PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

476

Transcript of PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Page 1: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Process Framework

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 2: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Definition as per PMBOK® Guide

A project is a temporary endeavor undertaken to

create a unique product or service.

Definition of Project

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 3: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

A temporary endeavor – means that every project has a definite beginning and end.

Unique means that the product or service or result is different from other product or service or result.

Progressively elaborated - proceeding in steps

Project Definition

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 4: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Building a Software

A Major Enhancement to the software

Filming a Motion Picture

Building a new office

Designing a new product or service

Creating an advertisement campaign

Creating a new process with a business unit

Moving from one building to another

Designing a space vehicle

Examples of Project

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 5: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

PROJECTS OPERATIONS

Temporary Ongoing

Unique Repetitive

Closes after attaining the objectives Objective is to sustain business

Prototyping the new car model Assembly line production

Project vs Operation

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 6: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Constraints

Source: A Guide to the Project Management Body of Knowledge, Fourth Edition (PMBOK® Guide) ©2008 Project

Management Institute, Inc. All Rights Reserved.

Risk

Scope

Budget

Resources

Quality

Schedule

Quality

Cost Scope

Schedule

PM Triangle

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 7: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Why Projects Fail ?

Lack of clearly defined purpose

Inexperienced project Managers

Poor estimation of duration and cost

Cultural and ethical misalignment

Poor requirements and scope management

Lack of coordination of resources and activities

Poor communication

Inadequate planning of scope, schedule, resources, cost, risk and quality

Lack of progress and quality control

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 8: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

What Is Project Management ?

Project management is the application of knowledge, skills, tools and techniques to project activities to meet the project requirements - PMBOK® Guide 4th edition (Glossary)

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 9: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Management Benefits

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 10: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Management Process Groups

Process Groups

Project management processes have been bundled into 5 groups and these groups are called project management process groups

Initiating

Planning

Executing

Monitoring and controlling

Closing

These process groups are common to most of the projects across various domains – construction, technology, IT, life sciences etc.

Process groups are different than the Phases

Process groups may overlap / repeat based on the activities in the project

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 11: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Initiating Process Group

Processes within this group launches the project or a project phase

Key activities associated with Initiation includes:

Identifying business needs

Creating a feasibility study

Creating a Product description

Creating Detailed Business Case

Creating a Project Charter

Selecting a Project Manager

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 12: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Planning Process Group

It involves creation of Project Management Plan that acts as a roadmap for project execution Key activities would include: Collect Requirements Define Scope Create Work Breakdown Structure Define and Sequence Activities Estimate Activity Resource Requirement and Duration Creating Schedule Estimate Cost and Determine Budget Planning Human Resource, Quality, Communications Identify, Analyze and Prepare Risk Response Plan Planning Procurement Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 13: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Executing Process Group

Executing process group consists of processes to complete the work in each of the phases

Helps the PM coordinate and direct project resources to meet the objectives of the project plan

Key activities would include:

Direct and manage project execution

Acquire project team

Perform quality assurance

Manage Stakeholders Expectation

Distributing project information

Develop and Manage project team

Conduct Procurement

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 14: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Monitoring and Controlling Process Group

Controlling processes are the activities that

ensure that the project goes according to plan

the actions to implement when project is not going as per the plan

Variances from the project baselines are identified and necessary corrective measures are undertaken

Key activities would include:

Ensuring Quality Control

Providing scope verification

Implementing change control

Configuration management

Controlling key parameters like cost, schedule and scope

Monitor and Control Risks

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 15: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Closing Process Group

This process group includes all processes to close all activities in a project or project phase

Closing activities to be performed even for the aborted / terminated projects

Key activities would include:

Auditing procurement documents

Scope verification

Closing vendor contracts

Closing administrative duties

Submitting final reports

Archiving project records

Celebrating!!!

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 16: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Process Group Interaction

Level

Of

Activity Initiating Processes

Planning Processes

Executing Processes

Closing Processes Controlling Processes

Phase Finish

Phase Start Time

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 17: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Projects are divided into phases

The project will have at least a beginning, intermediate and ending phase

Number of phases depends on complexity and size of the project

Reviews are conducted at the end of each phase to measure performance

Phase end reviews allows to decide if the project should continue

The collection of phases is called project life cycle

The project life cycle defines the beginning and end of a project

Project Life Cycle

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 18: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

The completion of one or more deliverables marks the project phase

Deliverables are reviewed and formally accepted by customer at phase end

Phase end reviews are also called phase exits, stage gates or kill points

Rolling wave planning summarizes the future phases at high level

Characteristics of Project Phase

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 19: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Characteristic of Project Life Cycle

Source : PMI PMBOK® Fifth Edition

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 20: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Management Knowledge Areas

There are 10 Knowledge Areas covered in PMBOK® Guide 5th edition

These 10 Knowledge Areas are:

Project Integration management

Project Scope Management

Project Time Management

Project Cost Management

Project Quality Management

Project Human Resource Management

Project Communications Management

Project Risk Management

Project Procurement Management

Project Stakeholder Management

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 21: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Individuals and organizations involved in the project

Those who will be directly or indirectly impacted

Stakeholders should be identified throughout the project

They may have a positive or negative influence on the outcome

Stakeholder influence goes down as the project progresses

Project Stakeholders

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 22: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Key stakeholders include:-

Project Manager

Customer / User

Performing organization

Project team members

Project management team

Sponsor

Influencers

PMO

Project Stakeholders

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 23: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Manager – Skill Set

Communication Skills

Organizational and Planning skills

Budgeting Skills

Conflict Management Skills

Negotiation and Influencing Skills

Leadership Skills

Team Building and Motivating skills

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 24: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Programs Collection of related projects

Controls are implemented and managed in a coordinated way

Collective benefits are realized

Each project has a project manager

Portfolios Collection of programs and projects

Projects meet a specific business goal or objective

Includes weighing the value of each project against the portfolios strategic objective

Project, Program & Portfolio Management

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 25: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Management Office [PMO] Centralized units to oversee project and programs within the organization

Establishes and maintains the standards of project management methodologies

Support managers in planning, estimating, risk management and provide trainings

Project Management Office (PMO)

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 26: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Organization Type - PM Influence

Source: A Guide to the Project Management Body of Knowledge, Fifth Edition.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 27: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Organization Type – Functional Organization

Source: A Guide to the Project Management Body of Knowledge, Fifth Edition.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 28: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Organization Type – Weak Matrix

Source: A Guide to the Project Management Body of Knowledge, Fifth Edition.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 29: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Organization Type – Balanced Matrix

Source: A Guide to the Project Management Body of Knowledge, Fifth Edition.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 30: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Organization Type – Strong Matrix

Source: A Guide to the Project Management Body of Knowledge, Fifth Edition.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 31: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Organization Type – Projectized

Source: A Guide to the Project Management Body of Knowledge, Fifth Edition.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 32: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Organization Type – Composite

Source: A Guide to the Project Management Body of Knowledge, Fifth Edition.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 33: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Organization Types – Advantages & Disadvantages

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 34: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Process Framework

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 35: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur SolutionsPM Knowledge Area – Process Mapping

Source: A Guide to the Project Management Body of Knowledge, Fifth Edition

Author - Pankaj Sharma

Page 36: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Integration Management

Author - Pankaj Sharma

Page 37: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Integration Management

Processes and activities needed to identify, define, combine, unify,

and coordinate the various processes and project management

activities within the Project Management Process Groups

Author - Pankaj Sharma

Page 38: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Project Charter—the process of developing a document that formally authorizes a project or a phase and documenting initial requirements that satisfy the stakeholder’s needs and expectations.

Develop Project Management Plan—the process of documenting the actions

necessary to define, prepare, integrate, and coordinate all subsidiary plans. Direct and Manage Project Work—the process of performing the work defined in the

project management plan to achieve the project’s objectives. Monitor and Control Project Work—the process of tracking, reviewing, and

regulating the progress to meet the performance objectives defined in the project management plan.

Perform Integrated Change Control—the process of reviewing all change requests,

approving changes, and managing changes to the deliverables, organizational process assets, project documents, and the project management plan.

Close Project or Phase—the process of finalizing all activities across all of the Project

Management Process Groups to formally complete the project or phase.

Project Integration Management

Author - Pankaj Sharma

Page 39: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Project Charter

Inputs Tools and Techniques Outputs

Project statement of work

Business case

Agreements

Enterprise environmental factors

Organizational Process Assets

Expert Judgment

Facilitation Techniques

Project Charter

Author - Pankaj Sharma

Page 40: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Charter

Project Title and Description Measurable project objectives and related success criteria, High-level requirements Assumptions and Constraints High level project descriptions and boundaries High Level Risks Summary milestone schedule Summary budget Stakeholder list Project Approval Requirements( i.e. What constitutes the project

success, who decide that the project is successful, and who signs off the project)

Project Manager Assigned and Authority Level (Who is given authority to lead the project, and can he / she determine, manage and approve changes to budget, schedule, staffing, etc.?)

Name and Authority of the sponsor or other persons authorizing the project charter.

.

Author - Pankaj Sharma

Page 41: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Numeric Methods

Benefit Measurement Model (also called Comparative approach )

• Payback Period

• Cost Benefit Analysis

• Scoring Models

• Net Present Value (NPV)

• Internal Rate of Return (IRR)

Mathematical Models (also called Constrained Optimization)

• Use linear, dynamic, non-linear, multi-objective programming to solve problem

Project Selection Methods

Author - Pankaj Sharma

Page 42: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Selection Methods

Non Numeric Method

Sacred cow

Operating necessity

Murder Board

Competitive necessity

Author - Pankaj Sharma

Page 43: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Payback period – the amount of time to recover your cost. It compares the initial investment to the cash inflows expected over the life of the product.

• For example, Initial investment on a project is Rs. 4,00,000, Expected cash inflows: Rs. 50,000 per quarter for first two years, Rs. 100,000 per quarter thereafter.

• What is the payback period?

• Cash inflows = Rs. 50,000 x 4 (quarters in a year) = Rs. 2, 00,000 per year for first two years. Hence, year 1 inflow = Rs. 2, 00,000, year 2 inflow = Rs. 2, 00,000. Total Rs. 4, 00,000 in 2 years

• So payback is reached in 2 years.

Project Selection Methods

Author - Pankaj Sharma

Page 44: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Benefit Cost Ratio (BCR) or profitability Index . This is the ratio of project benefit

and the project cost.

• BCR = Revenue / Cost

• Select the project with a higher BCR

Project Selection Methods

Author - Pankaj Sharma

Page 45: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Present Value (PV) is the expected future cash flows expressed in today’s monetary value

PV = FV / (1+r) n

• For example, Calculate the Present Value of $ 100,000 received three years from now. The interest rate is 10 percent.

• PV = 100000 / (1+10/100)3 = $ 75,131

Project Selection Methods

Author - Pankaj Sharma

Page 46: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Net Present value (NPV) is the sum total of the Present Value of Cash Inflows – Cash Outflows

NPV of the Project is 353-291 = 62

Select the project with higher NPV

Project Selection Methods

TIME PERIOD INCOME/REVENUE PRESENT VALUE AT

10% INT RATE

COSTS PRESENT VALUE AT

10% INT RATE

0 0 0 200 200

1 50 45 100 91

2 100 83 0 0

3 300 225 0 0

TOTAL 353 291

Author - Pankaj Sharma

Page 47: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Internal Rate of Return (IRR): The rate of interest at which the revenues and

costs are equal.

• Select the project with a higher IRR.

Return On Investment (ROI) – A return ratio that compares the net benefits of

a project/ product, verses its total cost.

• ROI = Operating Income / Investments

Project Selection Methods

Author - Pankaj Sharma

Page 48: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Scoring Model Weighted Criteria (example, using scale of 1-5)

Item

Criteria4 5 3

2 3 5

5 4 2

4 4 5

Good ROI 3 12 15 9 0 0

Wei

ght

Project A Project B Project C

CEO Likes It 5 10 15 25 0 0

Provide

Better

Service

4 20 16 8 0 0

Match New

Initiatives of

Competition

3 12 12 15 0 0

0 0 0 0 0

Total: 0Total: 54 Total: 58 Total: 57 Total: 0

Our Winner!! (hmmmm…)

Author - Pankaj Sharma

Page 49: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Sacred Cows and Pressing Needs

“Sacred Cow” selection—Senior Management wants it! (it may often turn out well; many visionary projects start here)

Business opportunity (make more $$$)

Savings potential (save $$$)

Keeping up with competition (example, many e-commerce projects were in response to competitor’s initiatives)

Risk management (examples: disaster recovery initiatives, Y2K)

Government or regulatory requirements

URGENT!!!

Author - Pankaj Sharma

Page 50: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Murder Board

“Murder Board" is a term often used for the team created to see if they can push hard on a project plan to see where it will break. This process is called by other names as well, depending on the subject of the scrutiny and type of firm in which it is employed. For a hard review of a proposal, it is usually called a "red team." Some consulting firms call final briefing reviews "gauntlet drills."

Author - Pankaj Sharma

Page 51: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Method Project A Project B Which One?

Scoring Model 17 20 B

Payback Period 24 Months 25 months A

Benefit Cost Ratio 3.5 4.5 B

Net Present Value

(NPV)

£95,000 £80,000 A

IRR 9.5% 11.5% B

Exercise 1: Which Project Will You Select

Author - Pankaj Sharma

Page 52: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Management Plan

The project management plan defines how the project is executed, monitored and controlled, and closed. The project management plan content will vary depending upon the application area and complexity of the project.

Author - Pankaj Sharma

Page 53: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Project Management Plan

Inputs Tools and Techniques Outputs

Project Charter

Outputs from other Process

Enterprise environmental factor

Organizational Process Assets

Expert Judgment

Facilitation techniques

Project Management Plan

Author - Pankaj Sharma

Page 54: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Requirements Management Plan

Scope management plan

Schedule management plan

Cost management plan

Quality management plan

Process improvement plan

Human Resource management plan

Communication management plan

Risk management plan

Procurement management plan

Stakeholder management plan

Project baselines (include but not limited to scope, schedule and cost baselines)

Components of Project Management Plan

Author - Pankaj Sharma

Page 55: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

The project management plan may also include the following.

Life cycle selected for the project and the processes that will be applied to each phase

Details of the tailoring decisions specified by the project management team as follows Project management processes selected by the project management team

Level of implementation for each selected process

Description of the tools and techniques to be used for accomplishing those processes and

Description of how the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes and the essential inputs and outputs.

Description of how work will be executed to accomplish the project objectives

Change management plan that documents how the changes will be monitored and controlled

Configuration management plan that documents how the configuration management will be performed

Components of Project Management Plan

Author - Pankaj Sharma

Page 56: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Description of how the integrity of the project baselines will be maintained

Requirements and techniques for communicating among stakeholders

Key management reviews for the content, the extent of, and timing to address, open issues and pending decisions

Components of Project Management Plan

Author - Pankaj Sharma

Page 57: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Direct and Manage Project Work

Direct and Manage Project Work is the process of performing the work defined in the project management plan and implementing approved changes to achieve the project’s objectives.

Author - Pankaj Sharma

Page 58: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Activities in Direct and Manage Project Work

The activities include, but are not limited to: Perform activities to accomplish project requirements;

Create project deliverables

Staff, train, and manage the team members assigned to the project

Obtain, manage, and use resources including materials, tools, equipment, and facilities

Author - Pankaj Sharma

Page 59: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Activities in Direct and Manage Project Work

The activities include, but are not limited to:

Establish and manage project communication channels, both external and internal to the project team

Generate project data, such as cost, schedule, technical and quality progress, and status to facilitate forecasting

Issue change requests and adapt approved changes into the project’s scope, plans, and environment

Manage risks and implement risk response activities

Collect and document lessons learned, and implement approved process improvement activities

Author - Pankaj Sharma

Page 60: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Direct and Manage Project Work-

Inputs Tools and Techniques Outputs

Project Management Plan

Approved Change Requests

Enterprise environmental factor

Organizational Process Assets

Expert Judgment

Project Management Information System

Meetings

Deliverables

Work Performance Data

Change Requests

Project Management Plan updates

Project Document Updates

Author - Pankaj Sharma

Page 61: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Monitor and Control Project Work

Monitor and Control Project Work is the process of tracking, reviewing, and regulating the progress to meet the performance objectives defined in the project management plan. Continuous monitoring gives the project management team insight into the health of the project, and identifies any areas that may require special attention. Control includes determining corrective or preventive actions or re-planning and following up on action plans to determine if the actions taken resolved the performance issue.

Author - Pankaj Sharma

Page 62: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Monitoring and Control Project Work

Inputs Tools and Techniques Outputs

Project Management Plan

Schedule Forecasts

Cost Forecasts

Validated Changes

Work Performance Information

Enterprise environmental factors

Organizational Process Assets

Expert Judgment

Analytical techniques

Project Management Information Systems

Meetings

Change requests

Work Performance Reports

Project management plan updates

Project document

updates

Author - Pankaj Sharma

Page 63: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Integrated Change Control

Perform Integrated Change Control is the process of review in all change requests, approving changes and managing changes to the deliverables, organizational process assets, project documents and the project management plan. The Perform Integrated Change Control process is conducted from project inception through completion. The project management plan, the project scope statement, and other deliverables are maintained by carefully and continuously managing changes, either by rejecting changes or by approving changes thereby assuring that only approved changes are incorporated into a revised baseline.

Author - Pankaj Sharma

Page 64: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Integrated Change Control

Inputs Tools and Techniques Outputs

Project management Plan

Work performance reports

Change requests

Enterprise environmental factors

Organizational process assets

Expert judgment

Meetings

Change control tools

Approved change requests

Change log

Project management plan updates

Project documents

updates

Author - Pankaj Sharma

Page 65: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Close Project or Phase

Close Project or Phase is the process of finalizing all activities across all of the Project Management Process Groups to formally complete the project or phase.

When closing the project, the project manager will review

all prior information from the previous phase closures to ensure that all project work is complete and that the

project has met its objectives.

Author - Pankaj Sharma

Page 66: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Close Project or Phase

Inputs Tools and Techniques Outputs

Project Management Plan

Accepted Deliverables

Organizational Process Assets

Expert Judgment

Analytical techniques

Meetings

Final product, service, or result transition

Organizational process assets updates

Author - Pankaj Sharma

Page 67: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms

Exercise 2: Integration Management

1. The project management plan is the collection of ______ Plans

2. Work Culture and company policies are called Enterprise__________ Factors

3. ___________ is a document that gives the project manager authority over the team

Author - Pankaj Sharma

Page 68: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms

Answer to Exercise 2: Integration Management

1. The project management plan is the collection of

Subsidiary Plans

2. Work Culture and company policies are called Enterprise

Environmental Factors

3. Project Charter is a document that gives the project

manager authority over the team

Author - Pankaj Sharma

Page 69: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

QUIZ !

Author - Pankaj Sharma

Page 70: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Scope Management

Author - Pankaj Sharma

Page 71: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Scope Management

Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully. Managing the project scope is primarily concerned with defining and controlling what is and is not included in the project.

Author - Pankaj Sharma

Page 72: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Why Manage Project Scope?

Some of the issues faced in projects

Project teams believe the additional work is a change request, but the client insists it is part of the original scope

The project suddenly finds itself crunched for time. A number of additional requirements are coming up along with the continuing development work

The client talks about a high level vision which the project is expected to achieve, but the stakeholders are either unable to articulate this vision in concrete objectives and deliverables or provide conflicting views

Contradicting requirements. Different interpretation of the same statement by different people

Commitment made to the customer without understanding the application portfolio

Author - Pankaj Sharma

Page 73: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Scope Management

Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully. Managing the project scope is primarily concerned with defining and controlling what is and is not included in the project.

Author - Pankaj Sharma

Page 74: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Scope Management – The process of creating a scope management plan that documents how the project scope will be defined , validated and controlled

Collect Requirements—The process of defining and documenting stakeholders’ needs to meet the project objectives

Define Scope—The process of developing a detailed description of the project and product

Create WBS—The process of subdividing project deliverables and project work into smaller, more manageable components

Validate Scope—The process of formalizing acceptance of the completed project deliverables

Control Scope—The process of monitoring the status of the project and product scope and managing changes to the scope baseline

Project Scope Management

Author - Pankaj Sharma

Page 75: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Scope Management

Plan Scope Management is the process of creating a scope management plan that documents how the project scope will be defined , validated and controlled.

The key benefit of this process is that it provides guidance and direction on how scope will be managed throughout the project.

Author - Pankaj Sharma

Page 76: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Scope Management

Inputs Tools and Techniques Outputs

Project Management Plan

Project Charter

Enterprise environmental factors

Organization process assets

Expert Judgment

Meetings

Scope Management Plan

Requirements Management Plan

Author - Pankaj Sharma

Page 77: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Scope Management Plan

The scope management plan is a component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and verified. The scope management plan is a major input into the Develop Project Management Plan process, and the other scope management processes.

Author - Pankaj Sharma

Page 78: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Scope Management Plan

The components of a scope management plan include: • Process for preparing a detailed project scope statement • Process that enables the creation of the WBS from the detailed project scope statement • Process that establishes how the WBS will be maintained and approved • Process that specifies how formal acceptance of the completed project deliverables will be obtained and • Process to control how requests for changes to the detailed project scope statement will be processed.

Author - Pankaj Sharma

Page 79: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Requirements Management Plan

The requirements management plan is a component of the project management plan that describes how requirements will be analyzed, documented, and managed.

Author - Pankaj Sharma

Page 80: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Requirements Management Plan

Components of the requirements management plan can include, but are not limited to: • How requirements activities will be planned, tracked, and reported; • Configuration management activities such as: how changes to the product will be initiated, how impacts will be analyzed, how they will be traced, tracked, and reported, as well as the authorization levels required to approve these changes; • Requirements prioritization process; • Product metrics that will be used and the rationale for using them; and • Traceability structure to reflect which requirement attributes will be captured on the traceability matrix.

