PRE FEASIBILITY REPORT FOR BUILDING STONE...
Transcript of PRE FEASIBILITY REPORT FOR BUILDING STONE...
Prepared by
SMS ENVOCARE LIMITED ,# 301, 3rd Floor, Shreshta Bumi Complex, K R Road, Bangalore – 560 004
PRE FEASIBILITY REPORT FOR
BUILDING STONE QUARRY
Applicant:
M/s. Hirehosba Stone Crusher
Sy.no.346/2,3 Hanehalli Village, Kumta Taluk, Uttara
Kannada District, Karnataka
1
1. Executive Summary
The proposed building stone quarry area is a private patta land belongs to M/s. Hirehosba
Stone Crusher situated at Sy.No. 346/2, 3 Hanehalli Village, Kumta Taluk &Uttara
Kannada District in an area of 4.00 Acres.
Mining of minor minerals with an area less than 50 ha. Of mining lease area are
categorized as category ‘B’ as per the notification S.O.2731 (E) dated 9th September, 2013.
According to office memorandum no. J-1301/12//2013-IA-II dated 24.12.2013 category B
has been further sub divided into category B1 and B2.
In further continuation vide OM No. L- 11011/47/2011-IA. II (M) dated 24.06.2013. B2
category will include minor minerals project with mining lease area <5.0 ha.
As per the Karnataka Minor Minerals Concession Rules, 1994 an approved mining plan
shall be submitted for getting mines work permit. The mining plan shall be duly certified
by RQP as per the requirement of Karnataka Minor Minerals Concession Rules, 1994 which
is enclosed as annexure-1.
The quarrying will be carried out by opencast semi mechanised method as per the
approved mining plan. The quarry area is a private patta land. The proposed rate of
production would be 73,260 M3/ annum. The estimated cost of the project isRs.30 Lakhs.
2. Introduction of the Project/Background information
i. Identification of project and project proponent. in case of mining project, a copy of
mining lease / letter of intent should be given:
The proposed building stone quarry area to M/s. Hirehosba Stone Crusher is located at
the Sy.No. 346/2,3 of Hanehalli Village, Kumta Taluk &Uttara Kannada, Karnataka. The
quarry area is of private patta land. The land owner has obtained land conversion from
Deputy Commissioner of Karwar for conversion for non-agriculture purpose
(quarrying) with approval letter no.ALN/1/VI VA-29/2015-16 dated 10th July 2015 and
also obtained the notification for quarrying of building stone from Department of
Mines & Geology, Uttara Kannada with vide letter DMG/UKD/AQL/NTN/04/2014-
15/3436, dated 29.01.2015 and the copy of notification is enclosed as annexure – 2.
The Department of Mines and Geology has directed the land owner to submit
approved quarry plan and obtain Environmental Clearance from State Environment
Impact Assessment Authority, (SEIAA) Karnataka. Accordingly, the quarry plan is
prepared under the pursuance of rule 27 and rule 18(3) & 32 of Karnataka Minor
Minerals Concession Rules – 1994” for 4.00 Acres and the copy quarry plan is enclosed
as annexure – 1. And the application for Environmental clearance along with this
report is submitted to MoEF for obtaining Environmental Clearance.
2
As per the technical report from the Department of Mines & Geology the proposed
area has enormous amount of economically viable building stone deposits and
therefore not fit for agricultural purpose.
ii. Brief Description of nature of project
The proposed quarry area is spread across over an area of 4.00 acres. The area is
abundant in building stone. The building stone shall be extracted by open cast with
semi mechanized method and processed further to produce final product suitable for
construction and building purpose.
iii. Need for the project and its importance to the country and or region
The Indian real estate sector has witnessed high growth in recent times with the rise for
office and residential spaces. The major need of building stone is due to its high
compressive strength and durability (among the hardest, dimensional & structural
stones) it can effectively withstand the vagaries of nature. Fine-grained granite is
employed for ornamental and monumental work as well as for inscription purposes.
