Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch...

34
Practical project risk assessment Simon White APM North West branch & APM Risk Management SIG A world in which all projects succeed - but not without risk management 10 th October 2016, Alderley Park Conference Centre

Transcript of Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch...

Page 1: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Practical project risk

assessment

Simon White

APM North West branch & APM Risk Management SIG

A world in which all projects succeed - but not without risk management

10th October 2016, Alderley Park Conference Centre

Page 2: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

• Introduction

• Project risk …

– Assessment

– Analysis

– Awareness

• Summary

A g e n d a

Page 3: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Poll – your role and experience

• What is your role?

– Risk manager (specific “risk” role)

– Project team member (engineer, analyst, …)

– Project manager (project controls, PMO, support, …)

– Other

• Have you been in a risk workshop?

– Yes / No

• If yes, did you see any output from a QRA (e.g. a P90, or S-curve)?

– Yes / No

• If yes, did you believe it?

– Yes / No

Page 4: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Key concepts

• probability

• expectation

• three-point estimate

• impact

• exposure

• contingency

• mitigation

• probability distribution

• P10, P50, P90

Page 5: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Poll – key concepts

• What do you mean by “mitigation”? – Plans put in place in advance to make it better

– Avoiding it

– Dealing with it when (or if) it happens

• What do you mean by “contingency”? – The cost if it happens

– The amount we set aside for risk

– The amount we spend to mitigate risk

• What do you mean by “fall-back”? – Dealing with it when (or if) it happens

– The plan if the contingency fails

– Plans put in place in advance to make it better

Page 6: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Introduction

Page 7: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Risk …

• Assessment

– Beliefs: what do we believe about the risk?

• Analysis

– Effects: what does it mean to the overall project?

• Awareness

– Actions: what should we do about it?

Page 8: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Expressing risk

• Two popular ways of expressing risk: 1. Probability and impact (risk register)

2. Three-point estimate

“Three-point estimate”

VH

Major

scope

change

H

DECC

requires

recycle

M

Delay to

lift vessel

arrival

LSIMOPS

issues

L M H VH

Probability

Imp

act

Page 9: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Expressing risk

• Never been done before

• Challenging conditions

• Uncertain regulations

• Early phase

• Been done before

• Easy conditions

• Established regulations

• Mid-execution

P10P50

P90

Base

P10P50

P90

Base

• “Cheaper but

more risky”

• “More expensive,

less risky”

X

X

Page 10: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Assessment

Page 11: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

The risk workshop

• Valuable discussion: assumptions, inter-discipline issues, allows honesty

• Structured approach, best practice

• Engage project team, management and stakeholders

• Skilled facilitation, ensuring contribution from all team members, keeping focus

• Identify, discuss and qualify risks

– Cause, risk, effect

– Probability (H / M / L …)

– Impact on schedule, cost and safety, production, operations (H / M / L …)

• Capture mitigation options and fallback options

– Effect of mitigation

– Agree action owners and deadlines

– Make decisions – is it worth mitigating?

Probability Impact Score

Major scope change M VH 25

SIMOPS issues H L 17

DECC requires recycle L H 15

Delay to lift vessel arrival L M 9

… …

Page 12: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

The risk workshop

• Risks can be ranked and summarised

• Give focus on response / mitigation

• Establish agreement

• Demonstrate robustness

• What are our top risks?

• A useful live project document

• Track response actions

• Keep risk visible throughout planning and execution

• But …

• Quantitative risk assessment adds more value …

VH

Major

scope

change

H

DECC

requires

recycle

M

Delay to

lift vessel

arrival

LSIMOPS

issues

L M H VH

Probability

Imp

act

Page 13: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

The quantitative risk assessment

• Base cost estimate (CBS) – Around 20-50 high-level cost elements

– Allowances / contingency identified

• Optionally: Base schedule (WBS) – Around 50-300 activities

– Allowances / contingency identified

– “Forward-driven” logic

– Can use existing schedule, or create in a workshop

• Any risks already identified

Page 14: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

The quantitative risk assessment

• Quantify significant risks – Probability (%)

– Cost impact in £: P10, P50 and P90 (if it occurs)

– Schedule impact in days: P10, P50 and P90 (if it occurs)

• Associate the risks with the schedule activities (WBS) – E.g. “Delay to lift vessel arrival” will impact installation activities

• Associate the risks with the cost elements (CBS) – E.g. “Delay to lift vessel arrival” will impact topsides cost

(optional)

Page 15: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

The quantitative risk assessment

• May or may not happen (probability)

• Deviation from base, if it happens (impact)

“Impact”

“Pro

babili

ty”

“Impact”

“Pro

babili

ty”

Page 16: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

• Further quantitative assessments – Cost variance (-5% / +10% for jacket fabrication cost)

– Schedule variance (-10% / +30% for engineering activities)

– Variance accounts for:

• Estimating uncertainty

• Risks not specifically modelled

• Deviation from base

– Correlation (all fabrication costs are uncertain because of common

causes)

