Post Tension BIJAN AALAMI

download Post Tension BIJAN AALAMI

of 14

Transcript of Post Tension BIJAN AALAMI

  • 8/13/2019 Post Tension BIJAN AALAMI

    1/14

    The 10 Steps in Design ofThe 10 Steps in Design of

    PostPost--Tensioned FloorsTensioned Floors

    Dr Bijan O Aalami

    Professor Emeritus,

    San Francisco State University

    Principal, ADAPT Corporation; [email protected]

    www.adaptsoft.comwww.adaptsoft.com

    301 Mission Street

    San Francisco, California

    High Seismic Force Region

    Four Seasons Hotel; Florida

    High Wind Force Region

    Column supported multistory

    building

    Two-way flat slab construction

  • 8/13/2019 Post Tension BIJAN AALAMI

    2/14

    Multi-level parking structures

    One-way beam and slab design

    (a) STRAND (b) TENDON

    NOTE: * NOMINAL DIAMET

    (0.5

    "*)

    CORROSIONINHIBITING

    12.7mm

    SHEATH

    (c) ANCHORAGE ASSEMBLY

    STRAND

    PLASTIC

    WIRECOATING

    TUBE

    GREASE FILLED PLASTIC CAP

    SHEATH

    Post-Tensioning SystemsUnbonded System

    Example of a Floor System using the Unbonded

    Post-tensioning System

    An example of a grouted

    system hardware with flat duct

    Post-Tensioning Systems

    Grouted System

  • 8/13/2019 Post Tension BIJAN AALAMI

    3/14

    Example of a Floor System Reinforced

    with Grouted Post-Tensioning System

    Preliminary Considerations

    Design of Post-Tensioned Floor

    Dimensions (sizing) Optimum spans; optimum thickness

    Structural system One-way/two-way; slab band

    Boundary conditions; connections Service performance; strength condit

    Load Path; Design strips

    Design sections; design values

    Preliminary Considerations

    Design of Post-Tensioned Floors

    Dimensions (sizing) Optimum spans; optimum thickness

    An optimum design is one in which thereinforcement determined for servicecondition is used in its entirety forstrength condition.

    PT amount in service condition is

    governed mostly by: Hypothetical tensile stresses (USA), orcrack width (EC2)

    Tendon spacing (USA)

    Common spans: 25 30 ft (8 9 m)

    Span/thickness ratios 40 - 45 for interior

    35 for exterior with no overhang

    Selection of load path for two-wasystems Design Strips

    Preliminary Considerations

    Design of Post-Tensioned Floors

    Subdivide the structure into design

    strips in two orthogonal directions(Nahid slab)

  • 8/13/2019 Post Tension BIJAN AALAMI

    4/14

    X

    Y

    G

    F

    E

    D

    C

    B

    A

    31 2 4 5

    Subdivide the floor along support

    lines in design strips

    Preliminary Considerations

    Design of Post-Tensioned Floors

    X

    Y

    1 2 3 4 5

    F

    E

    D

    C

    B

    A

    Subdivide slab along support lines in desig

    strips in the orthogonal direction

    An important aspect of load path selection in a

    two-way system is that every point of the slab

    should be assigned to a specific design strip.

    portion of the slab should be left unassigned.

    Preliminary Considerations

    Design of Post-Tensioned Floors

    Design sections Design sections extend over the entire

    design strip and are considered at criticallocations, such as face of support andmid-span

    Preliminary Considerations

    Design of Post-Tensioned Floors

    Design valuesActions, such as moments at each de

    section are reduced to a singlerepresentative value to be used for des

    559 is the area (total) value of bending

    moment at face of support

  • 8/13/2019 Post Tension BIJAN AALAMI

    5/14

    10 Steps

    Design of Post Tensioned Floors

    . Geometry and Structural System

    2. Material Properties. Loads

    . Design Parameters

    . Actions due to Dead and Live Loads

    . Post-Tensioning

    . Code Check for Serviceability

    . Code Check for Strength

    . Check for Transfer of Prestressing

    0. Detailing

    Select design strip and Idealize Extract; straighten the support line;

    square the boundary

    Step 1

    Geometry and Structural System

    Select design strip and Idealize Extract; straighten the support line;

    square the boundary

    Model the slab frame with a row ofsupports above and below. Thisrepresents an upper level of multi-storyconcrete frame.