Author - Pankaj Sharma

Page 81: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Collect Requirements (Planning Process Group)

Collect Requirements is the process of defining and documenting stakeholders need to meet the project objectives

Many organizations categorize requirements into project requirements and product requirements. Project requirements can include business requirements, project management requirements, delivery requirements, etc. Product requirements can include information on technical requirements, security requirements, performance requirements etc.

Author - Pankaj Sharma

Page 82: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Product Scope: The features and functions in a product,

service, or result.

Project Scope: The work that needs to be done in order

to deliver a product, service or result

with the specified features and

functions.

Product Scope and Project Scope

Author - Pankaj Sharma

Page 83: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Collect Requirements

Inputs Tools and Techniques Outputs

Scope management plan

Requirements management plan

Stakeholder management plan

Project Charter

Stakeholder Register

Interviews

Focus Groups

Facilitated Workshop

Group Creativity Techniques

Group Decision Making Techniques

Questionnaires and surveys

Observations

Prototypes

Benchmarking

Context Diagrams

Document analysis

Requirements Documentation

Requirements Traceability Matrix

Author - Pankaj Sharma

Page 84: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Collect Requirements – Requirement Traceability Matrix

Author - Pankaj Sharma

Page 85: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Define Scope

Define Scope is the process of developing a detailed description of the project and product. The preparation of a detailed project scope statement is critical to project success and builds upon the major deliverables, assumptions, and constraints that are documented during project initiation.

Author - Pankaj Sharma

Page 86: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Define Scope -

.

Inputs Tools and Techniques Outputs

Scope management plan

Project Charter

Requirements Documentation

Organizational Process Assets

Expert Judgment

Product Analysis

Alternatives Identification

Facilitated Workshops

Project Scope Statement

Project Document Updates

Author - Pankaj Sharma

Page 87: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Scope Statement

Project Objectives

Product scope description

Project requirement

Project boundaries

Project deliverables

Product acceptance criteria

Project scope statement describes, in detail, the project’s

deliverables and the work required to create those deliverables

Project constraints/assumptions

Initial identified risk

Schedule milestones

Initial project organization

Fund limitation

Configuration management

requirement

Approval requirement

Author - Pankaj Sharma

Page 88: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Create WBS (Planning Process Group)

Create WBS is the process of subdividing project deliverables and project work into smaller, more manageable components.

The planned work is contained within the lowest level WBS components, which are called work packages. A work package can be scheduled, cost estimated, monitored, and controlled.

Author - Pankaj Sharma

Page 89: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Create WBS -

(Planning Process Group)

Inputs Tools and Techniques Outputs

Scope management plan

Project Scope Statement

Requirements Documentation

Enterprise environmental factors

Organizational Process Assets

Decomposition

Expert judgment

Scope Baseline

Project Document Updates

Author - Pankaj Sharma

Page 90: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Create WBS

The Work Breakdown Structure breaks down deliverables

Work Packages are deliverables / work packages, NOT activities

A sample WBS for a car manufacturing project

Author - Pankaj Sharma

Page 91: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Phase-Based WBS

Partial WBS for Software Project Based on Phase

Planning

Reporting

Administration

Meetings

Documentation Planning

Project Management

Client Interviews

Review of Current Workflows

Business Objectives

Preliminary Test Planning

Documentation Planning

Training Requirements

Requirements

Process Models

Use Cases

Logical Data Models

Logical Design

Process Models

Use Cases

Physical Data Models

Logical Design

Design

etc.

Build

Customer Relationship Management System

Author - Pankaj Sharma

Page 92: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Component-Based WBS

Partial WBS for Luxury Townhouse Complex by Component

Planning

Reporting

Administration

Meetings

Documentation Planning

Project Management

Townhouse Units

Clubhouse

Gatehouses

Pro Shop

Documentation Planning

Maintenance Staffing Requirements

Permits and Inspections

Buildings

Water and Sewers

Roads and Access Lanes

Retention Ponds

18-Hole Golf Course

Permits and Inspections

Land Planning

Advertising

Association Declarations

General Legal

Sales and Marketing

IYHTAYCAI* Village Project

(*If you have to ask, you can't affort it)

Author - Pankaj Sharma

Page 93: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur SolutionsWBS Dictionary Template

WBS Dictionary

Project Name: WBS Name:

Start Date: WBS Owner:

WBS Detail:

WBS Element Description:

Acceptance Criteria:

Assumptions:

Resources Assigned:

WBS dependencies:

Cost:

Approved by: Date:

End Date:

Parent Id: WBS Id:

Author - Pankaj Sharma

Page 94: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Definition: An approved specific version of the detailed scope statement, work breakdown structure (WBS), and its associated WBS dictionary

When finalizing scope baseline, the items that are eliminated from the project must be formally documented as exclusions to the project.

If their exclusion is not properly documented, they may return again and again as new requirements to be considered.

Scope Baseline

Author - Pankaj Sharma

Page 95: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Validate Scope

Validate Scope is the process of formalizing acceptance of the completed project deliverables. This process includes reviewing deliverables with the customer or sponsor to ensure that they are completed satisfactorily and obtaining formal acceptance of deliverables by the customer or sponsor.

Author - Pankaj Sharma

Page 96: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Once the scope of the project has been defined and delivered, the scope of the project delivered must be verified.

This means getting approval of the delivered scope of the project from all of the stakeholders.

It is a good practice to get the stakeholders to agree to the acceptance criteria at the beginning of the project rather than at the end of it.

A set of acceptance criteria is drawn up and the acceptance criteria are agreed to when the project scope is accepted by the stakeholders.

Validate Scope

Author - Pankaj Sharma

Page 97: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Validate Scope

Inputs Tools and Techniques Outputs

Project Management Plan

Requirements Documentation

Requirements Traceability Matrix

Verified Deliverables

Work performance data

Inspection

Group decision making techniques

Accepted deliverables

Change requests

Work performance information

Project document updates

Author - Pankaj Sharma

Page 98: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Scope (Monitoring and Controlling Process Group)

Monitoring the status of the project and product scope and managing changes to the scope baseline.

Author - Pankaj Sharma

Page 99: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Scope (Monitoring and Controlling Process Group )

Inputs Tools and Techniques Outputs

Project Management Plan

Requirements Documentation

Work Performance Data

Requirements Traceability Matrix

Organizational Process Assets

Variance Analysis Work Performance Information

Change Requests

Project Management Plan Updates

Project Document Updates

Organization Process Assets Updates

Author - Pankaj Sharma

Page 100: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Arrange the following activities in correct order

Exercise 1: Correct Order

Define

scope

Collect

Requirements

Create

WBS Validate Scope

Author - Pankaj Sharma

Page 101: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Complete the following

Exercise 2: Scope Management Crossword

1. ____________ Scope means the features or functions of the thing or service that you are building

2. The process where you write the project scope statement is called _________ Scope

Author - Pankaj Sharma

Page 102: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Complete the following

Exercise 2: Scope Management Crossword

1. Product Scope means the features or functions of the thing or service that

you are building

2. The process where you write the project scope statement is called Define

Scope

Author - Pankaj Sharma

Page 103: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

QUIZ !

Author - Pankaj Sharma

Page 104: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Time Management

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 105: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Time Management

Project Time Management includes the processes required to manage timely completion of the project. Plan schedule management – The process of establishing the policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule Define Activities—The process of identifying the specific actions to be performed to produce the project deliverables. Sequence Activities—The process of identifying and documenting relationships among the project activities. Estimate Activity Resources—The process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity. Estimate Activity Durations—The process of approximating the number of work periods needed to complete individual activities with estimated resources. Develop Schedule—The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. Control Schedule—The process of monitoring the status of the project to update project progress and managing changes to the schedule baseline.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 106: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Schedule Management

Plan schedule Management is the process of establishing the policies, Procedures, and documentation for planning, developing, managing and controlling the project schedule The key benefit of this process is that it provides direction on how the project schedule will be managed throughout the project.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 107: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Schedule Management

Inputs Tools and Techniques Outputs

Project management plan

Project charter

Enterprise Environment Factors

Organization Process Assets

Expert Judgment

Analytical techniques

Meetings

Schedule management plan

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 108: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Schedule Management

Pankaj Sharma, 9810996356

The schedule management plan can establish the following: • Project schedule model development. The scheduling methodology and the scheduling tool to be used • Level of accuracy. The acceptable range used in determining realistic activity duration estimates is . • Units of measure. Each unit used in measurements (such as staff hours, staff days, or weeks for time • Organizational procedures links. The WBS provides the framework for the schedule . • Project schedule model maintenance. The process used to update the status and record progress of

Author - Pankaj Sharma

Page 109: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Schedule Management

Pankaj Sharma, 9810996356

• Control thresholds. Variance thresholds for monitoring schedule performance may be specified to indicate An agreed-upon amount of variation to be allowed before some action needs to be taken. Thresholds are typically expressed as percentage deviations from the parameters established in the baseline plan.

Author - Pankaj Sharma

Page 110: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Define Activities

Define Activities is the process of identifying and documenting the specific actions to be performed to produce the project deliverables. The key benefit of this process is to break down work packages into Activities that provide a basis for estimating, scheduling, executing, Monitoring , and controlling the project work.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 111: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Define Activities

Inputs Tools and Techniques Outputs

Schedule management plan

Scope Baseline

Enterprise Environment Factors

Organization Process Assets

Decomposition

Rolling Wave Planning

Expert Judgment

Activity List

Activity Attributes

Milestone List

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 112: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions Define Activities : Inputs

Schedule Management Plan - provides direction on how the project schedule will

be managed throughout the project.

Scope Baseline provides the project deliverables, assumptions and constraints

Enterprise Environmental Factors that can influence the Define Activities process include, but are not limited to, the project management information system (PMIS).

Organizational Process Assets that can influence the Define Activities process include, but are not limited to:

Existing formal and informal activity planning-related policies, procedures, and guidelines, such as the scheduling methodology, that are considered in developing the activity definitions, and

Lessons-learned knowledge base containing historical information regarding activities lists used by previous similar projects.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 113: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Define Activities : Tools and Techniques

Decomposition involves subdividing the project work packages into smaller, more manageable components called activities.

Rolling Wave Planning is a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of the WBS.

Templates is a standard activity list or a portion of an activity list from a previous project is often usable as a template for a new project. The related activity attributes information in the templates can also contain other descriptive information useful in defining activities.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 114: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Define Activities : Outputs

Activity List is a comprehensive list including all schedule activities required on the project. Activity attributes depicts the multiple components associated with each activity Activity ID, WBS ID, Activity Name, activity description, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions. Activity attributes can be used to identify the person responsible for executing the work, geographic area, or place where the work has to be performed, and activity type such as level of effort (LOE), discrete effort, and apportioned effort (AE). Milestone List identifies all milestones and indicates whether the milestone is mandatory, such as those required by contract, or optional, such as those based upon historical information.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 115: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Sequence Activities

Sequence Activities is the process of Identifying and documenting relationships among the project activities. The key benefit of this Process is that it defines the logical sequence of Work to obtain the greatest efficiency given all project constraint.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 116: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Sequence Activities

Inputs Tools and Techniques Outputs

Schedule management plan

Activity List

Activity Attributes

Milestone List

Project Scope Statement

Enterprise environmental Factors

Organization Process Assets

Precedence Diagramming Method (PDM)

Dependency determination

Leads and Lags

Project Schedule Network Diagrams

Project Document Updates

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 117: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Sequence Activities - Inputs

Schedule Management Plan - provides direction on how the project schedule will be

managed throughout the project.

Activity List – Output of Define Activities process

Activity Attributes – Output of Define Activities process

Milestone List - Output of Define Activities process

Project Scope Statement – Output of Define Scope Process

Organizational Process Assets - The organizational process assets that can influence the Sequence Activities process include, but

are not limited to, project files from the corporate knowledge base used for scheduling methodology.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 118: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Sequence Activities – Tools and Techniques

Precedence Diagramming Method (PDM)- Also known as activity on node (AON) as the activities are represented on nodes and the logical relationship between activities is represented through arrows

The relationship in the figure below represents that the Activity B is dependent on Activity A. i.e. Activity B can only start after the completion of activity A

B A

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 119: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Sequence Activities – Tools and Techniques

Types of dependencies in PDM

Finish – to – Start (FS) – This relationship means Task A must complete before Task B can begin. This is the most common relationship.

Finish – to – Finish (FF) - Finish of successor activity depends on finish of the predecessor

Start-to-Start (SS) – Start of a successor activity depends on start of a predecessor activity.

Start- to – Finish (SF) – Finish of Successor depends on the start of preceding activity.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 120: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Sequence Activities – Tools and Techniques

Dependency Determination

There are three kinds of dependencies, Mandatory dependency, Discretionary dependency and external dependency

Mandatory dependencies referred as hard logic are natural order of activities or which are contractually required.

Discretionary dependencies referred as preferred logic, soft logic or preferential logic are defined as best practices and are considered the preferred choice among the other alternatives.

External dependencies are external to the project and are not in project’s control. E.g. Deliverable from other project or expected new law etc

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 121: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Activity Resources

Estimate Activity Resources is the process of estimating the

type and quantities of material, human resources,

Equipment, or supplies required to perform each activity.

The key benefit of this process is that it identifies the type,

Quantity, and characteristics of resources required to

Complete the activity which allows more accurate cost and

duration estimate

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 122: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Activity Resources

Inputs Tools and Techniques Outputs

Schedule Management Plan

Activity List

Activity Attributes

Resource Calendars

Risk Register

Enterprise Environmental Factors

Organization Process Assets

Expert judgment

Alternatives analysis

Published estimating data

Bottom-up estimating

Project management software

Activity resource requirements

Resource breakdown structure

Project management updates

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 123: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Activity Resources - Inputs

Schedule Management Plan – Identifies the level of accuracy and the units of measure for the resource to be estimated

Activity List – Identifies the activities which will need resources

Activity Attributes – Provide the primary data input for use in estimating those resources required for each activity in the activity list.

Resource Calendar – Resource calendars specify when and how long identified project resources will be available during the project

Enterprise Environmental Factors- The enterprise environmental factors that can influence the Estimate Activity Resources process include but are not limited to resource availability and skills

Organizational Process Assets – that influence this process include but are not limited to; Policies and Procedures related to staffing, policies and procedures related to rental purchase of supplies and equipments, Historical information regarding types of resources used for similar work on previous projects

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 124: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Activity Resources –Tools and Techniques

Expert Judgment is often required to assess the resource-related inputs to this process. Any group or person with specialized knowledge in resource planning and estimating can provide such expertise.

Alternatives Analysis

Many schedule activities have alternative methods of accomplishment. They include using various levels of resource capability or skills, different size or type of machines, different tools (hand versus automated), and make-or-buy decisions regarding the resource.

Published Estimating Data

Several companies routinely publish updated production rates and unit costs of resources for an extensive array of labor trades, material, and equipment for different countries and geographical locations within countries.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 125: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Bottom-Up Estimating When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail. The resource needs are estimated. These estimates are then aggregated into a total quantity for each of the activity’s resources. Activities may or may not have dependencies between them that can affect the application and use of resources. If there are dependencies, this pattern of resource usage is reflected and documented in the estimated requirements of the activity.

Project Management Software Project management software has the capability to help plan, organize, and manage resource pools and develop resource estimates. Depending on the sophistication of the software, resource breakdown structures, resource availability, resource rates and various resource calendars can be defined to assist in optimizing resource utilization.

Estimate Activity Resources –Tools and Techniques

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 126: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Activity Resources – Outputs

Activity Resource Requirements identifies the types and quantities of resources required for each activity in a work package. These requirements can then be aggregated to determine the estimated resources for each work package. The amount of detail and the level of specificity of the resource requirement descriptions can vary by application area. The resource requirements documentation for each activity can include the basis of estimate for each resource, as well as the assumptions that were made in determining which types of resources are applied, their availability, and what quantities are used. Resource Breakdown Structure is a hierarchical structure of the identified resources by resource category and resource type. Examples of resource categories include labor, material, equipment, and supplies. Resource types can include the skill level, grade level or other information as appropriate to the project. The resource breakdown structure is useful for organizing and reporting project schedule data with resource utilization information. Project Documents may be updated include, but are not limited to: Activity list, Activity attributes, and Resource calendars.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 127: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Activity Duration

Estimate Activate Durations is the process of estimating the

Number of work periods needed to complete individual

Activities with estimated resources.

The key benefit of this process is that it provides the

amount of time each activity will take to complete, which is

a major input to Develop schedule process.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 128: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Activity Duration

Inputs Tools and Techniques Outputs

Schedule management plan

Activity List

Activity Attributes

Activity Resource Requirements

Resource Calendars

Project Scope Statement

Risk Register

Resource Breakdown Structure

Enterprise Environmental Factors

Organization Process Assets

Expert judgment

Analogous Estimating

Parametric Estimating

Three point estimates

Group decision making techniques

Reserve Analysis

Activity duration updates

Project document updates

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 129: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Activity Duration - Inputs

Schedule Management Plan – defines the method used and the level of accuracy along with other criteria required to estimate activity durations including the project update cycle. Activity List – Defines activity list that will need duration estimates. Activity Attributes- Output of Define Activities process Activity Resource Requirements –The number of resources allocated will impact the duration of most of the activities. Resource Calendars - can include the type, availability, and capabilities of human resources. The type, quantity, availability, and capability, when applicable, of both equipment and material resources, which could significantly influence the duration of schedule activities, are also considered. Examples such as Existing conditions, Availability information and length of the reporting periods. Examples of constraints include , Available skilled resources and contract terms and requirement.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 130: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Activity Duration - Inputs

Project Scope Statement- The assumptions and constraints from the project scope statement are considered when estimating the activity durations. This includes Existing conditions Availability of information Length of the reporting periods

Examples of constraints include, but are not limited to Available skilled resources Contract terms and requirements Enterprise Environmental Factors that can influence the Estimate Activity Durations process include, but are not limited to: Duration estimating databases and other reference data, Productivity metrics, and Published commercial information. Organization Process Assets that can influence the Estimate Activity Durations process include but are not limited to: Historical duration information, Project calendars, Scheduling methodology and Lessons learned.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 131: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Expert Judgment guided by historical information, can provide duration estimate information or recommended maximum activity durations from prior similar projects. Expert judgment can also be used to determine whether to combine methods of estimating and how to reconcile differences between them. Analogous estimating uses parameters such as duration, budget, size, weight, and complexity, from a previous, similar project, as the basis for estimating the same parameter or measure for a future project. Parametric Estimating Parametric estimating uses a statistical relationship between historical data and other variables (e.g., square footage in construction) to calculate an estimate for activity parameters, such as cost, budget, and duration. Reserve Analysis include contingency reserves, (sometimes referred to as time reserves or buffers) into the overall project schedule to account for schedule uncertainty. The contingency reserve may be a percentage of the estimated activity duration, a fixed number of work periods, or may be developed by using quantitative analysis methods.

Estimate Activity Duration – Tools and Techniques

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 132: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Activity Duration – Tools and Techniques

Three-Point Estimates (PERT) is based on statistical methods in particular normal distribution. The estimation of activity duration is done based on the following three points Most likely (M). The duration of the activity, given the resources likely to be assigned, their productivity, realistic expectations of availability for the activity, dependencies on other participants, and interruptions. Optimistic (O). The activity duration is based on analysis of the best-case scenario for the activity. Pessimistic (P). The activity duration is based on analysis of the worst-case scenario for the activity. PERT analysis calculates an Expected (E) activity duration using a weighted average of these three estimates: Double Triangular or Beta Distribution - E = O + 4M + P/6 , Standard Deviation - SD= P-0/6 Triangular Distribution – E= 0+M+P/3 , Standard Deviation =√ 02+M2+P2-OM-MP-PO/18

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 133: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Schedule

Develop schedule is the process of analyzing activity

sequences, durations, resource requirements, and

schedule constraints to create the project schedule model.

The key benefits of this process is that by entering schedule

activities , durations, resources, resource availabilities and

Logical relationships into the scheduling tool , it generates a

schedule model with planned dates for completing project

activities

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 134: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Schedule

Inputs Tools and Techniques Outputs

Schedule management

Activity List

Activity attributes

Project schedule network diagrams

Activity resource requirements

Resource calendars

Activity duration estimates

Project scope statement

Project staff assignments

Resource Breakdown Structure

Risk Register

Enterprise Environmental Factors

Organizational Process Assets

Schedule network analysis

Critical path method

Critical chain method

Resource optimization techniques

Modeling techniques

Leads and lags

Schedule compression

Scheduling tool

Project schedule

Schedule baseline

Schedule data

Project Calendars

Project Management Plan updates

Project document

updates

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 135: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Schedule Management Plan – Identifies the scheduling method and tool used to create the schedule and how schedule is to be calculated.

Activity List – Identifies the activities that will be included in the schedule model

Activity attributes – Provide the details used to build the schedule model.

Project schedule network diagram – contains logical relationship between predecessor and successor that will be used to build the schedule.

Activity resource requirements – Identify the types and quantities of resources required for each activity used to create the schedule model.

Resource calendars- specify when and how long identified project resources will be

available during the project

Activity duration estimates contain the quantitative assessment of the likely number of work periods that will be required to complete an activity that will be used to calculate the schedule.

Develop Schedule - Inputs

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 136: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project scope statement- contains assumptions and the constraints that can impact the development of the schedule.

Enterprise Environmental Factors that can influence the Develop Schedule process include, but are not limited to, a scheduling tool that can be used in developing the schedule.

Organizational Process Assets The organizational process assets that can influence the Develop Schedule process include, but are not limited to:

Scheduling methodology and Project calendar.

