PMP Exam Prep, Sixth Edition-Rita's Course in a Book for Passing the PMP Exam
PMP EXAM PREP COURSE · Session 5 THE PMP® EXAM PREP COURSE PMI, PMP and PMBOK are registered...
Transcript of PMP EXAM PREP COURSE · Session 5 THE PMP® EXAM PREP COURSE PMI, PMP and PMBOK are registered...
www.falcontraining.com
Session 5
THE PMP® EXAMPREP COURSE
PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc.
2
9:00 – 10:15 Procurement Management (Pass the PMP® Exam Ch.10)
10:15 – 10:30 Break
10:30 – 11:45 Stakeholder Management (Pass the PMP® Exam Ch.11)
11:45- 12:15 Ethics and Prof Conduct (Pass the PMP® Exam Ch.12)
12:15 – 1:00 Lunch
1:00 – 2:45 Practice the PMP Exam Questions
2:45 – 3:00 Break
3:00 – 4:00 Wrap up, Questions and Queries
Agenda
www.falcontraining.co.nz
PROCUREMENT MANAGEMENT
Chapter 10 of Pass the PMP® Exam
Chapter 12 of the PMBOK® Guide
Overview
Difficulty Memorisation Exam Importance
Low
Medium
High
4
Procurement Management
USA government-based in its approach
It should be a formal documented process
Buyer = organisation or party purchasing (procuring) the
goods or services from the seller
Seller = organisation or party selling the goods or
services to the buyer
TIP: Read the question carefully to determine if you
are the buyer or seller
5
Procurement Management
Initiating Planning ExecutingMonitoring &
ControllingClosing
Project Management Process Groups
Knowledge
Area Processes
• Plan
Procurement
Management
• Conduct
Procurements
• Control
Procurements
• Close
ProcurementsProject
Procurement
Management
6
Table 3-1. Project Management Process Groups and Knowledge Area MappingA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
.1 Inputs
.1 Project management plan
.2 Requirements documentation
.3 Risk register
.4 Activity resource requirements
.5 Project schedule
.6 Activity cost estimates
.7 Stakeholder register
.8 Enterprise environmental factors
.9 Organizational process assets
.2 Tools and Techniques
.1 Make-or-buy analysis
.2 Expert judgment
.3 Market research
.4 Meetings
.3 Outputs
.1 Procurement management plan
.2 Procurement statement of work
.3 Procurement documents
.4 Source selection criteria
.5 Make or buy decisions
.6 Change requests
.7 Project document updates
.1 Inputs
.1 Project management plan
.2 Procurement documents
.3 Source selection criteria
.4 Seller proposals
.5 Project documents
.6 Make or buy decisions
.7 Procurement statement of work
.8 Organizational process assets
.2 Tools and Techniques
.1 Bidder conference
.2 Proposal evaluation techniques
.3 Independent estimates
.4 Expert judgment
.5 Advertising
.6 Analytical techniques
.7 Procurement negotiations
.3 Outputs
.1 Selected sellers
.2 Agreements
.3 Resource calendars
.4 Change requests
.5 Project management plan updates
.6 Project document updates
Project Procurement Management
12.1 Plan Procurement Management 12.2 Conduct Procurements
.1 Inputs
.1 Project management plan
.2 Procurement documents
.3 Agreements
.4 Approved change requests
.5 Work performance reports
.6 Work performance data
.2 Tools and Techniques
.1 Contract change control system
.2 Procurement performance reviews
.3 Inspections and audits
.4 Performance reporting
.5 Payment systems
,6 Claims administration
.7 Records management system
.3 Outputs
.1 Work performance information
.2 Change requests
.3 Project management plan updates
.4 Project documents updates
.5 Organizational process assets updates
12.3 Control Procurements
.1 Inputs
.1 Project management plan
.2 Procurement documents
.2 Tools and Techniques
.1 Procurement audits
.2 Procurement negotiations
.3 Records management system
.3 Outputs
.1 Closed procurements
.2 Organizational process assets updates
12.4 Close Procurements
7
Figure 12-1. Project Procurement Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Plan Procurement Management
8
Inputs Tools and Techniques Outputs
.1 Project management plan
.2 Requirements
documentation
.3 Risk register
.4 Activity resource
requirements
.5 Project schedule
.6 Activity cost estimates