    Assume rotational fixity at the farends;

    Assume rollersupport at the farends

    Step 1

    Geometry and Structural System

    View of idealized slab-frame

    Step 2

    Material Properties

    ConcreteWeight 24 kN/m3

    28 day cylinder 40 MPa

    Elastic modulus 35,220 MPa

    Long-term deflection factor 2

    Non-Prestressed reinforcement fy 460 MPa

    Elastic modulus 200,000 M

    Prestressing Strand diameter 13 mm

    Strand area 99 mm2

    Ultimate strength 1,860 MPa

    Effective stress 1,200 MPa

    Elastic modulus 193,000 M

  • 8/13/2019 Post Tension BIJAN AALAMI

    6/14

    Step 3

    Loads

    Selfweight Based on member volume

    Superimposed dead load Min (partitions) 1 kN/m2

    Live load Residential 2.0 kN/m2

    Office 2.5 kN/m2

    Shopping mall 3.5 kN/m2

    Parking structure 2.0 kN/m2

    Lateral loads

    Wind

    Earthquake

    Example assumes Superimposed DL SDL= 2 kN/m2

    Live load LL = 3 kN/m2

    Step 4

    Design Parameters

    Applicable codeACI 318-11; EC2 EN 1992-1-1:2004

    IBC 2012

    Local codes, such as California BuildiCode (CBC 2011); or otherwise

    Cover for protection against corros

    Cover to rebar Not exposed to weather 20 mm Exposed to weather 50 mm

    Cover to tendon

    Not exposed to weather 20 mm Exposed to weather 25 mm

    Step 4

    Design Parameters

    Cover for fire resistivity

    Identify restrained and unrestrainedpanels.

    Restrained or

    UnrestrainedAggregate Type Cover Thickness, mm. for

    Fire Endurance of

    1 hr 1.5 hr 2 hr 3 hr 4 hr

    Unrestrained Carbonate

    SiliceousLightweight

    -

    --

    -

    --

    40

    4040

    50

    5050

    -

    Restrained CarbonateSiliceousLightweight

    ---

    ---

    202020

    252525

    303030

    --

    For 2-hour fire resistivity Restrained 20 mm.

    Unrestrained 40 mm

    Step 4

    Design Parameters

    Cover for fire resistivity

    Identify restrained and unrestraipanels.

  • 8/13/2019 Post Tension BIJAN AALAMI

    7/14

    Step 4

    Design Parameters

    Allowable Stresses or Crack WidthSelection for Two-Way System

    Based on ACI Total load case

    Tension

    Compression 0.60fc Sustained load case

    Tension 0.5fcCompression 0.60 fc

    Based on EC2 Frequent load case

    Tension Ft = 0.30 fck(2/3)

    Compression 0.60fck Quasi permanent load case

    Tension Ft = 0.30 fck(2/3)

    Compression 0.45fck Crack width normal exposure (?)

    Unbonded

    Bonded

    0.5fc

    Step 4

    Design Parameters

    Allowable deflections (EC2/ approx. A

    For visual impact use total deflection Span/250

    Use camber, if necessary

    Total deflection subsequent to installationmembers that are likely to be damaged

    Span/350

    Immediate deflection due to live load

    Span/500

    Long-term deflection magnifier 2. This brinthe total long-term deflection to 3,

    Step 5

    Actions due to Dead and Live Loads

    Analyze the design strip as a singlelevel frame structure with one row ofsupports above and below, using

    In-house simple frame program(Simple Frame Method; SFM); or

    in-house Equivalent Frame Program (EFM);

    Specialty commercial software

    All the three options yield safe designs.But, each will give a different amount ofreinforcement.

    The EFM is suggested byACI-318. To someextent, it accounts for biaxial action of theprototype structure in the frame model.

    Accuracy and ability of commercial softwarefor optimization varies

    Step 5

    Actions due to Dead and Live Loa

    Analyze the design strip as a single levelframe structure with one row of supportsabove and below.

  • 8/13/2019 Post Tension BIJAN AALAMI

    8/14

    Step 6

    Post-Tensioning

    Selection of design parameters

    Selection of PT force and profile

    Effective force/tendon selection option- force selection

    Calculation of balanced loads;adjustments for percentage of loadbalanced

    Calculation of actions due to balancedloads

    Step 6

    Post-Tensioning

    Selection of PT force and profileTwo entry value assumptions must be mad

    initiate the computations. Selectprecompression and % of DL to balance

    Step 6

    Post-Tensioning

    Selection of design parameters Select average precompression 1 MPa

    Target to balance 60% of DL

    Selection of PT force and profileAssume simple parabola mapped within

    the bounds of top and bottom covers

    Force diagram of simple parabola

    Step 6

    Post-Tensioning

    Assume simple parabola forhand calculation

  • 8/13/2019 Post Tension BIJAN AALAMI

    9/14

    Calculation of balanced loads;

    adjustment of % of DL balanced

    STEP 6

    Post-Tensioning

    Select critical span

    Select max drape

    Calculate %of DL balanced (%DL)

    %DL < 50%?

    Reduce P/AReduce drape

    Yes

    Increase P/A

    NoYes

    No

    No Yes

    Yes No

    Assume P/A =150psi[1MPa]

    P /A 80%?