The quantitative risk assessment

Base cost

“Three-point estimate”

Page 17: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

The quantitative risk assessment

• Use the uniform or triangular distribution, or better

Single value 1-point estimateMore knowledge /

less uncertainty

Beta Pert(larger shape parameter,

default shape parameter of 4)

3-point estimate

Triangle / Trigen 3-point estimate

Beta Pert(smaller shape parameter)

3-point estimate

Uniform 2-point estimateLess knowledge /

more uncertainty

Credit: from Centrica Energy’s QRA training manual

Page 18: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Analysis

Page 19: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Quantitative risk analysis

• The risk model shows the effect of the risk assessment,

on the overall project

Base

estimate

(MM USD)

Bulks 2.3

Fabrication 5.7

Transportation 1.9

Heavy lift vessel 1.6

Hook-up and

commissioning

4.3

Project services 0.6

Total 16.4

The P90 is a "reasonably likely" worst case.

Contingency at P90 = 6.6

“Exposure”

“Probability distribution”

Page 20: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Example project risk analysis

• Simple schedule

– Activities, durations, logic

– Costs (lump sums and day rates)

– Risks, variance, associated with activities and costs

• Risk analysis gives us

– Probabilistic finish date

– Probabilistic costs

– Much more

Page 21: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Other analysis outputs

• The total contingency can be shown (on average)

against the individual costs

Page 22: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Other analysis outputs

• The total contingency can be shown (on average)

phased over time

Page 23: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Awareness

Page 24: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Awareness

• Never been done before

• Challenging conditions

• Uncertain regulations

• Early phase

• Been done before

• Easy conditions

• Established regulations

• Mid-execution

P10P50

P90

Base

P10P50

P90

Base

• “Cheaper but

more risky”

• “More expensive,

less risky”

X

X

Page 25: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Awareness

Base

(MM USD)

Bulks 2.3

Fabrication 5.7

Transportation 1.9

Heavy lift vessel 1.6

Hook-up and

commissioning

4.3

Project services 0.6

Total 16.4

- % + %

Base

- % + %

Base

P10P50

P90

Base

Mitigate

“Response

/ mitigation”

X

Base

(MM USD)

Bulks 2.3

Fabrication 5.7

Transportation 1.9

Heavy lift vessel 1.6

Hook-up and

commissioning

4.3

Project services 0.6

Total 16.4

- % + %

Base

- % + %

Base

P10P50

P90

Base

Mitigate

X

Base

(MM USD)

Bulks 2.3

Fabrication 5.7

Transportation 1.9

Heavy lift vessel 1.6

Hook-up and

commissioning

4.3

Project services 0.6

Total 16.4

- % + %

Base

- % + %

Base

P10P50

P90

Base

Mitigate

Page 26: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Awareness

• Given the risk as we have expressed it:

– How valuable is response x?

– How much overall contingency is likely needed?

– Where is it likely needed?

– And when?

– What’s our biggest risk at P50?

– At P90?

– What contractual incentivisations are appropriate?

Page 27: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Contingency

Credit: from Centrica Energy’s PACE guidelines

“Contingency”

Page 28: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Contingency

Credit: from Centrica Energy’s PACE guidelines

Page 29: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Contingency

Page 30: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Benefits of risk assessment

• A valuable process

– Challenge project teams and base estimates

– Express uncertainty in the team’s base assumptions

– Capture risks, assumptions, issues, and their consequences

– Encourage open discussion amongst integrated team

• Demonstrate awareness of risk – Agree and communicate the team’s view of the risk

– Justify contingency and mitigation efforts

– Allow challenges, discussion and negotiation

– Set realistic stakeholder expectations

• The risk assessment and analysis represents the perceived risk, and its

logical consequences

Page 31: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Summary

Page 32: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

Quantitative risk analysis

• The risk model shows the effect of the assumptions on

the overall project

Base

estimate

(MM USD)

Bulks 2.3

Fabrication 5.7

Transportation 1.9

Heavy lift vessel 1.6

Hook-up and

commissioning

4.3

Project services 0.6

Total 16.4

The P90 is a "reasonably likely" worst case.

Contingency at P90 = 6.6

Page 33: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

About Simon White

• Over 20 years’ experience in risk management and risk analysis

– Wide variety of industries and major projects

– Three years as UK Risk Analyst for ConocoPhillips

– Previously Senior Risk Management Consultant and trainer for Pertmaster,

Primavera and Oracle

– Risk analyst for current major oil / gas projects such as Cygnus, Clair Ridge and

Jasmine, and a major government infrastructure programme

• Recognised as one of the leading practitioners of integrated project schedule

and cost risk management and analysis

– Methods allow project risk models to be interrogated and understood by project

teams and senior management

– Designed and built commercial risk software: Predict!, Arrisca, and a contributing

architect to Primavera Risk Analysis (Pertmaster)

– Develops tools for more practical and valuable project and business risk

management.

Page 34: Practical project risk assessment, presented by Simon White, 10th Oct 2016, APM North West branch conference

White Box by BOLD