.7 Stakeholder register
.8 Enterprise environmental
factors
.9 Organizational process
assets
.1 Make-or-buy analysis
.2 Expert judgment
.3 Market research
.4 Meetings
.1 Procurement management plan
.2 Procurement statement of work
.3 Procurement documents
.4 Source selection criteria
.5 Make or buy decisions
.6 Change requests
.7 Project document updates
Figure 12-1. Project Procurement Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Plan Procurement Management
Determining which components or services of the
project will be:
– made or performed internally, or
– procured from an external source
Then determining the most appropriate types of
contracts to use on the project
Producing the procurement management plan
9
Tools
Make-or-Buy analysis
– Analysis of ALL factors that go into deciding whether
to produce something in house or buy it externally
– Includes risk factors, cost, IP, and other
organisational factors external to the project
Expert judgment
Market research
Meetings
10
Figure 12-1. Project Procurement Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Types of Contract
Fixed price (lump sum) Favours the Buyer
– Incentive fee
– Economic Price Adjustment
Cost reimbursable
– + fixed fee
– + incentive fee
Time and Materials Favours the Seller
11
Point of Total Assumption (PTA)The point at which the seller assumes total
responsibility for all cost increases
Requires a fixed price incentive fee contract with a
target price, ceiling price, target cost and agreed
% split of cost overruns. The difference between
the target cost and the target price is the incentive
After the target price, the incentive starts to get eaten
into because the seller is responsible for some of the
overrun
PTA = (Ceiling price – Target price)
Buyers % share of cost overrun+ Target cost
12
Point of Total Assumption (PTA)
13
$0.00
$2,000.00
$4,000.00
$6,000.00
$8,000.00
$10,000.00
$12,000.00
Mar Apr May Jun Jul Aug Sep Oct
Buyer's Price
Seller's Costs
Seller’s Profit
(Incentive)
Target Cost
Target Price
Point of Total Assumption (PTA)
14
$0.00
$2,000.00
$4,000.00
$6,000.00
$8,000.00
$10,000.00
$12,000.00
Mar Apr May Jun Jul Aug Sep Oct
Buyer's Price
Seller's Costs
Seller’s Profit
(Incentive)
Ceiling Price
PTA
Target Cost
Target Price
Point of Total Assumption (PTA)Fixed Price Incentive Fee Contract
15
$0.00
$2,000.00
$4,000.00
$6,000.00
$8,000.00
$10,000.00
$12,000.00
Mar Apr May Jun Jul Aug Sep Oct
Buyer's Price
Seller's Costs
Seller’s Profit
(Incentive)
Target Cost
Target Price
Ceiling Price
PTA
Seller’s Loss
Example
16
Target cost: $50,000
Target price: $54,000
Ceiling price: $60,000
Cost overruns are paid
75% by the buyer.
Project Cost Cost Overruns Buyer’s Price Incentive Fee
/Profit
$50,000 $0 $54,000 $4,000
$51,000 +$1,000 $54,750 (+$750) $3,750 (-$250)
$52,000 +$2,000 $55,500 (+$1500) $3,500 (-$500)
~ ~ ~ ~
$58,000 +$8,000 $60,000 (+$6000) $2,000 (-$2000)
$59,000 +$9,000 $60,000 (+$0) $1,000 (-$1000)
$60,000 +$10,000 $60,000 (+$0) $0 (-$1000)
$61,000 +$11,000 $60,000 (+$0) -$1,000 (-$1000)
Point of Total Assumption (PTA)
48000
50000
52000
54000
56000
58000
60000
62000
64000
0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000 11000 12000
Seller's Cost Buyer's Price
17
Ceiling Price
PTA
Target Cost
Target Price
Outputs
Procurement management plan
Procurement statement of work
Procurement documents
Source selection criteria
Make or buy decisions
Change requests
Project document updates
18
Conduct Procurements
19
Inputs Tools and Techniques Outputs
.1 Project management plan
.2 Procurement documents
.3 Source selection criteria
.4 Seller proposals
.5 Project documents
.6 Make or buy decisions
.7 Procurement statement of
work
.8 Organizational process
assets
.1 Bidder conference
.2 Proposal evaluation
techniques
.3 Independent estimates
.4 Expert judgment
.5 Advertising
.6 Analytical techniques
.7 Procurement negotiations
.1 Selected sellers
.2 Agreements
.3 Resource calendars
.4 Change requests
.5 Project management plan
updates
.6 Project document updates