    P/A>125psi [0.8MPa]?

    Go to next span

    1

    2

    F121_ACI_PT_2_way_082012

    Member with widely

    different spans

    Calculation of balanced loads;

    adjustment of % of DL balanced

    STEP 6

    Post-Tensioning

    Select max drap e using tendons

    from critical span

    Calculate %of DL balanced (%DL)

    Move to next span

    Reduce P/A or tendons to%DL balanced ~ 60% ;

    P/A >= 125 psi [0.8 MPa]

    YesNo

    No Yes

    Is it practical to reduceP/A or tendons?

    %DL > 80%?

    Raise tendon to reach%DL ~ 60%

    Exit after last span

    F121_ACI_2-way_PT_force_0

    Calculation of balanced loads Lateral forced from continuous tendons

    Lateral force from terminated tendons

    Moments from change in centroid of

    member

    Example of force from continuous tendon

    STEP 6

    Post-Tensioning

    P = 500 k

    a = 93 mm ; b = 186 mm ; L = 9 m ;

    c = {[93/186]0.5/[1 + (93/186)0.5]} * 9.00 = 3.73 m

    Wb/tendon = 2 P*a/c2 = 119.0 kN * (2*93/1000)/3.732

    = 119.0 kN / tendon * 0.013 / m =1.59 kN/m / tendon

    Calculation of balanced loads Lateral forced from continuous tendons

    Lateral force from terminated tendons

    Moments from change in centroid of mem

    Force from terminated tendon

    STEP 6

    Post-Tensioning

    L = 10 m ; a = 93 mm ; P = 119 kN; c =0.20*10 = 2.00

    Wb = (3 * 119.0 * 2 * 93 / 1000) / 2.02 16.60 kN/m

    Concentrated force at dead end = 2*16.60 = 33.20 k

  • 8/13/2019 Post Tension BIJAN AALAMI

    10/14

    Calculation of balanced loads

    Lateral forced from continuous tendons

    Lateral force from terminated tendons

    Moments from change in centroid of member

    Example of force from change in membercentroid

    STEP 6

    Post-Tensioning

    Moment at face of drop = M

    M = P * shift in centroid =P * (Yt-Left Yt-Right)

    P = 23*119 kN; Yt-Left = 120 mm ; Yt-Right =

    146 mm

    M= 23*119(120 146)/1000 = -71.16 kNm

    Calculation of actions due to balanced load

    Check balanced loads for static equilibrium

    Determine moments/shears from balanced loads

    applied the frame used for dead and

    live loads

    Note down reactions from balanced loads

    STEP 6

    Post-Tensioning

    Calculation of actions due to balanced loads Obtain moments at face-of-supports and mid-spans

    Note the reactions. The reactions are hyperstatic

    actions.

    Comments:

    Moments and precompression will be used for serviceability check.

    Reactions will be used for Strength check.

    STEP 6

    Post-Tensioning

    Code requirements for serviceability Load combinations

    Stress/crack width check

    Minimum reinforcement

    Deflection check.

    Load combination

    Frequent (Total) load condition

    1.00DL + 0.50LL + 1.00PT

    Quasi Permanent (Sustained) load condition

    1.00DL + 0.30LL + 1.00PT

    Stress check

    STEP 7

    Code Check for Serviceabil ity

    Using engineering judgment, select the locatio

    likely to be cr itical. Typically, these are at the f

    and for hand calculation at mid-span

    At each section selected for check, use the de

    applicable to the entire design section and app

    the entire cross-section of the design section

    the hypothetical stresses used in code check.

    = (MD + 0.5ML + MPT) / S + P/AS = I/Yc ; I = second moment of area of ;

    Yc = distance to farthest tension fiber

  • 8/13/2019 Post Tension BIJAN AALAMI

    11/14

    ACI Minimum Reinforcement

    STEP 7

    Code Check for Serviceabil ity

    Yes

    6

    ACI Minimum Rebarfor two-way systems

    F114_041112

    BondedUnbonded

    At supportsAs = 0.0075Acf

    Add rebar to resistforce in tensile zone

    No added rebarrequired

    EXIT

    Add rebar to increaseMoment capacity to

    1.2 Mcr

    5

    4

    3

    2

    1

    11

    10

    9

    PT system?

    `

    `

    No

    ft ?tension stress

    In span calculatehypothetical tension

    stress ft

    ft > 2 root 'c[ft > 0.17 root f'c ]

    ft =< 2 root 'c[ ft =< 0.17 root f'c ]

    Does Mcr exceeed1.2xmoment capacity?