Develop Schedule - Inputs

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 137: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Schedule Tools and Techniques

The critical path method calculates the theoretical early start and finish dates, and late start and finish dates, for all activities without regard for any resource limitations, by performing a forward and backward pass analysis through the schedule network. Critical Chain Method is a schedule network analysis technique that modifies the project schedule to account for limited resources. The resource-constrained critical path is known as the critical chain. The critical chain method adds duration buffers that are non-work schedule activities to manage uncertainty.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 138: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Schedule Tools and Techniques

Resource Optimization Techniques – that can be used to Adjust the schedule model due to demand and supply of resources include. Resource Levelling - Is necessary when resources have been over-allocated, such as when a resource has been assigned to two or more activities during the same time period, when shared or critical required resources are only available at certain times or are only available in limited quantities. Resource leveling can often cause the original critical path to change. Resource Smoothing – A technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined resource limits. There is no change in the project completion date the activities may only be delayed within their free and total float.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 139: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Schedule Tools and Techniques

Modeling Techniques include What-If Scenario Analysis- A schedule network analysis is performed using the schedule to compute the different scenarios, such as delaying a major component delivery, or introducing external factors, such as a strike The outcome of the what if scenario analysis can be used to assess the Feasibility of the project schedule under adverse conditions Simulation involves calculating multiple project durations with different sets of activity assumptions. The most common technique is Monte Carlo Analysis in which a distribution of possible activity durations is defined for each activity and used to calculate a distribution of possible outcomes for the total project.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 140: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Applying Leads and Lags - Leads and lags are refinements applied during network analysis to develop a viable schedule.

Schedule Compression

Crashing. A schedule compression technique in which cost and schedule tradeoffs are analyzed to determine how to obtain the greatest amount of compression for the least incremental cost. Examples of crashing could include approving overtime, bringing in additional resources, or paying to expedite delivery to activities on the critical path. Crashing only works for activities where additional resources will shorten the duration. Crashing does not always produce a viable alternative and may result in increased risk and/or cost.

Fast tracking. A schedule compression technique in which phases or activities normally performed in sequence are performed in parallel. An example is constructing the foundation for a building before completing all of the architectural drawings. Fast tracking may result in rework and increased risk. Fast tracking only works if activities can be overlapped to shorten the duration.

Develop Schedule Tools and Techniques

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 141: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Schedule Tools and Techniques

Scheduling Tool - Automated scheduling tools expedite the scheduling process by generating start and finish dates based on the inputs of activities, network diagrams, resources and activity durations. A scheduling tool can be used in conjunction with other project management software applications as well as manual methods.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 142: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Schedule Outputs

Schedule Baseline - is a real or theoretical construct that captures the approved schedule. It is used to provide a comparison or contrast with the actual progress of work against the schedule and to determine if performance to date is within acceptable parameters. Project schedule displays the start and end dates of all the activities in the project and the same for overall project. It can be represented in the form of Gantt Chart, Milestone Chart or a project network diagram. Schedule data is the data on the basis of which schedule was developed. It includes resource requirements by time period, alternative schedules such as best-case or worst case, not resource leveled or resource leveled with, or without imposed dates and scheduling of contingency reserves

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 143: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Schedule Outputs

Project Calendars – A project calendar identifies working days and shifts that are available for scheduled activities. It distinguishes time period in days or part of days that are available to complete scheduled activities from time period that are not available. Project Management Plan Updates – Elements of the project management plan that may be updated include Schedule baselines Schedule management plan Project document updates includes updates to resource requirement, activity attributes, risk registers and calendars

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 144: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

For the network diagram below find Critical Path, float for activity A and E

Exercise : Critical Path

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 145: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

For the network diagram below find Critical Path, float for activity A and E

Exercise : Critical Path

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 146: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Exercise : Forward and Backward Pass

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 147: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Complete the following Project Network Diagram

Exercise : Critical Path

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 148: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Based on the portion of network diagram shown below find ES and LF for

activity F

Exercise : Critical Path

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 149: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Schedule (Monitoring and Controlling Process Group)

Control Schedule is the process of monitoring the status of the project to update project progress and manage changes to the schedule baseline.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 150: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Schedule

Control Schedule is the process of monitoring the status of

project activities to update project progress and manage

changes to the schedule baseline to achieve the plan.

The key benefit of this process is that it provides the means

to recognize deviation from the plan and take corrective

action and preventive actions and thus minimizes risk.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 151: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Schedule

Inputs Tools and Techniques Outputs

Project management plan

Project schedule

Work performance data

Organizational process assets

Performance reviews

Project management Software

Resource optimization techniques

Modeling techniques

Leads and lags

Schedule compression

Scheduling tool

Work performance information

Schedule forecasts

Change Requests

Project Management Plan updates

Project document updates

Organization Process asset updates

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 152: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Schedule- Inputs

Project Management Plan is a formal, approved document that defines how the project is executed, monitored and controlled.

Project Schedule is the primary input to this process, since it is the source against which the results are controlled.

Work Performance Data details the work that is being executed, recently completed, and next steps. This information is gathered from the Direct and Manage Project execution process.

Project Calendars - A schedule model may require more than one project calendar to allow for different work periods for some activities to calculate the schedule forecasts.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 153: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Schedule- Inputs

Schedule Data will be reviewed and updated in the Control Schedule process.

Organizational Process Assets can be a system for formally evaluating schedule change, or a software system to help detect changes or measuring variance

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 154: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Schedule- Tools and Techniques

Performance Reviews keeps project manager updated on how project is progressing against the base lined schedule. Some of the techniques that can be used for performance reviews are :

Trend analysis – examines project performance over time to determine whether performance is improving or deteriorating.

Critical path method – Comparing the progress along the critical path can help determine schedule status. The variance on the critical path will have a direct impact on the project end data. Evaluating the progress of activities on near critical paths can identify schedule risk.

Critical Chain method- Comparing the amount of buffer remaining to the amount of buffer needed to protect the delivery date can help determine schedule status. The difference between the buffer needed and the buffer remaining can determine whether corrective action is appropriate.

Earned Value Management - Measurements such as SV and SPI helps you to know whether you are ahead or behind in terms of the schedule.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 155: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Schedule- Tools and Techniques

Project Management Software automates the other tools and techniques in control schedule

Resource optimization techniques involves the scheduling of activities and resources required by those activities while taking into consideration both the resource availability and the project time.

Modeling techniques are used to review various scenarios guided by risk monitoring to bring the schedule model into alignment with the project management plan and approved baseline.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 156: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Leads and lags have impact on the schedule and as the project progresses lead and lags need to be adjusted to reflect reality so as to provide the most realistic view of the schedule possible

Schedule compression includes shortening the duration of the plan through Crashing and Fast tracking

Scheduling tool provides various features (Views, reports etc) that helps in managing the schedule

Control Schedule- Tools and Techniques

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 157: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Schedule- Outputs

Work Performance Information– The updated schedule performance index (SPI) , Schedule variance (SV) and other earned value measurements relevant to the schedule need to be calculated and communicated out.

Change Requests – Any change in the schedule due to change in scope or due to any other valid reason requires Change Request.

Project Management Plan Updates - As the schedule changes, the project management plan is updated.

Project Document Updates – This includes any project document (Other than project management plan) that has changed as a result of Control Schedule. For example Scheduled data such as revised planned start and finish dates, Project schedule and the Risk register

Organization Process Updates – Any times a lesson is learned in Control Schedule, it becomes a reusable asset for the performing organization.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 158: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Complete the following

Exercise 3: Time Management

1. Adding more resources to a project so you can get it done

faster is called____________ .

2. _________ is the process where you put the activities in

order.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 159: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Answers to Exercise 3: Time Management

1. Adding more resources to a project so you can get it done

faster is called Crashing .

2. Sequence Activities is the process where you put the

activities in order.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 160: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

QUIZ !

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 161: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Cost Management

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 162: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Cost Management

Project Cost Management includes the processes involved in estimating, budgeting, and controlling costs so that the project can be completed within the approved budget.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 163: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Cost Management Processes

Process Process Group

Plan Cost Management Planning

Estimate Costs Planning

Determine Budget Planning

Control Costs Monitoring and Controlling

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 164: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Costs

Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The table below shows five different types of estimates that can be used based on the need.

Estimate Type Range

Order of Magnitude Estimates -50% to +50%

Conceptual Estimate -30% to +50%

Preliminary Estimate -20% to +30%

Definitive Estimate -15% to +20%

Control Estimate -10% to +15%

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 165: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Direct Cost- Any cost that is identified specifically with a particular final

cost objective.

Indirect Cost- Any cost not directly identified with a single, final cost

objective (more than one project)

Fixed Cost - Periodic charge that does not vary with business volume

Variable Cost - Cost that fluctuates based on the business volume

Opportunity Cost: When there is a decision to be made between two

opportunities, the opportunity cost is the value / money forgone for the not

doing the project.

Types of Cost

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 166: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

• Lifecycle Costing: Takes into account cost of development of a project

and also the cost of supporting during the lifecycle.

• Sunk Cost - Cost already incurred which cannot be recovered regardless

of future events

Types of Cost

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 167: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Cost Management

The process that establishes the policies, procedures , and documentation for planning , managing , expending , and controlling project costs.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 168: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Cost Management

Inputs Tools and Techniques Outputs

Project Management Plan

Project Charter

Enterprise Environmental Factors

Organizational Process Assets

Expert Judgment

Analytical Techniques

Meetings

Cost Management Plan

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 169: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Cost Management- Inputs

Project Management Plan component that is important for this process are primarily the scope and cost baselines.

Project Charter provides the summary budget from which the detailed project costs are developed . It also defines the project approval requirements that will influence the management of the project costs.

Enterprise Environmental Factors include factors such as Organization structure/culture, Market conditions, currency exchange rates (for project sourced from more than one country) that influence the project cost.

Organizational Process Assets include financial control procedures , historical information . Existing formal and informal cost estimating and budgeting related policies, procedures and guidelines.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 170: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Cost Management- Tools and Techniques

Expert Judgment – Guided by historical information, provides valuable insight about the environment and information from prior similar projects. Judgment based upon expertise in an application area, knowledge area , discipline, industry can be useful in this process.

Analytical Techniques – Some of the techniques payback period, return on investment, internal rate of return, discounted cash flow and net present value can be useful in this process

Meetings - Project teams may hold meetings planning meetings to develop the cost management plan. These meetings may include, project sponsor, project manager, selected team members , selected stakeholders, anyone with responsibility for project costs.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 171: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Cost Management- Outputs

Cost Management Plan – is a component of the project management plan and describes how the project costs will be planned, structured , and controlled. The cost management plan can establish the following.

Units of measure - Each unit of measure for each resource.

Level of precision – The degree to which activity cost estimates will be rounded up or down.

Level of accuracy - The acceptable range (e.g. +_ 100%) used in determining realistic activity cost estimates is specified , may include an amount for contingencies.

Control threshold – Variance threshold for monitoring cost performance may be specified to indicate an agreed – upon amount of variation to be allowed before some action need to be taken.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 172: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Cost Management- Outputs

The cost management plan also contains.

Rules of performance measurement – Earned value management (EVM) rules of performance measurement are set. For example

Define the points in the WBS at which measurement of control accounts will be performed

Establish the earned value measurement techniques (e.g. weighted milestones, fixed formula, percent complete, etc) to be used and

Specify tracking methodologies and the earned value management computation equations for calculating projected estimate at completion (EAC) forecasts to provide a validity check on the bottom-up EAC

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 173: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Cost

pankaj sharma, 9810996356

Estimate cost is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of this process is that it determines the amount of cost required to complete project work.

Author - Pankaj Sharma

Page 174: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Costs

Inputs Tools and Techniques Outputs

Cost Management Plan

Human Resource Management Plan

Scope baseline

Project Schedule

Risk Register

Enterprise Environmental Factors

Organizational Process Assets

Expert Judgment

Analogous Estimating

Parametric estimating

Bottom-up estimating

Three-point estimates

Reserve Analysis

Cost of Quality

Project management estimating software

Vendor bid analysis

Group decision – making techniques

Activity Cost estimates

Basis of estimates

Project document updates

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 175: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Costs - Inputs

Cost management plan – The cost management plan defines how project costs will be managed and controlled . It includes the method used and the level of accuracy required to estimate activity cost.

Human Resource Plan provides detail on Project staffing attributes, personnel rates, and related rewards/recognition, these are necessary components for developing the project cost estimates.

Scope baseline include inputs from scope statement, Work Breakdown Structure and WBS dictionary.

Project Schedule provides detail on the type and quantity of resources and the amount of time which those resources are applied to complete the work of the project, all these factors directly impact the cost

Risk Register provides input related to costs associated with risk response

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 176: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Costs - Inputs

Enterprise Environmental Factors include availability of resources, published commercial information

Organizational Process Assets – include cost estimating policies, historical information, cost estimating templates and lesson learned

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 177: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Costs -Tools and Techniques

Expert Judgment guided by historical information, provides valuable insight about the environment and information from prior similar projects. Expert judgment can also be used to determine whether to combine methods of estimating and how to reconcile differences between them.

Analogous Estimating relies on historical information (Previous projects executed by the organization) to predict the cost of current project. This is a top-down approach is good for fast estimates to get a general idea of what the project may cost. The accuracy depends upon how similar the two projects actually are.

Parametric estimating uses a mathematical model based on known parameters to predict the cost of a Project. A parameter can be cost per unit, cost per cubic yard etc. Two Parametric estimating techniques are Regression Analysis and Leaning curve.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 178: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Costs -Tools and Techniques

Bottom-up estimating produces a separate estimate for each scheduled activity. The detailed cost is then summarized or “rolled up” to higher levels for subsequent reporting and tracking purposes. The cost and accuracy of bottom-up cost estimating is typically influenced by the size and complexity of the individual activity or work package.

Three-point estimates concept originated with the program evaluation and review technique (PERT). PERT uses three estimates to define an approximate range for an activity’s cost: Triangular Distribution Estimated Cost = Optimistic + Most Likely + Pessimistic)/ 3 Beta Distribution

ESTIMATED COST = (Optimistic + 4*(Most Likely) + Pessimistic) / 6

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 179: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Estimate Costs -Tools and Techniques

Reserve Analysis adds reserve amount (Contingency) to the cost. This is done to take care of uncertainties in the project.

Cost of Quality includes assumptions related to Cost of Quality

Project management software is helpful in performing calculations, Organizing and storing large amount of information needed for preparing cost estimates and for reporting purpose

Vendor bid analysis may include analysis of what the project should cost, based on the responsive bids from qualified vendors. Group Decision Making Techniques Team – based approaches , such as brainstorming, the Delphi or nominal group techniques, are used for engaging team members to improve estimate accuracy and commitment to the emerging estimates.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 180: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions Estimate Costs - Outputs

Activity Cost estimates details how much it would cost to complete each schedule activity on the project

Basis of estimates include supporting documentation of the cost estimates and it may include documentation of the basis of estimates , documentation of all assumptions made , documentation of any known constraint , indication of the range of possible estimates and indication of the confidence level of the final estimates

Project document updates include project risk register and cost management plan

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 181: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revise Tools to Estimate Cost

Exercise : Estimate Cost

1. You figure out a best case scenario and , a likely scenario and a worst

case scenario. Then you use a formula to come up with an expected cost

for the project. The tool used by you is ________

2. John creates a document with all the historical information from similar

project he had done in past and also takes input from a contractor who

provides his input. The tool used by John is_________

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 182: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revise Tools to Estimate Cost

Answers to Exercise : Estimate Cost

1. You figure figures out a best case scenario and , a likely scenario and a

worst case scenario. Then you use a formula to come up with an

expected cost for the project. The tool used by you is Three-point

estimate

2. John creates a document with all the historical information from similar

project he had done in past and also takes input from a contractor who

provides his input. The tool used by John is Expert Judgment

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 183: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Determine Budget

Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. This baseline includes all authorized budgets, but excludes management reserves.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 184: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Determine Budget

Inputs Tools and Techniques Outputs

Cost management plan

Activity cost estimates

Basis of estimate

Scope baseline

Project Schedule

Resource Calendars

Risk register

Agreements

Organizational Process Assets

Cost Aggregation

Reserve Analysis

Expert Judgment

Historical relationship

Funding limit reconciliation

Cost baseline

Project funding requirements

Project document updates

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 185: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Cost Management Plan - describes how the project costs will be managed and controlled

Scope baseline refers to collection of approved project scope statement and its associated WBS and WBS dictionary.

Activity cost estimates of a work package is a summation of the activity cost estimates of activities under the work package

Basis of estimate includes supporting detail for cost estimates contained in the basis for estimates should specify any basic assumptions

Project Schedule helps in mapping the cost back to time for planning purpose

Determine Budget - Inputs

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 186: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Resource Calendars along with Project schedule will help plan for when the costs will be incurred

Agreements Applicable agreement information and costs relating to products, services or results that have been or will be purchased are included when determining the budget.

Organizational Process Assets include cost budgeting policies procedures , guidelines and reporting method

Determine Budget - Inputs

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 187: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Determine Budget – Tools and Techniques

Cost Aggregation involves aggregating the costs of individual activities to work packages that are further aggregated to higher levels of WBS and finally into the project cost

Reserve Analysis include contingency reserve and management reserves for the project. Contingency reserves are allowances for response plan strategized for the identified risks. These are also known as “known unknowns” . Management reserves are allowance for unplanned changes to thee project scope and cost. The are also known as “unknown unknowns”. Reserves are not the part of the project cost baseline.

Expert Judgment can be taken from experienced consultant in the project application area. This can be from an internal organizational resource or external sources

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 188: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Determine Budget – Tools and Techniques

Historical relationship result in parametric estimates or analogous estimates that

involve parameter to develop mathematical models to predict total project costs.

Funding limit reconciliation refers to reconciliation of planned spending with the

funding limit

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 189: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Determine Budget – Outputs

Cost performance baseline is an authorized time-phased budget at completion (BAC) used to measure, monitor, and control overall cost performance on the project. It is developed as a summation of the approved budgets by time period and is typically displayed in the form of an S-curve, as is illustrated in Figure below (Reference PMBOK 4th edition). In the earned value management technique the cost performance baseline is referred to as the performance measurement baseline (PMB).

Reference PMBOK 5th Edition

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 190: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Determine Budget – Outputs

Project funding requirements are derived from cost baselines. Total funding requirement is sum of cost baseline and management reserve.

Project document updates include updates to risk register, cost estimates and project schedule

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 191: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Budget Components

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 192: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revise Tools to Determine Budget

Exercise 2: Determine Budget

Monika reads a newspaper article that says there has been sharp increase in steel

cost recently. She knows this was not in her contractor’s original plan and decides to

put a few hundred dollars aside to deal with the price hike if it should happen. The

tool used by Monika is

• Parametric estimating

• Reserve analysis

• Cost aggregation

• Fund Limit Reconciliation

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 193: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revise Tools to Determine Budget

Answers to Exercise 2: Determine Budget

Monika reads a newspaper article that says there has been sharp increase in steel

cost recently. She knows this was not in her contractor’s original plan and decides to

put a few hundred dollars aside to deal with the price hike if it should happen. The

tool used by Monika is

• Parametric estimating

• Reserve analysis

• Cost aggregation

• Fund Limit Reconciliation

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 194: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Costs

Control Costs is the process of monitoring the status of the project

to update the project budget and managing changes to the cost

baseline.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 195: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Costs

Inputs Tools and Techniques Outputs

Project management plan

Project Funding Requirements

Work Performance data

Organizational Process Assets

□ Earned value management

□ Forecasting

□ To-complete performance index TCPI

□ Performance reviews

□ Project management software

□ Reserve analysis

Work performance Information

Cost forecasts

Change Requests

Project management plan updates

Project document updates

Organizational Process assets updates

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 196: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Management Plan contains Cost management plan and Cost performance

Baseline, these are helpful in controlling the cost.

Project Funding Requirements As explained earlier include projected expenditures plus anticipated liabilities

Work Performance Data provides information on the status and cost of project activities and ensures that the project goals and objectives are met as per the project management plan

Organizational Process Assets that can influence this process include cost

budgeting policies, procedures, guidelines , cost budgeting tools and reporting

methods

Control Costs - Inputs

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 197: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Costs – Tools and Techniques

Earned value management is used to measure the performance of the project, It integrates project scope, cost, and schedule measures to help the project management team assess and measure project performance and progress. The EVM technique involves evaluating the planned value , Earned Value and the Actual cost for each schedule activity , work package or control account. 1. Planned Value (PV) is the authorized budget assigned to the scheduled work to be

accomplished for a schedule activity or work breakdown structure component. It is also known as Budgeted Cost of Work Scheduled (BCWS)

2. Earned Value (EV) is the value of work performed expressed in terms of the approved budget assigned to that work for a schedule activity or a WBS component. It is also known as Budgeted cost of Work Performed (BCWP)

3. Actual Cost (AC) is the total cost actually incurred and recorded in accomplishing work performed for an activity or work breakdown structure component.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 198: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Costs – Tools and Techniques

Variance Analysis helps in analyzing the performance of the project vis-à-vis cost

and schedule baselines

Schedule Variance (SV) is a measure of schedule performance on a project. It is equal to the earned value (EV) minus the planned value (PV). SV= EV-PV. Cost variance (CV) is a measure of cost performance on a project. It is equal to the earned value (EV) minus the actual costs (AC). CV = EV-AC Schedule performance Index (SPI) in addition to project status is used to predict the completion date. SPI = EV/PV Cost Performance Index (CPI) measures the cost efficiency for the work completed, it is the ration of EV to AC. CPI = EV/AC.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 199: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Costs – Tools and Techniques

Forecasting Techniques are used to calculate Estimate at completion (EAC) and

Estimate to complete (ETC).

EAC = AC + ETC

EAC forecast for ETC work performed at the budgeted rate

EAC = AC + BAC – EV

EAC forecast for ETC work performed at the present CPI

EAC = BAC / cumulative CPI

EAC forecast for ETC work considering both SPI and CPI factors.

AC + [(BAC – EV) / (cumulative CPI x cumulative SPI)].

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 200: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Costs – Tools and Techniques

To-complete performance index (TCPI) is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal, such as the BAC or the EAC.

TCPI based on the BAC: Work Remaining (BAC – EV) / Fund Remaining (BAC – AC).

TCPI based on EAC : (BAC-EV)/(EAC-AC)

Performance reviews involves following three types of analysis

1. Variance Analysis compares actual project performance to planned or expected

performance. Cost and schedule variances are the most frequently analyzed.