Figure 12-1. Project Procurement Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Conduct Procurements
Issue bid package to potential sellers
Hold bidder conferences
Evaluate proposals
Select sellers
20
Bidder Conferences
– All interested potential sellers are given procurement
documents, usually in advance
– All potential sellers are allowed to ask questions and
receive answers to ensure a level playing field, where
nobody has more information than anyone else
Just like a formal tender process you may be familiar
with
21
Proposal evaluation techniques
Weighting system: means of ranking potential sellers
Independent estimates: also referred to as ‘should-cost’
estimates, can serve as benchmark
Screening system: filters, such as;
– ISO-9001, ISO-21500
– The PMP exam
22
Other tools
• Expert Judgement
• Advertising
• Analytical techniques
• Procurement negotiations
23
Figure 12-1. Project Procurement Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Control Procurements
24
Inputs Tools and Techniques Outputs
.1 Project management plan
.2 Procurement documents
.3 Agreements
.4 Approved change requests
.5 Work performance reports
.6 Work performance data
.1 Contract change control
system
.2 Procurement performance
reviews
.3 Inspections and audits
.4 Performance reporting
.5 Payment systems
.6 Claims administration
.7 Records management
system
.1 Work performance
information
.2 Change requests
.3 Project management plan
updates
.4 Project documents updates
.5 Organisational process
assets updates
Figure 12-1. Project Procurement Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Control Procurements
Is done by both buyer and seller
Do the results match the contract?
– Were the goods or services delivered?
– Were they delivered on time?
– Were the right amounts invoiced or paid?
– Were any additional conditions of the contract
met?
25
Control Procurements: Tools
Contract change control system
– Component of integrated change control
– Procedures, forms, tracking, and dispute resolution processes
Procurement performance review
Inspections and audits
Performance reporting
26
Figure 12-1. Project Procurement Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Control Procurements
Payment system
– Helps ensure invoices and payments match and the
right amount is being invoiced for the right
deliverables at the right time
Claims administration
– Handles disagreements
– Records management system
27
Figure 12-1. Project Procurement Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Close Procurements
28
Inputs Tools and Techniques Outputs
.1 Project management plan
.2 Procurement documents
.1 Procurement audits
.2 Procurement negotiations
.3 Records management
system
.1 Closed procurements
.2 Organisational process
assets updates
Figure 12-1. Project Procurement Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Close Procurements
Finally – something else in the closing process!
Every contract must be closed!
Done at the end of the contract – does not mean the
end of the project!
29
Close Procurements: Tools
Procurement audits
– Capture lessons learned from a contracting
perspective
Procurement negotiations – if you encounter a claim or
dispute then go through these stages:
– Negotiation, Mediation, Arbitration, Litigation
Records management system
– Used to archive documentation for future reference
30
Figure 12-1. Project Procurement Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Practice Questions
Pass the PMP® Exam p. 295
31
www.falcontraining.co.nz
PROJECT STAKEHOLDER
MANAGEMENT
Chapter 11 of PMP® Training Kit
Chapter 13 of the PMBOK® Guide
33
Overview
Difficulty Memorisation Exam Importance
Low
Medium
High
Project Stakeholder Management
34
Initiating Planning ExecutingMonitoring &
ControllingClosing
Project Management Process Groups
Knowledge
Area Processes
• Identify
Stakeholders
• Plan
Stakeholder
Management
• Manage
Stakeholder
Engagement
• Control
Stakeholder
EngagementProject
Stakeholder
Management