    No added rebarrequired

    Calculate the crackingmoment Mcr at

    supports and spans

    12

    ACI 318-11 Minimum Reinforcement Rebar over support is function of geometry of t

    design strip and the strip in the orthogonal

    direction

    Rebar in span is a function of the magnitude o

    the hypothetical tensile stress

    STEP 7

    Code Check for Serviceabil ity

    As = 0.00075 * Acf

    As = Area of s teel required

    Acf = Larger of cross-sectional area of the

    strip in

    direction of analysis and orthogonal to

    ACI 318-11 Minimum Reinforcement Rebar in span is a function of the magnitude of the

    hypothetical tensile stress

    In span, provide rebar if the hypothetical

    tensile

    stress exceeds 0.166f cThe amount of reinforcement As is

    given by:

    As

    = N / (0.5*fy

    )

    where N is the tensile force in tension

    e

    STEP 7

    Code Check for Serviceabil ity

    h = member thickness; b = design section

    width

    EC2 Minimum Reinforcement Minimum based on cross-sectional area

    Minimum based on hypothetical tensile stress

    Based on cross-sectional area of section

    Asmin (0.26* fctm *bt*d / fyk) 0.0013

    *d

    STEP 7

    Code Check for Serviceabil ity

    Based on value of hypothetical tensile stressesfor crack control Check probable crack width Add rebar based using the code

  • 8/13/2019 Post Tension BIJAN AALAMI

    12/14

    Read deflections from the frame analysis of thedesign strip for dead, live and PT; (DL , LL , and PT ).

    . Make the following load combinations and

    check against the allowable values for each case

    Total Deflection

    (1 + 2)(

    DL +

    PT + 0.3

    LL ) + 0.7

    LL < span/250This is on the premise of sustained load being 0.3

    time the design live load. It is for visual effects;

    Provide camberto reduce value, where needed and

    practical

    Immediate deflection from live load

    immediate = 1.00L < span/500

    This check is applicable, where non-structural

    members are likely to be damaged. Otherwise,

    span/240 applies

    Presence of members likely to be damaged fromsustained deflection

    (1+ 2)(0.3 LL ) + 0.7 LL < span/350

    STEP 7

    Deflection Check

    Steps in strength check Load combinations

    Determination of hyperstatic actions

    Calculation of design moments (Mu)

    Calculate capacity/rebarfor design moment Mu

    Check for punching shear

    Check/detail for unbalanced moment at support

    Load combinations (EC2)

    U1 = 1.35DL + 1.50LL + 1.0HYP

    where, HYP is moment due to hyperstatic actions

    from prestressing

    Determination of Hyperstatic actions

    Direct Method based on reactions from balan

    loads

    Indirect Method Using primary and post-tensi

    moments

    STEP 8

    Strength Check

    Determination of Hyperstatic actions

    Direct Method based on reactions from balanced

    loads

    STEP 8

    Strength Check

    A comment on capacity versus demand Post-tensioned members possess both a positive

    and negative moment capacity along the memb

    length

    Rebar needs to be added, where capacity falls sh

    of demand

    First, find the capacity and compare it with deman

    STEP 8

    Strength Check

  • 8/13/2019 Post Tension BIJAN AALAMI

    13/14

    The figure below shows the forces on a PT member.

    In calculating the force from PT tendons, use either

    the code formulas or the following simplified

    procedure, based on parametric study of common

    building structures can be sued.

    STEP 8

    Strength Check

    USING EC2

    Assume tendon st ress under serv ice cond it ion 1,200 M

    Assume tendon st ress at ul timate limi t s tate 1300 MPa

    USING ACI

    Tendon Length 38 m for single end stressing; ; length

    35 m length 75 m double end stressing

    fps is conservatively 1,480 MPa if span is less than 11

    fps is conservatively 1,340 MPa if span is greater than

    Check for adequate ductility

    ACI

    Ductility is deemed adequate, if c/dt

  • 8/13/2019 Post Tension BIJAN AALAMI

    14/14

    STEP 9

    Check for Transfer of Prestressing

    Load combination

    U = 1.00*Selfweight + 1.15*PT

    Check for allowable stresses

    Tension stress

    Compression stress

    If tension exceeds, provide rebar in tensile

    zone to resist Nc

    If compression exceeds, wait until concrete

    gains adequate strength

    Position of rebar

    STEP 10

    Detailing

    STAGGER

    SEE PLAN

    EQ.

    MID-SPAN

    STAGGER

    DROP CAP

    COLUMN

    SUPPORT

    EQ. EQ.EQ.

    SUPPORT TTOP REBAR

    SUPPORT

    EQ.

    WALL

    EQ.

    SUPPORT LINE

    POST-TENSIONED

    COLUMN

    DROP

    Lc/6

    Lc/3

    Lc

    SLAB

    Lc/6

    *

    BOTTOM

    PLAN

    ELEVATION

    Thank you for listening.

    www.adaptsoft.com;

    [email protected]