The mineral-rich colours, and the hardness & density, makes it useful for many
applications. Polished slabs and tiles are used in countertops, flooring, retaining walls
and landscaping around a centre fountain/pond, staircase and many other design
elements (residential and commercial applications). It is also known as the
maintenance-free stone. The proposed mining project will full fill its end uses in
buildings and construction, bridges, paving, monuments and many other exterior
projects. The mining and associated activities in the mineral bearing areas bring about
gains in gross domestic product, i.e. there is though a minor contribution by the
proposed project but will add to the gains in G.D.P. (Gross Domestic Product).
iv. Demand and Supply Gap
The demand of building stone is huge and it is a continuous process.
v. Imports vs. Indigenous production
The demand for building stone is in only domestic market since it is a locally produced
product.
vi. Export Possibility
Since the building stone is a locally produced product there is no possibility of
exporting.
vii. Domestic and Export Markets
There is a continuous demand for building stone in the domestic market for all the
developmental & infrastructural projects.
3
viii. Employment Generation (Direct/Indirect) from the project
The Proposed quarry provides direct employment to ~ 35 people and generates
indirect employment for the surrounding localities. The direct employment includes
labours from highly skilled to Unskilled. Highly skilled labours would be quarry
manager, quarry engineer and etc. Skilled labours would include quarry foreman, Jack
drill machinery operators, mechanics etc. And Unskilled labours would be helpers,
cleaners etc.
3. Project Description
i. Type of Project including interlinked and interdependent projects, if any.
The Proposed quarry is an independent project and not interlinked to any other
projects. The project is based on the quarrying of building stone from 4.00 acres of
land.
ii. Location (map showing general location, specific location and project boundary and
project site layout) with coordinates.
The Proposed quarry area is located at the Sy.No. 346/2, 3 of Hanehalli Village, Kumta
Taluk and Uttara Kannada District, Karnataka. As per the Survey of India (SOI), the
quarry area falls on Toposheet no. 48 J/06 with Latitude N 14° 33’ 40.8” & N 14° 33’
48.0” and Longitude E 74° 19’ 32.9”&E 74° 19’ 35.4” and the same is shown in the plate-
2.The location of quarry area is depicted in the plate-1 and the Satellite imagery with 5
Kms radius surrounding the quarry area is depicted in the plate-3.
iii. Details of alternate sites
The proposed area for quarrying is site specific and no alternative site is selected.
iv. Size or Magnitude of operation
The estimation of reserves has been made on the basis of the cross sectional method. The proved reserves are estimated up to a combined depth of 18m. Based on the experience gained by the earlier activities, around 95% of the geological reserves are taken as recoverable. The Mineable reserves of the applied area were carried out as per the field studies and geological mapping after leaving the buffer zone of 7.5 meters all along the lease boundary. The conventional method of total sectional area in square meters, depth in meters and recovery factor of 95%. The detail of Mineable Reserves is furnished in Table – 1.
Table 1: Mineable Reserves
RL
Area in M2
Depth in m
Volume in Cu.m.
Recovery factor (%)
Total Reserves m3
Specific Gravity
Total Reserves Tons
Proved 60-20 5,932 40 2,37,280 95 2,25,416 2.7 6,08,623
Proved 45-20 5,932 25 1,48,300 95 1,40,885 2.7 3,80,390
11,864
Total 3,66,301
9,89,013
4
The proposed quantity of granite extraction from the said area of 4.00 acres of land in
the village of Hanehalli would be 2,65,050 M3/ five years when the quarry is fully
functional. On an average 4,417 M3/month would be produced. The detailed
production assessment plan for the first five years is given below:
Table 1: Production Assessment for first five Years
Year RL Area in M2
Depth in m
Volume in Cu.m.
Recovery factor
(%)
Total Reserves
m3
Specific Gravity
Total Reserves
Tons 1st 60-20 1,200 40 48,000 95 45,600 2.7 1,23,120
2nd 60-20 1,200 40 48,000 95 45,600 2.7 1,23,120
3rd 60-20 1,200 40 48,000 95 45,600 2.7 1,23,120
4th 45-20 2,700 25 67,500 95 64,125 2.7 1,73,138
5th 45-20 2,700 25 67,500 95 64,125 2.7 1,73,138
9,000
Total 2,65,050
7,15,635
v. Project description with process details (a schematic diagram/flow chart showing the
project layout, components of the project etc. should be given).
