PMP 02 Project Scope Management

65
PMP - Project Scope Management 1 Project Scope Management Based on PMBOK 5 th Edition Abdelrahman Sheta, PMP,ITIL facebook.com/ Sheta.Page

description

PMP 02 Project Scope Management

Transcript of PMP 02 Project Scope Management

Page 1: PMP 02 Project Scope Management

PMP - Project Scope Management 1

Project Scope ManagementBased on PMBOK 5th Edition

Abdelrahman Sheta, PMP,ITIL

facebook.com/Sheta.Page

Page 2: PMP 02 Project Scope Management

Introduction to Project Scope

Plan Scope Management

Collect Requirements

Define Scope

Create WBS

Control Scope

Validate ScopePMP - Project Scope Management 2

Agenda

facebook.com/Sheta.Page

Page 3: PMP 02 Project Scope Management

Scope refers to all the work involved in

creating the deliverables of the project

and the processes used to create them.

Project scope management includes the

processes required to ensure that the

project includes all the work required,

and only the work required, to complete

the project successfully.

What is Project Scope?

PMP - Project Scope Management 3facebook.com/Sheta.Page

Page 4: PMP 02 Project Scope Management

Product scope: The futures & functions that

characterize the product, service, or result.

Project Scope: The work that needs to

be accomplished to deliver a product,

service, or result with the specified

features and functions.

Product Scope vs. Project Scope

PMP - Project Scope Management 4facebook.com/Sheta.Page

Page 5: PMP 02 Project Scope Management

PMP - Project Scope Management 5facebook.com/Sheta.Page

Page 6: PMP 02 Project Scope Management

The process of creating a scope management plan that documents how the project scope will be defined, validated, and controlled.

It provides guidance and direction on scopewill be managed.

5.1 Plan Scope Management

PMP - Project Scope Management 6facebook.com/Sheta.Page

Page 7: PMP 02 Project Scope Management

Plan Scope Management DataFlow

PMP - Project Scope Management 7facebook.com/Sheta.Page

Page 8: PMP 02 Project Scope Management

1. Project Management Plan: it defines how the project is executed, monitored, controlled and closed. It integrates all plan components.

2. Project Charter

3. Enterprise Environmental Factors

4. Organizational Process Assets

PMP - Project Scope Management 8

Plan Scope Management: Inputs

facebook.com/Sheta.Page

Page 9: PMP 02 Project Scope Management

1. Expert Judgment: knowledgeable and

experiences parties.

2. Meetings.

PMP - Project Scope Management 9

Plan Scope Management: T & T

facebook.com/Sheta.Page

Page 10: PMP 02 Project Scope Management

1. Scope Management Plan. It includes:

Process for preparing a detailed project scope statement.

Process to enable the creation of WBS Process to establish how the WBS will

bemanaged

Define formal acceptance criteria

of deliverables How change requests will be

applied to scope

PMP - Project Scope Management

Plan Scope Management: Output

10facebook.com/Sheta.Page

Page 11: PMP 02 Project Scope Management

2. Requirements Management Plan: describes how requirements will be analyzed, documented, and managed. It includes, but not limited to:

How requirements activities will be planned,tracked and reported.

Configuration management activities. Requirements prioritization process. Product metrics Traceability structurePMP - Project Scope Management 11

Plan Scope Management: Output (2)

facebook.com/Sheta.Page

Page 12: PMP 02 Project Scope Management

Which is the BEST description of project scope?

A. All of the features and deliverables your project will deliver

B. All of the products your project will make

C. All of the people involved in your project

D. All of the work you will do to build the project deliverables

Quiz

PMP - Project Scope Management 12facebook.com/Sheta.Page

Page 13: PMP 02 Project Scope Management

The process of determining, documenting and managing stakeholder needs to meet project objectives.

The key benefit is to provide the basis fordefining and managing project scope.

Requirements includes the quantified and documented needs and expectations of the sponsor, customer, and other stakeholders.

Requirement must be analyzed and recorded ina clear and detailed way to be measured.

5.2 Collect requirements

PMP - Project Scope Management 13facebook.com/Sheta.Page

Page 14: PMP 02 Project Scope Management

Requirements can be grouped into classifications including: Business requirements, describe the high-level

needs of the organization as a whole. Stakeholder requirements, describe needs of a

stakeholder or stakeholder group. Solution requirements, describe features,

functions and characteristics of the product, service, or results.

