pptpowergrid2-130809071137-phpapp02

download pptpowergrid2-130809071137-phpapp02

of 33

Transcript of pptpowergrid2-130809071137-phpapp02

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    1/33

    Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    2/33

    Synergy Institute of Engineering &

    Technology,Dhenkanal

    Seminar on

    Power Grid Design

    Submitted by

    Susanta Das7th Semester B.Tech

    Reg.No-0901230234

    Seminar Guide Mr. A. Panda

    Department of Electrical

    Engg.SIET,Dhenkanal.2

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    3/33

    Outline of Presentation

    Introduction Need of Power Grids

    Selection Site

    Layout Design

    1.Busbar Schemes

    2.Electrical Layout Drawing

    3.Bill of Material

    Safety Clearance in Grid

    Design of Earth Mat

    Control Room Switch/Relay Room

    Grid Equipments

    Conclusion

    Reference

    Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    4/33

    INTRODU TION An electrical grid is an

    interconnected network fordelivering electricity fromsuppliers to consumers. Itconsists of three maincomponents; 1) powerstation that produceelectricity from combustiblefuels or non-combustiblefuels; 2) transmissionlines that carry electricity

    from power plants todemand centers; and3) transformers that reducevoltage so distribution linescarry power for finaldelivery.

    Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    5/33

    WHY WE NEED GRID? Improvement of

    Reliability

    Improvement of

    economics

    Improvement ofefficiency

    Imrovement of power

    quality

    Improvement ofsecurity

    & safety Controller of entire power

    system

    Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    6/33

    SELECTION OF SITE Selection of site for construction of a Grid Sub Station is the first

    and important activity. This needs meticulous planning, fore-sight,

    skillful observation and handling so that the selected site is

    technically, environmentally, economically and socially optimal

    and is the best suited to the requirements

    The site should be:-

    As near the load centre as possible. Easily accessible to the public road to facilitate transport of

    material

    Above highest flood level (HFL) so that there is no water logging.

    Sufficiently away from areas where police and military rifle

    practices are held.

    Free from master plans / layouts or future development activities

    to have free line

    The should be far away from Airport

    Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    7/33

    REQUIREMENT OF LAND / AREA:-

    The site should have sufficient area to properly accommodate

    the Sub Station buildings, structures, equipments, etc. and

    should have the sufficient area for future extension of the

    buildings and / or switchyard.

    The requirement of land for construction of Sub Station including

    staff colony is as under:

    S.No. Voltage Class of GSS Required Area

    1 400 20.0 Hectare

    2 220 6.0 Hectare

    3 132 3.5 Hectare

    Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    8/33

    Layout Design-Bus bar Schemes

    The commonly usedbus bar schemes atSub Stations are:

    Single bus bar.

    Main and Auxiliarybus bar.

    Double bus bar.

    Double Main and

    Auxiliary bus barOne and a half

    breaker scheme.

    Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    9/33

    Single bus bar:- This is the simplest switching scheme

    in which each circuit is provided with

    one circuit breaker.

    This arrangement offers little security

    against bus bar faults .

    The entire Sub Station is lost in case

    of a fault on the bus bar.

    In case of maintenance of circuit

    breaker, the associated feeder has

    also to be shutdown.

    Main and Auxiliary busBar:- This is technically a single bus bar

    arrangement with an additionalbus bar called Auxiliary bus.

    As in the case of single bus

    arrangement, due to the fault the

    entire substation is lost.

    This bus arrangement has been

    extensively used in 132 kV SubStations.

    De artment of Electrical En .SIET Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    10/33

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    11/33

    One A Half Breaker Arrangement In this scheme, three circuit breakers

    are used for controlling two circuits

    which are connected between two busbars. Normally, both the bus bars are

    in service.

    A fault on any one of the bus bars is

    cleared by opening of the associated

    circuit breakers connected to the faulty

    bus bar without affecting continuity of

    supply. Similarly any circuit breaker

    can be taken out for maintenance

    without causing interruption.

    Load transfer is achieved through the

    breakers and, therefore, the operation

    is simple.

    The breaker and a half scheme is best

    for those substations which handle

    large quantities of power and where

    the orientation of out going.

    This scheme has been used in the

    400 kV substations.

    Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    12/33

    Electrical Layout Drawing

    Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    13/33Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    14/33

    List of Material The lists of material are only typical and cover the general requirement. Any

    other

    equipment / structure / material which may be required for construction of

    Sub Station as

    per layout and other requirements and not included in the above typical lists

    of

    Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    15/33

    Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    16/33

    S f Cl

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    17/33

    Safety Clearance The various equipments and associated / required facilities have to be so arranged within the substation that

    specified minimum clearances are always available from the point of view of the system reliability and safety

    of operating personnel. These include the minimum clearances from live parts to earth, between live parts of

    adjacent phases and sectional clearance between live parts of adjacent circuits / bays. It must be ensured

    that sufficient clearance to ground is also available within the Sub Station so as to ensure safety of the

    personnel moving about within the switchyard.

    As per Rule 64 (2) of the Indian Electricity Rules, 1956, the following safety working

    clearances shall be maintained for the bare conductors and live parts of any apparatus in any

    Sub Stations, excluding over head lines of HV and EHV installations:

    Nominal

    system

    Voltage

    in (kv)

    Highes

    t

    Syste

    m

    Voltage in(kv)

    Lightin

    g

    impulse

    Level(K

    Vp)

    Switching

    Implulse

    Voltage in

    (KVp)

    Minm

    Clearance

    Betn Phase

    &Earth(mm)

    Minm

    clearanc

    e Betn

    Phases

    (in mm)

    Safety

    Clearan

    ce(mm)

    Grou

    nd

    Clear

    ance(

    mm)

    11 12 70 ---- 178 229 2600 3700

    33 36 170 ---- 320 320 2800 3700

    132 145 550

    650

    ---- 1100

    1300

    1100

    1300

    3700

    3800

    4600

    4600

    220 245 950

    1050

    ---- 1900

    2100

    1900

    2100

    4300

    4600

    5500

    5500

    400 420 1425 1050(Ph-

    E)

    -

    3400

    ----

    ----

    4200

    6400 8000

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    18/33

    Earth Mat Design Provision of adequate earthing system

    in a Sub Station is extremely importantfor the safety of the operatingpersonnel as well as for proper systemoperation and performance of the

    protective devices. The primary requirements of a good

    earthing system in a Sub Station are

    a):-The impedance to ground shouldbe as low as possible but it should notexceed 1.0 (ONE) Ohm.

    b):- The Step Potential, which is themaximum value of the potential

    difference possible of being shunted bya human body between two accessiblepoints on the ground separated by thedistance of one pace (which may beassumed to be one metre), should bewithin safe limits.

    c):- Touch Potential, which is themaximum value of potential differencebetween a point on the ground and a

    point on an object likely to carry faultcurrent such that the points can betouched by a person, should also bewithin safe limits.

    Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    19/33

    Cont.The details of the earthing material generally used in a

    sub station are given below:

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    20/33

    Design of Control Room The control room is the

    main command centre ofthe substation. The entireoperation of the site ismonitored and controlledfrom this central location.

    A control room may rangefrom a small, seldommanned, non-ventilatedroom to a large, airconditioned area containingnumerous staff membersand electronic equipment(PCs, control

    panels/consoles, electricaland electronic switchingdevices, under floorcabling, etc.).

    Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    21/33

    Design of battery Room The Battery Room houses lead acid or

    nickel cadmium batteries for uninterrupted

    power supply (UPS) to the substation.

    In power grid normally 110 no. of batteries

    are present, having each capacity of 2.1V

    to maintain 220V output & the specific

    gravity of liquid is 1.835.

    Power House FCBC are designed to

    supply continuous power to the DC load

    and simultaneously charge the batteries

    connected. Input supply form 415V. AC 3Phase or 220V. AC 1 Ph. is converted to

    regulated DC. The charger has two

    independent systems.

    Normally the DC Power is supplied to he

    load by the Float Charger. It also supplies

    trickle current to the battery to keep ithealthy. If the charging current under Float

    Mode exceeds a set level.Boost charger is

    switched ON. It supplies Quick charging

    current to the battery. On battery reaching

    the set value the Boost Charger is switched

    OFF.