The said quarry of building stone would be extracted by open cast method by manually
and semi mechanised method by using air compressor operated jack hammer drills,
excavators, truck dumpers etc. Since the rocks and reserves are exposed, the open cast
quarrying is sufficient enough to extract the deposits. Further continuous development
and production will be ensured till the deposits exhaust. The flow chart of the project is
as follows:
5
Figure 1 Flowchart of the Quarry Process
Open Cast Method
Drilling
Dislodging
Dressing
Bench Formation
Excavation
Secondary drilling & blasting
Loading
Transportation
Processing of Raw material
Final Product
6
vi. Raw material required along with estimated quantity, likely source, marketing area of
final product/s , mode of transport of raw material and finished product and Finished
Product
The said project is not manufacturing any product as such. The project’s process itself is
involved in extracting raw material i.e., rock from the earth and process further into
desired size of jelly stone. The raw material from the site to the processing plant would
be transported via trucks and Lorries. The finished products from the outlet to
customers would be transported in suitable vehicles based on the quantity. The
finished product will be sold out in domestic market.
vii. Resource Optimization/recycling and reuse envisaged in the project, if any, should be
briefly outlined.
The said quarry area is a hillock and the top soil generated during the process of
quarrying is very minimal. However, topsoil excavated from the quarry will be dumped
separately at pre-determined place and subsequently will be utilized in spreading over
reclaimed areas for plantation.
About 5% of the reserves are considered as waste. The waste rock mainly consists of
weathered rock and intercalated wastes which are non-toxic in nature. The 60% of
waste will be used for retention wall, agriculture, roads etc., and the 40% of waste will
be transported to dump yard designated for the purpose. Therefore, the waste dump
area identified is sufficient to accommodate the dump in a phase wise manner.
viii. Availability of water, energy sources/ power requirement and source should be given.
The water is used for the domestic purpose and for the suppression of dust particles
generated by transportation of raw material on haul roads. There are borewells in the
neighbouring site from which the water will be sourced for said purposes. For the
operation of Air Compressors DG sets will be utilized.
The total water requirement is as follows:
Table 2 Water Consumption
Sl.no Particulars Quantity in KLD
1. Domestic Purpose 2.8
2. Dust Suppression 4.0
TOTAL 6.8
ix. Quantity of waste to be generated (Liquid & Solid)
As such there will be no liquid waste generated from the entire process apart from
sewage waste generated from the office which is about 2.24 KLD and the solid waste
generated from the process would be only the weathered material of granitic gneisses
and its associated rocks with secondary intrusive. Weathered and highly fragmented
rock is also considered as waste along with chipped out remains of building stone
formed due to the quarrying process which will be utilised for back filling of the pit
7
formed due to quarrying and also can be used as aggregates in road and building
constructions.
4. Site Analysis
i. Connectivity
The said quarry area is very well connected to roads and railways. The distance from
the site to NH-17 is about 11 Kms.
The distance from the site to Gokarna Road Railway station is about 8 Kms.
The Distance from the site to Mangalore airport is about 160 Kms.
ii. Land form, Land use and Land Ownership
The said quarry land is a private land. Due to the presence of abundant rock material
just 1-3 m below from the top soil the said land is not suitable for agricultural purpose.
The private land belongs to M/s. Hirehosba Stone Crusher with the Sy.No. 346/2, 3 of
Hanehalli Village, Kumta Taluk and Uttara Kannada District, Karnataka.
iii. Topography (along with map).
The area identified is highly undulating terrain surrounded by rolling pediment and
pediplain shallow. In this terrain, Granitic gneiss is the basement rock formation above
which, grey granite is over lined with various dimensions horizontally and vertically.
The litho unit is partially exposed as well as hidden type in the identified area and the
trend of the formation is North 18⁰ West to South 18⁰ East. The highest ground level of
the area is around 85 m above mean sea level as per the GPS readings and also
Toposheet No. 48J/06. The quarry area is well connected by metalled and asphalted
roads.
iv. Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including
area under CRZ), shortest distances from the periphery of the project to periphery of the
forests, national park, wildlife sanctuary, eco sensitive areas, water bodies (distance from
the HFL of the river), CRZ. In case of the notified industrial area, a copy the Gazette
notification should be given.
