Practical final pit depth considering the future underground mining- A case study

28
100 YEARS OF MINING RESEARCH: 100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010 Practical final pit depth Practical final pit depth considering the future underground considering the future underground mining- A case study mining- A case study Title of Title of paper: paper: Authors: Authors: 1- Ezzeddin Bakhtavar; Urmia University of Technology 2- Kazem Oraee ; University of University of Stirling, Stirling, UK Stirling, Stirling, UK 3- Kourosh Shahriar; Amirkabir University of Technology 4- Farhad Samimi Namin, Zanjan University

description

Title of paper:. Practical final pit depth considering the future underground mining- A case study. Authors: 1- Ezzeddin Bakhtavar ; Urmia University of Technology 2- Kazem Oraee ; University of Stirling , Stirling , UK - PowerPoint PPT Presentation

Transcript of Practical final pit depth considering the future underground mining- A case study

Page 1: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

Practical final pit depth considering the Practical final pit depth considering the

future underground mining- A case studyfuture underground mining- A case study

Title of paper:Title of paper:

Authors:Authors:

1- Ezzeddin Bakhtavar; Urmia University of Technology

2- Kazem Oraee; University of Stirling, Stirling, UKUniversity of Stirling, Stirling, UK

3- Kourosh Shahriar; Amirkabir University of Technology

4- Farhad Samimi Namin, Zanjan University

Page 2: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

2

Page 3: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

In some cases it is considered that the most suitable and economical

method for the exploitation of an ore deposit (such as the investigated

case study) is to combine open-pit and underground methods.

In this regard, the most critical problem is the determination of optimal

final pit depth with considering the underground alternative.

Here, to determine optimal final open-pit depth of Gol-e-Gohar Area 3

mine (case study) a method, which was recently introduced on the basis

of economical block models of open-pit and underground, was used.

3

Page 4: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

4

Page 5: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

The main idea of the applied model was concluded from the initial

algorithm of Nilsson.

In order to reduce the shortcomings of the Nilsson algorithm and to

accomplish some modifications, a number of essential requirements

were added to the algorithm, for instance, to take into consideration to

a suitable crown pillar.

The target of the model can be achieved by comparison between the

obtained values of various scenarios of combined mining.

5

Page 6: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

6

In this method, it is necessary to split up the future pit volume into

several level-cuts (independent pit).

Page 7: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

Considering and below each level-cut, an underground option can be

included, but after to bear in mind the most effective crown pillar.

7

Page 8: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

At most, a crown pillar with a height as a multiple of blocks height

considering the selected underground mining method and geotechnical

investigations must be contemplated.

The main part of the present method is associated with selection of a

combined mining scenario includes maximum NPV.

8

Page 9: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

9

Page 10: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

1.1. General description of the siteGeneral description of the site Ore complex located in Kerman province of Iran and includes six areas.

10

Gol-e-Gohar Iron Ore complex

Page 11: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

The Area 3 zone is approximately 1730 meters above sea level in an area of

planar desert topography.

Length of the Gol-e-Gohar Area 3 ore body is about 2200 m (N-S).

Average width of the ore body is nearly 1800 m (E-W).

Thickness of overburden and waste rock above the ore zone varies from 95

to 560 m.

Depth of the ore body varies from 95 m at the north end to 600 m at the

southern end.

Ore body thickness varies from 15 to 130 m with an average of 40 m.

The indicated resources have been estimated to be 496 Mt and an Inferred

resource of 147 Mt.

11

Page 12: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

2.2. Technical considerations of the open-pit optionTechnical considerations of the open-pit option A bench height of 15 m (Therefore, the block height of 15 m used in

the block model)

Pit slopes of 45 degrees in ore and waste rock and 32 to 33 degrees in

dry overburden

A safety berm height of 2 m

A drainage ditch width of 2 m

The required width of the haul road is 26 m with a grade of 10%.

Four shovels with 9-m3 buckets for use primarily in ore and 15-m3

buckets for use in overburden.

12

Page 13: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

During the production stage, 13 to 29 hauling tracks with capacity of 136

ton will be required.

Other mining support equipments: one wheel dozer, four track dozers, two

motor graders, one water truck, one ANFO / emulsion truck, and etc.

Four rotary blast hole drills

Burden by spacing in ore is 5.5m*7m

Burden by spacing in all waste rock zones is 5.5m*6m

Burden by spacing in dry and wet overburden zones are 8m*10m and

8m*9m, respectively.

Sub-drilling is 1.5 m in ore and waste rock and 2.5 m in overburden.

13

Page 14: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

3.3. Selection of a suitable underground optionSelection of a suitable underground option During the selection of a low cost and productive underground method

the following assumptions are considered and finally “room and pillar”

has been chosen.

o Backfilling of openings will not be economically viable; therefore

mining will be by room and pillar or open stoping methods.

o Due to the potential height of the mining, multiple levels would be

required, separated by sill pillars.

o Due to the plunge of the ore body (approximately 20 degrees to the

south) and the potential for low friction contacts (gouge and broken

zones) between the ore zone and hanging wall / foot wall rocks, it is

assumed that pillars left in place will be continuous ribs generally

oriented in a N-S direction (i.e. along dip).

14

Page 15: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

4.4. Technical considerations of the underground optionTechnical considerations of the underground option A room width of 10 m

Pillar height varies from 60 m at 100-m depth to 9 m at 400 m depth.

A 60% of ore extraction and recovery

The rock support consists of bolts, screen and concrete (for waste).