Table 3-1. Project Management Process Groups and Knowledge Area MappingA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
35
.1 Inputs
.1 Project charter
.2 Procurement documents
.3 Enterprise environmental factors
.4 Organizational process assets
.2 Tools and Techniques
.1 Stakeholder analysis
.2 Expert judgment
.3 Meetings
.3 Outputs
.1 Stakeholder register
.1 Inputs
.1 Project management plan
.2 Stakeholder register
.3 Enterprise environmental factors
.4 Organizational process assets
.2 Tools and Techniques
.1 Expert judgment
.2 Meetings
.3 Analytical techniques
.3 Outputs
.1 Stakeholder management plan
.2 Project documents updates
Project Stakeholder Management
13.1 Identify Stakeholders 13.2 Plan Stakeholder Management
.1 Inputs
.1 Stakeholder management plan
.2 Communications management plan
.3 Change log
.4 Organizational process assets
.2 Tools and Techniques
.1 Communication methods
.2 Interpersonal skills
.3 Management skills
.3 Outputs
.1 Issue log
.2 Change requests
.3 Project management plan updates
.4 Project documents updates
.5 Organizational process assets updates
13.3 Manage Stakeholder Engagement
.1 Inputs
.1 Project management plan
.2 Issue log
.3 Work performance data
.4 Project documents
.2 Tools and Techniques
.1 Information management systems
.2 Expert judgment
.3 Meetings
.3 Outputs
.1 Work performance information
.2 Change requests
.3 Project management plan updates
.4 Project documents updates
.5 Organizational process assets updates
13.4 Control Stakeholder Engagement
35
Figure 13-1. Project Stakeholder Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Identify Stakeholders
36
Inputs Tools and Techniques Outputs
.1 Project charter
.2 Procurement documents
.3 Enterprise environmental
factors
.4 Organisational process
assets
.1 Stakeholder analysis
.2 Expert judgment
.3 Meetings
.1 Stakeholder register
Figure 13-1. Project Stakeholder Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Stakeholder
37
• A stakeholder is any person, or organisation, that can
affect, or be affected by your project
• Identify them, their details, their interest in the project,
their expectations and then rank them so you know
which ones are more important
• Then proactively influence them and mange their
expectations, to support your project or at least not
oppose them
Power and Interest Matrix
38
Keep Satisfied
Manage closely
MonitorKeep
Informed
Power
InterestMendelow, A. (1991) ‘Stakeholder Mapping’, Proceedings of the 2nd International Conference on Information Systems, Cambridge, MA
Salience Model
39
Power
Urgency
Legitimacy
DormantDominant
Discretionary
Dangerous
Definitive
Dependent
Demanding
Mitchell, R., Agle, B. and Wood, D. 1997. Toward a Theory of Stakeholder Identification and Salience: Defining the Principle of Who and What Really Counts. The Academy of Management Review, 22 (4), pp. 853-886.
Plan Stakeholder Management
40
Inputs Tools and Techniques Outputs
.1 Project management plan
.2 Stakeholder register
.3 Enterprise environmental
factors
.4 Organisational process
assets
.1 Expert judgment
.2 Meetings
.3 Analytical techniques
.1 Stakeholder management
plan
.2 Project documents updates
Figure 13-1. Project Stakeholder Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Plan Stakeholder Management
41
This is the process where you develop the
Stakeholder Management plan
The stakeholder management plan guides your
identification of stakeholders and the implementation
of strategies for managing their expectations and
levels of engagement.
Analytical techniques
42
In addition to the Gardner Power and Interest grid,
and the salience model there are other analytical
techniques that can be used to asses stakeholders.
You can use a matrix to asses whether or not a
stakeholder is unaware, resistant, neutral, supportive
or leading
See table on page 309 of Pass the PMP® Exam.
The kick off meeting
43
• The kick off meeting is an excellent tool for managing
stakeholder engagement and expectation as it
transmits a message of confidence to the stakeholders.
