Pmp Exam Prep Part 1

download Pmp Exam Prep Part 1

of 4

Transcript of Pmp Exam Prep Part 1

  • 8/22/2019 Pmp Exam Prep Part 1

    1/4

    PMP Exam Preparation

    Points to Remember-1

    9 Aprojectisatemporaryendeavortocreateauniqueproductorservice.Operationsareongoingactivities.9 Progressiveelaborationistheprocessoftakingaprojectconceptthroughtotheprojectplan.Astheplanningand

    researchactivitiescontinue,themoredetailedandfocusedtheconceptbecomes.Progressiveelaborationhappens

    throughouttheproject.Itistheprocessofelementswithintheprojectbecomingmoreandmoreexactasadditional

    informationanddetailsbecomeavailable.

    9 Milestonesarecompletedbytheprojectteamastheresultsofactivities.9 Projectscopedefinestherequiredwork,andonlytherequiredworktocompletetheproject.9 Scopeverificationistheproofthattheprojectmanagerhascompletedtheproject.9 Qualitypolicyistheorganizationwiderulesandrequirementsforquality.9 Programsareacollectionofprojectswithacommoncause.9 Businessesexisttomakemoney.9 Customers,internalorexternal,arethemostimportantstakeholdersinaproject.9 Adifferenceinrequirementsresolvedinfavorofthecustomer.However,itistheprojectmanager'sresponsibilityto

    informthecustomerofotheroptions.

    9 Theprojectmanagementofficecanbeestablishedtoofferservicesrangingfrombasicsupporttototalmanagementofprojects.

    9 Maintenanceactivitiesarenotpartofprojects.9 Managementbyobjectivestriestofocusallactivitiesonmeetingthecompany'sobjectives.Iftheproject'sobjectivesa

    not

    in

    line

    with

    the

    company's

    objectives,

    the

    project

    may

    be

    impacted

    or

    cancelled.

    9 Theprojectcoordinatorreportstoahigherlevelmanagerandhasauthoritytomakesomedecisions.Theprojectexpediterhasnoauthoritytomakedecisions.

    9 Crossdisciplinarymeansthattheprojectcoversmorethanonedepartmentortechnicalareaofexpertise.Insuchacasamatrixorganizationisneededwithrepresentativesfromeachdepartmentordiscipline.

  • 8/22/2019 Pmp Exam Prep Part 1

    2/4

    9 Effectiveprojectmanagementrequiresalifecycleapproachtorunningtheproject.9 ThePMOdetermineswhetheraprojectsupportstheorganization'sstrategicplanandcanauthorizeexceptionsto

    projectsnotlinkedtothestrategicplan.

    9 Itisaresponsibilityoftheprojectmanagementofficetoprioritizethecompany'sprojects.Whenprioritizationisclear,ieasiertoallocateresourcesamongprojects.

    9 VerifyScopeprocessoccursduringprojectmonitoringandcontrolling,butproductverificationisdoneduringprojectclosing.

    9 Deliverablesaredeterminedinpartbythecustomer,butnotthesponsor.9 Theprojectmanagerortheprojectmanagementteamdetermineshowbesttoaccomplishtheproject.9 Duringthemonitoringandcontrollingprocessgroup,projectperformanceismeasured,andneededchangesare

    identifiedandapproved.

    9 Theprojectchartergivesauthorizationtobeginaprojectorprojectphase.Theprojectcharterisapprovedintheinitiatprocessgroup.

    9 EnterpriseEnvironmentalFactorsOrganizationalProcessAssetsmustbetakenintoaccountforeveryprocess,eveniftheyarenotexplicitlylistedasinputsintheprocessspecification.

    9 ProjectManagementTeamActivities:9 Analyzeandunderstandthescope.Thatincludestheprojectandproductrequirements,criteria,assumptions,

    constraints,and

    other

    influences

    related

    to

    aproject,

    and

    how

    each

    will

    be

    managed

    or

    addressed

    within

    the

    projec

    9 Understandhowtotaketheidentifiedinformationandthentransformitintoaprojectmanagementplanusingastructuredapproach.

    9 Performactivitiestoproduceprojectdeliverables.9 Measureandmonitorallaspectsoftheproject'sprogressandtakeappropriateactiontomeetprojectobjectives.

    9 Scope,Schedule,andCostBaselineswillbecombinedintoaPerformanceMeasurementBaselinethatisusedasanoverallProjectBaselineagainstwhichintegratedperformancecanbemeasured.

    9 ThePerformanceMeasurementBaselineisusedforEarnedValueMeasurements.9 ConfigurationManagementSystem(CMS):IsasubsystemofthePMIS,whichincludestheprocessesthatdefinehow

    projectdeliverablesanddocumentsarecontrolled,changed,andapproved.AnditincludestheChangeControlSystem

    provideastandardized,effective,andefficientwaytocentrallymanageapprovedchangesandbaselineswithinaproje

    9 ConfigurationManagementActivities:1.ConfigurationIdentification,2.ConfigurationStatusAccounting,and3.ConfigurationVerificationandAudit.