A sill pillar thickness of 6.7 m

One production shaft with a diameter of 6.71 m, one service shaft with

a diameter of 7.62 m, and one exhaust ventilation shaft with a diameter

of 7.62 m

Two crusher stations (each crusher can crush 900 ton/hr)

15

Page 16: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

Conveyor belts at the bottom of the crusher will transport the ore to a

1000-ton bin.

A two-boom electric-hydraulic drill jumbo

A crawler-mounted, Single-boom, electric hydraulic bench drill will

drill 12.5-m long, 64-mm diameter holes on a 1.2-m by 1.4-m burden

and spacing pattern.

Each bench hole will contain 1 m of water gel explosives followed by

8.5 m of ANFO prills and 0.3 m of collar stemming materials.

50-ton trucks and 16-ton loaders.

A total of 17 trucks and 15 loaders

16

Page 17: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

4.4. Economical considerations of the open-pit and underground Economical considerations of the open-pit and underground

A)A) Estimation of the annual incomes Estimation of the annual incomes The actual production of the processing plant was determined to be 6

Mt/year considering a loss of 5% of concentrate to dust in the plant. To produce the actual targeted 6 Mt of concentrate, the annual tonnage of

processed ore will be in the range of 8.7 Mt. The price for concentrate is US$0.235 per Fe unit in concentrate based on

US$16/t at 68% Fe.

17

Characteristic Open-pit underground

Annual concentration (ton) 6000000 6000000

Price of Fe unit (US$) 0.235 0.235

Annual income 96585000 96585000

Table- Annual incomes achieving from open-pit and underground mining

Page 18: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

B)B) Estimation of the costs Estimation of the costs The total operating cost was estimated to be equal to 554.65 (US$ million).

Here, operating cost is divided into three groups of mining, processing, and

general and administration.

“Processing” cost as well as “general and administration” cost are the same

in both open-pit and underground.

An average process operating cost was estimated to be US $3.00/ton per

feed ore.

General and administration cost was estimated to be equal to 2.3 (US$

million/year).

Therefore, the operating cost of processing plant for open-pit and

underground mining is calculated to be 26.17 and 24.7 (US$ million/year),

respectively.

18

Page 19: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

Ascendant trend of operating cost per each tonnage of produced ore in regard to

different open-pit mine sizes, is assessed (following Figure).

As it is clear in following Figure, in relation to an open-pit mine including 130

Mt of ore, mining operating cost is US$2.28 per each tonnage of produced ore.

19

Page 20: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

During the three years of overburden removal, operating cost of mine is

taken into account to be US$0.4 per each tonnage of overburden removal.

Therefore, before ore production and during development stage mining cost

will be 13.666 (US$ million/year).

On the basis of an open-pit mine with maximum production capacity of

130.87 Mt of ore capital cost is considered to be 100.712 (US$ million).

20

Page 21: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

All estimations for the underground costs are in US dollars, using 2002

prices, and have an error of estimate of 25%. A 15% contingency has been

added to all cost estimates.

The Capital costs include:o 124.962 (US$ million) for underground mobile mining equipment,o 17.34 (US$ million) for miscellaneous mine equipment,o 36.453 (US$ million) for shaft development and installations,o 33.119 (US$ million) for mine development,o 2.2 (US$ million) for mine construction,o 2.919 (US$ million) for miscellaneous mine operating,o 5.23 (US$ million) for staff and labour.

21

Page 22: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

As it shown in following Figure, the total operating cost for direct operating and

maintenance supplies and labour for stope and production development, room

and pillar mining has been estimated to be 4.47 (US$/ton, Milled).

Therefore, mining cost of the room and pillar will be 36.9 (US$ million/year).

On the basis of the room and pillar mine with maximum production capacity of

122.455 Mt of ore capital cost is considered to be 208.142 (US$ million).

22

Page 23: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

23

Page 24: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

It is first necessary to identify several scenarios of combined mining on the

basis of the benches height of 15-m in open-pit.

Each scenario includes three components of open-pit, a crown pillar, and

underground.

Crown pillar stability will be dependent on numerous parameters including

rock type, rook quality, rock strength, overburden depth, water influence,

in-situ rock stress, and pillar geometry.

In the next step, through the economical comparison between the

scenarios, the most profitable one can be selected.

It is notable that the main assessment is done according to the constructed

economical block models of open-pit and underground mining.

24

Page 25: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

Open-pit depth (m)

As it shown in following Figure, considering a discount rate of 12%, a net

present value of 63 (US$ million) is achieved due to the related scenario of

285-m depth of open-pit. It means that the optimal final open-pit depth considering the room and

pillar mining to be equal to 285 m achieving a 63 (US$ million) of net

present value.

25

Page 26: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

26

Page 27: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

Due to the significance of determining the optimal open-pit depth

considering an underground option for Gol-e-Gohar Area 3 ore body, an

effective method was used.

In this regard, according to the benches height of 15-m several scenarios of

combined mining of open-pit and room and pillar were initially

considered.

Then, with considering a discount rate of 12% the related NPV of each

scenario was determined.

After that, during an economical comparison between the scenarios, the

most profitable one was selected.

In this relation, the optimal open-pit depth was assessed to be equal to 285

m, which achieves a total NPV of 63 (US$ million).

27

Page 28: Practical final pit depth considering the future underground mining- A case study

100 YEARS OF MINING RESEARCH:100 YEARS OF MINING RESEARCH: Phoenix, Arizona; February 28 - March 03, 2010

28