2. Trend Analysis examines project performance over time to determine if performance is improving or deteriorating.

3. Earned value management compares the baseline plan to actual schedule and cost performance.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 201: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Costs – Tools and Techniques

Project management software is often used to monitor the three EVM dimensions (PV, EV, and AC), to display graphical trends, and to forecast a range of possible final project results. Reserve Analysis – During cost control, reserve analysis is used to monitor the status of contingency and management reserves for the project to determine if these reserves are still needed or if additional reserves need to be requested.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 202: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Costs – Outputs

Work Performance Information includes the calculated CV, SV, CPI, and SPI

values for WBS components, in particular the work packages.

Cost Forecasts includes a calculated EAC value or a bottom-up EAC value.

Organizational Process Assets Updates include Causes of variances, Corrective

action chosen and the reasons, and Other types of lessons learned from project cost

control.

Change Requests include change request to the cost performance baseline

or other components of the project management plan. Change requests can include

preventive or corrective actions and are processed for review and disposition through

the Perform Integrated Change Control process

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 203: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Costs – Outputs

Project Management Plan Updates Elements of the project management plan that

may be updated include Cost performance baseline, Cost management plan.

Project Documents Updates include updates to cost estimates, basis of

Estimates

Organizational Process Assets Updates

Organizational Process Assets that may be updated include, but are not limited to :

Cause of variances

Corrective action choosen and the reasons

Financial databases

Other types of lesson learned from project cost control

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 204: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Practice Earned Value Formulae

Exercise 1 : EVM

Your current project is an $800,000 software development effort, with

two teams of programmers that will work for six months, at a total of

10,000 hours. According to the project schedule your team should be

done with 38% of the work. You find that the project is currently 40%

complete. You have spent 50% of the budget so far. Calculate the

following

1. BAC

2. EV, PV

3. SV, CV

4. SPI, CPI

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 205: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Practice Earned Value Formulae

Answer to Exercise - 1 : EVM

1. BAC = $ 800,000, AC = $ 400,000

2. PV = $ 80,000 * 38 / 100 = $ 304,000

EV = $ 80,000 * 40 / 100 = $ 320,000

3. SV = EV – PV = $ 16,000

CV = EV – AC = - $ 80,000

4. SPI = EV / PV = 1.05

CPI = EV / AC = 0.8

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 206: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Practice Earned Value Formulae

Exercise – 2 : EVM

You’re managing a highway construction project. Your total budget is $650,000, and there are a total of 7,500 hours of work scheduled on the project. You check with your accounting department, and they tell you that you’ve spent a total of $400,000. According to the schedule, your crew should have worked 4,500 hours, but your foreman says that the crew was allowed to work some overtime, and they’ve actually put in 5,100 hours of work. Based on this Calculate the following Earned Value numbers: PV = EV = CV = BAC = AC = SV = SPI = , CPI =

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 207: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Practice Earned Value Formulae

Answer to Exercise - 2 : EVM

BAC = $ 650,000 AC = $ 400,000 PV = 650,000 x 60% = $390,000 EV = 650,000 x 68% = $ 442,000 CV =442,000 – 400,000 = $42,000 SV = $ 52,000 SPI = 1.13 , CPI = 1.11

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 208: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Practice Earned Value Formulae

Exercise - 3 : EVM

It’s nine months into your project. The total budget for your project is $4,200,000. You’ve spent $1,650,000 so far, and you’ve got a CPI of .875. Use the Earned Value Management formulas from forecasting to figure out where things stand.

Find the following EAC = ETC = VAC =

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 209: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Practice Earned Value Formulae

Answer to Exercise - 3 : EVM

EAC = $ 4,200,000 / 0.875 = $ 4,800,000 ETC = $ 4,800,000 – $ 1,650,000 = $ 3, 150,000 VAC = $ 4,200,000 – $ 4,800,000 = $ 600,000

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 210: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

QUIZ !

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 211: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Risk Management

Author - Pankaj Sharma

Page 212: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

What is Risk?

Project risk is an uncertain event that can have a positive or a negative impact on the result

If a project risk materializes and has a negative impact on the project, it is called “Threat” to the project e.g.

Unproven technology impacting project schedule

Loosing critical resource from project

If an uncertain event has a positive impact on the project, it is called “opportunities”. E.g.

Emergence of new tool to increase productivity

New resource replacing the lost resource is a better one!

Not all risks are bad, however most of them are perceived as “Threat” to success

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 213: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Risk Vs Issue

Risk

Risk is an uncertain event or event that might happen in future

Once risk is identified, its impact should be analyzed and the response plan should be prepared

Examples:

Lack of Business/Application knowledge which may impact the quality of work products

Issue

Issue is an event that has already occurred

Once the impact of Issue is analyzed, the same should be resolved or escalated

Examples:

Client contact is not providing review comments on deliverables in spite of repeated reminders

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 214: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Risks – Key characteristics

Some of the risks are known risks e.g.

Working in a project with competitor (multi-vendor scenario)

Doing a project in a new geography (cultural differences)

Project attracting environmentalists attention

Accident during Travel

To manage “known risks”, risk response plan is prepared

Known risks are predicted / identified based on the past experience of similar projects

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 215: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Risks – Key characteristics

All the risks can not be predicted and such risks are known as “unknown risks”. e.g.

Natural disaster

Unknown risks cannot be managed proactively

Most of the organizations address such risks through “Business continuity” and “Disaster Recovery” plan

What is the difference between “Risk” and “Issue”?

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 216: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Risk Management

Project Risk Management includes the processes of conducting risk management planning, identification, analysis, response planning and monitoring and control on a project. The objectives of Project Risk Management are to increase the probability and impact of positive events, and decrease the probability and impact of negative events in the project.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 217: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Risk Management Processes

Process Process Group

Plan Risks Management, Identify Risks, Perform Qualitative Risk Analysis, Perform Quantitative Risk Analysis , Plan Risk Responses

Planning

Control Risks

Monitoring and Controlling

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 218: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Management

Plan Risk Management is the process of defining how to conduct risk management activities for a project. The Plan Risk Management process should begin as a project is conceived and should be completed early during project planning.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 219: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Management

Inputs Tools and Techniques Outputs

Project management plan

Project charter

Stakeholder register

Enterprise Environmental Factors

Organizational Process Assets

Analytical techniques

Expert Judgment

Meetings

Risk management plan

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 220: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Management - Inputs

Project Management Plan . All approved subsidiary plans and baselines should be taken into consideration in order to make the risk management plan consistent with them. The project management plan provides baseline or current state of risk- affected areas including scope, schedule and cost.

Project Charter can provide various inputs such as high level risks, high – level project descriptions and high – level requirements.

Stakeholder Register , which contains all details related to the project’s stakeholder , provide an overview of their role.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 221: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Management - Inputs

Enterprise Environmental Factors include the company culture and existing systems that are dealt with and used by the project manager to run the project. The other factors that can influence this process are risk attitudes and tolerances that describe the degree of risk that an organization will withstand

Organizational Process Assets that can influence this process include risk categories, common definitions of concepts and terms, risk statement formats, standard templates, roles and responsibilities, authority levels for decision making, lessons learned and stakeholder register

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 222: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Management -Tools and Techniques

Analytical Techniques

Analytical techniques are used to understand and define the overall risk management

context of the project. Risk management context is a combination of stakeholder risk

attitudes and the strategic risk exposure of a given project based on the overall project

Context. Some of the examples of these techniques are , use of strategic risk scoring

Sheets, a stakeholder risk profile analysis may be performed to grade and qualify the

project stakeholder appetite and tolerance.

Expert Judgment

To ensure that a comprehensive risk management plan is developed expert advice

should be taken from groups or individuals with specialized knowledge on the subject

area.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 223: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Management -Tools and Techniques

Meetings helps in development of the risk management plan. The

meeting will consist of the project manager, project team members, selected relevant

Stakeholders, and anyone other than these who will be performing the risk management

Activities

The following decisions can be taken at the meeting

1. Basic plans for conducting the risk management

2. Risk, cost elements and schedule activities are developed for inclusion in the project budget and schedule respectively

3. Risk contingency reserve application approaches may be established or reviewed

4. Risk management responsibilities should be assigned

5. General organizational templates for risk management will be tailored as per the project

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 224: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions Plan Risk Management - Outputs

Risk management plan describes the various risk management processes that will be implemented, monitored and controlled throughout the project lifecycle. It can include the following

1. Methodology – Defines the approaches, tools and the data sources that may be used to perform risk management on the project

2. Roles and Responsibilities – Defines the lead, support and risk management team membership for each type of activity in the risk management plan, assigns people to these roles and clarifies their responsibilities

3. Budgeting - Assigns resources and estimates costs needed for risk management for inclusion in the project cost baseline

4. Timing – Defines when and how often the risk management process will be performed throughout the project life cycle and establishes risk management activities to be included in the project schedule.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 225: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions Plan Risk Management - Outputs

5. Risk Categories provides a structure that ensures a comprehensive process of systematically identifying risks to a consistent level of detail and contributes to the effectiveness and quality of Identify risks process.

An organization can use a previously prepared categorization of typical risk. A risk breakdown structure (RBS) is one approach to providing such a structure, but it can also be addressed by simply listing the various aspects of the project.

The risk categories may be revisited during the Identify risks process. A good practice is to review the risk categories during the Risk Management Planning process prior to their use in Identify risks process. Risk categories based on prior projects may need to be tailored, adjusted or extended to new situations before those categories can be used on the current project.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 226: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Management - Outputs

Source : PMI PMBOK® Fourth Edition

Risk Breakdown Structure (RBS)

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 227: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Management - Outputs

Source : PMI PMBOK® Fourth Edition

6. Definition of Risk Probability and Impact

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 228: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Management - Outputs

7. Definition of Risk Probability and Impact matrix, A grid mapping of probability of happening of risk and the impact if happens, Based on the probability and impact values the risks are rated as High, Moderate and Low. 8. Revised stakeholder’s tolerance, based on the project may be revised in the risk management process. 9. Reporting formats, define how the outcomes of the risk management process will be documented , analyzed and communicated. It describes the content and format of the risk register as well as any other risk report required. 10. Tracking. Tracking documents how risk activities will be recorded for the benefit of the current project and how risk management processes will be audited.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 229: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Sources of Project Risks

Project

Risk

Project Initiation

Com

munic

ation

Hu

man

Reso

urc

e

Procurement

Co

st

Time

Qual

ity

ScopeLifecycle and

Environment Variables

Expectation

Feasibility

Requirement

Standards

Time Objectives

Restraints

Restraints

Cost Objectives

Performance

Services

Materials

Availability

Productivity

Ideas

Directives

Data Accuracy

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 230: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Identify Risks Process

Risk Identification process determines which risks may affect the project and

documenting their characteristics. It is an iterative process as risk can be identified at

any levels in the project. Irrespective of risks having positive or negative

consequences, all risks events and their consequences should be identified.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 231: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Identify Risks

Inputs Tools and Techniques Outputs

Risk management plan

Cost management plan

Schedule management plan

Quality management plan

Human resource management plan

Scope baseline

Activity cost estimates

Activity duration estimates

Stakeholder register

Project documents

Procurement documents

Enterprise environmental factors

Organizational Process Assets

Documentation reviews

Information gathering techniques

Checklist analysis

Assumptions analysis

Diagramming techniques

SWOT analysis

Expert Judgment

Risk Register

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 232: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Risk Management Plan provides inputs regarding the assignment of roles and responsibilities, provision for risk management activities in the budget and schedule, and categories of risk, which are sometimes expressed in a Risk Breakdown Structure.

Cost Management Plan provides processes and controls that can be used to help identify risks across the project

Schedule Management Plan provides insight to project time / schedule objectives and expectations which may be impacted by risks (Known and Unknown)

Quality management plan contains information related to the quality management plan which is an important input to Identify risk process as the project specific approach may generate or alleviate risk by its nature or structure

Identify Risks - Inputs

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 233: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Human Resource Management Plan . The human resource management plan provides guidance on how project human resource should be defined , staffed , and eventually released. It can also contain roles and responsibilities, project organization charts, and the staffing management plan, which forms a key input to identify risk process.

Scope baseline is a component of scope statement which should be evaluated as potential causes of project risk

Activity Cost Estimates provide a quantitative assessment of likely cost to complete schedule activities and ideally are expressed as a range, with the width indicating the degree of risk

Activity duration estimates are useful in identifying risks related to the time allowances for activities or project as a whole, with the width of the ranges of these estimates indicating the relative degree of risk.

Stakeholder register contains information on stakeholders, which will be useful in interviewing the key stakeholders for their inputs to this process

Identify Risks - Inputs

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 234: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Documents that may be useful while identifying risks are assumptions log, work performance reports, network diagrams, baselines and other project information that may be useful in identifying risks.

Procurement Documents , If the project requires external procurement of resources , procurement documents become a key input to the identify Risks process. The complexity and the level of detail of the procurement documents should be consistent with the value of, and risks associated with, planned procurement.

Enterprise Environmental Factors that can influence this process are published information which consists of commercial database, academic studies, published checklists, benchmarking, industry studies and risk attitudes.

Organizational Process Assets that can influence this process are project files, organizational and project process controls, risk statement templates and lessons learned

Identify Risks - Inputs

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 235: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Identify Risks– Tools and Techniques

Documentation reviews includes structured review of the project documentation, which may include project files, project plans, assumptions, historical information, and other information from the project level as well as individual activity level. It is also essential to identify the quantity of plans and the consistency between the plans

Information gathering techniques – There are five key techniques for information gathering

□ Brainstorming session is conducted by a facilitator and a group of Subject Matter Expert (SMEs), who perform brainstorming and arrive at a comprehensive list of project risks. Identified risks are categorized by the type of risks. A risk breakdown structure (RBS) can be used as a framework for risk identification.

□ Delphi Technique is conducted by a facilitator and a group of experts, who are given a questionnaire to fill. The results are collected and summarized and the results are again circulated to get feedback from the experts.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 236: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Identify Risks– Tools and Techniques

Interviewing is one of the main sources of risk gathering techniques where experienced project managers, stakeholders and subject matter experts are interviewed for risk identification.

Root Cause identification involves identifying the causes of risks and improves the understanding of the risk. It sharpens the definition of the risk and allows grouping risks by causes. Effective risk response can be developed if the root cause of the risk is addressed

Checklist Analysis can be based on historical information gathered from previous

similar projects. The lowest level of Risk Breakdown Structure (RBS) can also be used

as a checklist. Checklists can be updated at the end of the project completion to add

new risks, if any. Checklists are not a very much efficient method of identifying risks.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 237: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Identify Risks– Tools and Techniques

Assumption Analysis reviews the validity of assumptions defined in the

project to ensure that risks are not missed due to inaccuracy or

incompleteness of the assumption. Assumptions are tested against their strength. The

consequences that might occur if the assumptions were false are also analyzed. In

such cases the assumptions are considered as risks.

Diagramming Techniques may include Cause and effect diagrams also known

as Ishikawa or fishbone diagrams, System or process flowcharts, and

influence diagrams, which are graphical representation of situations showing

causal influences

SWOT Analysis examines the project from its Strengths, Weaknesses,

Opportunities and Threats to identify the probable risk events.

Expert Judgment involves participation of SMEs based on their previous

experience and area of expertise

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 238: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Identify Risks– Outputs

Risks Register The identified risks are mentioned in the document called a Risk Register, which becomes a component of the project management plan. Following items can be included in the Risk Register

□ List of identified risks – The list can state the EVENT that may occur , the IMPACT and if CAUSE, EVENT may occur , then listing of EFFECT. Root causes of the risk events can also be listed

□ List of potential responses – If identified during the process of risk identification, responses should be documented and it may be a useful input to the plan Risk Responses process

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 239: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Qualitative Risk Analysis

Prioritizing risks for further analysis or action by assessing and combining

their probability of occurrence and impact.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 240: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Qualitative Risk Analysis

Inputs Tools and Techniques Outputs

Risk Management Plan

Scope baselines

Risk Register

Enterprise environmental factors

Organizational Process assets

Risk probability and impact assessment

Probability and impact matrix

Risk data quality assessment

Risk categorization

Risk urgency assessment

Expert judgment

Project document updates

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 241: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Risk Management Plan documents the roles and responsibilities for :

Budgets and schedule activities for risk management

Risk Categories

Definition of probability and impact

The probability and impact matrix

Revised stakeholder’s risk tolerances

These inputs are documented during Perform Qualitative Risk analysis if not defined during the risk management process.

Scope Baseline mentions the project deliverables, assumptions and constraints. Depending on the project type, i.e. whether it is a state-of-the-art project or a common recurring project type, the risks and level of uncertainty can be evaluated. A project which is more complex than the ones the team has handled earlier and where the uncertainty level is high requires more diligence during the process.

Perform Qualitative Risk Analysis - Inputs

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 242: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Risk Register contains all the identified risks, it’s a component of the project management plan

Enterprise Environmental Factors, may provide insight and context to the risk assessment such as :

Industry studies of similar projects by risk specialists and

Risk databases that may be available from industry or proprietary sources

Organizational Process assets that can influence this process are information of similar previous projects, studies of similar projects by risk specialists and risk databases that may be available from industry or proprietary sources.

Perform Qualitative Risk Analysis - Inputs

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 243: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Qualitative Risk Analysis– Tools and Techniques

Risk probability and impact assessment examines the likelihood that each specific risk will occur and evaluates the potential effect of any of the project objectives such as time, cost, scope or quality. It also evaluates the positive opportunities and negative threats. To assess the probability and impact of each risk, a meeting or interview with subject matter experts either internal or external to the organization is conducted where levels are assigned to each risk and also the potential effects of these risks is evaluated in case the risk occurs

Probability and impact matrix assigns ratings to each risk and classifies them for either perform quantitative risk analysis or plan risk responses. Ratings are assigned to risks based on the combination of probability and impact. The risk may guide in providing risk responses as indicated below

□ Risks that have a negative impact on the project objectives if they occur (threats) and that are in the high – risk (black zone of the matrix), may require priority action and aggressive response strategies.

□ Threats in low – risk (medium gray zone) may not require proactive management action beyond being placed on a watch list or adding a contingency reserve.

□ For opportunities, those in the high-risk (black zone) that can be obtained most easily and offer the greatest benefit should, therefore be targeted first

□ Opportunities in the low-risk (Medium gray zone) should be monitored

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 244: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Qualitative Risk Analysis– Tools and Techniques

Probability Impact Matrix

Source : PMI PMBOK® Fourth Edition

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 245: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Qualitative Risk Analysis– Tools and Techniques

Risk data quality assessment involves determining the quality or usefulness of the data collected to evaluate the risk as per the risk management plan. It involves examining degree to which the risk is understood, and the accuracy, quality, reliability and integrity of the data about risk. If data quality is unacceptable, it may be necessary to gather higher-quality data.

Risk categorization – Project risks can be categorized by the source of risk (e.g., using the RBS), areas of the project affected (e.g. ,using the WBS) or other useful category (e.g. , project phase, etc.) to determine areas of the project most exposed to the effects of uncertainty. Grouping risks by common root causes can lead to developing effective risk responses.

Risk urgency assessment determines how soon the potential risks may occur, and it also identifies near- term responses for those risks.

Expert judgment is required to assess the probability and impact of each risk to determine its location in the probability impact matrix

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 246: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Qualitative Risk Analysis – Outputs

Risk Register Updates – Risk register is initiated during identify risk process ,and is updated with information from Perform Qualitative Risk Analysis.

Following are the updates from Perform Quantitative Risk Analysis:

Relative ranking or priority list of the project risks. The probability and impact matrix can be used to classify risks according to their individual significance. The project manager can then use the prioritized list to focus attention on those items of high significance to the project, where responses can lead to better project outcomes. Risk may be listed by priority separately for cost, time, scope and quality as organizations may value one objective over another. A description of the basis for the assessed probability and impact should also be included for the assessed risks.

Risk grouped by categories can reveal common root cause of the risk or project areas requiring particular attention.

Cause of risk or project areas requiring particular attention. Discovering concentrations of risk may improve the effectiveness of risk.

List of risks requiring response in the near-term. Those risks that require an urgent response and those that can be handled at a later date may be put into different groups.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 247: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Qualitative Risk Analysis – Outputs

List of risks for additional analysis and response. Some risks might warrant more analysis , including perform qualitative risk analysis as well as response action

Watch-lists of low priority risks. Risks that are not assessed as important in the Qualitative Risk Analysis process can be placed on a watch-list for continued monitoring

Trends in qualitative risk analysis results. As the analysis is repeated , a trend for particular risks may become apparent and can make risk response or further analysis more or less urgent/important

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 248: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quantitative Risk Analysis Process

Numerically analyzing the effect of identified risks on overall

project objectives.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 249: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quantitative Risk Analysis Process

Inputs Tools and Techniques Outputs

Risk management plan

Cost management plan

Schedule management plan

Risk register

Enterprise environmental Factors

Organizational process assets

Data gathering and representation techniques

Quantitative risk analysis and modeling techniques

Expert Judgment

Project document updates

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 250: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quantitative Risk Analysis -Inputs

Risk management plan provides guidelines , methods and tools to be used in quantitative risk analysis.

Cost management plan contains baseline data related to cost, this may help to determine the approach for Quantitative analysis for the project.

Schedule management plan contains baseline data related to schedule, this may help to determine the approach for Quantitative analysis for the project.

Risk register is used as a reference point for performing quantitative risk analysis

Organizational process assets that can influence this process are information of previous projects, studies of similar projects by risk specialists and risk databases that may be available from industry or proprietary sources.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 251: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quantitative Risk Analysis -Inputs

Enterprise Environmental Factors may provide insight and context to the risk analysis, such as :

Industry studies of similar projects by risk specialists, and

Risk databases that may be available from industry or proprietary sources.

Organizational process assets that can influence this process are information of previous projects, studies of similar projects by risk specialists and risk databases that may be available from industry or proprietary sources.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 252: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quantitative Risk Analysis - Tools and Techniques

Data gathering and representation techniques

Interviewing : Experienced project managers , stakeholders and subject matter experts are interviewed to quantify the probability and impact of risks on project objective. During interviewing different kind of probability distribution are used. In case a triangular one is used then the three values for 3 point estimates are taken as input from the SMEs which is used to quantify risk for each element.

