Pmp cost chapter 7

71
1 Project Cost Management Chapter 7

Transcript of Pmp cost chapter 7

Page 1: Pmp cost chapter 7

1

Project Cost ManagementChapter 7

Page 2: Pmp cost chapter 7

2

Project Cost Management

Why do we need to manage our project cost ?

Sponsor Project manager

I need fund for the

project

You didn’t tell

before. I don’t have

now

No

money……No

Page 3: Pmp cost chapter 7

3

Project Cost Management

Why do we need to manage our project cost ?

Page 4: Pmp cost chapter 7

4

Definitions

7.1 Plan Cost Management

7.2 Estimate Costs

7.3 Determine Budget

7.4 Control Costs

Earned Value Management

KEY TERMS

Page 5: Pmp cost chapter 7

Project Cost Management

5

Knowledge

Area

Process

Initiating Planning ExecutingMonitoring &

ControlClosing

Cost

7.1 Plan Cost Management

7.2 Estimate Costs

7.3 Determine Budget

7.4 Control

Costs

Enter phase/

Start project

Exit phase/

End project

Initiating

Processes

Closing

Processes

Planning

Processes

Executing

Processes

Monitoring &

Controlling Processes

Page 6: Pmp cost chapter 7

Project Cost Management

6

7.1 Plan Cost Management—The process that establishes

the policies, procedures, and documentation for planning,

managing, expending, and controlling project costs.

7.2 Estimate Costs—The process of developing an

approximation of the monetary resources needed to

complete project activities.

7.3 Determine Budget—The process of aggregating the

estimated costs of individual activities or work

packages to establish an authorized cost baseline.

7.4 Control Costs—The process of monitoring the status of

the project to update the project costs and managing

changes to the cost baseline.

Page 7: Pmp cost chapter 7

Definitions

7

Profit = Revenue – Costs

Direct costs are costs that can be directly related

to producing the deliverable of the project: Salaries, cost

of hardware & software purchased specifically for the

project

Indirect costs are costs that are not directly related to

the deliverable of the project, but are indirectly related

to performing the project, e.g. cost of electricity,

Internet, rent and office supplies.

Page 8: Pmp cost chapter 7

8

Page 9: Pmp cost chapter 7

9

Variable Costs: change with the amount of production

(cost of material).

Fixed Costs: do not change with production (rent,

setup costs, … etc.).

BUS IS

Fixed cost

Variable

cost

Variable

cost

Variable

cost

Page 10: Pmp cost chapter 7

10

Contingency reserves: Cost Baseline : the cost

impacts of the remaining risk ( known-unknown )

Management reserves: Cost Budget : extra fund

to cover unforeseen risk or changes to the project

( unknown-unknown )

Page 11: Pmp cost chapter 7

11

• Cost Of Quality

Refers to the total cost of the conformance work and the

nonconformance work

Page 12: Pmp cost chapter 7

12

**** Life Cycle Costing

• Costs over the entire life of the product.

• You plan the project to produce the product at a lower

level of quality and save $9,000.

• Project is completed. Maintenance costs are $100,000

over the product's life.

• Maintenance cost could be $20,000 if higher quality was

applied.

• Your $9,000 project "savings" cost the company $80,000.

Page 13: Pmp cost chapter 7

13

• Level of precision. ( measure of exactness )

The degree to which activity cost estimates will be rounded

up or down (e.g., US$100.49 to US$100, or US$995.59 to

US$1,000).

based on the scope of the activities and magnitude of the

project.

• Level of accuracy. ( assessment of correctness )

The acceptable range (e.g., ―/+ 10%) used in determining

realistic activity cost estimates is specified, and may include

an amount for contingencies

Page 14: Pmp cost chapter 7

14

**** Analogous Estimate ( Top Down )

• Use actual values of a similar in fact project.

• Is used in project initiation when no details.

• Quick, less costly but less accurate.

• Difficult for projects with uncertainty.

• ( Rough Order Of Magnitude ) Accuracy of estimate

- 50 % to + 75 % or -25 % to +75 %

**** Parametric Estimate ( Budgetary)

• Is used in project Planning when more details are available.

• ( Budgetary estimate ) Accuracy of estimate is

-10 % to +25 % or -25% to +25%

Page 15: Pmp cost chapter 7

15

**** Bottom-Up Estimating

• Creating detailed estimates for each part of an activity (if

available) or work package (if activities are not defined).

