PMP Introduction PMBOK V4.0

download PMP Introduction PMBOK V4.0

of 51

Transcript of PMP Introduction PMBOK V4.0

  • 8/10/2019 PMP Introduction PMBOK V4.0

    1/51

  • 8/10/2019 PMP Introduction PMBOK V4.0

    2/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 1

    Overview

    Introduction and Overview of PMI methodology andPMBOK (4thEd.)

    Relationships between Project Management, Program

    Management and Portfolio management

    Project and Operations Management

    Project Lifecycle

    Differences between Product Management and Project

    Management

    Organizational Structures

  • 8/10/2019 PMP Introduction PMBOK V4.0

    3/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 2

    Certification

    PMP: for professionals experiencedin Project Management

    Eligibility (Partial List)

    PM experience4500 Hours (over last three years)

    PM Education35 Hours (this course) Bachelors Degree

    For a complete list please visit http://www.pmi.org

    http://www.pmi.org/http://www.pmi.org/
  • 8/10/2019 PMP Introduction PMBOK V4.0

    4/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 3

    PMBOK, PMI and PMP Special Jargon and New Concepts

    Preparing for PMP (or CAPM) certification means

    Learning a new set of terms as well as new definitions for

    words

    Understanding new concepts and approaching problems from

    a strictly PMI point-of-view

    Mapping these new terms and concepts to your existing PM

    experience

    Analyze a scenario and explain what is happening

    Understand the next steps will be ,or solve an existing

    problem (put this in the notes).

    PMBOK 4thEdition is the bible; Your Experience is agood supplement

  • 8/10/2019 PMP Introduction PMBOK V4.0

    5/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 4

    Project Management Myths

    MS-Project plans (and Gantt charts in general) are project plans

    Project life cycle is the same as the product management

    lifecycle

    Project managers are the same as functional managers

    Project management is common sense

    The Project Manager creates the Project Plan and the team

    simply carries out the plan

    The above statements are partially true from ProjectManagement perspective

  • 8/10/2019 PMP Introduction PMBOK V4.0

    6/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 5

    Project Management Institute (PMI)

    The Project Management Institute (PMI) is the

    worlds foremost authority for the project

    management profession. PMI sets industrystandards, conducts research, and provides

    education, certification, and professional exchange

    opportunities, designed to strengthen and further

    establish the profession.

  • 8/10/2019 PMP Introduction PMBOK V4.0

    7/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 6

    PMBOK

    is a PMI Standard

    PMI Standard is a document

    that defines what to measure against a document created by anappropriate diverse group through an open consensus-building process

    covering commonly accepted knowledge and/or practices and dealingwith core concepts for the practice of the profession

    consistent with PMIs Standards Setting Process and published as aproject management standard

  • 8/10/2019 PMP Introduction PMBOK V4.0

    8/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 7

    PMBOK

    - and also a Guide

    The primary purpose of the PMBOKGuide is to identify

    that subset of the Project Management Body of Knowledgethat is generally recognizedas good practice.

    Generally recognized means the knowledge and

    practices described are applicable to most projects most of

    the time, and there is consensus about their value and

    usefulness.

    Good practice means there is general agreement that the

    application of these skills, tools and techniques can enhance

    the chances of success over a wide range of Projects.

  • 8/10/2019 PMP Introduction PMBOK V4.0

    9/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 8

    PMBOK

    - and also a Guide

    It describes established norms, methods, processes and practices

    It Summarizes processes, inputs, and outputs that are considered goodpractices on most projects most of the time.

    Provides and promotes common vocabulary

    It is a fundamental project management reference for PMIs

    professional development programs and certifications

    It has interrelationships to other project management disciplines such

    as program management and portfolio management

    Please refer to PMIs Code of Ethics and Professional Conduct

  • 8/10/2019 PMP Introduction PMBOK V4.0

    10/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 9

    What is a Project? (PMI Definition)

    A projectis a temporary endeavor undertaken to create a

    unique product, service, or result.

    PROJECT

    has a beginning and end

    creates a unique product, service or result

    progressively elaborated

    Temporary does not mean short in duration

    Progressive Elaboration - Developing in steps and, continuing by increments.

    Project Management (PM) -the application of knowledge, skills, tools and

    techniques to project activities to meet the project requirements.

