PRDH12-2 - Session 13

download PRDH12-2 - Session 13

of 21

Transcript of PRDH12-2 - Session 13

  • 7/30/2019 PRDH12-2 - Session 13

    1/21

  • 7/30/2019 PRDH12-2 - Session 13

    2/21

    Dipankar Bose - XLRI

    Product A

    Profit = Rs. 80/unit

    Demand = 100/week

    Production = 0.4 hours/unit

    Product B

    Profit = Rs. 50/unit

    Demand = 200/week Production = 0.2 hours/unit

    Total available time = 60 hours/week

    What will be maximum profit?

  • 7/30/2019 PRDH12-2 - Session 13

    3/21

    Dipankar Bose - XLRI

    Throughput The rate at which products are sold

    Limited by internal constraints (plant capacity)

    Limited by external constraints (market demand)

    Constraint Anything that limits a systems performancerelative to its goal Bottleneck

    Inventory All the money used to purchase things the

    system intends to sell

    Paid but not sold Operating expense The money a system spends to turn

    inventory into throughput

    Throughput accounting An accounting system used to

    measure TOC operations

  • 7/30/2019 PRDH12-2 - Session 13

    4/21

    Dipankar Bose - XLRI

    Process batch Quantity of product processed at a work

    center before the work center is reset to produce another

    product

    Should be variable Transfer batch Quantity of product that move from one

    work center to next

    Should be small in size

    Two critical assumptions The goal of product or customer mix and volume

    should be to maximize throughput

    Once a certain capacity exists, operating expenses are

    fixed

  • 7/30/2019 PRDH12-2 - Session 13

    5/21

    Dipankar Bose - XLRI

    Balance flow, not capacity

    An hour lost at a bottleneck is an hour lost forever

    An hour saved at a non-bottleneck has no value

    Bottlenecks govern both throughput and inventory in thesystem

    Schedules should be established by looking at all

    constraints simultaneously

    The level of utilization of a non-bottleneck is determinednot by its own potential

    But by some other constraint in the system

    Utilization and activation of a resource are not

    synonymous

  • 7/30/2019 PRDH12-2 - Session 13

    6/21

    Dipankar Bose - XLRI

    the systems constraints

    Decide how to the constraints

    everything else to the exploitation of

    constraints the systems constraint

    If any of the constraints are violated, repeat the process

  • 7/30/2019 PRDH12-2 - Session 13

    7/21Dipankar Bose - XLRI

    Constraint management

    Synchronous/synchronized manufacturing (General

    Motors)

    Optimized Production Technology (OPT) software Drum-Buffer-Rope system

    Throughput technology

  • 7/30/2019 PRDH12-2 - Session 13

    8/21Dipankar Bose - XLRI

    The drum is the physical constraint of the plant

    The work center or machine or operation that limits the

    ability of the entire system to produce more

    The rest of the plant follows the beat of the drum They make sure that the drum has work and anything the

    drum has processed does not get wasted

    The buffer protects the drum

    The buffer always has work flowing to it Buffers in DBR have time as their unit of measure, rather

    than quantity of material

    This makes the priority system operate strictly based on

    the time an order is expected to be at the drum

  • 7/30/2019 PRDH12-2 - Session 13

    9/21Dipankar Bose - XLRI

    Traditional DBR usually calls for buffers for protection

    against several points in the system

    For the Drum Constraint Buffer

    For assembly of constraint & non-constraintAssembly Buffer

    For Due date Shipping Buffer

    The rope is the work release mechanism for the plant

    Only a "buffer time" before an order is due It gets released into the plant

    Pulling work into the system earlier than a buffer time

    Guarantees high work-in-process

    Slows down the entire system

  • 7/30/2019 PRDH12-2 - Session 13

    10/21

    Dipankar Bose - XLRI

    Exploit the drums

    Work drums continuously

    Reduce set-ups

    Off-load work to non-drum work centers Subordinate everything to drum

    Staffing

    Maintenance

    Engineering Support Run non-constraints using FIFO

    Buffer coordinator expedites at non-constraints to meet

    drum schedules

  • 7/30/2019 PRDH12-2 - Session 13

    11/21

    Dipankar Bose - XLRI

    Elevate DrumIncrease Capacity

    Add Capacity

    Process Improvements

    Offload Start OverIdentify new constraint

    Change Company Culture

    Educate Personnel in DBR/TOC

    Eliminate Cost Accounting Based PerformanceMeasures (Productivity, Efficiency, Product Cost, etc.)

    Its O.K. for non-drums to be idle

    Change culture company-wide, not just manufacturing

  • 7/30/2019 PRDH12-2 - Session 13

    12/21

    Dipankar Bose - XLRI

  • 7/30/2019 PRDH12-2 - Session 13

    13/21

    Dipankar Bose - XLRI

    A project will accumulate delays, it will not accumulate

    gains

    Individuals always desire a safety buffer

    No early finishes Parkinsons Law

    Student Syndrome

    Multi-tasking

  • 7/30/2019 PRDH12-2 - Session 13

    14/21

    Dipankar Bose - XLRI

    Halve original time estimates and apply CPM to prepare

    late start (LS) schedule

    If there is resource contention in the schedule obtained in

    Step 1, resolve it going backward in time and reschedulethe activities ensuring the minimum increase in the project

    duration. Avoid multi-tasking in the process

    Identify the critical chain. If there are more than one,

    choose any one of them Add a Project Buffer (PB) at the end of the project. It is

    equal to half of the total time stripped off the critical chain

    activities. The method is called the 50% cut-and-paste

    method of buffer sizing.

  • 7/30/2019 PRDH12-2 - Session 13

    15/21

    Dipankar Bose - XLRI

    Add Feeding Buffers (FB) at the places where non-critical

    chain activities merge into the critical chain, to protect the

    critical chain from any variations in the non-critical chain

    activities. The size of FB is again equal to the half of thetotal time stripped off the longest chain of non-critical

    activities

    Consider the Resource Buffer (RB) as a virtual task inserted

    prior to critical chain tasks that require critical resources Buffer management Green-Yellow-Red Rule

    Drum Buffer/Capacity Buffer Resources shared among

    multiple projects

  • 7/30/2019 PRDH12-2 - Session 13

    16/21

    Dipankar Bose - XLRI

    Identify CCRs

    Paretos Rule may help

    CCR has limited activities in any one project

    Identify CCR as the Drum Make the most of this resource

    Holdup of CCR is a delay in the project

    Protect from statistical fluctuations with time buffers

    (Buffer) Monitor Buffer Buffer Management (BM)

    Monitor CCRs to ensure the timely release of materials

    upstream (Rope)

    Subordinate other resources to CCR

  • 7/30/2019 PRDH12-2 - Session 13

    17/21

    Dipankar Bose - XLRI

    A (30) B (15)

    C (20) D (20)

    X

    X

    Y

    Z

  • 7/30/2019 PRDH12-2 - Session 13

    18/21

    Dipankar Bose - XLRI

    A (15) B (8)

    C (10) D (10)

    X

    X

    Y

    Z

  • 7/30/2019 PRDH12-2 - Session 13

    19/21

    Dipankar Bose - XLRI

    ES advantages

    Slack is available

    We can get payment if payment is based on % of job

    finished Takes care of uncertainties

    LS advantage

    Reduces WIP inventory Capital output is delayed

    Allows to incorporate last minute changes

  • 7/30/2019 PRDH12-2 - Session 13

    20/21

    Dipankar Bose - XLRI

  • 7/30/2019 PRDH12-2 - Session 13

    21/21

    Dipankar Bose - XLRI