PMGSY INSPECTION REPORT Name of the Scheme :- …

6
PMGSY INSPECTION REPORT 1) Name of the Scheme :- Construction/M.T/Black Topping of a road from L026 to Chyrmang 2) Date of Inspection :- 01-11-2018 3) Details of Location :- i) Village Chyrmang ii) Block Thadlaskein iii) District West JaintiaHills 4) Year of Sanctioned :- 2014-2015 5) Amount Sanctioned :- Rs.186.00(L) 6) Maintenance Cost:- Rs.16.92 (L) 7) Amount Utilized till date/completion :- Rs.185.97(L) 8) Date of commencement of the work :- 09-11-2015 9) Target date of completion :- 30-06-2016 10) Date of completion :- Jan, 2018 11) Physical progress of the work till date :-100% completed 12) Name of the executing agency :- Executive Engineer (T/C), PWD (R), DPIU, Jowai. 13) Whether there is any revised estimate :- Nil 14) The quality of construction of the road and side drain:- Good 15) Earth cutting of the road and side drain :-Good 16) The length of the motorable road connecting from L026 to Chyrmang village is 4.00 KM. 17) Formation width of the road:- 6.00 metres Completed Black Topped road Pucca side drain Guard Wall Black Topped

Transcript of PMGSY INSPECTION REPORT Name of the Scheme :- …

Page 1: PMGSY INSPECTION REPORT Name of the Scheme :- …

PMGSY INSPECTION REPORT

1) Name of the Scheme :- Construction/M.T/Black Topping of a road from L026 to Chyrmang

2) Date of Inspection :- 01-11-2018

3) Details of Location :- i) Village – Chyrmang

ii) Block – Thadlaskein

iii) District –West JaintiaHills

4) Year of Sanctioned :- 2014-2015

5) Amount Sanctioned :- Rs.186.00(L)

kl

6) Maintenance Cost:- Rs.16.92 (L)

7) Amount Utilized till date/completion :- Rs.185.97(L)

8) Date of commencement of the work :- 09-11-2015

9) Target date of completion :- 30-06-2016

10) Date of completion :- Jan, 2018

11) Physical progress of the work till date :-100%

completed

12) Name of the executing agency :- Executive Engineer (T/C),

PWD (R), DPIU, Jowai.

13) Whether there is any revised estimate :- Nil

14) The quality of construction of the road and side

drain:- Good

15) Earth cutting of the road and side drain :-Good

16) The length of the motorable road connecting from

L026 to Chyrmang village is 4.00 KM.

17) Formation width of the road:- 6.00 metres

Completed Black Topped road

rrrrrrrrrrrrrrrrrrroadkkkletrfffffed

with Black Topped

Pucca side drain

Guard Wall

Black Topped

Page 2: PMGSY INSPECTION REPORT Name of the Scheme :- …

18) Carriage way width of the road :- 3.00 metres.

19) Number of Habitations covered:- 1 (One)

20) Impact of the scheme: - With good road

connectivity there is an overall development in

the socio - economic conditions of the people

living in the rural areas by way of transportation

of agricultural and forest products to the market .

21) Problem faced by the Department in

implementing the scheme, if any:- Nil

22) Observations :- The Inspection Team found that:-

MBT level = 2.8 km

Kuccha side drain=(80*80cm).

26 Nos. of Hume Pipe Culvert, inner dia-

1000mm, outer dia-1200 mm.

CC Side Drain- 400mts length, 60 cm width,

60 cm height.

Informatory Signboard and Kilometer Stone

have been erected.

Though the work was 100% completed in

January, 2018 but the same has not been

written on the Signboard.

23) Suggestions:- The EE, PMGSY was advised to instruct the Contractor concerned to write

the actual date of completion on the signboard.

Sign Sign Board

of the road

Hume PipePipe

Signboard

BBBBBOARD

HumpipePip

e

Page 3: PMGSY INSPECTION REPORT Name of the Scheme :- …

PMGSY INSPECTION REPORT

1) Name of the Scheme :- Construction/M.T/Black Topping of a road from L024 to Chyrmang

2) Date of Inspection :- 01-11-2018

3) Details of Location :- i) Village – Chyrmang

ii) Block – Thadlaskein

iii) District –West Jaintia Hills

4) Year of Sanctioned :- 2014-2015

5) Amount Sanctioned :- Rs.71.22(L)

kl

6) Maintenance Cost:- Rs.7.224 (L)

7) Amount Utilized till date/completion :- Rs.68.92(L)

8) Date of commencement of the work :- 26-04-2014

9) Target date of completion :- 31-12-2015

10) Date of completion :- 29-4-2017

11) Physical progress of the work till date :-100%

completed

12) Name of the executing agency :- Executive Engineer

(T/C), PWD (R), DPIU Jowai.

