PMGSY INSPECTION REPORT Name of the Scheme :- …
Transcript of PMGSY INSPECTION REPORT Name of the Scheme :- …
PMGSY INSPECTION REPORT
1) Name of the Scheme :- Construction/M.T/Black Topping of a road from L026 to Chyrmang
2) Date of Inspection :- 01-11-2018
3) Details of Location :- i) Village – Chyrmang
ii) Block – Thadlaskein
iii) District –West JaintiaHills
4) Year of Sanctioned :- 2014-2015
5) Amount Sanctioned :- Rs.186.00(L)
kl
6) Maintenance Cost:- Rs.16.92 (L)
7) Amount Utilized till date/completion :- Rs.185.97(L)
8) Date of commencement of the work :- 09-11-2015
9) Target date of completion :- 30-06-2016
10) Date of completion :- Jan, 2018
11) Physical progress of the work till date :-100%
completed
12) Name of the executing agency :- Executive Engineer (T/C),
PWD (R), DPIU, Jowai.
13) Whether there is any revised estimate :- Nil
14) The quality of construction of the road and side
drain:- Good
15) Earth cutting of the road and side drain :-Good
16) The length of the motorable road connecting from
L026 to Chyrmang village is 4.00 KM.
17) Formation width of the road:- 6.00 metres
Completed Black Topped road
rrrrrrrrrrrrrrrrrrroadkkkletrfffffed
with Black Topped
Pucca side drain
Guard Wall
Black Topped
18) Carriage way width of the road :- 3.00 metres.
19) Number of Habitations covered:- 1 (One)
20) Impact of the scheme: - With good road
connectivity there is an overall development in
the socio - economic conditions of the people
living in the rural areas by way of transportation
of agricultural and forest products to the market .
21) Problem faced by the Department in
implementing the scheme, if any:- Nil
22) Observations :- The Inspection Team found that:-
MBT level = 2.8 km
Kuccha side drain=(80*80cm).
26 Nos. of Hume Pipe Culvert, inner dia-
1000mm, outer dia-1200 mm.
CC Side Drain- 400mts length, 60 cm width,
60 cm height.
Informatory Signboard and Kilometer Stone
have been erected.
Though the work was 100% completed in
January, 2018 but the same has not been
written on the Signboard.
23) Suggestions:- The EE, PMGSY was advised to instruct the Contractor concerned to write
the actual date of completion on the signboard.
Sign Sign Board
of the road
Hume PipePipe
Signboard
BBBBBOARD
HumpipePip
e
PMGSY INSPECTION REPORT
1) Name of the Scheme :- Construction/M.T/Black Topping of a road from L024 to Chyrmang
2) Date of Inspection :- 01-11-2018
3) Details of Location :- i) Village – Chyrmang
ii) Block – Thadlaskein
iii) District –West Jaintia Hills
4) Year of Sanctioned :- 2014-2015
5) Amount Sanctioned :- Rs.71.22(L)
kl
6) Maintenance Cost:- Rs.7.224 (L)
7) Amount Utilized till date/completion :- Rs.68.92(L)
8) Date of commencement of the work :- 26-04-2014
9) Target date of completion :- 31-12-2015
10) Date of completion :- 29-4-2017
11) Physical progress of the work till date :-100%
completed
12) Name of the executing agency :- Executive Engineer
(T/C), PWD (R), DPIU Jowai.
13) Whether there is any revised estimate :- Nil
14) The quality of construction of the road and side drain:-
Good
15) Earth cutting of the road and side drain :- Good
16) The length of the motorable road connecting from
Syntuksiar to Chyrmang village is 1.50 KM.
Black Topped Road
Kilometer Stone
Completed Road
17) Formation width of the road:-6.00 metres
18) Carriage way width of the road :-3.00 metres.
19) Number of Habitations covered:- 1 (One)
20) Impact of the scheme: - With good road
connectivity there is an overall development in
the socio - economic conditions of the people
living in the rural areas by way of transportation
of agricultural and forest products to the market.
21) Problem faced by the Department in implementing the scheme, if any:- Nil
22) Observations :- It was observed that the Signboard shows date of completion as 24/12/2015,
whereas it is completed on 29/4/2017. The Inspection Team also found that the signboard was
broken and fell on the ground. However, it was found that the quality of work done for the said
road is good.
23) Suggestions:- The EE, PMGSY who accompanied the inspection team was advised to
instruct the contractor concerned to repair and re-erect the broken Signboard in the same place
and also to write the actual date of completion on it. Five years maintenance should be started
with effect from 29-04-2017 which is the actual date of completion of the work.
Signboard
PMGSY INSPECTION REPORT
1) Name of the Scheme :- Construction/M.T/Black Topping of a road from L026 207th Km of
NH40E to Iongnoh.
2) Date of Inspection :- 01-11-2018
3) Team of Inspecting Officers:- Shri D.S.Kharpan,
Asstt. Director, Shri M.C Khonglah, ARO, Shri
R.M.G. Nongtdu, EE. accompanied by Smt. A.
Phawa, EE, Shri C.W. Kynjing, AE, and Shri
S.Pashiang from PWD, (Rds) PMGSY.
4) Details of Location :- i)Village – Iongnoh
ii) Block – Thadlaskein
iii) District –West Jaintia Hills
5) Year of Sanction :- 2012-2013
6) Amount Sanction :- Rs. 292.17(L)
kl
7) Maintenance Cost:- Rs.17.52 (L)
8) Amount Utilized till date/completion :-Rs.318.25 (L)
9) Date of commencement of the work :- 19-11-2013
10) Target date of completion :- 06-05-2015
11) Date of completion :- December, 2015
12) Physical progress of the work till date :-100%
completed
13) Name of the executing agency :-Executive Engineer
(T/C), PWD (R), DPIU Jowai.
14) Whether there is any revised estimate :- Nil
15) The quality of construction of the road and side
drain:- Good
Completed road
Black topped road
Hume Pipe
16) Earth cutting of the road and side drain :- Good
17) The length of the motorable road connecting from
L026 to Iongnoh village is 3.00 KM.
18) Formation width of the road:-7.00 metres
19) Carriage way width of the road :-3.75metres.
20) Number of Habitations covered:- 1 (One)
21) Impact of the scheme: - With good road
connectivity there is an overall development in
the socio - economic conditions of the people
living in the rural areas by way of transportation
of agricultural and forest products to the market.
22) Problem faced by the Department in implementing
the scheme, if any:- Nil
23) Observations :- The Inspection team observed that:-
Hume Pipe, Earthwork, side drain, bridge and
guard wall were done at Stage I.
Metalling and Black Topping were done at Stage II.
11 numbers of Hume pipes/ Culverts.
2(two) numbers of RCC bridge culverts.
1(one) number of causeway bridge
RCC Bridge culvert-1, Span 6.70 mts width 5.40 mts., wing-wall-2.20 mts length and
3.60 mts height, Pucca Side Drain-(60*60) cms with a length of 120 mts.
24) Suggestions:- Sign board shows date of completion as 20/05/2015, whereas it is completed
in December, 2015. The EE, PMGSY was advised to write the actual date of completion on the
Signboard and 5 (five) years maintenance should start with effect from the actual date of
completion of the work.
Guard Wall and RCC Bridge
Signboard