The present land use pattern of the proposed quarry area is as follows:
Table 4: Present Land Use Pattern
S. No. Type of Land use Area in percentage 1 Area already degraded due to Quarrying/Pitting Not Applicable
2 Dumping Not Applicable
3 Roads Not Applicable
4 Processing plant Not Applicable
5 Workshop Not Applicable
6 Township Not Applicable
7 Others Not Applicable
8
The Proposed area is a non-agricultural land and there are no forests, national parks,
wildlife sanctuary, eco sensitive areas, water bodies, CRZ within the radius of 5 km from
the periphery of the proposed quarry site area.
v. Existing Infrastructure
The construction of site services like site office, workers shelter, site workshop, store
room and first aid counter will be constructed in the non- mineable area. Drinking
water facility will be made available for the labourers.
The post office is situated from the quarry site at a distance of 3.5Km at Gokarna
village and the power line passes at a distance of 60m from the identified quarry site.
The nearest railway station is at Ankola, which is located about 30Km north-west of the
site. The nearest port identified is Karwar at a distance of 58 Km from the site.
vi. Soil Classification
The area is covered by thick lateritic soil derived from chemical weathering of
basement rock granitic gneiss as well as over lined granitic formation. Pegmatite veins
are observed at the elevated portions and are identified as thin linear patches
embedded within the gneisses and granites. Grey granites are identified in the form of
younger rock types at shallow depths and are exposed rarely in the vicinity with
differential elevations.
The area is covered by thick layer of lateritic soil derived from chemical weathering of
granites and gneisses. The soil sometime looks like yellowish sandy and loamy and is to
medium grained in nature. The maximum thickness of the soil noticed in the area is
around 2.5 m at slopes.
These are the acidic intrusions embedded within the crevices of granitic gneiss and
granites. Thin intrusions of pegmatite veins were noticed in rock cut areas and are
white in colour due to enrichment of orthoclase minerals. The intrusions are seen
sporadically at deeper levels.
Granites occur in the form of exposure in and around the identified area and are grey
in colour with fine grain size. Granites are locally identified as building stones with
varying thickness and extended NNW to SSE in direction, cutting across the basement
rock granitic gneisses. The deposits run over a length of about 200 m with varied
thickness.
The study area is underlined by granitic gneisses, having strike direction NNW to SSE
and dipping towards south to south-east with 68⁰ to 70⁰ slope. The foliation and
lineation can significantly be seen in the gneisses with uniform mineral assemblage.
9
Figure 2 Local Geological Sequence
vii. Climatic Data from secondary sources
The climate in Uttara Kannada district is Tropical monsoon climate. The weather is
generally hot and humid throughout the year in the coastal zones. The district falls
under highly agro-climatic zone except the western parts of Karwar, Ankola, Kumta,
Honnavar and Bhatkal which fall under coastal agro climatical zone. The temperature
starts rising from January to peak May. The mean maximum temperature ranges from
28.2°C to 37.6°C. The mean minimum temperature ranges from 19°C to 27°C.
viii. Social infrastructure
The said quarry area is located towards NW direction of village. Karwar is district Head
Quarters and Kumta is the Taluk. All the facilities such as Schools, Colleges, hospitals,
Police Station and Railway Station are accessible in the Gokarna Town.
5. Planning Brief
i. Planning Concept (type of industries, facilities, transportation etc.) town and country
planning/development authority classification.
The proposed project is a quarrying of minor mineral in Hanehalli village of Kumta
Taluk which has good infrastructure in terms of water availability, Road/ rail
connectivity and power availability. Since the site is just few kilometres away from
State and National Highways which is most suitable for transportation of raw materials
to processing plants and as well as finished goods.
ii. Population Projection
The said project employs labours from the nearby villages so there will be no increase
in the population.
Lateritic Soil
Pegmatite
Grey Granite
Granitic
Gneiss
10
iii. Land use Planning (break up along with green belt etc.)
