![Page 1: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/1.jpg)
Berrima Colliery -
Closure Working
Group
Meeting #2
Mittagong RSL 8 October 2018 >Welcome
![Page 2: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/2.jpg)
Titlefefefefeffff4g45g4545
Agenda
1. Welcome and Apologies
2. Review of minutes & actions
3. Terms of Reference
4. Groundwater storage volume
5. Water Quality Trends and Preliminary Macroinvertebrate Comments
6. EPA Presentation – Ecotoxicology Study
7. Bulkhead Seals Explanation
8. EPL/MOP Updates
9. Communications Plan
10.Loch Catherine Update
11.General business
12.Next meeting
![Page 3: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/3.jpg)
Titlefefefefeffff4g45g4545
Welcome - CWG Representatives, Apologies & Guests
● Boral - Fabio Colusso, Greg Johnson, David Spears,
● Resource Regulator - Greg Kininmonth, Will Mitry
● Environment Protection Authority - William Dove, Andrew Couldridge
● WaterNSW - Ravi Sundaram
● Wingecarribee Shire Council - Barry Arthur (apologies), Proxy?
● Western Sydney University - Dr Ian Wright
● Community - Clive West, Alan Lindsay, Graham Kelly, Ray Nolan, Julian Brophy
● Independent chair - Brad Mullard
● Minute taker – Rob Byrnes ● Guest - Pamela Klioufis
![Page 4: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/4.jpg)
Titlefefefefeffff4g45g4545
Review of Minutes – suggested amendments
![Page 5: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/5.jpg)
Titlefefefefeffff4g45g4545
Review of Actions
● CWG Terms of Reference and that it is not the only way Boral will engage with the Community
![Page 6: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/6.jpg)
Titlefefefefeffff4g45g4545
Terms of Reference
Minor change to clarify that the CWG will not be the only way Boral engages with the Community.
![Page 7: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/7.jpg)
Titlefefefefeffff4g45g4545
Estimated volume of water contained in the workings
548ML
(Based on: Mine ceasing discharge on
1/09/2015 and free draining on 21/03/2016.
203 days X 2.7ML = 548ML)
There was also a question in relation to the size of the
mine void in total:
5.5 million m2 x 2.2 m (seam height) x 0.4 (% recovery) =
4.8 Million cubic metres
This equates to around 7 Million tonnes (using SG of
1.45).
Or 4,800 ML if all the void could be filled with water, which
wouldn’t happen
![Page 8: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/8.jpg)
Titlefefefefeffff4g45g4545
The underground treatment was installed in 3 stages from early December
2017 until mid January 2018
![Page 9: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/9.jpg)
Titlefefefefeffff4g45g4545
Site and surrounding environment
![Page 10: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/10.jpg)
Titlefefefefeffff4g45g4545
Discharge Volumes
● Additional pumping commenced
early August 2018
● Water level has now dropped 800-
900mm
● Sufficient level to install bulkheads
● Additional pumping has ceased and
will revert to likely levels of 2.7ML
average
![Page 11: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/11.jpg)
Titlefefefefeffff4g45g4545
Water Quality Trends - pH & EC
![Page 12: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/12.jpg)
Titlefefefefeffff4g45g4545
Water Quality Trends - Iron and Manganese
![Page 13: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/13.jpg)
Titlefefefefeffff4g45g4545
Water Quality Trends - Nickel and Zinc
![Page 14: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/14.jpg)
Titlefefefefeffff4g45g4545
Water Quality Trends along the treatment path - Iron example
● 400 D12 Sump - Pump
pick up location
● 400 C8 - After
aeration, treatment
through lime bed and
filtered through goaf
● Adit Discharge - V -
Notch sample
![Page 15: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/15.jpg)
Titlefefefefeffff4g45g4545
Macroinvertebrate study update - Preliminary findings
Based on (two sampling occasions in Autumn 2018) similar story to what was observed previously (2017), although
thorough analysis not been completed at this stage.
● There was a loss of sensitive order mayflies (families Baetidae, Caenidae and Leptophlebiidae) and riffle beetle Elmidae upto
1km d/s of the adit.
● Stonefly Gripopterygidae was observed to be impacted 100m downstream (in 2017), however at 300-500m d/s this was not as
evident and appears to have recovered 500m d/s.
● There was some caddis missing (Philopotamidae) 500m d/s however they were present in good numbers 1km d/s.
● In general there appears to be an impact up to 1km downstream, however the macroinvertebrate fauna appear to be recovering
at this distance downstream.
● At 2km downstream the aquatic fauna appears to have fauna that were missing at sites 500m d/s and 1km d/s and I suspect
closer to upstream reference condition.
![Page 16: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/16.jpg)
Titlefefefefeffff4g45g4545
EPA Presentation – Ecotoxicology Assessment
![Page 17: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/17.jpg)
Titlefefefefeffff4g45g4545
Interim Sealing Plan - Location in respect of workings
![Page 18: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/18.jpg)
Titlefefefefeffff4g45g4545
Bulkhead Seal design - Explained
![Page 19: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/19.jpg)
Titlefefefefeffff4g45g4545
Environmental Protection Licence/ Mine Operations Plan Updates
EPL 608
● Background - Special Condition R3 was added to the EPL late last year as a means to monitor the
performance of the underground treatment trial. The condition requires water quality summary reports
to discuss effectiveness of the trial every 2 - 6 months and annual scientific reports including
sediment and macroinvertebrates due annually on 31 Jan 2019 and 31 January 2020.
● Boral difficulties
○ The Special Conditions were agreed prior to the installation of the complete system.
○ The full treatment system was not operational until mid January 2018.
○ Weather and other conditions (bushfire) can vary time of month sampling
○ Laboratory results can take 7+ days from sampling to be received
○ Macroinvertebrate numbers even longer
○ Time required to analyse and assess trends
● Administrative request submitted to the EPA to vary submission dates by 6 weeks
“to allow more time for the licensee's consultants to complete and synchronise the in-situ water quality, sediment and macro-
invertebrate sampling and report preparation as required in the Performance Monitoring Program”.
![Page 20: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/20.jpg)
Titlefefefefeffff4g45g4545
Environmental Protection Licence/ Mine Operations Plan Updates
MOP - Stage 1 Mine Closure Plan
Background - The current approved closure plan dated January 2018 excludes detail on the proposed
bulkheads. Post the last CWG Boral provided the Resources Regulator a letter update on the bulkheads as
an attachment to the Stage 1 Plan.
● The RR requested feedback from Water NSW and the NSW EPA.
● The RR also requested evidence from Mine Safety they were satisfied with proposed designs
● WaterNSW and the EPA requested how waters will be monitored during and post installation of
bulkheads.
Boral Actions
● Boral has agreed to an updated sampling plan that will be included in a letter amendment to the
MOP.
● Once the final bulkhead designs are finalised, Boral will further consult with Mine Safety and provide
correspondence with the RR
![Page 21: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/21.jpg)
Titlefefefefeffff4g45g4545
Communication Plan - Workshop
Pamela Klioufis
![Page 22: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/22.jpg)
Titlefefefefeffff4g45g4545
Loch Catherine Update
![Page 23: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/23.jpg)
Titlefefefefeffff4g45g4545
General business
![Page 24: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/24.jpg)
Titlefefefefeffff4g45g4545
Next meeting date
Proposing: Monday 11 February 2019
9am – 1pm
Location – Berrima Colliery (including a pit top site inspection)
![Page 25: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved](https://reader030.fdocuments.in/reader030/viewer/2022040712/5e1581384fbf050efe679aab/html5/thumbnails/25.jpg)