  • 8/22/2019 Pmp Exam Prep Part 1

    3/4

    9 Faitaccompli:Anaccomplishedfact;anactionwhichiscompletedbeforethoseaffectedbyitareinapositiontoqueryreverseit.

    9 WBS:WBSadeliverableorientedhierarchicaldecompositionoftheworktobeexecutedbytheprojectteam.TheWBSfinalizedbyestablishingControlAccountsfortheworkpackagesandauniqueidentifierfromacodeofaccounts.The

    WBSrepresentsallproductandprojectwork,includingtheprojectmanagementwork(Thisissometimescalledthe100

    rule).

    9 TheWBScanbestructuredasanoutline,anorganizationalchart,afishbonediagram,orothermethod.9 Differentdeliverablescanhavedifferentlevelsofdecomposition.9 Excessivedecompositioncanleadtononproductivemanagementeffort,inefficientuseofresources,anddecrease

    efficiencyinperformingthework.

    9 Decompositionmaynotbepossibleforadeliverableorsubprojectthatwillbeaccomplishedfarintothefuture.9 WorkPerformanceInformation:FocusonWHAThasbeendone(providesinformationontheStatusofaDeliverable.9 PerformanceReports:FocusonHOWitwasdone.(FocusonCost,Time,andQualityperformance).ActualResultsare

    comparedagainsttheBaselinestoshowhowtheprojectisperformingagainstthePlan.

    9 ProjectCostBaseline=ProjectEstimates+(Cost)ContingencyReserves.9 ProjectCostBudget=ProjectCostBaseline+ManagementReserves9 ResidualRiskscompriseof:1.Riskthatremainafterapplyingriskresponsestrategies,and2.RisksthatwesimplyACCE

    if

    it

    happens,

    it

    happens,

    we

    have

    aplan

    to

    deal

    with

    it.

    9 ContingencyPlansdealwiththeoutcomeofResidualRisksonproject.9 ContingencyReservecoverstheoutcomeofResidualRisk,andaccountforthe"KnownUnknowns".9 FallbackPlansareemployedforResidualRiskswhentheContingencyPlansfail.9 SecondaryRisksarenewrisksthatemergeasaresultofRiskResponsePlan.9 Watchlist:Allnoncritical/nontop/lowratingrisksareputontheWatchlistandmonitored(Watched)regularly.Itis

    createdatPerformQualitativeRiskAnalysisProcess.

    9 ManagementReservesaccountfortheUnknownUnknowns.9 UtilityTheory:AnappropriatemethodfordescribingRiskTolerance.

  • 8/22/2019 Pmp Exam Prep Part 1

    4/4

    9 RiskAverse:Wherethereismoremoneyatstake,theRiskAverter'ssatisfactiondiminishes;heorsheprefersamorecertainoutcomeanddemandsapremiumtoacceptprojectsofhighrisk.

    9 RiskNeutral:Toleranceforriskremainsthesameasthemoneyatsakeincreases.9 RiskSeeker:Thehigherthestakes,thebetter;asriskincreases,theriskseeker'ssatisfactionincreases;heorsheiseve

    willingtopayapenaltytotakeonprojectsofhighrisks.

    9 ForceMajeureRisks,suchasEarthquakes,Floods,ActsofTerrorism,Etc.,shouldbecoveredunderDisasterRecoveryProceduresinsteadofRiskManagement.

    9 MonteCarloAnalysiswouldshowyouWHERESCHEDULERISKEXISITS(PointsofScheduleRisk).ItisaComputerbasedAnalysis&usefulforrevealingScheduleRisks

    9 Committeedecisionscanhavetheparadoxoutcome,thatajointlymadeorapproveddecisionisnotdesiredbyanyindividualgroupmember.

    9 Whatisaconstructivechange?Adirectionbythebuyeroranactiontakenbythesellerthattheotherpartyconsidersundocumentedchangetothecontract."

    9 Liquidateddamages(LDs)arecontractuallyagreedpaymentsinordertocoverthecustomer'scostscausedbylatecompletionorfailuretomeetspecificationsbythecontractor.

    Success is yours,

    FormorePMPexamtipsvisitourwebsitewww.pmlead.net andsubscribetoournewsletter.

    FollowusonTwitter&Facebook

    [email protected]

    Good management is the art of making problems so interesting and their solutions so constructive

    that everyone wants to get to work and deal with them. Paul Hawken

    http://www.pmlead.net/http://www.twaitter.com/pmleadvoicehttp://www.facebook.com/PMlead.Uhttp://www.facebook.com/PMlead.Umailto:[email protected]:[email protected]://www.facebook.com/PMlead.Uhttp://www.twaitter.com/pmleadvoicehttp://www.pmlead.net/