PRDH12-2 - Session 13
-
Upload
priya-jain-mittal -
Category
Documents
-
view
217 -
download
0
Transcript of PRDH12-2 - Session 13
-
7/30/2019 PRDH12-2 - Session 13
1/21
-
7/30/2019 PRDH12-2 - Session 13
2/21
Dipankar Bose - XLRI
Product A
Profit = Rs. 80/unit
Demand = 100/week
Production = 0.4 hours/unit
Product B
Profit = Rs. 50/unit
Demand = 200/week Production = 0.2 hours/unit
Total available time = 60 hours/week
What will be maximum profit?
-
7/30/2019 PRDH12-2 - Session 13
3/21
Dipankar Bose - XLRI
Throughput The rate at which products are sold
Limited by internal constraints (plant capacity)
Limited by external constraints (market demand)
Constraint Anything that limits a systems performancerelative to its goal Bottleneck
Inventory All the money used to purchase things the
system intends to sell
Paid but not sold Operating expense The money a system spends to turn
inventory into throughput
Throughput accounting An accounting system used to
measure TOC operations
-
7/30/2019 PRDH12-2 - Session 13
4/21
Dipankar Bose - XLRI
Process batch Quantity of product processed at a work
center before the work center is reset to produce another
product
Should be variable Transfer batch Quantity of product that move from one
work center to next
Should be small in size
Two critical assumptions The goal of product or customer mix and volume
should be to maximize throughput
Once a certain capacity exists, operating expenses are
fixed
-
7/30/2019 PRDH12-2 - Session 13
5/21
Dipankar Bose - XLRI
Balance flow, not capacity
An hour lost at a bottleneck is an hour lost forever
An hour saved at a non-bottleneck has no value
Bottlenecks govern both throughput and inventory in thesystem
Schedules should be established by looking at all
constraints simultaneously
The level of utilization of a non-bottleneck is determinednot by its own potential
But by some other constraint in the system
Utilization and activation of a resource are not
synonymous
-
7/30/2019 PRDH12-2 - Session 13
6/21
Dipankar Bose - XLRI
the systems constraints
Decide how to the constraints
everything else to the exploitation of
constraints the systems constraint
If any of the constraints are violated, repeat the process
-
7/30/2019 PRDH12-2 - Session 13
7/21Dipankar Bose - XLRI
Constraint management
Synchronous/synchronized manufacturing (General
Motors)
Optimized Production Technology (OPT) software Drum-Buffer-Rope system
Throughput technology
-
7/30/2019 PRDH12-2 - Session 13
8/21Dipankar Bose - XLRI
The drum is the physical constraint of the plant
The work center or machine or operation that limits the
ability of the entire system to produce more
The rest of the plant follows the beat of the drum They make sure that the drum has work and anything the
drum has processed does not get wasted
The buffer protects the drum
The buffer always has work flowing to it Buffers in DBR have time as their unit of measure, rather
than quantity of material
This makes the priority system operate strictly based on
the time an order is expected to be at the drum
-
7/30/2019 PRDH12-2 - Session 13
9/21Dipankar Bose - XLRI
Traditional DBR usually calls for buffers for protection
against several points in the system
For the Drum Constraint Buffer
For assembly of constraint & non-constraintAssembly Buffer
For Due date Shipping Buffer
The rope is the work release mechanism for the plant
Only a "buffer time" before an order is due It gets released into the plant
Pulling work into the system earlier than a buffer time
Guarantees high work-in-process
Slows down the entire system
-
7/30/2019 PRDH12-2 - Session 13
10/21
Dipankar Bose - XLRI
Exploit the drums
Work drums continuously
Reduce set-ups
Off-load work to non-drum work centers Subordinate everything to drum
Staffing
Maintenance
Engineering Support Run non-constraints using FIFO
Buffer coordinator expedites at non-constraints to meet
drum schedules
-
7/30/2019 PRDH12-2 - Session 13
11/21
Dipankar Bose - XLRI
Elevate DrumIncrease Capacity
Add Capacity
Process Improvements
Offload Start OverIdentify new constraint
Change Company Culture
Educate Personnel in DBR/TOC
Eliminate Cost Accounting Based PerformanceMeasures (Productivity, Efficiency, Product Cost, etc.)
Its O.K. for non-drums to be idle
Change culture company-wide, not just manufacturing
-
7/30/2019 PRDH12-2 - Session 13
12/21
Dipankar Bose - XLRI
-
7/30/2019 PRDH12-2 - Session 13
13/21
Dipankar Bose - XLRI
A project will accumulate delays, it will not accumulate
gains
Individuals always desire a safety buffer
No early finishes Parkinsons Law
Student Syndrome
Multi-tasking
-
7/30/2019 PRDH12-2 - Session 13
14/21
Dipankar Bose - XLRI
Halve original time estimates and apply CPM to prepare
late start (LS) schedule
If there is resource contention in the schedule obtained in
Step 1, resolve it going backward in time and reschedulethe activities ensuring the minimum increase in the project
duration. Avoid multi-tasking in the process
Identify the critical chain. If there are more than one,
choose any one of them Add a Project Buffer (PB) at the end of the project. It is
equal to half of the total time stripped off the critical chain
activities. The method is called the 50% cut-and-paste
method of buffer sizing.
-
7/30/2019 PRDH12-2 - Session 13
15/21
Dipankar Bose - XLRI
Add Feeding Buffers (FB) at the places where non-critical
chain activities merge into the critical chain, to protect the
critical chain from any variations in the non-critical chain
activities. The size of FB is again equal to the half of thetotal time stripped off the longest chain of non-critical
activities
Consider the Resource Buffer (RB) as a virtual task inserted
prior to critical chain tasks that require critical resources Buffer management Green-Yellow-Red Rule
Drum Buffer/Capacity Buffer Resources shared among
multiple projects
-
7/30/2019 PRDH12-2 - Session 13
16/21
Dipankar Bose - XLRI
Identify CCRs
Paretos Rule may help
CCR has limited activities in any one project
Identify CCR as the Drum Make the most of this resource
Holdup of CCR is a delay in the project
Protect from statistical fluctuations with time buffers
(Buffer) Monitor Buffer Buffer Management (BM)
Monitor CCRs to ensure the timely release of materials
upstream (Rope)
Subordinate other resources to CCR
-
7/30/2019 PRDH12-2 - Session 13
17/21
Dipankar Bose - XLRI
A (30) B (15)
C (20) D (20)
X
X
Y
Z
-
7/30/2019 PRDH12-2 - Session 13
18/21
Dipankar Bose - XLRI
A (15) B (8)
C (10) D (10)
X
X
Y
Z
-
7/30/2019 PRDH12-2 - Session 13
19/21
Dipankar Bose - XLRI
ES advantages
Slack is available
We can get payment if payment is based on % of job
finished Takes care of uncertainties
LS advantage
Reduces WIP inventory Capital output is delayed
Allows to incorporate last minute changes
-
7/30/2019 PRDH12-2 - Session 13
20/21
Dipankar Bose - XLRI
-
7/30/2019 PRDH12-2 - Session 13
21/21
Dipankar Bose - XLRI