    Department of Electrical Engg.SIET,Dhenkanal.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    22/33

    Design of Switch/Relay Room The Switch Room

    accommodates high density of

    electronic equipment housed

    in cabinets and automated

    switch-gear. In-cabinet

    equipment maintain the

    primary functions of the facility

    and form the switching

    interface between the Control

    Room and the field

    equipment. The area may also

    accommodate a significantamount of metering and

    logging equipment. Due to the

    high volume of critical

    electronic equipment, it is

    essential that a fire event be

    detected before the operationof the plant is compromised.Department of Electrical Engg.SIET,Dhenkanal.

    G E t

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    23/33

    Gr Equ pmentsLighting Arrestor It is an instrument that protect

    vital equipments in the grid

    when a lightning strikes a

    power transmission line, the

    induced high voltage travels

    along the line towards both

    ends; this arrester will bypass

    this high voltage to the groundso that the nearby transformer

    will not be damaged.

    Line Volt.(KV) L.A.Rating(KV)

    400 327220 180

    132 108

    33 27

    CVT

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    24/33

    CVT:- It is that type tfr which is used to

    measure potential

    It is the major advantage of PT, &

    also used for carrier

    communication, which replace the

    coupling capacitor.

    At first for carrier communication a

    coupling capacitor is used with a

    PT, which is costlier than CVT.

    It act as a high pass filter.

    Connection diagram of CVT

    Potential

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    25/33

    Potential

    transformer:- Potential Transformer or Voltage

    Transformer are used in electrical

    power system for stepping downthe system voltage to a safe value

    which can be fed to low ratings

    meters and relays. Commercially

    available relays and meters used

    for protection and metering, aredesigned for low voltage.

    Current Transformer

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    26/33

    Current Transformer:-

    A current transformer isused in high voltagecircuits where it is not

    possible to measurecurrent directly.

    A CT is a step uptransformer with only oneturn in primary. There willbe as many cores based

    on the purposes likemetering, protection etc.

    The secondary of a CTshould never be kept opencircuited because very highflux will be developed in thesecondary and hence itmay be damaged.

    Power TRANSFORMER

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    27/33

    Power TRANSFORMER

    It is a static device which

    transforms electrical energy from

    one ckt to another ckt without

    change of frequency, but changing

    voltage with the principle mutualinduction.

    Most of the power transformer are

    in MVA ratings.

    It is the most costlier equipments

    in the grid.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    28/33

    INSULATOR:- Insulators are used to prevent

    flow of current from

    conducting material to non

    conducting material. It should be mechanically

    strong & high dielectric

    strength.

    Each insulator rating is of

    11kv to 16kv.

    Wave Trap:-

    It is the combination of inductance &

    capacitance, which act as a low pass filter,

    which passes low frequencies in to the

    grid, & this frequency is used in the grid.

    The Line trap offers high impedance tothe high frequency communication signals

    thus obstructs the flow of these signals in

    to the substation bus bars. If there were

    not to be there, then signal loss is more

    and communication will be

    ineffective/probably impossible.

    Circuit breaker: Isolators:-

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    29/33

    Circuit breaker:- It is protective equipments in the

    grid.

    It is the automatic on load switch.

    There are of 5 medium type ofcircuit breaker., but SF6 ckt

    breaker is used for best.

    Isolators:- This is an off load switching

    device to used open or close for

    flow of current or not to flow

    respectively in the grid.

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    30/33

    Conclusion:- Grid is the nodal point of the

    entire power system.

    It has two objectives i.e.1: Supply

    Quality Power, 2:Supply the powerfrom source to load with an

    economic reasons.

    AS Grids are interconnected so,

    there is an improvement of

    reliability of can achieved.

    As grid is the nodal point, if it failsto work, then entire power system

    will fails.

    Grid efficiency is lower i.e. 50-

    70%.

    As Grid has too many equipments

    so, design of grid is too costlier.

    R f

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    31/33

    Reference:- Construction Manual for substations by Shreemat Pandey Chairman &

    Managing Director Jaipur Rajasthan Rajya Vidyut Prasaran Nigam Ltd.

    Albert, R., Albert, I., and Nakarado, G. L. (2004). Structural Vulnerability of

    the North American Power Grid. Physical Review E 69 025103(R). 1-4 pgs.

    Grid Manual of OPTCL.

    http://www.powergridindia.com

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    32/33

  • 8/12/2019 pptpowergrid2-130809071137-phpapp02

    33/33