Table 5 proposed land use planning
Sl.no. Particulars Area in
Acres
Area in
Sq.m Area in %
1. Quarry Area 2.23 9,000 55.75
2. Mineral Storage Yard 0 0 0
3. Waste Dump Yard 0.67 2,670 16.75
4. Quarry Infrastructure 0 0 0
5. Roads/ Country Track 0.07 236 1.75
6. Un trenched area 0 0 0
7. Green Belt/ Buffer
Zone 1.03 4,158 25.75
Total 4.00 16,064 100.00
iv. Assessment of infrastructure demand (physical &Social)
The existing road network will be sufficient to meet the proposed production capacity.
However, required infrastructure for transport within the leasehold area will be further
strengthened and improved. No new routes or alternations are required in this regards.
v. Amenities/facilities
The construction of site services like site office, workers shelter, site workshop, store
room and first aid counter will be constructed in the non- mineable area. Drinking
water facility will be made available for the labourers.
6. Proposed Infrastructure
i. Industrial Area (Processing area)
The proposed area is very well connected by roads. The area is self-sufficient to cater
the needs of the project. Hence, no infrastructure is proposed.
ii. Residential Area
Since the local persons will be employed, no residential area or housing is proposed
except the labour shed.
iii. Green Belt
Plantation will be carried out along the approach road, in the bund around the quarry
site and nearby village roads. Rain tree (Samanea saman), Honge (Millettia pinnata),
Neem (Azadirachta indica), and other local species will be planted. It is proposed to
plant with 30 saplings annually. Anticipated survival rate is 70-80%.
11
Table 6 Afforestation Programme for five years
Year Numbers Saplings Species
1st 40
Rain tree (Samanea saman),
Honge (Millettia pinnata),
Neem (Azadirachta indica),
and other local species
2nd 40
3rd 40
4th 40
5th 40
TOTAL 200
iv. Social Infrastructure
Additional social infrastructure is not proposed.
v. Connectivity
The proposed quarry area is very well connected to road and railway network.
Therefore additional connectivity network is not proposed.
vi. Drinking Water Management
The drinking water is sourced from nearby bore well which is further purified by water
purifiers. The detailed water balance is specified in the table – 3 of above section.
vii. Sewerage System
The sewage generated from the site office which is about 2.24 KLD will be diverted to
septic tank followed by soak pit.
viii. Industrial Waste Management
There will be no industrial waste generated from the proposed project.
ix. Solid Waste Management
The solid waste generated from the process is only the weathered rock and chipped
out remains of black granite which will be used for back filling of the pit formed due to
quarrying and also will be sued as aggregates for building and road construction.
x. Power requirement & Supply
The total power requirement will be used by HESCOM for Infrastructure.
12
7. Rehabilitation & Resettlement Plan
i. R & R policy to be adopted (central/State) in respect of the project affected persons
including home out sees, land out sees and landless labourers (a brief outline to be
given).
The proposed quarry project does not involve shifting of any village or human
settlements and is a private land therefore rehabilitation and resettlement plan is
not proposed.
ii. Amenities/facilities
Not Proposed.
8. Project Schedule & Cost Estimates
A. Likely date of start of construction and likely date of completion (Time
schedule for the project to be given).
The quarrying activity in the proposed area will be started after obtaining
Environmental Clearance from SEIAA, Karnataka.
B. Estimated project cost along with the analysis in terms of economic viability
of the project.
The total estimated cost for the proposed project including operation & maintenance
would be Rs. 30 Lakhs.
Expenditure proposed for Environmental protection activities:
It is proposed to invest an amount of Rs.4, 00,000/- Per annum towards environmental
action plan and the details of the same are given below:
Table 7 Proposed Cost for Environmental Protection
Sl.no Particulars Recurring Cost (in Lakhs)
1 Air pollution control – Water sprinkling 0.50
2 Afforestation works 0.50
3 Retaining walls etc 2.0
4 Environmental Monitoring 0.5
5 Personnel Protective Equipments 0.50
TOTAL 4.00
9. Analysis of Proposal
I. Financial and social benefits with special emphasis on the benefit to the local
people including tribal population, if any, in the area.
No tribal population is residing in the proposed area. There will be social
benefit from said quarrying project. As mentioned in the earlier section the
13
said project will improve the standard living of the local population by
providing direct and indirect employment. There is no requirement of
Rehabilitation and resettlement policy for the said project. Also it will not have
any impact on the environment of the proposed area. Though the building
stone is a minor mineral but has its own contribution to our GDP.