13) Whether there is any revised estimate :- Nil

14) The quality of construction of the road and side drain:-

Good

15) Earth cutting of the road and side drain :- Good

16) The length of the motorable road connecting from

Syntuksiar to Chyrmang village is 1.50 KM.

Black Topped Road

Kilometer Stone

Completed Road

Page 4: PMGSY INSPECTION REPORT Name of the Scheme :- …

17) Formation width of the road:-6.00 metres

18) Carriage way width of the road :-3.00 metres.

19) Number of Habitations covered:- 1 (One)

20) Impact of the scheme: - With good road

connectivity there is an overall development in

the socio - economic conditions of the people

living in the rural areas by way of transportation

of agricultural and forest products to the market.

21) Problem faced by the Department in implementing the scheme, if any:- Nil

22) Observations :- It was observed that the Signboard shows date of completion as 24/12/2015,

whereas it is completed on 29/4/2017. The Inspection Team also found that the signboard was

broken and fell on the ground. However, it was found that the quality of work done for the said

road is good.

23) Suggestions:- The EE, PMGSY who accompanied the inspection team was advised to

instruct the contractor concerned to repair and re-erect the broken Signboard in the same place

and also to write the actual date of completion on it. Five years maintenance should be started

with effect from 29-04-2017 which is the actual date of completion of the work.

Signboard

Page 5: PMGSY INSPECTION REPORT Name of the Scheme :- …

PMGSY INSPECTION REPORT

1) Name of the Scheme :- Construction/M.T/Black Topping of a road from L026 207th Km of

NH40E to Iongnoh.

2) Date of Inspection :- 01-11-2018

3) Team of Inspecting Officers:- Shri D.S.Kharpan,

Asstt. Director, Shri M.C Khonglah, ARO, Shri

R.M.G. Nongtdu, EE. accompanied by Smt. A.

Phawa, EE, Shri C.W. Kynjing, AE, and Shri

S.Pashiang from PWD, (Rds) PMGSY.

4) Details of Location :- i)Village – Iongnoh

ii) Block – Thadlaskein

iii) District –West Jaintia Hills

5) Year of Sanction :- 2012-2013

6) Amount Sanction :- Rs. 292.17(L)

kl

7) Maintenance Cost:- Rs.17.52 (L)

8) Amount Utilized till date/completion :-Rs.318.25 (L)

9) Date of commencement of the work :- 19-11-2013

10) Target date of completion :- 06-05-2015

11) Date of completion :- December, 2015

12) Physical progress of the work till date :-100%

completed

13) Name of the executing agency :-Executive Engineer

(T/C), PWD (R), DPIU Jowai.

14) Whether there is any revised estimate :- Nil

15) The quality of construction of the road and side

drain:- Good

Completed road

Black topped road

Hume Pipe

Page 6: PMGSY INSPECTION REPORT Name of the Scheme :- …

16) Earth cutting of the road and side drain :- Good

17) The length of the motorable road connecting from

L026 to Iongnoh village is 3.00 KM.

18) Formation width of the road:-7.00 metres

19) Carriage way width of the road :-3.75metres.

20) Number of Habitations covered:- 1 (One)

21) Impact of the scheme: - With good road

connectivity there is an overall development in

the socio - economic conditions of the people

living in the rural areas by way of transportation

of agricultural and forest products to the market.

22) Problem faced by the Department in implementing

the scheme, if any:- Nil

23) Observations :- The Inspection team observed that:-

Hume Pipe, Earthwork, side drain, bridge and

guard wall were done at Stage I.

Metalling and Black Topping were done at Stage II.

11 numbers of Hume pipes/ Culverts.

2(two) numbers of RCC bridge culverts.

1(one) number of causeway bridge

RCC Bridge culvert-1, Span 6.70 mts width 5.40 mts., wing-wall-2.20 mts length and

3.60 mts height, Pucca Side Drain-(60*60) cms with a length of 120 mts.

24) Suggestions:- Sign board shows date of completion as 20/05/2015, whereas it is completed

in December, 2015. The EE, PMGSY was advised to write the actual date of completion on the

Signboard and 5 (five) years maintenance should start with effect from the actual date of

completion of the work.

Guard Wall and RCC Bridge

Signboard