  • 8/10/2019 PMP Introduction PMBOK V4.0

    11/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 10

    What is a Project? (PMI Definition)

    A Project can create

    A Product that can be either a component of another item or an enditem in itself

    A capability to perform a service

    A result such as an outcome or document

    End of Project is reached when

    Projects objectives have been achieved or

    Its objectives will not or can not be met or

    Need for the project no longer exists

  • 8/10/2019 PMP Introduction PMBOK V4.0

    12/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 11

    Project and Strategic planning

    Projects are typically authorized as a result of one or more of

    the following strategic considerations

    Market demand

    Strategic opportunity / business need

    Customer request

    Technological advance

    Legal requirements

  • 8/10/2019 PMP Introduction PMBOK V4.0

    13/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 12

    Project Management

    Project Management typically includes

    Identifying requirements

    Addressing the various needs, concerns and expectations

    of the stakeholders as the project is carried out

    Balancing the competing project constraints

  • 8/10/2019 PMP Introduction PMBOK V4.0

    14/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 13

    Progressive Elaboration - Rolling Wave Planning

    Developing in steps, and continuing by increments towork out the details.

    Early in the project, project scope will be more broadlydefined.

    Project scope will become more explicit and detailed as thePM team develops a better and more completeunderstanding of the objectives and deliverables.

    Both project specifications and product specifications maybe progressively elaborated.

  • 8/10/2019 PMP Introduction PMBOK V4.0

    15/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 14

    Project / Program / Portfolio Management

    Program

    A Program is defined as a group of related projects managed in a

    coordinated way to obtain benefits and control not available from

    managing them individually.

    Program Management

    The centralized coordinated management of a program to achieve the

    programs strategic objectives and benefits.

  • 8/10/2019 PMP Introduction PMBOK V4.0

    16/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 15

    Project / Program / Portfolio Management

    Portfolio

    A portfolio refers to a collection of Projects or programs and other work

    that are grouped together to facilitate effective management of that work

    to meet strategic business objectives.

    Portfolio Management

    It refers to the centralized management of one or more portfolios, which

    includes identifying, prioritizing, authorizing, managing and controlling

    projects, programs, and other related work, to achieve specific business

    objectives.

  • 8/10/2019 PMP Introduction PMBOK V4.0

    17/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 16

    Project / Program / Portfolio Management

  • 8/10/2019 PMP Introduction PMBOK V4.0

    18/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 17

    Project / Program / Portfolio ManagementProjects Programs Portfolios

    Scope

    Projects have defined objectives.

    Scope is progressively elaborated

    throughout the project life cycle.

    Programs have a large scope and

    provide more significant benefits.

    Portfolios have a business scope that

    changes with the strategic goals of the

    organization.

    Change

    Project Managers expect change and

    implement processes to keep change

    managed and controlled.

    The program manager must expect

    change from both inside and outside

    the program and be prepared to

    manage it.

    Portfolio managers continually monitor

    changes in the broad environment.

    Planning

    Project managers progressively

    elaborate high-level information into

    detailed plans throughout the project

    life cycle.

    Program managers develop the overall

    program plan and create high-level

    plans to guide detailed planning at the

    component level.

    Portfolio managers create and

    maintain necessary processes and

    communication relative to the

    aggregate portfolio.

    Management

    Project managers manage the project

    team to meet the project objectives.

    Program managers manage the

    program staff and the project

    managers; they provide vision and

    overall leadership.

    Portfolio managers may manage or

    coordinate portfolio management staff.

    Success

    Success is measured by product and

    project quality, timeliness, budget

    compliance, and degree of customersatisfaction.

    Success is measured by the degree to

    which the program satisfies the needs

    and benefits for which it wasundertaken.

    Success is measured in terms of

    aggregate performance of portfolio

    components.

    Monitoring

    Project managers monitor and control

    the work of producing the products,

    services or results that the project was

    undertaken to produce.

    Program managers monitor the

    progress of program components to

    ensure the overall goals, schedules,

    budget, and benefits of the program will

    be met.

    Portfolio managers monitor aggregate

    performance and value indicators.

  • 8/10/2019 PMP Introduction PMBOK V4.0

    19/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 18

    Project Management Office

    It is an organizational body or entity assigned various

    responsibilities related to the centralized and coordinated

    management of those projects under its domain.

    The specific form, function and structure of a PMO is

    dependent upon the needs of the organization that it

    supports.