Probability distributions : are basically of two types – Asymmetrical distribution or Uniform distributions

Asymmetrical distribution depicts shape which are compatible with the data typically developed during project risk analysis. Asymmetrical distributions are of two types- Continuous probability distributions represent the uncertainty in values, such as durations of schedule activities and costs of project components, whereas Discrete probability distributions can be used to represent uncertain events, such as the outcome of a test or a possible scenario in the decision tree.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 253: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quantitative Risk Analysis -Outputs

Uniform distributions can be used if there is no obvious value that is more likely than any other between specified high and low bounds

Quantitative risk analysis and modeling techniques

Commonly used techniques in Quantitative Risk Analysis and Modeling techniques include:

Sensitivity analysis. This aid in determining which risks have the most potential impact on the project. It examines the extent to which the uncertainty of each project element affects the objective being examined when all other uncertain elements are held at their baseline values. Sensitivity analysis can be done by using the Tornado diagram.

Expected monetary value (EMV) analysis is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen (i.e. analysis under uncertainty). The EMV of opportunities will generally be expressed as positive values while those of risks will be negative. EMV is calculated by multiplying the value of each possible outcome by its probability of occurrence and adding them together.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 254: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quantitative Risk Analysis - Tools and Techniques

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 255: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quantitative Risk Analysis - Tools and Techniques

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 256: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quantitative Risk Analysis

Source: A Guide to the Project Management Body of Knowledge, Fourth Edition

(PMBOK® Guide) ©2008 Project Management Institute, Inc., All Rights Reserved.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 257: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quantitative Risk Analysis –Tools and Techniques

Modeling and simulation. A project simulation uses a model that translates the uncertainties or potential risks specified at a detailed level of the project into their potential impact on project objectives.

Simulation techniques compute the project model using the inputs such as cost or schedule to determine the probability distribution. Simulation techniques should be the preferred one for predicting schedule or cost risks as compared to other techniques

Simulations are typically performed using the Monte Carlo technique. In a simulation, the project model is computed many times (iterated) with the input values randomized from a probability distribution function (e.g. cost of project elements or duration of schedule activities) chosen for each iteration from the probability distribution of each variable. A probability distribution is then calculated.

Expert Judgment – Subject matter experts internal or external to the organization such as Engineering or statistical experts are required to identify potential cost and schedule impacts , to evaluate probability and to define inputs to tools

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 258: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quantitative Risk Analysis – Outputs

Risk Register Updates – The register initiated in the Identify Risks process and is updated in

Perform Qualitative Risk Analysis process. The risk register is a component of the

project management plan. Updates include the following components :

Probabilistic analysis of the project. Estimates are made of potential project schedule and cost outcomes, listing the possible completion dates and costs with their associated confidence levels. This output typically expressed as a cumulative distribution is used with stakeholder risk tolerances to permit qualification of the cost and time contingency reserves

Probability of achieving cost and time objectives. With the project facing the risks, the probability of achieving project objectives under the current plan can be estimated using quantitative risk analysis results

Prioritized list of quantified risks. This list of risks includes those that pose the greatest threat or present the greatest opportunity to the project. These include the risks that require the greatest cost contingency and those that are most likely to influence the critical path.

Trends in quantitative risk analysis results. As the analysis is repeated a trend may become apparent that leads to conclusions affecting risk responses

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 259: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Responses

Developing options and actions to enhance opportunities and

reduce threats to project objectives

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 260: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Inputs Tools and Techniques Outputs

Risk management plan

Risk register

Strategies for negative risks or threats

Strategies for positive risks or opportunities

Contingent response strategy

Expert Judgment

Project management plan updates

Project document updates

Plan Risk Responses

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 261: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Responses - Inputs

Risk management plan include roles and responsibilities, risk analysis definitions, risk thresholds for low, moderate and high risks and the time and budget required to conduct the project Risk Management Processes. Some components of the Risk Management Plan that are important inputs to Plan Risk Responses may include risk thresholds for low, moderate and high risks to help understand those risks for which responses are needed, assignment of personnel and scheduling and budgeting for risk response planning.

Risk register provides important inputs related to this process and this include the relative rating or priority list of project risks, a list of risk for additional analysis and response, trends in qualitative risk analysis results, root causes, risk grouped by categories and a watch list of low priority risks.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 262: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Responses – Tools and Techniques

Strategies for negative risks or threats

Avoid. Risk avoidance involves changing the project management plan to eliminate the threat posed by an adverse risk, to isolate the project objectives from the risk’s impact or to relax the objective that is in jeopardy, such as extending the schedule or reducing scope. Some risks that arise early in the project can be avoided by clarifying requirements, obtaining information, improving communication or acquiring expertise.

Transfer. Risk transference requires shifting the negative impact of a threat, along with ownership of the response to a third party. Transferring the risk simply gives another party responsibility for its management, it doesn’t eliminate it. Risk transference nearly always involves payment of a risk premium to the party taking on the risk. Transference tools can be quite diverse and can include but are not limited to the use of insurance, performance, bonds, warranties, guarantees etc.

Mitigate. Risk Mitigation implies a reduction in the probability and impact of an adverse risk event to an acceptable threshold. E.g. Conducting more tests, a more stable supplier etc

Accept. This includes passive or active acceptance. Passive acceptance requires no action , the most common active acceptance strategy is to establish a contingency reserves, including amounts of money or resources to handle known or unknown threats/ opportunities

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 263: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Responses – Tools and Techniques

Strategies for positive risks or opportunities

Exploit .This strategy may be selected for risks with positive impacts where the organization wishes to ensure that the opportunity is realized. This strategy seeks to eliminate the uncertainty associated with a particular upside risk by making the opportunity definitely happen. Directly exploiting responses include assigning more talented resources to the project to reduce time to completion or to provide better quality than originally planned.

Share. Sharing a positive risk involves allocating ownership to a third party who is best able to capture the opportunity for the benefit of the project. E.g. forming risk-sharing partnerships, teams, special-purpose companies or joint ventures, which can be established with the express purpose of managing opportunities.

Enhance . This strategy modifies the size of an opportunity by increasing probability and /or positive impacts and by identifying and maximizing key drivers of these positive-impact risks. Seeking to facilitate or strengthen the cause of the opportunity and proactively targeting and reinforcing its trigger conditions, might increase the probability

Accept. Accepting an opportunity is being willing to take advantage of it if it comes along, but not actively pursuing it.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 264: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Responses – Tools and Techniques

Contingent response strategy. Some responses are designed for use only if certain events occur. For some risks, it is appropriate for the project team to make a response plan that will only be executed under certain predefined conditions, if it is believed that there will be sufficient warning to implement the plan. Events that trigger the contingency response such as missing intermediate milestones or gaining higher priority with a supplier, should be defined and tracked

Expert Judgment. Expertise may be provided by any group or person with specialized education, knowledge, skill, experience or training in establishing risk responses.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 265: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Responses – Outputs

Project Management Plan Updates- Elements of the project management plan that may be updated include

Schedule management plan

Cost management plan

Quality management plan

Procurement management plan

Human resource management plan

Scope baseline

Schedule baseline

Cost baseline.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 266: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Responses – Outputs

Project Document Updates. This include components of the Risk register such as

Identified risks their descriptions, areas of the project (e.g. WBS element) affected, their causes (e.g. RBS element) and how they may affect project objectives

Risk owners and their assigned responsibilities

Output from the Perform Qualitative and Perform Quantitative Risk Analysis processes, including prioritized lists of project risks and probabilistic analysis of the project

Agreed – upon response strategies

Specific actions to implement the chosen response strategy

Symptoms and warning signs of risks’ occurrence

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 267: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Risk Responses – Outputs

Budget and schedule activities required to implement the chosen responses

Contingency reserves of time and cost designed to provide for stakeholders risk tolerance.

Contingency plans and trigger that call for their execution

Fallback plans for use as a reaction to a risk that has occurred and the primary response proves to be inadequate

Residual Risks that are expected to remain after planned response have been taken as well as those that have been deliberately accepted

Secondary risks that arise as a direct outcome of implementing a risk response

Contingency reserves that are calculated based on the quantitative analysis of the project and the organization’s risk thresholds.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 268: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Risks

Implementing risk response plans, tracking identified risks, monitoring

residual risks, identifying new risks, and evaluating risk process

effectiveness throughout the project.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 269: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Inputs Tools and Techniques Outputs

Project management plan

Risk register

Work performance data

Work performance reports

Risk reassessment

Risks audits

Variance and trend analysis

Technical performance measurement

Reserve analysis

Status meetings

Work Performance Information

Change requests

Project management plan updates

Project document updates

Organizational process assets updates

Control Risks

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 270: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Risks- Inputs

Project management plan consists of the risk management plan which includes the assignment of people, time, and resources to the project risk management process.

Risk register which is a subset of the project management plan, includes a list of identified risks agreed upon risk responses, specific implementation actions, symptoms and warning signs of risk, residual and secondary risks, watch-list of low priority risks and cost contingency reserves.

Work Performance Data includes information such as project deliverables status , schedule progress and incurred costs.

Work Performance reports gather and summarize the information required by the stakeholders. This information is an analysis of the work performed during the execution process vis-à-vis project baseline and is relevant to the risk management process.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 271: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Risks- Tools and Techniques

Risk reassessment indicates reassessing the identified risks and identification of new risks as defined in the risk management plan. Project risk reassessment should be performed regularly and it can be included as an agenda item at the project status meetings.

Risks audits are scheduled audits that document the effectiveness of risk responses with respect to their dealing with identified risks and their associated root causes. This aids in determining the effectiveness of the risk management process.

Variance and trend analysis Performance data provides the data for variance and trend analysis. Using this data and applying the earned value analysis and similar methods of project variance and trend analysis; it is possible to monitor the overall project performance.

Technical performance measurement. This involves identifying the variance in the technical performance from the planned technical schedule. Any variance from the defined milestone(s) can aid the project team to forecast the degree of success in achieving the project’s scope.

Reserve analysis. During the planning phase, contingency reserves are defines as a part of risk response plan. During execution some of the reserves get exhausted. This tool determines if the remaining reserves are sufficient to tackle the remaining risks.

Meetings. Status review meetings help in monitoring the risks

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 272: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Risks- Outputs

Work Performance Information , as a Control Risks output , provides a mechanism to communicate and support decision making.

Change requests - During this process, there may be requested change due to implementation of the contingency plans or workarounds. These changes are reviewed and approved through the integrated change control process.

Project management plan updates may arise as a result of the approved change requests

Project document updates- Project documents that may be updated as a result of this process are assumptions log updates and technical documentation updates.

Organizational process assets updates- The risk management processes produce information that should be documented for future reference. The organizational process assets may be updated to include templates for the risk management plan, including the probability and impact matrix and risk register, risk breakdown structure and lessons learned from the project risk management activities.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 273: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

QUIZ !

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 274: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Quality Management

Author - Pankaj Sharma

Page 275: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

What is Quality?

Standard Definition:

Quality is “the degree to which a set of inherent characteristics fulfil requirements” – PMBOK®

Guide (Glossary)

“Conformance of requirements of the customer” – Philip Crosby

“Fitness for use” – Joseph Juran

Author - Pankaj Sharma

Page 276: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Grade is a category or rank given to entities having the same functional use but different technical characteristics. (as per PMBOK® Guide ).

What is Grade?

Author - Pankaj Sharma

Page 277: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Importance of Quality?

Why is quality important?

Quality = Customer Satisfaction = Business growth

Quality = Pride in delivery = Higher Team Morale

Lack of quality = Cost

Lack of quality = Loss of customer confidence

Lack of quality = Loss of Reputation = Difficulty in gaining new business

Lack of quality could lead to loss of life

Author - Pankaj Sharma

Page 278: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Quality is concerned with Prevention over Inspection.

Inspection is typically used to prove that the system works (because you’ve put good quality practices in place), rather than a way to reject the failures.

A good quote to remember is, “Quality should be planned in not inspected in” because the cost of rework can be very high.

Quality Principles

Author - Pankaj Sharma

Page 279: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Quality Management

Processes and activities of the performing organization that determine

quality policies, objectives, and responsibilities so that the project will

satisfy the needs for which it was undertaken

Author - Pankaj Sharma

Page 280: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Quality Management Processes

Process Process Group

Plan Quality Management Planning

Perform Quality Assurance Executing

Control Quality Monitoring and Controlling

Author - Pankaj Sharma

Page 281: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Quality Management

Identifying quality requirements and/or standards for the project and product, and documenting how the project will demonstrate compliance. This process is important to ensure that the resulting product is of acceptable quality. This is performed in parallel with the development of the project management plan and other planning process

Author - Pankaj Sharma

Page 282: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Quality Management

Inputs Tools and Techniques Outputs

□ Project Management Plan □ Stakeholder register □ Risk register □ Requirement documentation □ Enterprise Environmental Factors

Organizational Process Assets

Cost-benefit analysis

Cost of quality (COQ)

Seven basic quality tools

Benchmarking

Design of experiments

Statistical sampling

Additional quality planning tools

Meetings

□ Quality Management Plan

□Process improvement plan

□ Quality Metrics

□ Quality Checklists

□ Project document updates

Author - Pankaj Sharma

Page 283: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Quality Management - Inputs

Project Management Plan – The following contents of the project management plan are useful in creating Quality management plan

Scope baseline include Project scope statement, Work breakdown structure and WBS dictionary.

Schedule baseline contains the accepted schedule performance measures , including start and finish dates

Cost Base line documents the accepted time interval being used to measure cost performance

Other management plans . These plans contribute to the overall project quality and may highlight actionable areas of concern with regard to the project quality

Stakeholder register aids in identifying those stakeholders possessing a particular interest in, or having an impact on quality Risk register will list all the risks that may have impact on the quality

Author - Pankaj Sharma

Page 284: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Quality Management - Inputs

Requirement Documentation .Requirement documentation captures the requirements that the project shall meet pertaining to stakeholder expectations. The component of the requirements document include but is not limited to project and quality requirement Enterprise Environmental Factors that influence the plan quality management process include , Government agency regulation, standard & guidelines and rules specific to the application area, operating conditions that may impact the quality and cultural perception that may influence expectations about quality Organizational Process Assets that influence the Plan Quality Management process include Organizational quality policies, procedures and guidelines. The performing organization’s quality policy, as endorsed by senior management , sets the organization’s intended direction on implementing its quality management approach; Historical databases and lesson learned from previous phases or projects

Author - Pankaj Sharma

Page 285: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Quality -Tools and Techniques

Cost-benefit analysis considers the cost benefit trade offs, the benefit of quality activities must outweigh the costs e.g. higher productivity, less rework and lower cost.

Cost of quality (COQ) considers the expense of all the activities within a project to ensure quality and is the sum of the following

Appraisal Cost includes cost related to Audit, Inspection and Testing

Prevention Cost includes cost related Training, documentation , quality planning and process reviews

Internal Failure Cost includes cost related to rework , scrap etc

External Failure Cost is related to the defects found by the customer. It includes liabilities, Warranty work and lost business

Author - Pankaj Sharma

Page 286: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Quality -Tools and Techniques

Seven Basic Quality Tools – The seven basic QC tools include

Control chart determines whether or not the process is stable or has predictable performance. It illustrates the performance of project over time and is typically used in projects , or operations , where there are repetitive activities (Help desk, manufacturing , a series of testing). Upper (UCL) and lower(LCL) control limits together form the acceptable range of variation in the process. The UCL is typically set at +3 or +6 sigma while the LCL is set at -3 0r -6 sigma. The table below shows the four sigma values representing normal distribution.

Tolerances means the result is acceptable if it falls within the range specified and, Control Limits means that the process is in control if the result falls within the control limits.

Author - Pankaj Sharma

Page 287: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Quality -Tools and Techniques

Source : http://en.wikipedia.org/wiki/Control_chart

0

10

20

30

40

50

60

70

80

90

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31

CL

UCL

LCL

Single Point outside the UCL is an indication of process breakdown

7 points moving in one direction also indicates possible appearance of a special cause that needs investigation

7 points on one side of CL could indicate a change in the actual mean of the process i.e the prediction interval would have changed.

Author - Pankaj Sharma

Page 288: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Quality – Tools and Techniques

Cause and effect diagram (Ishikawa diagram or Fishbone diagram) is a

graphical representation that depicts how different factors relate together and how

these relations may contribute to inadequate quality.

Author - Pankaj Sharma

Page 289: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Quality – Tools and Techniques

Flowcharting depicts the sequence of operation, inspection ,decisions etc in a

system. This help in analyzing where quality problem may happen

Author - Pankaj Sharma

Page 290: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Quality – Tools and Techniques

Histogram is a statistical tool used in the analysis and determination of possible solutions to quality control problem. It depicts how often the problem happens or its frequency

Author - Pankaj Sharma

Page 291: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Quality – Tools and Techniques

Pareto Chart A Pareto chart is a specific c type of histogram, ordered by frequency of occurrence. It shows how many defects were generated by type or category of identified cause . Rank ordering is used to focus corrective action. The project team should address the causes creating the greatest number of defects first.

Author - Pankaj Sharma

Page 292: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Quality – Tools and Techniques

Check sheets, which are also known as tally sheets and may be used as a checklist

when gathering data. Check sheets are used to organize facts in a manner that will

facilitate the effective collection of useful data about a potential quality problem.

Author - Pankaj Sharma

Page 293: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Benchmarking is a technique where project’s quality standards are compared to best

practices of other projects . Based on the difference corrective actions are made to

the current project

Design of experiments approach relies on statistical what-if scenarios to determine

what variables within project will result in the best outcome

Statistical sampling is used to test a random sample instead of testing the entire

population. Attribute Sampling is the results conforms, or it does not where as,

Variable Sampling is when the result is rated on a continuous scale that measures

the degree of conformity.

Flowcharting depicts the relationship between the process steps graphically. It can

be used to predict where quality problems may happen

Proprietary quality management methodologies includes methodologies such

as Six Sigma, QFD, CMMI etc

Additional planning tool includes brainstorming, affinity diagrams and nominal

group techniques

Plan Quality - Tools and Techniques

Author - Pankaj Sharma

Page 294: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions Plan Quality - Outputs

Quality Management Plan defines how the project team will implement the organization’s quality policy

Process improvement plan explains how quality activities will be streamlined and improved. The areas to consider include process boundaries, process configuration, process metrics and targets for improved performance

Quality Metrics define how the quality will be measured. Quality metrics is also called as operational definitions

Quality Checklists ensures that a set of required steps have been performed and they were performed in the proper sequence

Project document updates that may be updated as plan quality is performed are Stakeholder register and responsibility assignment matrix.

Author - Pankaj Sharma

Page 295: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quality Assurance

Auditing quality requirements and the results from quality control measurements to ensure appropriate quality standards and operational definitions are used. This is performed as an ongoing activity in the project life cycle

Author - Pankaj Sharma

Page 296: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quality Assurance

Inputs Tools and Techniques Outputs

Quality management Plan

Process improvement plan

Quality Metrics

Quality control measurements

Project documents

Quality management and control tools

Quality Audits

Process Analysis

Change Requests

Project Management Plan Updates

Project Document Updates

Organizational Process Asset Updates

Author - Pankaj Sharma

Page 297: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quality Assurance - Inputs

Quality Management Plan describes the quality assurance and continuous process improvement approaches for the project.

Process Improvement Plan The project’s quality assurance activities should be supportive of and consistent with the performing organization’s process improvement plan.

Quality Metrics provide an objective means of measurement

Quality control measurements are used to analyze and evaluate the quality standards and processes of the performing organization

Project documents may influence quality assurance work and should be monitored within the context of a system for configuration management.

Author - Pankaj Sharma

Page 298: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quality Assurance– Tools and Techniques

Quality Management and Control Tools

The perform Quality Assurance uses the tools and techniques of the Plan Quality Management and Control quality process. In addition, other tools that are available include

Affinity Diagram. Similar to mind-mapping techniques in that they are used to generate ideas that can be linked to form organized patterns of thought about a problem. The creation of WBS may be enhanced by using the affinity diagram to give structure to the decomposition of scope.

Process decision program charts (PDPC). Used to understand a goal in relation to the steps for getting to the goal. The PDPC is a useful method for contingency planning because it aids teams in anticipating intermediate steps that could derail achievement of the goal.

Interrelationship digraphs. Provide a process for creative problem solving in moderately complex scenarios that posses intertwined logical relationships for up to 50 relevant items.

Author - Pankaj Sharma

Page 299: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quality Assurance– Tools and Techniques

Quality Management – Other tools

Tree Diagrams. Also known as systematic diagrams and may be used to represent decomposition hierarchies such as the WBS, RBS (Risk breakdown structure), and OBS (Organizational breakdown structure ). As the tree diagrams permit the creation of nested branches that terminates into a single decision point , they are useful as decision trees for establishing an expected value for a limited number of dependent relationships that have been diagrammed systematically.

Prioritization matrices. Identify the key issues and the suitable alternatives to be prioritized as a set of decisions for implementation. Criteria are prioritized and weighted before being applied to all available alternatives to obtain a mathematical score that ranks the options.

Author - Pankaj Sharma

Page 300: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quality Assurance– Tools and Techniques

Quality Management – Other tools

Activity networks diagrams . Previously known as arrow diagrams. They include both the AOA (Activity on Arrow) and , most commonly used , AON (Activity on Node) formats of a network diagram.

Matrix diagrams. A quality management and control tool used to perform data analysis within the organizational structure created in matrix. The matrix diagram seeks to show the strength of the relationships between factors , causes , and objectives that exist between the rows and columns that form the matrix.

Author - Pankaj Sharma

Page 301: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quality Assurance– Tools and Techniques

Quality Audits - A quality audit is a structured , independent process to determine if project activities comply with organizational and project policies , processes , and procedures.

Process Analysis - follows the steps outlined in the process improvement plan to identify needed improvements . This analysis also examines problems experienced , constraints experienced , and non – value – added activities identified during process operations. Process analysis includes root cause analysis – a specific technique used to identify a problem , discover the underlying causes that lead to it, and develop preventive actions.