Transition requirements, describe temporary capabilitiessuch as data conversion & training needs.

PMP - Project Scope Management 14

5.2 Collect requirements (2)

facebook.com/Sheta.Page

Page 15: PMP 02 Project Scope Management

Coll

ect

Req

uir

em

en

ts D

ata

F

low

PMP - Project Scope Management 15facebook.com/Sheta.Page

Page 16: PMP 02 Project Scope Management

PMP - Project Scope Management 16facebook.com/Sheta.Page

Page 17: PMP 02 Project Scope Management

1. Project Scope Management Plan

2. Requirements Management Plan

3. Stakeholder Management Plan

4. Project Charter

5. Stakeholder Register

Collect Requirements: Inputs

PMP - Project Scope Management 17facebook.com/Sheta.Page

Page 18: PMP 02 Project Scope Management

1. Interviews: meeting the stakeholders to ask prepared and spontaneous question & recording the responses.

Collect Requirements: T & T (1)

PMP - Project Scope Management 18facebook.com/Sheta.Page

Page 19: PMP 02 Project Scope Management

2. Focus groups: bring together stakeholders and subject matter experts to learn about their expectations and attitudes about a proposed product,

service or result.

Collect Requirements: T & T (1)

PMP - Project Scope Management 19facebook.com/Sheta.Page

Page 20: PMP 02 Project Scope Management

Collect Requirements: T & T (2)

3. Facilitated Workshops: Focused session with key cross-functional stakeholders to define product requirements.

4. Group Creativity Techniques: Brainstorming Nominal Group Idea/Mind Mapping Affinity Diagram Multi-criteria decision analysis

PMP - Project Scope Management 20facebook.com/Sheta.Page

Page 21: PMP 02 Project Scope Management

Mind Map

PMP - Project Scope Management 21facebook.com/Sheta.Page

Page 22: PMP 02 Project Scope Management

Affinity Diagram

PMP - Project Scope Management 22facebook.com/Sheta.Page

Page 23: PMP 02 Project Scope Management

5. Group Decision Making Techniques Unanimity Majority Plurality Dictatorship

6. Questionnaire and Surveys

7. Observations

8. Prototypes

Collect Requirements: T & T (3)

PMP - Project Scope Management 23facebook.com/Sheta.Page

Page 24: PMP 02 Project Scope Management

9. Benchmarking

10.Context Diagrams

11.Document Analysis

Collect Requirements: T & T (4)

PMP - Project Scope Management 24facebook.com/Sheta.Page

Page 25: PMP 02 Project Scope Management

1. Requirements Document

Business Requirements

Stakeholder requirements

Solution requirements

Project requirements

Transition requirements

2. Requirements Traceability Matrix

Collect Requirements: Outputs

PMP - Project Scope Management 25facebook.com/Sheta.Page

Page 26: PMP 02 Project Scope Management

Sample Requirements Traceability Matrix

PMP - Project Scope Management 26facebook.com/Sheta.Page

Page 27: PMP 02 Project Scope Management

The best tool in collecting requirements for across-functional project is:

A. Facilitated Workshops

B. Interviews

C. Surveys

D. Brainstorming

Quiz

PMP - Project Scope Management 27facebook.com/Sheta.Page

Page 28: PMP 02 Project Scope Management

The process of developing a detailed descriptionof the project and product.

5.3 Define Scope

PMP - Project Scope Management 28facebook.com/Sheta.Page

Page 29: PMP 02 Project Scope Management

Define Scope Data Flow

PMP - Project Scope Management 29facebook.com/Sheta.Page

Page 30: PMP 02 Project Scope Management

1. Scope Management Plan

2. Project charter

3. Requirements Document

4. Organizational Process Assets Procedures & Templates

Historical Data

Lessons learned from old Projects

Define Scope: Inputs

PMP - Project Scope Management 30facebook.com/Sheta.Page

Page 31: PMP 02 Project Scope Management

1. Expert Judgment

2. Product Analysis

3. Alternatives Identification

4. Facilitated workshops

Define Scope: T & T

PMP - Project Scope Management 31facebook.com/Sheta.Page

Page 32: PMP 02 Project Scope Management

1. Scope Statement: describes project’s deliverables and the work required to create those deliverables. It includes

Product scope description

Deliverables’ Acceptance Criteria

Project Deliverables

Project Exclusion

Project Assumptions

Constraints

Define Scope: Outputs (1)