    A primary function of a PMO is to support project managers

    in a variety of ways. The responsibilities of a PMO can

    range from providing project management support

    functions to actually being responsible for the direct

    management of the project.

  • 8/10/2019 PMP Introduction PMBOK V4.0

    20/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 19

    Projects vs. Operations

    Project has a beginning and end; creates a unique

    product or serviceOperationis ongoing and repetitive

    Common characteristics:

    Performed by individuals

    Limited by constraints

    Planned, executed, monitored and controlled

    Performed to achieve organizational objectives or strategic plans

  • 8/10/2019 PMP Introduction PMBOK V4.0

    21/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 20

    Project or Operation?

    1. Running the year-end W-2 form processing for a companys

    employees

    2. Upgrading the database containing the employee payroll data from

    Oracle 9i to Oracle 10i

    3. Running a campaign for political office

    4. An oil company rebuilds refineries destroyed by a hurricane

    5. The operations team of the I.T. department installs a software patch

    sent by the vendor

  • 8/10/2019 PMP Introduction PMBOK V4.0

    22/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 21

    Project or Operation? Solution

    1. W-2: operation

    2. Oracle Upgrade: project

    3. Political Campaign: project

    4. Rebuild refineries: project

    5. Install software patch: can be project or operation

  • 8/10/2019 PMP Introduction PMBOK V4.0

    23/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 22

    Sample Question

    Which of the following is not a project?A. Buying clothes from the market on a special sale.

    B. Planning for your friends wedding.

    C. Building a bridge across the Krishna river.

    D. Cleaning the office building every day.

  • 8/10/2019 PMP Introduction PMBOK V4.0

    24/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 23

    What is Project Life Cycle?

    The project life cycles generally define

    The phases that connect the beginning of a project to its end.

    What technical work to do in each phase

    When the deliverable are to be generated

    Who is involved in each phase

    How to control and approval for each phase

  • 8/10/2019 PMP Introduction PMBOK V4.0

    25/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 24

    Project Life Cycle Characteristics

    At the start of the project:

    Level of uncertainty is highest

    Risk of failure to achieve objectives is greatest

    Stakeholders influence on the final characteristics of projects

    product and final cost is highest

    Cost of changes and correcting errors is lowest

  • 8/10/2019 PMP Introduction PMBOK V4.0

    26/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 25

    Typical Sequence of Phases in a Project Life Cycle

    The completion and approval of one or more deliverables

    characterizes a project phase.

    Diagram Ref: PMBOK Guide 4thVersion, Page 16 and 17 (Figure 2-1)

  • 8/10/2019 PMP Introduction PMBOK V4.0

    27/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 26

    Project phases

    An element of the Project life cycle

    Divisions within a project where extra control is needed to effectively

    manage the completion of a major deliverable

    Allows the project to be segmented into logical subsets

    Typically completed sequentially, but can overlap

    It is not a Project Management Process group

    The number of phases, need for phases and the degree of control

    applied depend on the size, complexity and potential impact of the

    project.

  • 8/10/2019 PMP Introduction PMBOK V4.0

    28/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 27

    Project phases - Characteristics

    Close of a phase ends with some form of transfer or handoff of the

    work product produced as the phase deliverable

    The work has a distinct focus that differs from any other phase

    The primary deliverable or objective of the phase requires an extra

    degree of control to be successfully achieved.

    Diagram Ref: PMBOK Guide 4thVersion, Page 19 Figure 2-3

    One approach to managing the installation of a Telecommunications Network

  • 8/10/2019 PMP Introduction PMBOK V4.0

    29/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 28

    Project Management Process Groups

    Initiating: authorizing the project or phase

    Planning: defining and refining the objectives; selecting the best

    alternative courses of action to attain the objectives of the project(planning the work)

    Executing: integrates and coordinates people and other resources tocarry out the project management plan for the project (working the

    plan)

    Monitoring and Controlling: monitoring the project, measuring progress,reporting status, identifying variances, taking corrective action

    Closing: Formalizes the acceptance of the product, service or resultand brings the project or project phase to an end.

    Process: a set of interrelated act ion s and act iv i t ies performed to

    achieve a speci f ied set of p roducts, resul ts or services

  • 8/10/2019 PMP Introduction PMBOK V4.0

    30/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 29

    PM Lifecycle Processes

    While the PM processes

    are presented (by PMI) as

    discreet processes with

    well-defined interfaces, in

    practice they overlap and

    interact.