Author - Pankaj Sharma

Page 302: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Perform Quality Assurance – Outputs

Change Requests are the outcome of updating quality standards and processes to improve organization’s effectiveness and efficiency

Project Management Plan Updates includes updates in Quality management plan, Schedule management plan, Cost management plan as a result of Quality assurance activities

Project Document Updates include updates to training plans , process documentation and quality audit report

Organizational Process Asset Updates includes updating quality standards and processes to improve organization's effectiveness and efficiency

Author - Pankaj Sharma

Page 303: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Quality

Monitoring and recording results of executing the quality activities to assess

performance and recommend necessary changes. This process takes place throughout

the project lifecycle , involves inspection , measurement and testing of deliverables

and their comparison with the baseline

Author - Pankaj Sharma

Page 304: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Quality

Inputs Tools and Techniques Outputs

Project management plan

Quality Metrics

Quality Checklists

Work Performance data

Approved change requests

Deliverables

Project documents

Organizational Process Assets

□ Seven basic quality toold

□ Statistical sampling

□ Inspection

□ Approved change requests review

Quality Control measurements

Validated changes

Validated deliverables

Work performance information

Change requests

Project management plan updates

Project document updates

Organization process assets updates

Author - Pankaj Sharma

Page 305: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Quality- Inputs

Project management plan contains the quality management plan, which describes how quality control will be performed within the project

Quality Metrics will be used to measure whether the work result meet quality specification

Quality Checklists will assist in assessing conformance of the deliverables to quality

Work Performance Data evaluate actual progress against the planned progress.

Approved change requests include modification such as defect repairs, revised work methods and revised schedule

Deliverables of the project are primary input to this process

Author - Pankaj Sharma

Page 306: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Quality - Inputs

Project Documents such as Agreements , Quality audit reports and change logs supported with corrective actions plans, Training plans and assessments of effectiveness.

Organizational Process Assets that influence the control quality process include, but are not limited to:

The organization’s quality standard and policies

Standard work guidelines

Issue and defect reporting procedures and communication policies

Author - Pankaj Sharma

Page 307: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Quality – Tools and Techniques

Seven Basic Quality Tools

Statistical sampling is based on selecting and testing a random sample

instead of the entire population.

Inspection is the examination (reviews, peer reviews, audits, or walkthroughs) of a

work product to determine whether it conforms to documented standards.

Approve Change Request Review – All approved change requests should be

reviewed to verify that they were implemented as approved

Author - Pankaj Sharma

Page 308: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Quality – Outputs

Quality control measurements are the documented results of quality control

activities in the format specified during quality planning.

Validated changes involve inspection of any changed or repaired items and they will

be either accepted or rejected before notification of the decision is provided. Rejected

items may require rework.

Verified deliverables - A goal of quality control is to determine the correctness of

deliverables. The results of the execution quality control processes are validated

deliverables.

Work Performance Information – is the performance data collected from various

controlling processes, analyzed in context and integrated based on relationship across

areas

Author - Pankaj Sharma

Page 309: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Quality – Outputs

Change requests as a result of corrective or preventive action. These changes should be initiated in accordance with the Integrated change control Process

Project management plan updates includes update to quality management plan and the process improvement plan

Project documents that may be updated include, but are not limited to, quality standards, Agreements , Quality audit report and change log supported with corrective action plans.

Organization process assets updates includes updates to Completed checklists, lesson learned documentation etc.

Author - Pankaj Sharma

Page 310: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Complete the following

Exercise 4: Quality Management

1. ___________ is more important than inspection in Quality Management

2. When a process has data points above the upper limit or blow the lower

limit , those data points are out of _________

3. ______________ is the process of monitoring and recording results of

executing the quality activities to assess performance and recommend

necessary changes.

Author - Pankaj Sharma

Page 311: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Complete the following

Answers to Exercise 4: Quality Management

1. Prevention is more important than inspection in Quality Management

2. When a process has data points above the upper limit or below the lower

limit , those data points are out of Control

3. Perform Quality Control is the process of monitoring and recording

results of executing the quality activities to assess performance and

recommend necessary changes.

Author - Pankaj Sharma

Page 312: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

QUIZ !

Author - Pankaj Sharma

Page 313: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Communications Management

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 314: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Communications Management

Processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval and ultimate disposition of project information. This knowledge area is made up of five processes to determine what to communicate, to whom, how often, and when to reevaluate the plan An effective project manager spends about 90% of his time communicating and 50% of that time is spent communicating with the project team

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 315: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Sender The person who needs to initiate the communication

Receiver The person who gets the message

Medium The thing used to transmit the message

Feedback A response to a message

Noise Something that interferes with the message

Encode Modify a message so that it can be sent

Decode Modify a message that has been sent so that it can

be understood

Communication Model – Various Elements

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 316: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Communication Model

Exercise 1: Communication Model

1. _____________ is used to transmit the message

2. The person who gets the message is _____________

3. Something that interferes with the message is

_______________

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 317: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Communication Model

Answers to Exercise : Communication Model

1. Medium is used to transmit the message.

2. The person who gets the message is Receiver.

3. Something that interferes with the message is Noise.

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 318: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Formal vs Informal

Verbal vs Non-verbal

Official vs Non-official

Written vs Oral

Vertical vs Horizontal

Kinds of Communication

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 319: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Kinds of Communication

Communication

Type

Example

Formal Written RFP, Project Charter

Informal Written E-mail, Memos

Formal Verbal Speech

Informal Verbal Conversations

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 320: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Nonverbal Communication

Means gestures, facial expressions, and physical appearance while you

are communicating your message

Para lingual Communication

Is the tone and pitch of your voice when you are telling people what’s going

on with your project

Feedback

Is when you respond to communication.

Active listening

When you give feedback to someone who is speaking

Additional Information

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 321: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Kinds of Communication

Exercise 2: Kinds of Communication

1. The Project manager writes a requirement specification for your project. This is an

example of ___________ kind of communication.

A. Informal verbal

B. Informal written

C. Formal verbal

D. Formal written

2. You sent an email to some of your team members to get more information about an

issue that has been identified on your project. This is an example of ___________ kind

of communication

A. Informal verbal

B. Informal written

C. Formal verbal

D. Formal written

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 322: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Kinds of Communication

Answers to Exercise 2: Kinds of Communication

1. The Project manager writes a requirement specification for your project. This is an

example of ___________ kind of communication.

A. Informal verbal

B. Informal written

C. Formal verbal

D. Formal written

2. You sent an email to some of your team members to get more information about an

issue that has been identified on your project. This is an example of ___________ kind

of communication

A. Informal verbal

B. Informal written

C. Formal verbal

D. Formal written

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 323: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Communication Management Processes

Process Process Group

Plan Communications management

Planning

Manage Communications Executing

Control Communications Monitoring and Controlling

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 324: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Communication Management

Determining the project stakeholder information needs and defining a communication approach. It entails: □ How often communication will be distributed and updated □ Mode of communication (email, teleconference etc) □ Information that will be included in the project communications □ Stakeholders that will receive this information

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 325: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Communications Management

Inputs Tools and Techniques Outputs

Project management plan

Stakeholder Register

Enterprise Environmental Factors

Organizational Process Assets

Communications requirements analysis

Communications technology

Communication models

Communication method

Meetings

Communications Management Plan

Project document updates

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 326: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Communications Management - Inputs

Pankaj Sharma, 9810996356

Project Management Plan provides information on how the project will

be executed , monitored , controlled , and closed.

Stakeholder Register provides the information needed to plan the

communication with project stakeholders.

Enterprise Environmental Factors , plan communication management

process is tightly linked with enterprise environmental factors, since the

structure of an organization will have a major effect on the project’s

communication requirements.

Organization Process Assets, Lesson learned and historical information

are of particular importance because they can provide insights on both the

decision taken regarding communication issues and the result of the

decision in previous similar project

Author - Pankaj Sharma

Page 327: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Communications Management - Tools and Techniques

Pankaj Sharma, 9810996356

Communication Requirements Analysis , The analysis of the

communication requirements determine the information needs of

the project stakeholders. The project manager should also consider the

number of potential communication channel or paths as an indicator of the

complexity of a project’s communications. For Example if there are n

people involve in a project communication. The total number of channels

would be n(n-1)/2

4 people – 6 channels 6 people – 15 channels

Author - Pankaj Sharma

Page 328: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Communications Management - Tools and Techniques

Pankaj Sharma, 9810996356

Communication Technology, The method used to transfer information

among project stakeholder may vary significantly. For example, a project

team may use technique from brief conversation to extended meetings, or

from simple written documents to extensive materials which are accessible

online as a method of communication .

Factors that can affect the choice of communication technology include :

Urgency of the need for information

Availability of technology

Ease of use

Project environment

Sensitivity and confidentiality of the information

Author - Pankaj Sharma

Page 329: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Communications Management - Tools and Techniques

Pankaj Sharma, 9810996356

Communication Models, Basic model of communication includes

following parameters

Encode : Thoughts and ideas translated to a language which can be understood by other

Message & Feedback Message : Output of encoding

Medium : The method used to convey the message

Decode : Converting feedback back to understandable form

Author - Pankaj Sharma

Page 330: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Communications Management - Tools and Techniques

Pankaj Sharma, 9810996356

Communication Methods are broadly classified into

Interactive communication

Push Communication

Pull Communication

Meetings , The plan communication process requires discussion and

dialogue with the project team to determine the most appropriate way to

Update and communicate project information and to respond to request

from various stakeholders for that information. These discussions and

dialogue are commonly facilitated through meetings, which may be

conducted face to face or online and in different locations, such as the

project site or customer’s site.

Author - Pankaj Sharma

Page 331: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Communications Management - Outputs

Pankaj Sharma, 9810996356

Communication Management Plan contains the following

information

Stakeholder communication requirements

Information to be communicated including language , format , content and level of detail;

Reason for distribution of that information

Time frame and frequency for the distribution of required information and receipt of acknowledgement or response , if applicable

Person responsible for communicating the information

Person responsible for authorizing release of confidential information

Person or groups who will receive the information

Person or groups who will receive the information

Methods or technologies used to convey the information, such as memos, e-mail, and /or press releases;

Author - Pankaj Sharma

Page 332: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Communications Management - Outputs

Pankaj Sharma, 9810996356

Communication Management Plan contains the following

information

Methods or technologies used to convey the information, such as memos, e-mail, and /or press releases;

Glossary of common terminology

Flow charts of the information flow in the project, workflows with possible sequence of authorization , list of report, and meeting plans etc and

Communication constraints usually derived from a specific legislation or regulation , technology , and organization policies etc

The communications management plan can also include guidelines and

templates for project status meetings , project team meetings , e-

meetings and e-mail messages.

Author - Pankaj Sharma

Page 333: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Communication Plan

Communication Format Frequency Distribution

Team Briefing Restricted Intranet Daily at 9:00 Team and stakeholders

with access to secure

project info area

Weekly Web Bulletin Internal Intranet Weekly Team, sponsor, senior

management

Technical Incident

Report

Email Immediately after Incident Webmaster, IT Department

Budget and Schedule

Detail

Spreadsheets and Detailed

Gantt Chart

Bi-Weekly Sponsor, Senior

Management

Accomplishments and

Setbacks

Email and Intranet Weekly All internal stakeholders

Schedule Milestones Email and Intranet Weekly All internal stakeholders

Cost-to-Date Milestones Email and Intranet Weekly All internal stakeholders

Current Top 5 Risks Email and Intranet Weekly All internal stakeholders

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 334: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Communications

This process updates stakeholders on the progress of the project as per the

communications management plan. The information that gets distributed

includes status reports, review meetings etc

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 335: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Communications

Inputs Tools and Techniques Outputs

Communication management plan

Work performance reports

Enterprise environmental factors

Organizational process assets

□ Communication technology

□ Communication models

□ Communications method

□ Information management system

□ Performance reporting

Project communications

Project management plan updates

Project document updates

Organizational Process assets updates

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 336: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Communications Process

This process tracks how the project is progressing against the plan and provide report to stakeholders on status, progress metrics (Schedule and Cost variance) and forecasts

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 337: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Communications Process

Inputs Tools and Techniques Outputs

Project management plan

Project communications

Issue log

Work performance data

Organizational Process assets

□ Information management system

□ Expert Judgment

□ Meetings

Work performance information

Change requests

Project management plan updates

Project document updates

Organizational Process assets updates

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 338: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Communication Channels

Channels = n(n-1)/2

Where n is the number of people on the project

If there are five people on the project, then we have 10

communication channels.

This is calculated as follows: 5*(5-1) /2 = 10

Project Communication Management

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 339: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Communication Filtering

Ambiguous language

Predefined mindset

Hidden agenda in message content

Senders reputation

Senders status in the organization

Dysfunctional emotional behavior

Environmental Background

When a portion of the message is lost in communication.

Common reasons of filtering:

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 340: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Complete the following

Exercise : Communication Management

1. A contract is always __________ communication

2. A stakeholder with high interest and low power must be kept

_______ of your project’s progress

3. Information should be distributed to all _______

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 341: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Complete the following

Answers to Exercise : Communication Management

1. A contract is always formal communication

2. A stakeholder with high interest and low power must be kept

Informed of your project’s progress

3. Information should be distributed to all stakeholders

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 342: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Practicing the concept

Exercise 4: Number of Lines of Communication

You are managing a project with five team members and one

sponsor. Draw all the channels of communication on this picture.

Solution: Lines of Communication = 6 * (6 – 1)/2 = 15

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 343: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

QUIZ !

Pankaj Sharma, 9810996356

Author - Pankaj Sharma

Page 344: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Human Resource Management

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 345: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Human Resource Management

Processes that organize, manage and lead the project team. Project team is comprised of the

people with assigned roles and responsibilities for completing the project.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 346: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Human Resource Management Processes

Process Process Group

Plan Human Resource Management

Planning

Acquire Project Team Executing

Develop Project Team Executing

Manage Project Team Executing

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 347: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Human Resource Management

Identifying and documenting project roles, responsibilities and required skills,

reporting relationships and creating a staffing management plan.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 348: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Inputs Tools and Techniques Outputs

□ Project Management Plan □ Activity Resource Requirement

Enterprise Environmental Factors

Organizational Process Assets

Organization charts and position descriptions

Networking

Organizational theory

Expert Judgment

Meetings

□ Human Resource Plan

pankaj sharma, 9810996356

Plan Human Resource Management

Author - Pankaj Sharma

Page 349: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Human Resource Management- Inputs

Project Management Plan provides useful information such as , how work will be executed to accomplish the project objectives, A change management plan that documents how changes will be monitored and controlled, how integrity of the project baselines will be maintained . Need and method of communication among stakeholders. Activity Resource Requirements provides information on the preliminary resource requirement of the project. These requirements are progressively elaborated during the Human resource planning phase. Enterprise Environmental Factors that can influence this process include Organization culture and structure , Existing human resources, Personnel administration policies and marketplace condition. Organizational Process Assets that can influence this process include Organizational standard processes and policies and standardized role descriptions, Templates for organizational charts and position descriptions, and Historical information on organizational structures that have worked in previous projects.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 350: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Human Resource Management -Tools and Techniques

The objective of Organization charts and position descriptions is to ensure that each work package has an unambiguous owner and all the team members have clear understanding of their roles and responsibilities. Three formats that are most common for creating this document are hierarchical, matrix, and text-oriented

Fig Reference PMBOK 4th Edition

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 351: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Human Resource Management -Tools and Techniques

Sample RACI Chart

Fig Sample RACI Chart-Reference PMBOK 4th Edition

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 352: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Human Resource Management-Tools and Techniques

Networking is the process of communicating with others (within Organization, industry or professional environment). It includes luncheon meetings, informal conversations including meetings and events, trade conferences, and symposia. Networking within the organization helps project manager in understanding the political and organizational force that will influence the project.

Organizational theory -Different organizational structures have different individual response, individual performance, and personal relationship characteristics. Organizational theory provides information regarding the way in which people, teams, and organizational units behave. This information helps in effective planning and in reducing the amount of time, cost and effort needed to create the plan

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 353: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions Plan Human Resource Management - Outputs

Human Resource Plan has three components roles and responsibility, organization charts and the staffing management plan.

□ Roles and responsibility details role, authority, responsibility and competency for the resource requirement of the project.

□ Project Organization Chart is a graphic display of project team members and their reporting relationships. It can be formal or informal, highly detailed or broadly framed, based on the needs of the project.

□ Staffing Management Plan details how and when the project will be staffed, released, training needs of resources, recognition & rewards, compliance and resource calendar. It also includes policies and procedures that protect team members from safety hazards.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 354: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Acquire Project Team

Confirming human resource availability and obtaining the team necessary to complete project assignments

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 355: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Acquire Project Team

Inputs Tools and Techniques Outputs

Human resource management plan

Enterprise environmental factors

Organizational process assets

Pre-assignment

Negotiation

Acquisition

Virtual Teams

Multi- criteria decision analysis

Project Staff Assignments

Resource Calendars

Project Management Plan Updates

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 356: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Acquire Project Team - Inputs

Human Resource Management Plan provides information on how project human resource should be identified, staffed, managed, controlled and eventually released. It also contains details on skills required , roles and responsibilities for a particular position and the competency level that a project demands.

Enterprise Environmental Factors that can influence this process are existing information for human resources including who are available, competency levels, prior experience personnel administration policies, processes and procedures

Organizational Process Assets that can influence the Acquire Project Team process include, but are not limited to, organization standard policies, processes, and procedures.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 357: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Acquire Project Team– Tools and Techniques

Pre-assignment refers to assigning the project team members in advance, this is needed when specific skilled resources are required or the resources are defined in the project charter

Negotiation with functional managers and other project managers is required if project manager needs specific skills for the project

Acquisition is needed when specific skills are not available in the organization. This can involve hiring individual consultants or subcontracting work to another organization

Virtual teams can be defined as groups of people with a common goal who fulfill their roles with little or no time spent meeting face to face. Communication is important in such teams, the availability of electronic communication such as e-mail, audio conferencing, web-based meetings and video conferencing has made such teams feasible.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 358: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Acquire Project Team– Tools and Techniques

Multi – Criteria Decision Analysis, Selection criteria are often used as a part of acquiring the project team . By use of a multi- criteria decision analysis tool, criteria are developed and used to rate or score potential team members. The criteria are weighted according to the relative importance of the needs within the team. Some examples of selection criteria that can be used to score team members are:

Availability . Identify whether the team member is available to work on the project within time period needed. If there are any concerns for availability during project timeline.

Cost. Verify if the cost of adding the team member is within the prescribed budget.

Experience, Verify that the team member has the relevant experience that will contribute to the project success.

Ability, Verify that the team member has the competencies needed by the project.

Knowledge and Skills. The team member has relevant knowledge of the customer, similar implemented projects, nuances of the project environment and relevant skills to use a project tool.

Attitude that includes his ability to gel with other members of the team.

International factors such as location of the team member, time zone and communication capabilities

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 359: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Acquire Project Team – Outputs

Project Staff Assignments includes assignment of resource to each role defined initially. The documentation of these assignments can include a project team directory, memos to team members, and names inserted into other parts of the project management plan, such as project organization charts and schedules. Resource Calendars documents the time periods that each project team member can work on the project. This should be created keeping in mind each person’s schedule conflicts, involvement in other projects and his/her holiday Project Management Plan Updates Elements of the project management plan that may be updated include, but are not limited to the human resources plan.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 360: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Project Team

Process of improving competencies, team interaction, and the overall team

environment to enhance project performance.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 361: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Project Team

Inputs Tools and Techniques Outputs

Human resource management plan

Project staff assignments

Resource Calendars

□ Interpersonal Skills

□ Trainings

□ Team building activities

□ Ground rules

□ Co-location

□ Recognition and rewards

□ Personnel assessment tools

Team Performance assessments

Enterprise Environmental Factors updates

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 362: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Project Team - Inputs

Human Resource Management Plan provides guidance on how project human resource should be defined , staffed , managed , controlled , and eventually released. It identifies training strategies and plans for developing the project team. Items such as rewards, feedback, additional training and disciplinary actions can be added to the plan as a result of ongoing team performance assessments and other form of project team management.

Project staff Assignments details the assignments or activities to be performed by the Project team

Resource Calendars identify the times when the project team members can participate in team development activities.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 363: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Project Team – Tools and Techniques

Interpersonal Skills also referred to as soft skills are very critical for team development. It include skills such as empathy, influence, creativity, and group facilitation, these are valuable assets when managing the project team.

Trainings help in enhancing the competencies of the project team members. Training can be formal or informal. Training can be formal or informal ; classroom based ,on line, instructor-led or on the job training.

Team building activities are critical to improve interpersonal relationships,

resolving team issues and to keep the team motivated so that team members work

together effectively . They are critical for the team members who operate virtually from remote locations . Project managers should obtain top management support, obtain commitment of team members, introduce appropriate rewards and recognition, create a team identity, manage conflicts effectively, promote trust and open communication among team members, and, above all, provide good team leadership to build effective teams.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 364: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Project Team– Tools and Techniques

Traditionally, a team goes through five stages of development.

Forming: a group of people come together to accomplish a shared purpose.

Storming: Disagreement about mission, vision, and approaches combined with the

fact that team members are getting to know each other can cause strained

relationships and conflict.

Norming: The team has consciously or unconsciously formed working relationships

that are enabling progress on the team’s objectives.

Performing: Relationships, team processes, and the team’s effectiveness in working

on its objectives are synching to bring about a successfully functioning team.

