Powerpoint for Mayor Rev4

download Powerpoint for Mayor Rev4

of 26

Transcript of Powerpoint for Mayor Rev4

  • 7/31/2019 Powerpoint for Mayor Rev4

    1/26

    PROJECT PEGASUS vs.

    TRINITY TOLL ROAD

    BY COUNCILMEMBERS

    ANGELA HUNT, SANDY GREYSON, & SCOTT GRIGGS

    1

  • 7/31/2019 Powerpoint for Mayor Rev4

    2/26

    TRINITY TOLL ROAD vs. PROJECT PEGASUS

    CONCLUSION BASED ON TXDOT DATA

    Project Pegasus moves more cars, faster,

    with less congestion, for less money,than the Trinity Toll Road.

    2

  • 7/31/2019 Powerpoint for Mayor Rev4

    3/26

    TRINITY TOLL ROAD vs. PROJECT PEGASUS

    TXDOT DATA: PEGASUS MOVES MORE CARS

    TRAFFIC

    UTILIZATION

    TRINITY TOLL

    ROAD

    HORSESHOE CANYON LOWER

    STEMMONS(183 to I-30)

    TOTAL

    ADDED

    VEHICLES/DAY

    Current Conditions (2010) 305,000 185,000 230,000

    2035 Trinity Toll Road Only 100,000 to

    142,000 288,000 219,000 255,0002030 Project Pegasus Only 422,200 333,000 342,900

    Additional Vehicles Per Day(Current vs. Trinity Toll Road Only)

    100,000 to

    142,000-17,000 34,000 25,000 100,000 to 142,000

    Additional Vehicles Per Day(Current vs. Project Pegasus Only) 0 117,200 148,000 112,900 126,033 to 260,900*

    Project Pegasus moves more cars than the Trinity Toll Road.

    3

    *126,033 is the average of the three components of Project Pegasus (TXDOTs methodology for determining the capacity ofProject Pegasus, see Trinity Matrix Summary Table 1).260,900 is the sum of the Canyon and Lower Stemmons (TXDOTs methodology for determining the capacity of two inter-dependent components Project Pegasus and the Trinity Toll Road, see Trinity Matrix Summary Table 2).

  • 7/31/2019 Powerpoint for Mayor Rev4

    4/26

    TRINITY TOLL ROAD vs. PROJECT PEGASUS

    TXDOT DATA: PEGASUS MOVES TRAFFIC FASTER

    Project Pegasus moves traffic 5 mph faster than the Trinity Toll Road. 4

    AVERAGE SPEED TRINITY

    TOLL ROAD

    HORSESHOE CANYON LOWER

    STEMMONS(183 to I-30)

    Current Conditions (2010) 42 51 mph 43 mph 42 mph2035 Trinity Toll Road Only 30 mph2030 Project Pegasus Only 35 mph2030 Both Built 36 mph

  • 7/31/2019 Powerpoint for Mayor Rev4

    5/26

    Project Pegasus has a smaller percentage of lane miles with a FAILING Level of Service

    compared to the Trinity Toll Road.

    TRINITY TOLL ROAD vs. PROJECT PEGASUS

    TXDOT DATA: PEGASUS HAS BETTER LEVEL OF SERVICE

    LEVEL OF SERVICE TRINITY

    TOLL ROAD

    HORSESHOE CANYON LOWER

    STEMMONS(183 to I-30)

    Current Conditions (2010) F F F2035 Trinity Toll Road Only D-E F F F2030 Project Pegasus Only F F D-F2030 Both Built C-F C-F E-F D-F

    Project Pegasus improves the Level of Service on Lower Stemmons (from F to D-F).

    The Horseshoe, Canyon, and Lower Stemmons all remain level F if Trinity Toll Road is built.

    LANE MILES at LOS F TRINITY

    TOLL ROAD

    HORSESHOE CANYON LOWER

    STEMMONS(183 to I-30)

    Current Conditions (2010) Not Available N/A N/A

    2035 Trinity Toll Road Only 49%2030 Project Pegasus Only 46%2030 Both Built 43% 5

  • 7/31/2019 Powerpoint for Mayor Rev4

    6/26

    TRINITY TOLL ROAD vs. PROJECT PEGASUS

    TXDOT DATA: PEGASUS REDUCES CONGESTION

    CONGESTION DELAY(vehicle hours)

    TRINITYTOLL ROAD

    HORSESHOE CANYON LOWERSTEMMONS

    (183 to I-30)

    Current Conditions (2010) 2,964 to 9,653 9,653 2,94

    2035 Trinity Toll Road Only 67,982 hours

    2030 Project Pegasus Only 44,917 hours

    2030 Both Built 41,679 hours

    Cars sit in congested traffic 23,065 hours less if Project Pegasus is

    built than if the Trinity Toll Road is built.