    This interaction is

    presented in terms of the

    plan-do-check-act cycle (as

    described by Shewhart and

    Deming).

  • 8/10/2019 PMP Introduction PMBOK V4.0

    31/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 30

    Project Lifecycle

  • 8/10/2019 PMP Introduction PMBOK V4.0

    32/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 31

    Project Governance

    Provides a comprehensive, consistent method of controlling

    the project and ensuring its success.Governance approach to be described in project

    management plan.

    Must fit within the larger context of the program or

    organization.

    Project manager and project management team determines

    Appropriate method of carrying out project

    What resources are necessary General approach to completing the work

    Specific phased structure for the individual project

  • 8/10/2019 PMP Introduction PMBOK V4.0

    33/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 32

    Project Phases

    A sequential relationship

    An overlapping relationship

    An iterative relationship

    Potential Approach to building a new factory

    Initiating Processes Executing ProcessesPlanning Processes Closing Processes

    Monitoring and Controlling Processes

    Construction Phase

    Initiating Processes Executing ProcessesPlanning Processes Closing Processes

    Monitoring and Controlling Processes

    Design Phase

  • 8/10/2019 PMP Introduction PMBOK V4.0

    34/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 33

    Product Vs Project Life Cycles

    Product life cycle

    It consists of generally sequential, non overlapping product phasesdetermined by the manufacturing and control need of the organization.

    Projects lifecycles occur in one or more phases of a product life cycle

    One product may have many projects associated with it

  • 8/10/2019 PMP Introduction PMBOK V4.0

    35/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 34

    Major PMI Concepts

    The project manager is ultimately responsible for the project (planning,work execution, controlling & monitoring and closing) including the overall

    quality of the project.

    The project team assists with the planning, executes the work, inspectsand controls the work. Team members are responsible for the quality ofproject deliverables.

    Conduct yourself professionally at all times. When in doubt, always take

    the r ightpath.

    The people who do the work should estimate the work.

    The project team should solve its own problems and resolve its own

    issues whenever possible.

  • 8/10/2019 PMP Introduction PMBOK V4.0

    36/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 35

    Major PMI Concepts

    Closing processes should occur at the end of each projectphase, not just at the end of the project.

    The success or failure of a project is determined during projectplanning

    If you fail to plan, you plan to fail

    S Q

  • 8/10/2019 PMP Introduction PMBOK V4.0

    37/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 36

    Sample Question

    The most important task and skill of a project manager is:

    A. Negotiating

    B. Communicating

    C. Planning

    D. Leading

    WHY?

    P j t t k h ld

  • 8/10/2019 PMP Introduction PMBOK V4.0

    38/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 37

    Project stakeholders

    Project Stakeholders are individuals and organizations that are actively

    involved in the project, or whose interests may be affected as a result

    of project execution or project completion.

    Stakeholders are those who can affect or are affected by the project

    Stakeholders may a have positive or negative influence on a project.

    Key stakeholders on every project include:

    Customer / User

    Sponsor, PMO

    Portfolio / Program Managers

    Project Manager

    Project team

    Functional managers / Operations management

    Sellers / business partners

    P j t t k h ld Id tifi ti

  • 8/10/2019 PMP Introduction PMBOK V4.0

    39/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate 2009 Capgemini - All rights reserved 38

    Project stakeholders - Identification

    Technique of systematically gathering and analyzing quantitative and

    qualitative information to determine whose interest should be taken into

    account throughout the project.

    Steps

    Identify all potential project stakeholders and relevant information (roles,

    departments, interests, knowledge levels, expectations, and influence level)

    Identify other stakeholders by interviewing identified stakeholders Use expert judgment to ensure comprehensive identification and listing of

    stakeholders

    Identify the potential impact or support each stakeholder could generate and

    classify them so as to define an approach strategy. (Refer to figure 10-4

    Power / Interest grid) Assess how key stakeholders are likely to react or respond in various

    situations, in order to plan how to influence them to enhance their support

    and mitigate potential negative impacts.

