sridevi, G., Anjum, N.A., Ahmad, I., Pereira, M.E. (2013). Metal and Metalloids
Detoxification Mechanisms in Plants: Physiological and Biochemical Aspects. In Phytotechnologies:
Remediation of Environmental Contaminants, Anjum, N.A., Pereira, M.E., Ahmad, I, Duarte, A.C., Umar,
S., Khan, N.A. eds. (Boca Raton, FL: Taylor and Francis).
Update Report on Alberta Environment and Sustainable Resource Development’s Upstream Oil and
Gas Reclamation Certificate Program. (2013). Government of Alberta.
Van der Merwe, C. (2010a). EMS Completes Trials to Convert AMD to Potable Water. Mining Weekly.
(4 October 2010).
Van der Merwe, C. (2010b). Metal Nitrates Extracted from AMD Used in Explosives Test. Mining
Weekly. (15 November 2010).
Webster, M. & Hockley D. (2013). Stakeholder Engagement and Additional Remediation of the
Decommissioned Beaverlodge Uranium Mine Site. Paper presented to the British Columbia Mine
Reclamation Symposium, 2013.
Zagury, G.J., Neculita, C., Bussière, B. (2007). Passive Treatment of Acid Mine Drainage in Bioreactors:
Short Review, Applications, and Research Needs. Paper presented to the 60th Canadian Geotechnical
Conference (Ottawa, ON: 21-24 October 2007).
Zinck, J. & Griffith, W. (2013). Review of Mine Drainage Treatment and Sludge Management Options.
Mine Environment Neutral Drainage (MEND). (2013). Report No. 3.43.1
Zipper, C., Skousen, J., & Jage, C. (2013). Passive Treatment of Acid Mine Drainage. Virginia Cooperative
Extension: Powell River Project, Reclamation Guidelines for Surface Mined Land. Publication 460-133.