Manage Stakeholder Engagement
44
Inputs Tools and Techniques Outputs
.1 Stakeholder management
plan
.2 Communications
management plan
.3 Change log
.4 Organisational process
assets
.1 Communication methods
.2 Interpersonal skills
.3 Management skills
.1 Issue log
.2 Change requests
.3 Project management plan
updates
.4 Project documents updates
.5 Organisational process
assets updates
Figure 13-1. Project Stakeholder Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Manage Stakeholder Engagement
You as Project Manager are making sure the
stakeholders are heard and their needs are addressed
Your goal is to get their support or stop them opposing
your project
Proactive and influencing, begins early and goes
through the project
45
Issue Logs
A great way of keeping track of everything and, if
necessary, escalating it to the risk register
Gives stakeholders a way to see their issues are being
taken care of
46
Interpersonal skills
These include:
– Leadership,
– Decision-making
– Conflict resolution
– Change management
– Active listening
47
Management skills
In addition to leadership skills, there are management
skills a competent project manager must demonstrate
These include:
– Presentation skills
– Negotiation skills
– Time management skills
– Public speaking skills
48
Control Stakeholder Engagement
49
Inputs Tools and Techniques Outputs
.1 Project management plan
.2 Issue log
.3 Work performance data
.4 Project documents
.1 Information management
systems
.2 Expert judgment
.3 Meetings
.1 Work performance
information
.2 Change requests
.3 Project management plan
updates
.4 Project documents updates
.5 Organisational process
assets updates
Figure 13-1. Project Stakeholder Management OverviewA Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. ©2013 Project Management Institute, Inc. All rights reserved
Control Stakeholder Engagement
50
• This is where you check that your stakeholder
management plan (and communications management
plan) are working and if not, make changes to them.
• Use the issue log to ensure that stakeholder
engagement is kept high.
Practice PMP Questions
Pass the PMP® Exam p. 318
51
www.falcontraining.co.nz
ETHICS & PROFESSIONAL
CONDUCT
Chapter 12 of PMP® Training Kit
Overview
Difficulty Memorisation Exam Importance
Low
Medium
High
53
Ethics & Professional Conduct
Based on the Project Management Institute (PMI)®
Code of Ethics and Professional Conduct
This is very short session – don’t blink!
The values that are important are:
– Responsibility,
– Respect,
– Fairness, and
– Honesty.
54
PMI, (n.d.). Code of Ethics and Professional Conduct. [online] Pmi.org. Available at: http://www.pmi.org/about/ethics/code
Ethics & Professional Conduct
Project Manager is the leader and the buck stops there.
Deal with issues in a direct manner seeking to resolve
them.
Always act ethically and legally.
Always follow the laws of the country.
Always follow the policies of your company.
Act truthfully at all times. Be a whistleblower!
55
The Code Applies to
All the PMI members.
Individuals who are not members of the PMI but meet
one or more of the following criteria:
1. Anyone who holds the PMI certification.
2. Anyone who has applied to for the PMI certification.
3. Anyone who volunteers for the PMI.
56
Mandatory & Aspirational
StandardsThe mandatory standards establish firm requirements,
and in some cases, limit or prohibit practitioner
behaviour.
The aspirational standards describe the conduct that we
strive to uphold as practitioners.
Practitioners who do not conduct themselves in
accordance with these standards will be subject to
disciplinary procedures before the PMI Ethics Review
Committee.
57
Responsibility
Responsibility is our duty to take ownership for
the decisions we make or fail to make, the
actions we take or fail to take, and the
consequences that result.
58
Responsibility
Mandatory
– We follow policies, rules, regulations, and laws.
– We report unethical and/or illegal behaviour.
Aspirational
– We act to positively influence Society Interest, Public
Safety, Environmental Impact.
– We take on only what we are qualified to do.
– We take ownership of our errors and apply corrective
action.
59
Respect
Respect is our duty to show a high regard for ourselves,
others, and the resources entrusted to us.
60
Respect
Mandatory
– We negotiate in good faith.
– We do not abuse our authority or power.
– We do not act in an abusive or aggressive manner.
Aspirational
– We understand the norms, culture, customs of our
stakeholders.
– We listen and understand.
– We treat others how we want to be treated.
61
Fairness
Fairness is our duty to make decisions and act
impartially and objectively.
Our conduct must be free from competing self interest,
prejudice, and favouritism.
62
FairnessMandatory;
– We avoid or disclose Conflicts of Interest.
– We avoid favouritism.
– We say no to bribes.
Aspirational;
– We offer transparency in our decision making
– We remain impartial and objective (not subjective)
– We support equal opportunity for all to access
information
63
Honesty
Honesty is our duty to understand the truth and act in a
truthful manner both in our communications and in our
conduct.
64
Honesty
Mandatory;
– We do not condone deceitful or misleading behaviour.
– We do not act for personal gain.