• Accurate WBS is needed.

• Applied before project execution.

• ( Definitive estimate ) Accuracy of estimate is

-5 % to +10 % or -10 % to +10 %

• Takes time and more costly.

• Based on details

Page 16: Pmp cost chapter 7

16

GANTT Chart tells the progress of each activity

Page 17: Pmp cost chapter 7

17

Acronym Term Interpretation

PV Planed Value Authorized budget for work scheduled

EV Earned Value Budget cost for work done.

AC Actual Cost Actual cost incurred for the work accomplished.

BACBudget At

CompletionBudget for the total project effort.

EACEstimate At

CompletionExpectation of the total project to cost (a forecast).

ETCEstimate To

Complete

How much more do we expect it to cost to finish the

project (a forecast) ?

VACVariance At

Completion

How much over or under budget do we expect to be at

the end of the project?

**** Earned Value Management

• EVM is a Project Performance Measurement technique that

integrates scope, time, & cost data.

Page 18: Pmp cost chapter 7

CV ( Cost Variance )

The difference between Earned Value and Actual Cost

Negative value = Cost Overrun or over budget

Positive value = on or under cost or under budget

Are we under or over budget 1.0 or greater is good

EV = Earned Value

AC = Actual Costs

CV = EV – AC

18

Page 19: Pmp cost chapter 7

SV ( Schedule Variance )

The difference between Earned Value and Planned Value

Negative value = behind schedule

Positive value = on or ahead of schedule

Are we ahead or behind schedule 1.0 or greater is good

EV = Earned Value

PV = Planned Value

SV = EV – PV

19

Page 20: Pmp cost chapter 7

CPI - Cost Performance Index

The ratio of Earned Value to Actual Cost

Value < 1 = Cost over budget

Value > 1 = Cost below budget

How efficiently are we using our resources

Ex: We are only getting about 89 cents out of every dollar we put into the project – THIS IS BAD

EV = Earned Value

AC = Actual Costs

CPI = EV / AC

20

Page 21: Pmp cost chapter 7

SPI - Schedule Performance Index

The ratio of Earned Value to Planned Value

Value < 1 = behind schedule

Value > 1 = on or ahead of schedule

How efficiently are we using time

Ex: We are only progressing at about 83 percent of the rate planned – THIS IS BAD

EV = Earned Value

PV = Planned Value

SPI = EV / PV

21

Page 22: Pmp cost chapter 7

22

Estimate At Completion

Budget At Completion

Variance At

Completion

Page 23: Pmp cost chapter 7

EAC – Estimate At Completion

The ratio of Budget at Completion to Cost Performance Index

This formula is used if no variances from the BAC have occurred

This formula is used if you will continue typically at the same rate of spending ( same performance ).

Default way if exam mentioned nothing.

Past performance will be typically in future.

EAC = BAC / CPI

32

Page 24: Pmp cost chapter 7

EAC – Estimate At Completion

This formula calculates actual costs to date + a new estimate for the remaining work.

It is used when the original estimate was fundamentally flawed.

It is used when your plan is no longer valid

EAC = AC+ ETC (bottom-up)

24

Page 25: Pmp cost chapter 7

EAC – Estimate At Completion

This formula calculates Actual Costs + Remaining Budget.

It is used when current variances are thought to be atypicalof the future.

It is used if you will follow plan.

It accepts the actual project performance to date (whether favorable or unfavorable)

EAC = AC+ (BAC ـــ EV)

25

Page 26: Pmp cost chapter 7

EAC – Estimate At Completion

ETC work will be performed at an efficiency rate that

considers both the cost and schedule performance.

It is used when current variances are thought to be typicalof the future and when project schedule constraints will influence the completion of the remaining effort.

example, it might be used when the cumulative CPI is less than one and a firm completion date must be met.

EAC = AC+ BAC - EV

CPI X SPI

26

Page 27: Pmp cost chapter 7

To-Complete Performance Index (TCPI)

If CPI > 1

If CPI < 1

This formula divides the work remaining to be done by the money remaining to do it.

It answers the question "In order to stay within budget, what rate must we meet for the remaining work?"

Greater than one is bad and less than 1 is good.

TCPI = BAC - EV

BAC - AC

TCPI = BAC - EV

EAC - AC

27

Page 28: Pmp cost chapter 7

VAC -Variance at Completion

The difference between the Budget at Completion and the Estimate at Completion ratio.

This is a variance formula.