PMP - Project Scope Management 32facebook.com/Sheta.Page

Page 33: PMP 02 Project Scope Management

Elements

of Project

Charter

and Scope

Statement

PMP - Project Scope Management 33facebook.com/Sheta.Page

Page 34: PMP 02 Project Scope Management

2. Project Documents Updates: may include,

but not limited to:

Stakeholder register

Requirements Documents

Requirements Traceability Matrix

Define Scope: Outputs (2)

PMP - Project Scope Management 34facebook.com/Sheta.Page

Page 35: PMP 02 Project Scope Management

Why would you consider the scope statement so important in your project management methodology?

A. Mandatory to consult the plan before accepting change.

B. Project managers must document any changes before approving or declining them.

C. The project scope serves as a reference for all futureproject decisions.

D. The scope statement is the base of WBS creation

Quiz

PMP - Project Scope Management 35facebook.com/Sheta.Page

Page 36: PMP 02 Project Scope Management

Subdividing the project

deliverables and project work into

smaller and more manageable

components.

The work breakdown

structure is a deliverable-

oriented hierarchical

decomposition of project

work.

5.4 Create WBS

PMP - Project Scope Management 36facebook.com/Sheta.Page

Page 37: PMP 02 Project Scope Management

CreateWBSDataFlow

PMP - Project Scope Management 37facebook.com/Sheta.Page

Page 38: PMP 02 Project Scope Management

Sample WBS

PMP - Project Scope Management 38facebook.com/Sheta.Page

Page 39: PMP 02 Project Scope Management

Sample WBS

PMP - Project Scope Management 39facebook.com/Sheta.Page

Page 40: PMP 02 Project Scope Management

Sample

WBS

PMP - Project Scope Management 40facebook.com/Sheta.Page

Page 41: PMP 02 Project Scope Management

1. Scope Management Plan

2. Project Scope Statement

3. Requirements Document

4. Enterprise Environmental Factors

5. Organizational Process Assets

Create WBS: Inputs

PMP - Project Scope Management 41facebook.com/Sheta.Page

Page 42: PMP 02 Project Scope Management

1. Decomposition: The subdivision of project deliverables into smaller, more manageable components. The work package level is the lowest level in the WBS, and is the point at which the cost an activity durations can be reliably estimated and managed. The level of detail for work packages will vary with the size and complexity of the project.

2. Expert Judgment

Create WBS: T & T

PMP - Project Scope Management 42facebook.com/Sheta.Page

Page 43: PMP 02 Project Scope Management

1. Scope Baseline

Project Scope Statement

WBS

WBS Dictionary

2. Project Documents updates

PMP - Project Scope Management 43

Create WBS: Outputs

facebook.com/Sheta.Page

Page 44: PMP 02 Project Scope Management

WBS Dictionary may include (but not limited to)

Code of Account Identifier Description of work Assumptions and Constraints Schedule Milestone Resource required Cost Estimate Acceptance criteria Quality Requirements

Create WBS: Outputs (2)

PMP - Project Scope Management 44facebook.com/Sheta.Page

Page 45: PMP 02 Project Scope Management

Control

Account

s, Work

Package

s and

Activitie

s PMP - Project Scope Management 45facebook.com/Sheta.Page

Page 46: PMP 02 Project Scope Management

A work breakdown structure numbering system allows project staff to:

A. Systematically estimate costs of work breakdown structure elements.

B. Provide project justification

C. Identify the level at which individual elements arefound

D. Use it in project management software

Quiz

PMP - Project Scope Management 46facebook.com/Sheta.Page

Page 47: PMP 02 Project Scope Management

Which of the following documents contain detailed

descriptions of work packages?

A. Work breakdown structure (WBS) dictionary

B. Activity list

C. Preliminary project scope statement

D. Project scope management plan

Quiz

PMP - Project Scope Management 47facebook.com/Sheta.Page

Page 48: PMP 02 Project Scope Management

The work breakdown structure can best be thought of as an effective aid for communication

A. Team

B. PMO

C. Customer

D. Stakeholders

Quiz

PMP - Project Scope Management 48facebook.com/Sheta.Page

Page 49: PMP 02 Project Scope Management

5.5 Validate Scope Formalizing acceptance of the completed

• project deliverables.

