Pmp Exam Prep Part 1
-
Upload
sankalp-navghare -
Category
Documents
-
view
215 -
download
0
Transcript of Pmp Exam Prep Part 1
-
8/22/2019 Pmp Exam Prep Part 1
1/4
PMP Exam Preparation
Points to Remember-1
9 Aprojectisatemporaryendeavortocreateauniqueproductorservice.Operationsareongoingactivities.9 Progressiveelaborationistheprocessoftakingaprojectconceptthroughtotheprojectplan.Astheplanningand
researchactivitiescontinue,themoredetailedandfocusedtheconceptbecomes.Progressiveelaborationhappens
throughouttheproject.Itistheprocessofelementswithintheprojectbecomingmoreandmoreexactasadditional
informationanddetailsbecomeavailable.
9 Milestonesarecompletedbytheprojectteamastheresultsofactivities.9 Projectscopedefinestherequiredwork,andonlytherequiredworktocompletetheproject.9 Scopeverificationistheproofthattheprojectmanagerhascompletedtheproject.9 Qualitypolicyistheorganizationwiderulesandrequirementsforquality.9 Programsareacollectionofprojectswithacommoncause.9 Businessesexisttomakemoney.9 Customers,internalorexternal,arethemostimportantstakeholdersinaproject.9 Adifferenceinrequirementsresolvedinfavorofthecustomer.However,itistheprojectmanager'sresponsibilityto
informthecustomerofotheroptions.
9 Theprojectmanagementofficecanbeestablishedtoofferservicesrangingfrombasicsupporttototalmanagementofprojects.
9 Maintenanceactivitiesarenotpartofprojects.9 Managementbyobjectivestriestofocusallactivitiesonmeetingthecompany'sobjectives.Iftheproject'sobjectivesa
not
in
line
with
the
company's
objectives,
the
project
may
be
impacted
or
cancelled.
9 Theprojectcoordinatorreportstoahigherlevelmanagerandhasauthoritytomakesomedecisions.Theprojectexpediterhasnoauthoritytomakedecisions.
9 Crossdisciplinarymeansthattheprojectcoversmorethanonedepartmentortechnicalareaofexpertise.Insuchacasamatrixorganizationisneededwithrepresentativesfromeachdepartmentordiscipline.
-
8/22/2019 Pmp Exam Prep Part 1
2/4
9 Effectiveprojectmanagementrequiresalifecycleapproachtorunningtheproject.9 ThePMOdetermineswhetheraprojectsupportstheorganization'sstrategicplanandcanauthorizeexceptionsto
projectsnotlinkedtothestrategicplan.
9 Itisaresponsibilityoftheprojectmanagementofficetoprioritizethecompany'sprojects.Whenprioritizationisclear,ieasiertoallocateresourcesamongprojects.
9 VerifyScopeprocessoccursduringprojectmonitoringandcontrolling,butproductverificationisdoneduringprojectclosing.
9 Deliverablesaredeterminedinpartbythecustomer,butnotthesponsor.9 Theprojectmanagerortheprojectmanagementteamdetermineshowbesttoaccomplishtheproject.9 Duringthemonitoringandcontrollingprocessgroup,projectperformanceismeasured,andneededchangesare
identifiedandapproved.
9 Theprojectchartergivesauthorizationtobeginaprojectorprojectphase.Theprojectcharterisapprovedintheinitiatprocessgroup.
9 EnterpriseEnvironmentalFactorsOrganizationalProcessAssetsmustbetakenintoaccountforeveryprocess,eveniftheyarenotexplicitlylistedasinputsintheprocessspecification.
9 ProjectManagementTeamActivities:9 Analyzeandunderstandthescope.Thatincludestheprojectandproductrequirements,criteria,assumptions,
constraints,and
other
influences
related
to
aproject,
and
how
each
will
be
managed
or
addressed
within
the
projec
9 Understandhowtotaketheidentifiedinformationandthentransformitintoaprojectmanagementplanusingastructuredapproach.
9 Performactivitiestoproduceprojectdeliverables.9 Measureandmonitorallaspectsoftheproject'sprogressandtakeappropriateactiontomeetprojectobjectives.
9 Scope,Schedule,andCostBaselineswillbecombinedintoaPerformanceMeasurementBaselinethatisusedasanoverallProjectBaselineagainstwhichintegratedperformancecanbemeasured.
9 ThePerformanceMeasurementBaselineisusedforEarnedValueMeasurements.9 ConfigurationManagementSystem(CMS):IsasubsystemofthePMIS,whichincludestheprocessesthatdefinehow
projectdeliverablesanddocumentsarecontrolled,changed,andapproved.AnditincludestheChangeControlSystem
provideastandardized,effective,andefficientwaytocentrallymanageapprovedchangesandbaselineswithinaproje
9 ConfigurationManagementActivities:1.ConfigurationIdentification,2.ConfigurationStatusAccounting,and3.ConfigurationVerificationandAudit.