    O i ti l I fl P j t M t

  • 8/10/2019 PMP Introduction PMBOK V4.0

    40/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate 2009 Capgemini - All rights reserved 39

    Organizational Influence on Project Management

    Organizational cultures and styles

    Organizational structure

    Organization

    Structure

    ProjectCharacteristics

    Functional Matrix Projectized

    Weak Matrix Balanced Matrix Strong Matrix

    Project Managers

    Authority

    Little or none Limited Low to moderate Moderate to high High to almost

    total

    Resource availability Little or none Limited Low to moderate Moderate to high High to almost

    total

    Who controls the

    project budget

    Functional

    manager

    Functional

    manager

    Mixed Project manager Project manager

    Project Managers role Part-time Part-time Full-time Full-time Full-time

    Project management

    Administrative staff

    Part-time Part-time Part-time Full-time Full-time

    O i ti l St t

  • 8/10/2019 PMP Introduction PMBOK V4.0

    41/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate 2009 Capgemini - All rights reserved 40

    Organizational Structure

    Functional Manager:in charge of a functional area, e.g., finance,

    human resources, I.T. operations, training, marketing.

    Someone with management authorityover an organizational unit

    within a functional organization. The manager of any group that

    actually makes aproductor performs a service. Sometimes called a

    line manager.

    Project Manager:The person assigned by theperformingorganizationto achieve theproject objectives. Performing

    Organization: The enterprise whose personnel are most directly

    involved in doing the work of the project

    Project Objectives: The result to be obtained, the product to be

    produced or the purpose to be achieved by the project.

    F ti l O i ti

  • 8/10/2019 PMP Introduction PMBOK V4.0

    42/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate 2009 Capgemini - All rights reserved 41

    Functional Organization

    Picture Ref: PMBOK Guide, 4thVersion, Figure 2-7 Page 29

    W k M t i O i ti

  • 8/10/2019 PMP Introduction PMBOK V4.0

    43/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate 2009 Capgemini - All rights reserved 42

    Weak Matrix Organization

    Picture Ref: PMBOK Guide, 4thVersion, Page 29

    Strong Matri Organi ation

  • 8/10/2019 PMP Introduction PMBOK V4.0

    44/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate 2009 Capgemini - All rights reserved 43

    Strong Matrix Organization

    Picture Ref: PMBOK Guide, 4thVersion, Page 30

  • 8/10/2019 PMP Introduction PMBOK V4.0

    45/51

    Sample Question

  • 8/10/2019 PMP Introduction PMBOK V4.0

    46/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate 2009 Capgemini - All rights reserved 45

    Sample Question

    You are the Project Manager of XYZ consultants. The Project team

    members are from Finance and HR departments. The team members

    report to Finance and HR Managers respectively, and you havelimited control over them. What type of organizational hierarchy does

    XYZ consultants follow?

    A. Matrix organizationB. Projectized organization

    C. Functional organization

    D. None of these.

    Enterprise Environmental Factors

  • 8/10/2019 PMP Introduction PMBOK V4.0

    47/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate 2009 Capgemini - All rights reserved 46

    Enterprise Environmental Factors

    Considered as inputs to most planning processes

    Refers to both internal and external environmental factors

    that surround or influence a projects success

    Comes from any or all of the enterprises involved in the

    projectEnhances or constrain project management options

    May have a positive or negative influence on the project

    outcome

    Organizational Process Assets

  • 8/10/2019 PMP Introduction PMBOK V4.0

    48/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate 2009 Capgemini - All rights reserved 47

    Organizational Process Assets

    It may be grouped into two categories

    Processes and procedures

    Corporate knowledge base

    It will include

    All process related assets, from any or all of the organizations involved in the

    project that can be used to influence the projects success

    Formal and informal plans, policies, procedures and guidelines

    Organizations knowledge base such as lessons learned and historical

    information

    Completed schedules, risk data, and earned value data

    Recap

  • 8/10/2019 PMP Introduction PMBOK V4.0

    49/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate 2009 Capgemini - All rights reserved 48

    Recap

    Project

    ProgramPMO

    Operations

    Stakeholders

    Organization Structure

    Project Lifecycle

    Product Lifecycle

    Review Questions Time

  • 8/10/2019 PMP Introduction PMBOK V4.0

    50/51

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate 2009 Capgemini - All rights reserved 49

    Review Questions Time

    Review Questions

  • 8/10/2019 PMP Introduction PMBOK V4.0

    51/51

    www.capgemini.com/financialservices

    Thank You