Includes reviewing deliverables with the client

and obtaining formal acceptance of

deliverables.

Scope verification is concerned with

acceptance of deliverables while quality

control is concerned with correctness of the

deliverables and meeting quality

requirements.PMP - Project Scope Management 49facebook.com/Sheta.Page

Page 50: PMP 02 Project Scope Management

PMP - Project Scope Management 50facebook.com/Sheta.Page

Page 51: PMP 02 Project Scope Management

Validate Scope: Data Flow Diagram

PMP - Project Scope Management 51facebook.com/Sheta.Page

Page 52: PMP 02 Project Scope Management

1. Project Management Plan

2. Requirements Documentation

3. Requirements Traceability Matrix

4. Validated Deliverables

5. Work Performance Data

Validate Scope: Inputs

PMP - Project Scope Management 52facebook.com/Sheta.Page

Page 53: PMP 02 Project Scope Management

1. Inspection: measuring, examining, and

validating to determine whether work

and deliverables meet requirements

and product acceptance criteria.

Inspections may be called reviews,

audits, and walkthroughs.

2. Group Decision Making Techniques

Validate Scope: T & T

PMP - Project Scope Management 53facebook.com/Sheta.Page

Page 54: PMP 02 Project Scope Management

1. Accepted Deliverables

2. Change Requests

3. Work Performance Information

4. Project Document Updates

Validate Scope: Outputs

PMP - Project Scope Management 54facebook.com/Sheta.Page

Page 55: PMP 02 Project Scope Management

Which of the following is an output of

scope verification?

A. WBS template

B. Rework

C. Formal acceptance

D. SOW acceptance

Quiz

PMP - Project Scope Management 55facebook.com/Sheta.Page

Page 56: PMP 02 Project Scope Management

Monitoring the status of the project &products scope

Managing changes to scope baseline Ensure all requested changes and

recommended corrective or preventive actions are processed through the “Perform Integrated Change Control” process.

Uncontrolled changes are often referred to as project scope creep.

5.6 Control Scope

PMP - Project Scope Management 56facebook.com/Sheta.Page

Page 57: PMP 02 Project Scope Management

PMP - Project Scope Management 57facebook.com/Sheta.Page

Page 58: PMP 02 Project Scope Management

Contr

ol

Scope

Data

FlowPMP - Project Scope Management 58facebook.com/Sheta.Page

Page 59: PMP 02 Project Scope Management

1. Project Management Plan

Scope baseline

Scope management plan

Change management plan

Configuration management plan

Requirements management plan

2. Requirements Documentation

Control Scope: Inputs (1)

PMP - Project Scope Management 59facebook.com/Sheta.Page

Page 60: PMP 02 Project Scope Management

3. Requirements Traceability Matrix

4. Work Performance Data

5. Organizational Process Assets

Control Scope: Inputs (2)

PMP - Project Scope Management 60facebook.com/Sheta.Page

Page 61: PMP 02 Project Scope Management

1. Variance Analysis

Analyze performance measurements to

assess the variation from the baseline

scope. Analysis should determine the

cause and degree of variance.

Control Scope: T & T

PMP - Project Scope Management 61facebook.com/Sheta.Page

Page 62: PMP 02 Project Scope Management

1. Work Performance Information

2. Change Requests

3. Project Management Plan Updates

4. Project Document Updates

5. Organizational Process Asset Updates

Control Scope: Outputs

PMP - Project Scope Management 62facebook.com/Sheta.Page

Page 63: PMP 02 Project Scope Management

During a project team meeting, a team member suggests an enhancement to the scope that is beyond the scope of the project charter. The project manager points out that the team needs to concentrate on completing all the work and only the work required. This is an example of:

A. Change management process.

B. scope management.

C. quality analysis.

D. scope decomposition.

Quiz

PMP - Project Scope Management 63facebook.com/Sheta.Page

Page 64: PMP 02 Project Scope Management

Which of the following is the KEY attribute of scope

validation?

A. More complete project scope management plan

B. Customer acceptance of project deliverables

C. Improved schedule estimates

D. An improved project management

information system.

Quiz

PMP - Project Scope Management 64facebook.com/Sheta.Page

Page 65: PMP 02 Project Scope Management

PMP - Project Scope Management 65facebook.com/Sheta.Page