Adjourning : In the adjourning phase, the team completes the work and moves on

from the project.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 365: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Project Team – Tools and Techniques

Histogram is a statistical tool used in the analysis and determination of possible solutions to quality control problem. It depicts how often the problem happens or its frequency Ground Rules define the acceptable behavior by the project team members. This allows team members to discover values that are important to one another Co-Location involves placing many or all of the most active project team members in the same physical location to enhance their ability to perform as a team. E.g. create a war room where all the team members work, or co-locate the project team at the customer’s site. Recognition and Rewards helps in keeping the team motivated and to boost their spirits. People are motivated if they feel they are valued in the organization and this value is demonstrated by the rewards given to them.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 366: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Abraham Maslow’s Hierarchy of Needs (1954)

(In order of priority)

Self Actualization

Esteem

Social

Safety

Physiological Air, water, food, house, clothing

Security, stability, freedom from threat and physical harm

Love, affection, approval, friends, association

Accomplishment, Respect, Attention, Appreciation

Self fulfillment, growth, learning

Recognition and Rewards – Theories of Motivation

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 367: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Recognition and Rewards – Theories of Motivation

The average worker is inherently lazy and needs supervisions

The average worker dislikes work and avoids work whenever possible

To induce adequate effort, the supervisor must threaten punishment and exercise careful supervision

The average worker avoids increased responsibility and seeks to be directed

McGregor’s Theory X

Theory X relies on Strict Rules, Performance incentives, Rewards, Threats to job security

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 368: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Recognition and Rewards – Theories of Motivation

Workers are willing to do the job without continuous supervision

The average worker wants to be active and finds the physical and mental effort on the job satisfying

Greatest results come from willing participation which will tend to produce self-direction towards goals without coercion and

control

The average worker seeks opportunity for personal improvement and self respect

Theory Y relies on worker participation in decisions, cordial manager-worker relationships, worker designed job methodology, worker individualism

McGregor’s Theory Y

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 369: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Recognition and Rewards – Theories of Motivation

William Ouchi’s Theory Z

According to Theory Z, people who don’t fit either Theory X or Theory Y are really a combination of the two.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 370: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Recognition and Rewards – Theories of Motivation

Herzberg’s Motivation – Hygiene Theory As per this theory presence of hygiene factors doesn’t motivate someone , however their absence de-motivates. Motivation factors will motivate but they will not work without the hygiene factors in place.

I. Motivating factors

I. Achievements

II. Recognitions

III. Work Itself

IV. Responsibility

V. Advancement

VI. Possibility for growth

Hygiene Factors are Company Policy, Paycheck, status, Relationship with co-workers

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 371: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Recognition and Rewards – Theories of Motivation

Expectancy Theorem of Motivation by Victor Vroom

1. You need to give people an expectation of a reward in order to motivate them

2. The rewards or awards should be achievable, if they are impossible to achieve, they will de-motivate them

3. People are motivated by achievements

4. People “expect” to be rewarded for achievements

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 372: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Recognition and Rewards – Theories of Motivation

McLelland’s Achievement Theory

1. People need achievement, power and affiliation to be motivated.

2. Achievement is when someone performs well and is recognized for it

3. Power means he or she has a lot of control or influence in the company

4. Affiliation , a strong sense from being a part of a working team and having good relationships with coworkers

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 373: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Recognition and Rewards – Theories of Motivation

Ouchi’s Theory

1. Formulated from Quality movement and Quality circles

2. Both Management and Workers need to be involved, and they should trust each other

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 374: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Recognition and Rewards – Theories of Motivation

The Oldham-Hackman job characteristics model

I. Skill Variety – the number of job skills that the job holder has the opportunity to exercise

II. Task Identity – the degree to which your work and its result are identifiable as belonging to you

III. Task Significance – the degree to which your job has an influence on others

IV. Autonomy – the discretion you have about the way that you do the job

V. Feedback – the information that you get back about the result of your work

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 375: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Forms of Power

Below are the five Kinds of Power that can help the project managers maximize his ability to influence and manage the team

Formal – positional, granted by organizational/upper mgmt

Expert – power earned through a recognized level of knowledge or skill in a

specific area

Reward – the power to give a positive consequences, like promotions, salary rise

etc.

Penalty – the power to provide negative consequences, like suspension,

termination, reprimands

Referent – power gained when team members admire, and willingly follow an

individual as a role model

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 376: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Forms of Power at Work

Exercise : Forms of Power at Work

1. A functional manager assigns a tester to work on the project manager’s

team. This is an example of _________ power

2. The programmers always listen to the team lead because he’s really a

good software architect. This is an example of _________ power

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 377: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Forms of Power at Work

Answers to Exercise : Forms of Power at Work

1. A functional manager assigns a tester to work on the project manager’s

team. This is an example of Legitimate power

2. The programmers always listen to the team lead because he’s really a

good software architect. This is an example of Expert power

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 378: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Leadership Style

Following are the leadership style that managers can use to interact with organizational

members

Autocratic – traditional figure of a boss who makes binding decisions regardless of what subordinates think or desire

Laissez-Fare – Other extreme of autocratic, the staff can pursue anything they wish, enhances free thinking

Democratic – participative, decisions made jointly by management and staff

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 379: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Develop Project Team– Outputs

Team Performance assessments gives insight to project manager on areas that need improvement.

Enterprise Environmental Factors Updates The Enterprise environmental factors

that may be updated as a result of the Develop Project Team process include, but are

not limited to, personnel administration, including updates for employee training

records and skill assessments.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 380: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Project Team

Tracking team member performance, providing feedback, resolving issues and managing changes to optimize project performance.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 381: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Project Team

Inputs Tools and Techniques Outputs

Human resource management plan

Project staff assignments

Team Performance Assessments

Issue log

Work performance reports

Organizational process assets

□ Observation and Conversation

□ Project performance appraisals

□ Conflict management

□ Interpersonal skills

Change Requests

Project management plan updates

Project document updates

Enterprise Environmental Factors updates

Organizational process assets updates

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 382: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Project Team - Inputs

Human Resource Management Plan contains the human resource plan which includes roles and responsibilities, project organization and staffing management plan

Project staff assignments provide a list of team members assigned to the project that needs to be evaluated under the appraisal process

Team Performance Assessment is done on continuous basis formally or informally by the project management team. This helps in issues and conflict resolution

Issue Log, Issues arise in the course of managing the project team. An issue log can be used t document and monitor who is responsible for resolving specific issues by a target date.

Work Performance Reports provide information on project performance vis-à-vis project management plan. It aids in determining the future resource requirements, recognition and rewards and updates to the staffing management plan.

Organizational process assets that can influence this process include certificates of appreciation, newsletters, website, bonus structure, corporate apparel and organizational perquisites

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 383: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Project Team – Tools and Techniques

Observation and Conversation are used to stay in touch with the team member’s

work and attitudes. The project management team monitors progress toward project

deliverables, accomplishments that are a source of pride for team members, and

interpersonal issues.

Project performance appraisals helps in clarification of roles and responsibilities,

constructive feedback to team members, discovery of unknown or unresolved issues,

development of individual training plans, and the establishment of specific goals for

future time periods.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 384: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Project Team – Tools and Techniques

Interpersonal skills use a combination of technical, human and conceptual

skills to analyze situations and interact appropriately with team members. E.g.

Leadership, Influence and effective decision making

Conflict Management results in greater productivity and positive

working relationships. When managed properly, differences of opinion can lead to

increased creativity and better decision making. Below are the source of conflicts on

the Project

More than 50% conflicts on the projects are due to disagreement over

schedules, priorities and resources)

1. Schedules

2. Project Priorities

3. Human Resources

4. Technical Opinions

5. Procedures

6. Cost

7. Personality

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 385: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Project Team – Tools and Techniques

Conflict Resolution Methods

Confronting/Problem Solving. Treating conflict as a problem to be solved by examining alternatives; requires a give-and-take attitude and open dialogue.

Withdrawing/Avoiding. Retreating from an actual or potential conflict situation.

Smoothing/Accommodating. Emphasizing areas of agreement rather than areas of difference.

Compromising. Searching for solutions that bring some degree of satisfaction to all parties.

Forcing. Pushing one’s viewpoint at the expense of others; offers only win-lose solutions.

Collaborating. Incorporating multiple viewpoints and insights from differing perspectives; leads to consensus and commitment.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 386: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Project Team – Outputs

Change Requests due to change in staffing. The change request should be processed and approved through integrated change control process. Staffing changes may include moving people to different assignments , outsourcing some of the work, and replacing the team member who leave.

Project Management Plan Updates may include changes in the human resource management plan

Project Documents Updates that may be updated include

Issue Log

Role description

Project staff assignment

Enterprise Environmental Factors updates include input to organizational performance appraisals and personnel skill updates

Organizational process assets updates include Historical information and lessons learned documentation Templates, and Organizational standard processes.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 387: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Project Team – Outputs

Enterprise Environmental Factors updates include input to organizational performance appraisals and personnel skill updates

Organizational process assets updates include Historical information and lessons learned documentation Templates, and Organizational standard processes.

Change Requests due to change in staffing. The change request should be processed and approved through integrated change control process

Project management plan updates include updates to staffing management plan

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 388: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Conflict Management

Exercise 2: Resolving Conflict

Figure out the conflict resolution technique that is being used in the cases

below:

1. I don’t really have time to deal with this right now. Just figure it out and

get back to me.

2. Hold on a second. Let’s sit down and figure out what the real problem is.

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 389: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Conflict Management

Exercise 2: Resolving Conflict

Figure out the conflict resolution technique that is being used in the cases

below:

1. I don’t really have time to deal with this right now. Just figure it out and

get back to me - Withdrawal

2. Hold on a second. Let’s sit down and figure out what the real problem is –

Problem Solving / Confronting

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 390: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Halo Effect

Extending the impression of a particular outstanding trait to influence the total

judgment of a person E.g. : Assuming that a person who is good in technology will be

a good project manager

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 391: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Complete the following

Exercise 3: HR Management

1. The main output of the Acquire Project Team process is

___________ assignments

2. The _________ effect causes people with technical expertise

to be put in the position for which they are unqualified

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 392: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Complete the following

Exercise 3: HR Management

1. The main output of the Acquire Project Team process is

Project Resources assignments

2. The Halo effect causes people with technical expertise to be

put in the position for which they are unqualified

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 393: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

QUIZ !

pankaj sharma, 9810996356

Author - Pankaj Sharma

Page 394: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Consulting Solutions

Project Stakeholder Management

Author - Pankaj Sharma

Page 395: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Key Learning Objectives Who are Stakeholder and effective way to manage them

Project Stakeholder Management processes

Identify Stakeholder

Plan Stakeholder Management

Manage Stakeholder Engagement

Control Stakeholder Engagement

Quiz Quarter

Author - Pankaj Sharma

Page 396: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Stakeholder Management includes the processes required to identify people, groups or organizations that could impact or be impacted by the project, to analyze stakeholder expectations and their impact on the project and to develop appropriate management strategies for effectively engaging stakeholder in project decisions and execution.

What is Stakeholder Management?

Author - Pankaj Sharma

Page 397: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Identify Stakeholders

Identify Stakeholders is the process of identifying the people, groups or organizations that could impact or be impacted by decision, activity or outcome of the project analyzing and documenting relevant information regarding their interest , involvement, interdependencies, influence and potential impact on project success.

The key benefit of Identify stakeholder process is that it allows the project manager to identify the appropriate focus for each stakeholder or group of stakeholders

Author - Pankaj Sharma

Page 398: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Identify Stakeholders

Inputs Tools & Techniques Outputs

• Project Charter

• Procurement

documents

• Enterprise

Environmental

Factors

• Organizational

process assets

• Stakeholder

analysis

• Expert judgment

• Meetings

1. Stakeholder

Register

Author - Pankaj Sharma

Page 399: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Identify Stakeholders - Inputs

Project Charter - can provide information about internal and external parties related with the project and affected by the result or the execution of the project, such as project sponsor(s), customers, team members , groups and departments participating in the project, and other people or organizations affected by the project. Procurement Documents – If the project is the result of a procurement activity or is based on an established contract , the parties in that contract are key project stakeholders. Other relevant parties such as suppliers should also be considered as part of the project stakeholder list.

Author - Pankaj Sharma

Page 400: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Identify Stakeholders - Inputs

Enterprise Environmental Factors – relevant to Identify stakeholders are: • Organizational culture and structures • Governmental or industry standards (e.g. Regulations, product standards); and • Global , regional or local trends and practices or habits.

Organizational Process Assets – relevant to Identify stakeholder are : • Stakeholder register templates • Lessons learned from previous projects or phases and • Stakeholder register from previous projects.

Author - Pankaj Sharma

Page 401: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Identify Stakeholders -Tools and Techniques

1. Stakeholder Analysis - Identifies the interests, expectations and influence of the stakeholders and relates them to the purpose of the project.

There are multiple classification models used for stakeholders analysis , such as : • Power /Interest grid, grouping the stakeholders based on their level of authority (“power”) and their level or concern (“interest”) regarding the project outcomes • Power /Influence grid, grouping the stakeholders based on their level of authority (“power”) and their active involvement (“influence”) in the project. • Influence/ Impact grid , grouping the stakeholders based on their active involvement (“ Influence” ) in the project and their ability to effect changes to the project’s planning or execution (“ impact “). • Salience model, describing classes of stakeholders based on their power (ability to impose their will), urgency (need for immediate attention), and legitimacy (their involvement is appropriate).

Author - Pankaj Sharma

Page 402: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Identify Stakeholders -Tools and Techniques

2. Expert Judgement include suggestions and recommendations of Subject Matter Experts such as : • Senior Management • Other units within the organization • Identified key stakeholders • Project managers who have worked on projects in the same area • Subject Matter Experts in the business project area • Industry groups and consultants • Professional and technical associations , regulatory bodies and non governmental organizations (NGOs)

3. Meetings – Project meetings designed to develop an understanding of major project stakeholders and they an be used to exchange and analyze information about roles , interest , knowledge and the overall position of each stakeholder facing the project.

Author - Pankaj Sharma

Page 403: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Power Grid Matrix

Author - Pankaj Sharma

Page 404: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Identify Stakeholders - Output

The main output of Identify Stakeholder process is stakeholder register. It contains following details.

Identification Information : Name, Organizational Position, Location, Role in the project, Contact info Assessment Information: Major Requirement, Main expectation, Potential Influence Stakeholders Category: External/Internal, Supporter, Neutral, Resister

Author - Pankaj Sharma

Page 405: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Stakeholder Management

Plan Stakeholder Management is the process of developing

appropriate management strategies to effectively engage

stakeholders throughout the project life cycle, based on the

analysis of their needs, interests and potential impact on the

project success.

Author - Pankaj Sharma

Page 406: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Stakeholder Management

Inputs Tools & Techniques Outputs

• Project Management

Plan

• Stakeholder Register

• Enterprise

Environmental Factors

• Organizational process

assets

• Expert judgment

• Meetings

• Analytical Techniques

• Stakeholder

Management Plan

• Procurement document

updates

Author - Pankaj Sharma

Page 407: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Stakeholder Management –Inputs

Project Management Plan - The information that is taken from Project Management Plan to create stakeholder plan includes • Life cycle selected for the project and the processes that will be applied to each phase; • Description of how work will be executed to accomplish the project objectives; • Description of how human resources requirements will be met and how roles and responsibilities, reporting relationships, and staffing management will be addressed and structured for the project; • Change management plan that documents how changes will be monitored and controlled • Need and techniques for communicating among stakeholders .

Author - Pankaj Sharma

Page 408: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Stakeholder Management –Inputs

Stakeholder Register – Provides the information needed to plan appropriate ways to engage project stakeholders. Enterprise Environmental Factors - such as organizational culture, structure, and the political climate. These factors help in determining the best options to support a better adaptive process for managing stakeholders Organizational Process Assets – such as lessons learned database and historical information are of particular importance as they provide insight into previous stakeholder management plans and their effectiveness. These can be used to plan the stakeholder management activities for the current project.

Author - Pankaj Sharma

Page 409: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Stakeholder Management – Tools and Techniques

Expert Judgment – Suggestions and guidance should be sought from groups or individuals with specialized training or subject matter expertise or insight into the relationships within the organization, such as • Senior Management • Project Team Members • Other units or individuals within the organization • Identify key stakeholders • Project managers who have worked on the projects in the same area • Industry groups and consultants • Professional and technical associations , regulatory bodies and non governmental organizations.

Author - Pankaj Sharma

Page 410: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Stakeholder Management – Tools and Techniques

Meetings Should be held with experts and the project team to define the required engagement levels of all stakeholders. This information can be used to prepare the stakeholder management plan

Author - Pankaj Sharma

Page 411: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Stakeholder Management – Tools and Techniques

Analytical Techniques includes comparison of the current engagement level of stakeholder to the planned engagement levels required for successful project completion. Stakeholder engagement throughout the lifecycle of the project is critical to project success. The engagement level of the stakeholders can be classified as follows: • Unaware – Unaware of project and potential impacts • Resistant – Aware of project and potential impacts and resistant to change • Neutral – Aware of project yet neither supportive nor resistant • Supportive – Aware of project and potential impacts and supportive to change • Leading – Aware of project and potential impacts and actively engaged in ensuring the project is a success.

Author - Pankaj Sharma

Page 412: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Stakeholders Engagement Assessment Matrix

Author - Pankaj Sharma

Page 413: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Stakeholder Management - Outputs

Stakeholder Management Plan is a component of the project

management plan that explains the management strategies required to effectively

engage stakeholders. In addition to the data gathered in the stakeholder register it

provides.

• Desired and current engagement levels of key stakeholders

• Scope and impact of change to stakeholders

• Identified interrelationships and potential overlap between stakeholders

• Stakeholder communication requirements for the current project phase;

• Information to be distributed to stakeholders, including language, format, content , and level of detail;

• Reason for the distribution of that information and the expected impact to stakeholder engagement;

• Time frame and frequency for the distribution of required information to stakeholders.

• Method for updating and refining the stakeholder management plan as the

project progresses and develops.

Author - Pankaj Sharma

Page 414: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Stakeholder Management - Outputs

Project Document Updates includes project schedules and

stakeholder register

Author - Pankaj Sharma

Page 415: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Stakeholder Engagement

Manage Stakeholder Engagement is the process of communicating and working with stakeholders to meet their need/expectations, address issues as they occur, and foster appropriate stakeholder engagement in project activities throughout the project life cycle.

Author - Pankaj Sharma

Page 416: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Stakeholder Engagement

.

Inputs Tools & Techniques Outputs

• Stakeholder Management

Plan

• Communication

Management Plan

• Change Log

• Organizational process

assets

• Communication Methods

• Interpersonal skills

• Management Skills

• Issue Log

• Change Requests

• Project Management

Plan updates

• Project documents

updates

• Organizational process

assets updates

Author - Pankaj Sharma

Page 417: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Stakeholder Engagement - Inputs

.

Stakeholder Management Plan – This plan explains the management strategies required to effectively engage stakeholders. Communication Management Plan – This plan explains what to be communicated o whom and at what frequency. What to be communicated to external stakeholders or not Change log – Document changes that occur during a project. It is important to communicate . The impact of these changes on cost, time and quality should be communicated to the relevant stakeholders. Organizational Process Assets - The organizational process assets that can influence the Manage Stakeholder Engagement process include Issue management procedures, Change management procedure and Organizations communication requirement.

Author - Pankaj Sharma

Page 418: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Stakeholder Engagement – Tools and Techniques

.

Communication Methods – The methods of communication identified for each stakeholder in the communications management plan are utilized during stakeholder engagement management. Based on the stakeholders’ communication requirements, the project manager decides how, when, and which of these communication methods are to be used in the project

Interpersonal skills - This include conflict management skills, communication

skills, ability to overcome resistance to the change.

Management Skills - The project manager applies management skills such as negotiation, facilitation and ability to influence people to coordinate and harmonize the group toward accomplishing the project objectives

Author - Pankaj Sharma

Page 419: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Stakeholder Engagement – Outputs

.

Issue Log – It is good to maintain an issue log for managing stakeholder issues. This log is updated as new issues are identified and current issues are resolved. Change Requests - Managing stakeholder engagement may result in a change request to the product or the project. It may also include corrective or preventive actions to the project itself or to the interaction with the impacted stakeholders, as Appropriate

Project Management Plan updates - Stakeholder management plan or

communication management plan might be updated when new stakeholder

is identified Project documents updates Organizational process assets

updates

Author - Pankaj Sharma

Page 420: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Manage Stakeholder Engagement – Outputs

.

Project documents updates - Project documents that may be updated include, but are not limited to, the stakeholder register. This is updated as information on stakeholders change, when new stakeholders are identified, or if registered stakeholders are no longer involved in or impacted by the project, or other updates for specific stakeholders are required.

Organizational process assets updates - The organizational process assets that may be updated include, • Project records. Project records include correspondence, memos, meeting minutes, and other documents describing the project. • Lessons learned documentation. Documentation includes the root cause analysis of issues faced, reasoning behind the corrective action chosen, and other types of lessons learned about stakeholder management. Lessons learned are documented and distributed, and become part of the historical database for both the project and the performing organization.

Author - Pankaj Sharma

Page 421: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Stakeholder Engagement

Control Stakeholder Engagement is the process of monitoring overall project stakeholder relationship and adjusting strategies and plans for engaging stakeholders.

Author - Pankaj Sharma

Page 422: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Stakeholder Engagement

Inputs Tools & Techniques Outputs

1. Project Management Plan

2. Issue Log

3. Work Performance Data

4. Project Documents

1. Information Management

Systems

2. Expert Judgment

3. Meetings

1. Work Performance

Information

2. Change Requests

3. Project Management

Plan updates

4. Project documents

updates

5. Organizational process

assets updates

Author - Pankaj Sharma

Page 423: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Inputs - Control Stakeholder Engagement

1. Project Management Plan - The information related to Project Management that will be utilized include

• The lifecycle selected for the project and the processes that will be applied to each phase. • How work will be executed to accomplish the project objectives • How human resources requirements will be met, how roles and responsibilities , reporting

relationships, and staffing management will be addressed and structured for the project; • A change management plan that documents how change will be monitored and controlled • Needs and techniques for communication among stakeholders

2. Issue Log – The issue log is updated as new issues are identified and current issues are resolved

3. Work Performance Data – include reported percentage of work completed , technical performance measures, start and finish dates of schedule activities, number of change requests, number of defects , actual costs, actual durations etc.