    6

  • 7/31/2019 Powerpoint for Mayor Rev4

    7/26

    PROJECT PEGASUS:

    6 Main Lanes added to Canyon

    + 2 Main Lanes added to Lower Stemmons

    = 8 Main Lanes Added to Downtown System7

    TRINITY TOLL ROAD vs. PROJECT PEGASUS

    TXDOT DATA: PEGASUS ADDS MORE MAIN LANES

    TRINITY TOLL ROAD:

    6 Main Lanes Added to Downtown System

  • 7/31/2019 Powerpoint for Mayor Rev4

    8/26

    TRINITY TOLL ROAD vs. PROJECT PEGASUS

    TXDOT DATA: PEGASUS IS CHEAPER

    PROJECT PEGASUSTRINITY TOLL ROAD

    8

    $1.47 Billion

    $818 M Horseshoe

    $599 M Upper Stemmons

    $293 M Canyon

    + $309 M Lowest Stemmons

    $1.2 Billion

    $818 M Horseshoe

    $599 M Upper Stemmons

    $293 M Canyon

    + $309 M Lowest Stemmons

    $602 Million

    8

    $1.2 Billion $602 MillionOR

    (Horseshoe is already funded.)

    Project Pegasus costs $279 Million to $868 Million LESS than the Trinity Toll Road.

  • 7/31/2019 Powerpoint for Mayor Rev4

    9/26

    TRINITY TOLL ROAD vs. PROJECT PEGASUS

    CONFLICT BETWEEN DATA AND NARRATIVE

    Narrative and Trinity Matrix Summary are

    misleading, conflict with TXDOTs data, andreveal a bias in favor of the Trinity Toll Road

    that is not supported by TXDOTs documents.

    9

  • 7/31/2019 Powerpoint for Mayor Rev4

    10/26

    FLAWS IN MATRIX SUMMARY

    WRONG SCENARIO USEDCant compare projects using

    Both Built scenario.

    Cannot determine which project BY ITSELF moves more cars for less money if we

    use figures that assume BOTH projects are built.

    Using Both Built scenario minimizes Project Pegasus positive effects on traffic,which are superior to Trinitys.

    Should compare Trinity Only scenario to Pegasus Only scenario to properlycompare projects.

    10

  • 7/31/2019 Powerpoint for Mayor Rev4

    11/26

    Full capacity improvements for Lowest

    Stemmons (IH30 to DNT) cannot beattained unless Upper Stemmons (DNT

    to SH 183) is also improved.

    11

    FLAWS IN MATRIX SUMMARY

    CONCLUSIONS NOT SUPPORTED BY DATA

    Where is data or modeling to support this claim?

  • 7/31/2019 Powerpoint for Mayor Rev4

    12/26

    This significantly understates Pegasus added

    Vehicles Per Day and is not calculated the

    same way as the Trinitys added VPD.

    Trinity Parkway provides 132,000

    additional vpd and Pegasus

    provides 93,300 additional vpd.

    12

    FLAWS IN MATRIX SUMMARY

    INCONSISTENT CALCULATION FOR INCREASED VPD

  • 7/31/2019 Powerpoint for Mayor Rev4

    13/26

    FLAWS IN MATRIX SUMMARY

    HOW IS ADDED CAPACITY CALCULATED?

    Total Vehicles Per Day is the SUM of the components:

    TOTAL CAPACITY = COMPONENT A VPD + COMPONENT B VPD13

  • 7/31/2019 Powerpoint for Mayor Rev4

    14/26

    For Project Pegasus, however, TOTAL VPD is calculated by AVERAGING the components:

    DITTO

    DITTODITTO

    This error SIGNIFICANTLY REDUCES TOTAL Vehicles Per Day for

    Project Pegasus, comparing unfavorably to the Trinity Toll Road.

    FLAWS IN MATRIX SUMMARY

    PEGASUS ADDED VPD IS INCONSISTENT

    14

  • 7/31/2019 Powerpoint for Mayor Rev4

    15/26

    FLAWS IN MATRIX SUMMARY

    ADDED VPD SHOULD BE CALCULATED USING

    REAL TRAFFIC, NOT HYPOTHETICAL CAPACITY

    15

    This erroneous calculation for Added Vehicles Per Day benefits the Trinity Toll Road since

    its CAPACITY is greater than the REAL TRAFFIC it will move (132,000 vs. 114,000).

  • 7/31/2019 Powerpoint for Mayor Rev4

    16/26

    Use PROJECT PEGASUS ONLY build scenario versus TRINITY TOLL ROAD ONLY

    build scenario.

    FLAWS IN MATRIX SUMMARY

    HOW TO CALCULATE ACCURATE ADDED VPD

    16

    To correctly compare the increase in vehicles per day for Pegasusand the Trinity, we must:

    Calculate VPD using SUM methodology instead ofAVERAGING components.

    Use REAL TRAFFIC figures, not hypothetical CAPACITY.

  • 7/31/2019 Powerpoint for Mayor Rev4

    17/26

    FLAWS IN MATRIX SUMMARY

    CORRECT ADDED VPD CALCULATION

    TRAFFIC UTILIZATION

    TRINITY

    TOLL ROAD

    HORSESHOE CANYON LOWER

    STEMMONS(183 to I-30) TOTAL

    Future Conditions in 2030

    If Only TRINITY TOLL RD Is Built

    100,000 to

    142,000288,000 219,000 255,000

    Current Conditions in 2010 0 305,000 185,000 230,000

    Additional Vehicles Per Day

    TRINITY TOLL ROAD

    100,000 to

    142,000 -17,000 34,000 25,000100,000 to

    142,000

    17

    If only the Trinity Toll Road is built.