Aspirational;
– Truth is king.
– Our communications have nothing to hide.
– Accurate reporting is paramount.
65
Practice Questions
Pass the PMP® Exam p. 331
66
Practice the PMP Exam…
Covers all course material
You have 120 questions
Mark each one as A, B, C, or D
You have 1 hour and 30 minutes to complete
Good luck!
67
Grade Yourself…
Did you get all questions answered?
Calculate your percentage of correct answered
questions
Use the ‘Where Did I Go Wrong?’ sheet to assess why
you got the answers wrong.
This is a very useful tool to find out your weak areas!
68
Final Test Scores and PMP Success
69
Passed Failed
98
95
93
93
92
90
89
84
84
84 84
83
83
83
82 82
82
81
80
79
78
75
75
74 74
72 72
71 70
69 70
69
68
66
64 66
59
100
90
80PASS
70
60
50
TRY AGAIN40
30
20
10
0
www.falcontraining.co.nz
TEST-TAKING TECHNIQUES
The Pareto Principle
Study concepts, not facts
Get the big picture, then work towards greater detail:
rocks before sand
Train your weaknesses, race your
strengths
What kind of information do you struggle with? Spend
your study time on that.
What kind of information do you retain easily?
Learn by teaching
If you can explain it to a non-PMP in plain English, you
understand it.
– Budget at Completion: How much you thought it would
cost when you first started
– Estimate at Completion: How much you think it’s going
to cost now
– Estimate to Complete: How much more it’s going to
cost before it’s done
Learn by teaching
If you don’t have a non-PMP around who’s willing to listen,
explain it to your teddy bear
Student, know thyselfHow do you study; how do you learn?
On test day, you are the rock star, the Olympic
athlete, the diva. What do you need to feel
comfortable?
– Lots of sleep? A chocolate croissant?
Test-taking specifics
Don’t cram during the minutes before the test
Don’t get stuck!
– If you find a question at all confusing, have a guess,
mark it, then go back
– If you have time at the end, go back and look at them
again
6 steps for answering questions
First, read the question fully!
Second, reread the question!
Third, eliminate any obviously wrong answers.
Fourth, place the answers on a spectrum of most right to most
wrong and choose the most right one.
Fifth, organise the answers in order of which would be done first to
the one which would be done last, choose the one you would do
first.
Sixth, Guess! Leave no question unanswered.
77
Test-taking specifics
Read the entire question before looking at the answer
Are you 100% sure you actually read the question?
A bird in the hand…
Count every " F " in the following text:
FINISHED FILES ARE THE RESULT OF YEARS OF
SCIENTIFIC STUDY COMBINED WITH THE
EXPERIENCE OF YEARS...
Do you read things properly?
Did you notice on the previous slide that there were two
‘the’ in the title?
80
Who wants to be a millionaire?
Eliminate as many wrong answers as you can
But don’t phone a friend!
Finally…Nobody has ever scored 100%; don’t worry about
perfection
Learning the PMP material will help you no matter how you
perform on the test
Remember to breathe
…and make sure to turn off your cell phone!
Common Questions about the
ExamIs there a way to mark out/eliminate options that you
immediately know are not the right answer?
Is there a way to mark questions you are doubtful of?
When you are done, can you review the test?
Can you review just the questions marked as doubtful?
Do you get immediate test results?
83
Common Questions about the Exam
Can you bring any materials with you?
What is the physical setting like?
Can you take food or drink into the test area?
Can you take breaks during the exam? Lunch?
84
Common Questions about the Exam
What are the time constraints?
Are the test questions grouped by area such as
Scope, Time Management...?
Can you take paper and pen into the test area?
85
Checklist for the PMP Exam
You must take:
– Two forms of identification – one with a photo on it
– Your eligibility email: Paper-Based Testing Notification
– You MUST visit the site before the exam date
– How long will it take you to get there?
– Where is it?
– Where will you park?
86
Final Tips
Chapter 1 of the Pass the PMP® Exam may make more
sense now
Plan your study until the exam
Form study/revision groups if necessary
87
Final Tips
Do as many practice questions as you can
Get a good night’s sleep
Don’t panic!
88
GOOD LUCK!You’ll all do well
89