Ex : As of today will we be under or over budget at the end of the project

VAC = BAC ـــ EAC

28

Page 29: Pmp cost chapter 7

29

QUIZ

A project is estimated to cost $ 50,000 with a timeline of 50

days. After 25 days, the project manager finds that 50% of

the project is complete and Actual costs are $ 50,000. What

is the Cost Performance Index (CPI) ?

A. The CPI is 1

B. The CPI is 2

C. The CPI is 0.5

D. The CPI is 1.5

Page 30: Pmp cost chapter 7

30

QUIZ

A project is estimated to cost $ 50,000 with a timeline of 50

days. After 25 days, the project manager finds that 50% of

the project is complete and Actual costs are $ 50,000. What

is the Cost Performance Index (CPI) ?

A. The CPI is 1

B. The CPI is 2

C. The CPI is 0.5

D. The CPI is 1.5

Answer : C

Page 31: Pmp cost chapter 7

31

Task Progress Cost spent

Side 1 ||||||||||||||||||||||||||||||||||||||||100% $1,200

Side 2 ||||||||||||||||||||||||||||||||||||||||100% $1,000

Side 3 ||||||||||||||||||||||||||||||75% $750

Side 4 ||||||||||||||||||||50% $500

Side 5 0% $0

Side 6 0% $0

Question

You have a project to build a box. The box is six sided. Each side is to take

one day to build and is budgeted for $1000 per side. The sides are

planned to be completed one after the other. Today is the end of day

three.

• Using the following project status chart, calculate PV, EV, AC, BAC,

CV, CPI, SV, SPI, EAC, ETC, VAC.

Page 32: Pmp cost chapter 7

32

Parameter Calculation Result

PV 1000 + 1000 + 1000 3000

EV (100% x 1000) + (100% x 1000) + (75% x 1000) + (50% x 1000) 3250

AC 1200 + 1000 + 750 + 500 3450

BAC 6 x 1000 6000

CV EV – AC = 3250 - 3450 -200

CPI EV / AC = 3250 / 3450 0.942

SV EV – PV = 3250 - 3000 250

SPI EV / PV = 3250/ 3000 1.08

EAC BAC / CPI = 6000 / 0.942 6369.42

ETC EAC – AC = 6369.42 - 3450 2919.42

VAC BAC – EAC = 6000 – 6369.42 -369.42

• Over budget, getting 0.94 dollar for every dollar we spent,

• Ahead schedule, progressing 108% of the rate planned,

• Probably will spend $6369.42 at the end (estimation),

• Need $2919.42 to complete,

• Over budget at the end for about $369.42 (estimation)

Page 33: Pmp cost chapter 7

7.1- Plan Cost Management

33

Page 34: Pmp cost chapter 7

34

7.1- Plan Cost Management.

The process that establishes the policies, procedures, and

documentation for planning, managing, expending, and

controlling project costs.

Page 35: Pmp cost chapter 7

35

Page 36: Pmp cost chapter 7

7.1- Plan Cost Management INPUTS

36

1. Project

Management Plan

Scope Baseline

Schedule Baseline

2. Project Charter

3- EEF

4- OPA

7.1- Plan Cost Management T & T

1. Expert Judgment

1. Analytical Techniques

1. Meetings

Page 37: Pmp cost chapter 7

7.1- Plan Cost Management OUTPUTS

37

Co

st

Man

ag

em

en

tP

lan

• Units of Measure staff hours, staff days, meters, liters,

tons, kilometers

• Level of Precision (measure of exactness)

• Level of Accuracy (assessment of correctness)

• Control Accounts

• Control Thresholds (Percentage deviations from the

baseline plan.)

• Rules for Performance Measurement

Specify tracking methodologies

Earned value measurement techniques

Earned value management computation equations

• Reporting Formats (cost reports)

• Process Description

• Additional Details

Page 38: Pmp cost chapter 7

7.2- Estimate Cost

38

Page 39: Pmp cost chapter 7

39

7.2 Estimate Costs

The process of developing an approximation of the

monetary resources needed to complete project activities.