-
8/22/2019 Pmp Exam Prep Part 1
3/4
9 Faitaccompli:Anaccomplishedfact;anactionwhichiscompletedbeforethoseaffectedbyitareinapositiontoqueryreverseit.
9 WBS:WBSadeliverableorientedhierarchicaldecompositionoftheworktobeexecutedbytheprojectteam.TheWBSfinalizedbyestablishingControlAccountsfortheworkpackagesandauniqueidentifierfromacodeofaccounts.The
WBSrepresentsallproductandprojectwork,includingtheprojectmanagementwork(Thisissometimescalledthe100
rule).
9 TheWBScanbestructuredasanoutline,anorganizationalchart,afishbonediagram,orothermethod.9 Differentdeliverablescanhavedifferentlevelsofdecomposition.9 Excessivedecompositioncanleadtononproductivemanagementeffort,inefficientuseofresources,anddecrease
efficiencyinperformingthework.
9 Decompositionmaynotbepossibleforadeliverableorsubprojectthatwillbeaccomplishedfarintothefuture.9 WorkPerformanceInformation:FocusonWHAThasbeendone(providesinformationontheStatusofaDeliverable.9 PerformanceReports:FocusonHOWitwasdone.(FocusonCost,Time,andQualityperformance).ActualResultsare
comparedagainsttheBaselinestoshowhowtheprojectisperformingagainstthePlan.
9 ProjectCostBaseline=ProjectEstimates+(Cost)ContingencyReserves.9 ProjectCostBudget=ProjectCostBaseline+ManagementReserves9 ResidualRiskscompriseof:1.Riskthatremainafterapplyingriskresponsestrategies,and2.RisksthatwesimplyACCE
if
it
happens,
it
happens,
we
have
aplan
to
deal
with
it.
9 ContingencyPlansdealwiththeoutcomeofResidualRisksonproject.9 ContingencyReservecoverstheoutcomeofResidualRisk,andaccountforthe"KnownUnknowns".9 FallbackPlansareemployedforResidualRiskswhentheContingencyPlansfail.9 SecondaryRisksarenewrisksthatemergeasaresultofRiskResponsePlan.9 Watchlist:Allnoncritical/nontop/lowratingrisksareputontheWatchlistandmonitored(Watched)regularly.Itis
createdatPerformQualitativeRiskAnalysisProcess.
9 ManagementReservesaccountfortheUnknownUnknowns.9 UtilityTheory:AnappropriatemethodfordescribingRiskTolerance.
-
8/22/2019 Pmp Exam Prep Part 1
4/4
9 RiskAverse:Wherethereismoremoneyatstake,theRiskAverter'ssatisfactiondiminishes;heorsheprefersamorecertainoutcomeanddemandsapremiumtoacceptprojectsofhighrisk.
9 RiskNeutral:Toleranceforriskremainsthesameasthemoneyatsakeincreases.9 RiskSeeker:Thehigherthestakes,thebetter;asriskincreases,theriskseeker'ssatisfactionincreases;heorsheiseve
willingtopayapenaltytotakeonprojectsofhighrisks.
9 ForceMajeureRisks,suchasEarthquakes,Floods,ActsofTerrorism,Etc.,shouldbecoveredunderDisasterRecoveryProceduresinsteadofRiskManagement.
9 MonteCarloAnalysiswouldshowyouWHERESCHEDULERISKEXISITS(PointsofScheduleRisk).ItisaComputerbasedAnalysis&usefulforrevealingScheduleRisks
9 Committeedecisionscanhavetheparadoxoutcome,thatajointlymadeorapproveddecisionisnotdesiredbyanyindividualgroupmember.
9 Whatisaconstructivechange?Adirectionbythebuyeroranactiontakenbythesellerthattheotherpartyconsidersundocumentedchangetothecontract."
9 Liquidateddamages(LDs)arecontractuallyagreedpaymentsinordertocoverthecustomer'scostscausedbylatecompletionorfailuretomeetspecificationsbythecontractor.
Success is yours,
FormorePMPexamtipsvisitourwebsitewww.pmlead.net andsubscribetoournewsletter.
FollowusonTwitter&Facebook
Good management is the art of making problems so interesting and their solutions so constructive
that everyone wants to get to work and deal with them. Paul Hawken
http://www.pmlead.net/http://www.twaitter.com/pmleadvoicehttp://www.facebook.com/PMlead.Uhttp://www.facebook.com/PMlead.Umailto:[email protected]:[email protected]://www.facebook.com/PMlead.Uhttp://www.twaitter.com/pmleadvoicehttp://www.pmlead.net/