    TRAFFIC UTILIZATION TRINITYTOLL ROAD

    HORSESHOE CANYON LOWER

    STEMMONS(183 to I-30)

    TOTAL

    Future Conditions in 2030If Only PROJECT PEGASUS Is Built 0 422,200 333,000 342,900

    Current Conditions in 2010 0 305,000 185,000 230,000

    Additional Vehicles Per Day

    PROJECT PEGASUS0 117,200 148,000 112,900

    126,033 to

    260,900

    If only Project Pegasus is built.

    Project Pegasus moves more cars than the Trinity Toll Road.

  • 7/31/2019 Powerpoint for Mayor Rev4

    18/26

    $818 M Horseshoe

    $599 M Upper Stemmons

    $293 M Canyon

    + $309 M Lowest Stemmons

    $2.02 Billion

    FLAWS IN MATRIX SUMMARY

    INFLATED CALCULATION OF PEGASUS TOTAL COST

    $818 M Horseshoe ALREADY PAID FOR$599 M Upper Stemmons

    $293 M Canyon

    + $309 M Lowest Stemmons

    $1.2 Billion ($179M/mile)

    $818 M Horseshoe

    $599 M Upper Stemmons

    $293 M Canyon

    + $309 M Lowest Stemmons

    $602 Million ($177M/mile)18

  • 7/31/2019 Powerpoint for Mayor Rev4

    19/26

    According to TXDOTs documents, TrinityToll Road funding is TBD.

    The Trinity Parkway has a

    significant funding source (toll

    revenue) to help support the project.

    19

    Where is documentation that the NTTA willdefinitely fund project?

    How much money is significant andwhere are documents to support this?

    FLAWS IN MATRIX SUMMARY

    SIGNIFICANT TOLL ROAD FUNDING UNSUPPORTED

  • 7/31/2019 Powerpoint for Mayor Rev4

    20/26

    Where are documents supporting claim?

    20

    FLAWS IN MATRIX SUMMARY

    CANYON DETOUR COST INCREASE UNSUPPORTEDConstruction costs associated with

    the Canyon will increase if the Trinity

    Parkway is not available as an

    alternate route during construction.

    According to TXDOTs documents, Canyondetour cost is Not Available.

  • 7/31/2019 Powerpoint for Mayor Rev4

    21/26

    TXDOT documents: NO COST for detours for High Five, Central Expressway, and LBJ.

    Costs for alternative route improvements for those projects included bettersignalization and improvements to parallel streets.

    21

    FLAWS IN MATRIX SUMMARY

    CANYON DETOUR COST INCREASE UNSUPPORTED

  • 7/31/2019 Powerpoint for Mayor Rev4

    22/26

    TXDOT Documents: No documents or data supports claim that Canyon drivers would use

    Trinity Toll Road as detour during Canyon construction.

    TXDOT Documents: No analysis of how many cars would use Trinity Toll Road as relieverroute during Canyon construction.

    22

    FLAWS IN MATRIX SUMMARY

    CANYON DETOUR COST INCREASE UNSUPPORTED

  • 7/31/2019 Powerpoint for Mayor Rev4

    23/26

    6 Main Lanes added to Canyon (pp. 6 and 8)

    + 2 Main Lanes added to Lower Stemmons (pp. 6 and 8)

    = 8 Total Lanes Added to Downtown System by Project Pegasus

    FLAWS IN MATRIX SUMMARY

    UNDERSTATES PEGASUS ADDED MAIN LANES

    23

    Pegasus adds 8 Main Lanes, not 2 to 4

  • 7/31/2019 Powerpoint for Mayor Rev4

    24/26

    FLAWS IN MATRIX SUMMARY

    UNDERSTATES PEGASUS ADDED MANAGED LANES

    2 Managed Lanes added to Canyon (pp. 6 and 8)

    + 2 Managed Lanes added to Lower Stemmons (pp. 6 and 8)

    = 4 Total HOV/Managed Lanes Added by Project Pegasus 24

    Pegasus adds 4 Managed Lanes, not 2

  • 7/31/2019 Powerpoint for Mayor Rev4

    25/26

    Where is the documentation for this recent review concluding

    managed lanes are not feasible due to limited access to

    downtown they provide?

    FLAWS IN MATRIX SUMMARY

    MANAGED LANES SUDDENLY NOT FEASIBLE?

    According to Trinity SDEIS,only 1 out of 5 cars is

    traveling TO downtown.

    4 out of 5 cars are travelingTHROUGH downtown

    80% of cars on the Pegasussystem could use

    managed/tolled lanes.

    25

  • 7/31/2019 Powerpoint for Mayor Rev4

    26/26

    TRINITY TOLL ROAD vs. PROJECT PEGASUS

    CONFLICT BETWEEN DATA AND NARRATIVE

    Given the significant discrepancies between

    TXDOTs data and the narrative, an outside,independent analysis should be conducted.

    26