Page 40: Pmp cost chapter 7

40

Page 41: Pmp cost chapter 7

7.2- Estimate Cost INPUTS

41

1. Cost Management Plan

2. Human Resource Management Plan

3. Scope BaselinesScope Statement / WBS /

WBS Dictionary

4. Project Schedule

5. Risk Register (Risk mitigation costs)

6. EEF Market Conditions

Published Commercial Data

7- OPA

Cost Estimating Policies

Cost Estimating Templates

Historical Information

Lessons Learned

Page 42: Pmp cost chapter 7

7.2- Estimate Cost T & T

42

1. Expert Judgment

2. Analogous Estimating (Top down)

3. Parametric Estimating

4. Bottom-up estimating

5. Three-point

Estimation

(Beta Distribution) Weighted Average (P+4M+O) / 6

(Triangular Distribution) ( P+M+O ) / 3

6. Reserve

Analysis

• Contingency Reserve ( Known Unknown ) by project

manager for activities

• Management Reserve ( Unknown Unknown ) by

management for whole project

7. Cost Of

Quality

• Cost Of Conformance

• Cost Of Non Conformance

8. PMIS

9. Group Decision making techniques: Unanimity, Majority (>50%),

Plurality, Dictatorship

10. Vendor Bid analysis

Page 43: Pmp cost chapter 7

7.2- Estimate Cost Outputs

43

1. Activity Cost Estimates

2. Basis of Estimates

• how the cost estimate was derived

• Documentation of :

Assumptions

Known constraints

Range of possible estimates

3. Project Documents Updates

Page 44: Pmp cost chapter 7

44

7.3- Determine Budget

Page 45: Pmp cost chapter 7

45

7.3- Determine Budget

The process of aggregating the estimated costs of individual

activities or work packages to establish an authorized cost

baseline

Page 46: Pmp cost chapter 7

46

Page 47: Pmp cost chapter 7

7.3- Determine Budget INPUTS

47

1. Cost Management Plan

2. Scope Baseline

3. Activity Costs Estimates

4. Basis of Estimates

5. Project Schedule

6. Resource

Calendars

which resources are assigned to the project and

when they are assigned

7. Risk Register

8. Agreements

9. OPA

• Existing formal and informal cost budgeting-

related policies, procedures, and guidelines.

• Cost budgeting tools.

• Reporting methods.

Page 48: Pmp cost chapter 7

7.3- Determine Budget T & T

48

1. Cost Aggregation

2. Reserve Analysis

3. Expert Judgment

4. Historical

Relationships

• Historical information used to develop the model.

• Parameters used in the model are readily quantifiable.

5. Funding

Limit

Reconciliation

When to supply the fund needed on time along with the

work being done

Page 49: Pmp cost chapter 7

7.3- Determine Budget Outputs

49

1. Cost Baselinethe approved version of the time-phased project

budget

Known UnknownUnknown Unknown

This is the level of divisions to track measurement

Page 50: Pmp cost chapter 7

7.3- Determine Budget Outputs

50

2. Project

Funding

Requirements

When I will provide fund supply to work being done

Page 51: Pmp cost chapter 7

51

7.4- Control Cost

Page 52: Pmp cost chapter 7

52

7.4- Control Cost.

The process of monitoring the status of the project to

update the project costs and managing changes to the cost

baseline

Page 53: Pmp cost chapter 7

53

Page 54: Pmp cost chapter 7

7.4- Control Cost INPUTS

54

1. Project Management

Plan

• Cost Baseline

• Cost Management Plan

2. Project Funding Requirements

3. Work Performance Data

4. OPA

1. Earned Value Management

2. Forecasting

3. To-Complete Performance Index

4. Performance Reviews

• Variance Analysis

• Trend Analysis

• Earned Value Performance

5. Reserve Analysis

6. PMIS

7.4- Control Cost T & T

Page 55: Pmp cost chapter 7

7.4- Control Cost Outputs

55

1. Work Performance Measurements

2. Budget Forecasts ( EAC / ETC )

3. Change Requests

4. Project Management Plan

Updates

• Cost baseline.

• Cost management plan.

5. OPA Updates

6. Project Document Updates • Cost estimates, and

• Basis of estimates.

Page 56: Pmp cost chapter 7

56

Questions

l. One common way to compute estimate at completion

(EAC) is to take the budget at completion BAC

and:

• A. Divide by SPI.

• B. Multiply by SPI.

• C. Multiply by CPI.

• D. Divide by CPI.

• Answer : D

Page 57: Pmp cost chapter 7

57

Questions

2. Estimate at completion (EAC) is a periodic evaluation of:

A. The cost of work completed.

B. The value of work performed.

C. The anticipated total cost at project completion.

D. What it will cost to finish the project.

• Answer : C

Page 58: Pmp cost chapter 7

58

Questions

3. If earned value (EV) = 350, actual cost (AC) = 400, and

planned value (PV) = 325,

what is cost variance (CV)?