4. Project Documents – Multiple project documents originating from initiation , planning, execution , or control processes may be used as supporting inputs for controlling stakeholder engagement. These include

• Project schedule • Stakeholder register • Issue Log • Change Log • Project Communications

Author - Pankaj Sharma

Page 424: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Tools and Techniques - Control Stakeholder Engagement

1. Information Management Systems – An information management system provides a standard tool for the project manager to capture , store, and distribute information to stakeholders about the project cost, schedule progress, and performance.

2. Expert Judgement - Suggestions should be sought from subject matter expert such as :

• Senior Management

• Other units or individuals within the organization

• Identified key stakeholders

• Project Managers who have worked on projects in the same area

• Subject matter experts in the business or project area

• Industry groups and consultants

• Professional and technical associations, regulatory bodies and non governmental organization

3. Meetings – Status review meetings are used to exchange and analyze information about stakeholder engagement

Author - Pankaj Sharma

Page 425: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Outputs- Control Stakeholder Engagement

1. Work Performance Information is the performance data collected from various controlling processes, analyzed in context , and integrated based on relationships across areas. Thus work performance data have been transformed into work performance information.

2. Change Requests - Analysis of project performance and interactions with stakeholders often generates change requests. These change requests include

• Recommended corrective actions include changes that bring the expected future performance of the project in line with the project management plan and ;

• Recommended preventive actions can reduce the probability of incurring future negative project performance.

Author - Pankaj Sharma

Page 426: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Outputs- Control Stakeholder Engagement

1. Project Management Plan Updates – Elements of the project management plan that may be updated include :

• Change Management Plan

• Communication management plan

• Cost Management Plan

• Human resource management plan

• Procure management plan

• Quality management plan

• Requirements management plan

• Risk management plan

• Schedule management plan

• Scope management plan

• Stakeholder management plan

Author - Pankaj Sharma

Page 427: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Outputs- Control Stakeholder Engagement

1. Project Documents Updates – Following documents may be updated.

• Stakeholder register - This is updated as information on the stakeholders change, when new stakeholders are identified, or if registered stakeholders are no longer involved in or impacted by the project, or other updates for specific stakeholders are required.

• Issue log – This is updated as new issues are identified and current issues are resolved.

Author - Pankaj Sharma

Page 428: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Outputs- Control Stakeholder Engagement

1. Organizational Process Assets Updates – Following are the organization process assets that may be updated.

• Stakeholder notifications - Information may be provided to stakeholders about resolved issues, approved changes and general project status.

• Project reports - Formal and informal project reports describe project status and include lessons learned, issue logs, project closure reports , and outputs from other knowledge areas

• Project presentations - Information formally or informally provided by the project team to any or all project stakeholders

• Project records – Project records include correspondence, memos, meeting minutes, and other documents describing the project.

• Feedback from stakeholders – Information received from stakeholders concerning project operations can be distributed and used to modify or improve future performance of the project.

• Lesson learned documentation - Documentation includes the root cause analysis of issues faced, reasoning behind the corrective actions chosen, and other types of lessons learned about stakeholder management. Lesson learned are documented and distributed so that they become part of the historical database for both the project and performing organization.

Author - Pankaj Sharma

Page 429: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Procurement Management

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 430: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Procurement Management

Processes necessary to purchase or acquire products, services or results needed from outside the project team.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 431: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Procurement Management Processes

Process Process Group

Plan Procurements

Planning

Conduct Procurements

Executing

Control Procurements

Monitoring and Controlling

Close Procurements

Closing

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 432: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Procurements

Plan Procurements is the process of documenting project purchasing decisions, specifying the approach, and identifying potential sellers

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 433: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Procurements

Inputs Tools and Techniques Outputs

Project management plan

Requirements documentation

Teaming agreements

Risk Register

Project Schedule

Activity cost estimates

Stakeholder register

Enterprise Environmental Factors

Organizational Process Assets

Make or buy analysis

Expert Judgment

Market research

Meetings

Procurement management plan

Procurement statements of work

Make or buy decisions

Procurement documents

Source selection criteria

Change requests

Project document updates

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 434: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Procurements - Inputs

Project Management Plan - describes the need, justification, requirements, and current boundaries for the project. It consists of Scope statement, WBS and WBS dictionary.

Requirements documentation include Important information about project requirements that is considered during planning for procurements. Risk Register include risk-related information such as identified risk, risk owners and risk responses Activity resource requirements state the type and quantities of resources needed for project activities Project Schedule provides information on project timelines and milestones Activity cost estimates are used to evaluate the price quoted in the bids or proposals received from potential sellers Stakeholder Register describes the details on the participants and their interest in the project

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 435: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Procurements - Inputs

Enterprise Environmental Factors includes condition of marketplace, what product and service are available in the market, who is the seller and what are his terms and condition

Organizational Process Assets includes policies and procedures , standards ,guidelines, performance measurement criteria, defect management procedures, change control procedures and historical information. Some organizations may define certain constraint on procurement decisions. This also include the various types of contractual agreements used by the organization, All legal contractual relationships generally fall into one of two broad families: either fixed – price or

cost reimbursable. Also, there is a third hybrid type commonly in use called the time and materials contract.

The next slides describes the different contract types in details

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 436: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Procurements -Tools and Techniques

Time & Material – T & M The seller is paid for the amount of time it takes to accomplish the work and he is also reimbursed for the materials used for the project

Firm Fixed Price - FFP The seller is paid a fixed price for an agreed upon unit of work done by him

Fixed Price Incentive Fee – FPIF The seller is paid a fixed price plus an incentive amount for achieving pre-agreed project metrics

Fixed Price with Economic Price Adjustment Contracts – FP-EPA

The seller is paid a fixed price. The contract is reviewed at pre-defined intervals in the project for adjustments to the contract price based on certain parameters

Types of Contract

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 437: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Procurements -Tools and Techniques

Cost Plus Fixed Fee – CPFF The contractor is reimbursed its cost plus an additional fixed fee. Not desirable from the buyer’s point of view

Cost Plus Incentive Fee - CPIF Seller is reimbursed for an agreed upon performance cost along with a pre-established fee plus an incentive bonus. In this case, the buyer and seller share the uncertainty to a certain degree

Cost Plus Award Fee Seller is reimbursed for an agreed upon performance cost plus all legitimate cost

Types of Contract

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 438: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Plan Procurements -Tools and Techniques

Make or buy analysis helps project management team to decide whether it is beneficial (in terms of cost and quality) to procure a product or service or it can be produced within the organization.

Market Research includes examination of industry and specific vendor capabilities. Procurement teams may leverage information gained at conferences , online reviews and a variety of sources to identify market capabilities.

Meetings , by collaborating with potential bidders , the organization purchasing the material or service may benefit while supplier can influence a mutually beneficial approach or product.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 439: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions Plan Procurements - Outputs

Procurement management plan describes how the procurement process will be managed from planning procurement to close procurement. It contains detail on

1. Types of Contracts to be used

2. Risk management issues

3. Whether independent estimates will be used and whether they are needed as evaluation criteria

4. Standardized procurement documents, if needed

5. Process of managing multiple providers (sellers)

6. Coordination with other project aspects

7. Any constraints and assumptions that could affect planned procurements

8. Handling the long lead times to purchase certain items from sellers and coordinating the extra time needed to procure these items with the development of the project schedule

9. Handling make – or – buy decision and linking them to the Estimate Activity Resources and Develop schedule process.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 440: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions Plan Procurements - Outputs

Procurement statements of work defines the products, services , or result to be procured in details so that the seller can be sure that he can provide appropriate products , services, or results. It is developed from the project scope baseline and defines only that portion of the project scope that needs to be procured and stated in the contract.

Procurement documents define the buyer’s requirements and facilitate complete and correct response from the prospective sellers in the form of a proposal, which aids in the selection of the seller(s). The most commonly used procurement documents are RFP (Request for Proposal), IFB (Invitation for Bid and RFI (Request for Information

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 441: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions Plan Procurements - Outputs

Source selection criteria are the set of guidelines on the basis of which a particular seller is selected from among the proposals received. Some of the source selection criteria are seller’s understanding of need , overall- life-cycle cost, technical capability, Risk, past performance of the seller, Financial capacity, Warranty etc

Make –or - Buy Decisions, A make-or- buy analysis results in a decision of whether particular work can best be accomplished by the project team or needs to be purchased from outside sources.

Change requests may be there during this process due to updates in the project plan or its subsidiary plan and other components. These changes are reviewed and approved through the integrated change control process.

Project Documents Updates that may be updated include requirement documentation, requirements traceability matrix and risk register.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 442: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Practicing Key Concepts

Exercise 1: Make or Buy Analysis

You’ve been contracted by a construction company to manage their contracting.

They have a choice of either buying an excavator or renting it. To buy it, the

company would have to pay $105,000, but owning it will require approximately

$10,000 in maintenance costs per year. The price to rent the excavator is $5000 per

month, with a one-time service charge of $2000. What’s the minimum number of

months the company needs to use the excavator in order for it to make sense to

buy it rather than rent?

1. 8 months

2. 16 months

3. 21 months

4. 25 months

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 443: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Exercise 2: Plan Procurements

Which document are we referring below?

1. A type of procurement document used to request proposals from

prospective sellers of products or services.

2. A type of procurement document used to request price

quotations from prospective sellers of common or standard

products or services.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 444: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Exercise 2: Plan Procurements

Which document are we referring below?

1. A type of procurement document used to request proposals from

prospective sellers of products or services.

RFP

2. A type of procurement document used to request price

quotations from prospective sellers of common or standard

products or services.

RFQ

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 445: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Conduct Procurement

Conduct Procurements is the process of obtaining seller responses, selecting a seller, and awarding a contract

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 446: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Conduct Procurement

Inputs Tools and Techniques Outputs

Project Management Plan

Procurement documents

Source selection criteria

Seller proposals

Project documents

Make or buy decisions

Teaming agreements

Organizational Process Assets

Bidder conferences

Proposal evaluation techniques

Independent estimates

Expert Judgment

Advertising

Analytical Techniques

Procurement negotiation

Selected sellers

Agreements

Resource calendars

Change requests

Project management plan updates

Project document updates

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 447: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Management Plan contains procurement management plan and this describes how the procurement process will be managed from preparing procurement documentation through close procurements

Procurement Documents as explained earlier provide an audit trail for contracts and other agreements

Source Selection criteria are set of guidelines, either subjective or objective, that are used by the performing organization to select a particular contract/ vendor (seller) from among the proposals received.

Seller proposals are responses to the procurement document package that will be used for selection of the sellers by the organization’s evaluation body

Conduct Procurement - Inputs

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 448: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project documents that are important inputs to this process include risk register and risk related contract decisions.

Make- or -buy decisions as explained earlier is based on the outcome of Make –or-buy- Analysis. The factors that influence the decision making include , core competencies of the organization, value delivered, risk associated with meeting the need in a cost=effective manner and internal capability as compared to the vendor community.

Procurement Statement of Work provides suppliers with a clearly stated set of goals , requirements, and outcomes from which they can provide a quantifiable response. The statement of work include

Specifications

Quantity desired

Quality levels

Performance data, period of performance, work location and other requirements

Conduct Procurement - Inputs

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 449: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Organizational Process Assets that can influence this process include listings of prospective and previously qualified sellers and information on relevant past experience with sellers, prior agreements

Conduct Procurement - Inputs

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 450: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Conduct Procurement – Tools and Techniques

Bidder conferences are meetings wherein the prospective supplier (sellers) are called in to ensure that all the supplier have a clear understanding of the work defined in the procurement documents.

Proposal evaluation techniques are used to evaluate the proposals by giving a rating score to each proposal

Independent estimates are sometimes prepared by the procuring organization using internal expert in estimation or an outside professional estimator

Expert Judgment includes a team of experienced and skilled experts for evaluation of proposals under various areas of expertise as mentioned in the procurement documents and contract

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 451: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Conduct Procurement – Tools and Techniques

Advertising is used by the performing organization to invite the potential sellers to be

Contracted

Analytical Techniques, procurements involve defining a need in such as way

that vendors can bring value through offerings. To ensure that the need can be and is

met, analytical techniques can help organizations identify the readiness of a vendor to

provide the desired end state. By examining past performance information, teams may

identify areas that may have more risk and that need to be monitored closely to

ensure success of the project

Procurement negotiations between the buyers and the potential sellers are

performed with the goal of reaching mutual agreement on the contractual terms and

conditions. The goal is to reach a win-win scenario between the buyer and seller.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 452: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Conduct Procurements– Outputs

Selected Sellers are those who have met the evaluation criteria and negotiated a draft contract with the buyer, which will become the actual contract when the contract is awarded

Agreement is a formal document governing the relationship between the buyer and the seller. The contract describes the work to be performed and perhaps the way in which the work will be performed. An important to include with the contract is how disputes will be resolved. Depending upon the application area, an agreement can also be called an understanding , a contract, a subcontract, or a purchase order. Regardless of the document complexity , a contract is a mutually binding legal agreement that obligates the seller to provide the specific products, services, or results and obligates the buyer to compensate the seller. The major component of agreement are:

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 453: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Conduct Procurements– Outputs

Major components of an agreement

Statement of work or deliverables

Schedule baselines

Performance reporting

Period of performance

Roles and responsibilities

Seller’s place of performance

Pricing

Payment Terms

Place of delivery

Inspection and acceptance criteria

Warranty

Product Support

Limitation of liability

Fees and retainer

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 454: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Conduct Procurements– Outputs

Major components of an agreement

Penalties

Incentives

Insurance and performance bonds

Subordinate subcontractor approvals

Change request handling and

Termination clause and alternative dispute resolution (ADR) mechanism. The ADR method can be decided in advance as a part of the procurement award.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 455: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Conduct Procurements– Outputs

Resource Calendar state the availability and the quantity of contracted resource and the project period (dates) during which the resources are active or idle

Change Requests to the project management pan, its subsidiary plans and other components are processed for review and disposition through the Perform Integrated Change Control process.

Project Management Plan Updates, the elements of the project management plan that may be updated include Cost baseline, Scope baseline, Schedule baseline, Communication management plan, and Procurement management plan.

Project Document Updates, the project documents that may be updated include, requirement documentation, requirement traceability documentation, risk register and stakeholder register.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 456: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Conduct Procurements– Outputs

Selected Sellers are those who have met the evaluation criteria and negotiated a draft contract with the buyer, which will become the actual contract when the contract is awarded

Procurement Contract Award is a formal document governing the relationship between the buyer and the seller. The contract describes the work to be performed and perhaps the way in which the work will be performed. An important to include with the contract is how disputes will be resolved.

Resource Calendar state the availability and the quantity of contracted resource and the project period (dates) during which the resources are active or idle

Change Requests As discussed earlie

Project Management Plan Updates As discussed earlier

Project Document Updates As discussed earlier

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 457: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Procurements

Managing procurement relationships, monitoring contract performance and

making changes and corrections as needed.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 458: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Procurement

Inputs Tools and Techniques Outputs

Project Management Plan

Procurement documents

Agreement

Approved change requests

Work Performance reports

Work performance Data

Contract change control system

Procurement performance reviews

Inspections and audits

Performance reporting

Payment system

Claims administration

Records management system

Work performance information

Change requests

Project management plan updates

Project document updates

Organizational process assets update

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 459: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Project Management Plan describes how the procurement process will be managed from developing procurement documentation through contract closure.

Procurement documents contain complete supporting records for administration of the procurement processes; this includes procurement contract awards and the statement of work

Agreements As Explained earlier Agreements are understanding between parties, including understanding of the duties of each parties.

Approved change requests include modifications to the terms and condition of the contract including the procurement statement of work, pricing and the description of the products , services or results.

Control Procurement - Inputs

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 460: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Work Performance Reports – is a seller performance related documentation that include

Technical documentation. Sellers- developed technical documentation and other deliverable information are provided in accordance with the terms of the contract.

Work performance information. The seller’s performance reports indicate which deliverables have been completed and which have not.

Work Performance Data includes information on a regular basis of the performance and status of the seller’s project work activities. It includes information such as which deliverables have been completed and which have not, whether the quality standards defined for the project are being adhered to and the payment is being made for the costs that have been stated in the contract.

Control Procurement - Inputs

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 461: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Procurement – Tools and Techniques

Contract change control system is a component of integrated change control system and it describes the process of updating the contract

Procurement performance reviews are periodic reviews initiated by the buyer to measure the project’s progress against the plan

Inspections and audits are done by the buyer and supported by the seller to identify any non-compliance to the project’s process or deliverables.

Performance reporting provides information to management about how effectively the seller is achieving his contractual objective.

Payment system helps to ensure that invoices and payments match up and that the right amount is being invoiced for the right deliverables at the right time.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 462: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Procurement – Tools and Techniques

Claims administration are basically disagreements (about scope or change request). It is preferred that the claims should be resolved by the parties involved as per the dispute resolution procedure . If not resolved by the parties involved, then the disputes are resolved by the process of Arbitration whereby a third neutral party is given the task of getting the dispute resolved.

Records management system is a part of the project management information systems (PMIS). In addition to the documentation, it also consists of processes, control functions, and automated tools. This system should index various documents for their easy retrieval and archival.

pankaj sharma, Mobile -

9810996356

Author - Pankaj Sharma

Page 463: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Procurement – Outputs

Work Performance Information provides a basis for identification of current or potential problems to support later claims or new procurements. By reporting on the performance of a vendor, the organization increases the knowledge of the performance of the procurement , which supports improved forecasting , risk management and decision making. Performance reports also assist in the event there is a dispute with the vendor.

Change requests, changes to the project management plan, its subsidiary plans, and other components , such as the cost baseline, schedule baseline, and procurement management plan may result from the control procurement process.

Project management plan updates includes update to the procurement management plan ,schedule baseline and cost baseline

pankaj sharma, Mobile -

9810996356

Author - Pankaj Sharma

Page 464: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Control Procurement – Outputs

Project Documents Updates include updates to procurement documentation, it include the procurement contract with all supporting schedules, requested unapproved contract changes , and approved change requests. It also includes any seller developed technical documentation and other work performance information such as deliverable s, seller performance reports and warranties, financial documents including invoices and payment records, and the result of contract – related inspections.

Organizational process assets updates that will be updated as a result of this process includes documentation related to seller’s unsatisfactory performance, request for contract changes or clarifications, payments made by the buyer to the seller and also the documents related to seller’s performance.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 465: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Tools and Techniques

Exercise : Control Procurements

1. ___________________ involves process to change the

procurement contract. It can involve the approvals, paperwork

and the dispute resolution mechanism required for the change

control.

2. ______________ system refers to how the payments are made to

the seller.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 466: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Tools and Techniques

Answer to Exercise : Control Procurements

1. Contract Change Control System involves process to change the

procurement contract. It can involve the approvals, paperwork

and the dispute resolution mechanism required for the change

control.

2. Payment system refers to how the payments are made to the

seller.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 467: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Close procurements

Process of completing each project procurement. It involves administrative activities

such as updating the project records with results and archiving the information for

future use and finalizing open claims in accordance with the terms and conditions

stated in the contract document

Close Procurement process closes the procurement applicable to that phase of the

project

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 468: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Close procurements

Inputs Tools and Techniques Outputs

Project Management Plan

Procurement documentation

Procurement audits

Procurement Negotiations

Records management system

Closed procurements

Organizational process assets updates

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 469: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Close procurements- Inputs

Project Management Plan Discussed Earlier

Procurement documentation includes information on contract schedule, scope, quality and cost performance along with all contract change documentation, payment records and inspection results. This information can be used for lessons learned information and as a basis of evaluating contractors for future contracts.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 470: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Close procurements- Tools and Techniques

Procurement Audits is a structured review of the procurement processes from the plan procurements process through administer contracts process. The purpose of procurement audit is to identify the improvement areas and the flawed procurement processes and/ or procedure. This will assist in reusing the successful/updated procedures in other projects.

Procurement Negotiations refers to the settlement for any outstanding issues, claims and disputes through negotiation. Whenever the settlement cannot be achieved through direct negotiation, some form of alternative dispute resolution(ADR) including mediation or arbitration can be explored

Records Management System is used by the project manager to manage contract and procurement documentation and records. Contract documents and correspondence are archived through the records management system as part of the close procurement process

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 471: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Close procurements- Outputs

Closed Procurements is the process in which the buyer’s contract administrator sends formal written notice to the seller that the contract is complete.

Organizational Process Assets Updates will be updated due to modification in the procurement files and lessons learned documentation. Also, deliverable acceptance and rejection will be stated in the final contract documentation with supporting reasons.

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 472: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Reviewing Associated Risks to Buyers & Sellers

Exercise 5: Contract Type

Explain the risks from buyer and seller perspective in case of the following

types of contracts

1. Firm fixed price

2. Fixed price plus incentive fee (FPIF)

3. Cost plus fixed fee

4. Cost plus award fee

5. Cost plus incentive fee

6. Time and Material (T&M)

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 473: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Negotiations Techniques

– Deadline: imposing a deadline to reach an agreement

– Stalling: one party may claim that an agreement cannot be finalized

because of his limited authority

– Fair and Responsible: a negotiator may claim that the price for a

product is equitable because that’s what another company is

paying.

– Delay: are useful when tempers are beginning to flare, to divert from

a subject, etc (Ex: arrival of refreshments, request for recess etc)

– Withdrawal: one party may attack an issue, then retreat

Project Procurement Management

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 474: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Negotiations Techniques

– Arbitration: a third party may be brought in when agreement cannot

be reached. (out of court settlement)

– Fait Accompli: a party may claim that what is being asked for has

already been accomplished and cannot be changed

Project Procurement Management

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 475: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

Revising Key Terms : Complete the following

Exercise 5: Procurement Management

1. An Invitation for __________ is a document that ask sellers for

the price of work

2. The buyer selects the __________ selection criteria before

contacting potential sellers

3. The ___________contract has high risk to the seller because the

seller must cover costs that go beyond the price

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma

Page 476: PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP

Connoisseur Solutions

QUIZ !

pankaj sharma, Mobile - 9810996356

Author - Pankaj Sharma