A. 350

B. -75

c. 400

D. -50

• Answer : D

Page 59: Pmp cost chapter 7

59

Questions

4. Analogous estimating:

A. Uses bottom-up estimating techniques.

B. Is used most frequently during project executing.

C. Uses top-down estimating techniques.

D. Calculates estimates using actual detailed historical

costs.

• Answer : C

Page 60: Pmp cost chapter 7

60

Questions

5. A cost performance index (CPI) of 0.89 means:

A. At this time, we expect the total project to cost 89

percent more than planned.

B. When the project is completed, we will have spent 89

percent more than planned.

C. The project is progressing at 89 percent of the rate

planned.

D. The project is getting 89 cents out of every dollar

invested.

• Answer : D

Page 61: Pmp cost chapter 7

61

Questions

6. A schedule performance index (SPI) of 0.76 means:

A. You are over budget.

B. You are ahead of schedule.

C. You are progressing at 76 percent of the rate originally

planned.

D. You are progressing at 24 percent of the rate originally

planned.

• Answer : C

Page 62: Pmp cost chapter 7

62

Questions

7. Which type of cost is team training?

A. Direct

B. NPV

C. Indirect

D. Fixed

• Answer : A

Page 63: Pmp cost chapter 7

63

Questions

8. Project setup costs are an example of:

A. Variable costs.

B. Fixed costs.

C. Overhead costs.

D. Opportunity costs.

• Answer : B

Page 64: Pmp cost chapter 7

64

Questions

9. The project manager is allocating overall cost estimates

to individual activities to establish a baseline for measuring

project performance. What process is this?

A. Cost Management

B. Estimate Costs

C. Determine Budget

D. Control Costs

• Answer : C

Page 65: Pmp cost chapter 7

65

Questions

10. You provide a project cost estimate for the project to the

project sponsor. He is unhappy with the estimate, because

he thinks the price should be lower. He asks you to cut 15

percent off the project estimate. What should you do?

A. Start the project and constantly look for cost savings.

B. Tell all the team members to cut 15 percent from their

estimates.

C. Inform the sponsor of the activities to be cut.

D. Add additional resources with low hourly rates.

• Answer : C

Page 66: Pmp cost chapter 7

66

11. Lucy is currently preparing a high-level cost estimate for

her project in the initiation phase. Given the limited detail

available to her, what would you expect the range of her

estimate to be and what would you call such an estimate?

A. -25 to +75 %, Rough Order of Magnitude.

B. -5 to +10 %, Narrow.

C. 25 to +25 %, Rough Order of Magnitude.

D. -1 to +1 %, Definitive.

Questions

Page 67: Pmp cost chapter 7

67

11. Lucy is currently preparing a high-level cost estimate for

her project in the initiation phase. Given the limited detail

available to her, what would you expect the range of her

estimate to be and what would you call such an estimate?

A. -25 to +75 %, Rough Order of Magnitude.

B. -5 to +10 %, Narrow.

C. 25 to +25 %, Rough Order of Magnitude.

D. -1 to +1 %, Definitive.

Answer : A

Questions

Page 68: Pmp cost chapter 7

68

12. The Cost Performance Baseline is a time-phased

budget and is used as a basis to measure, monitor, and

control overall cost performance of the project. It is usually

displayed in the form of:

A. Pie-chart

B. An inverted S curve.

C. A Z curve

D. An S-curve

Questions

Page 69: Pmp cost chapter 7

69

12. The Cost Performance Baseline is a time-phased

budget and is used as a basis to measure, monitor, and

control overall cost performance of the project. It is usually

displayed in the form of:

A. Pie-chart

B. An inverted S curve.

C. A Z curve

D. An S-curve

Answer : D

Questions

Page 70: Pmp cost chapter 7

70

13. Contingency Reserves are estimated costs to be used

at the discretion of the project manager to deal with:

A. Anticipated but not certain events.

B. Scope creep

C. Anticipated and certain events

D. Unanticipated events

Questions

Page 71: Pmp cost chapter 7

71

13. Contingency Reserves are estimated costs to be used

at the discretion of the project manager to deal with:

A. Anticipated but not certain events.

B. Scope creep

C. Anticipated and certain events

D. Unanticipated events

Answer : A

Questions