    Activity ID Activity Name OriginalDuration

    Predecessors Successors

    CHEMICAL IN

    CHEMICAL INJECTION FACILITIES AT ADRD 360d

    MILESTONES

    MILESTONES 324d

    MILESTONE1000 Effective Date Of Contract 0d PRELIM1000

    MILESTONE1010 APPROVED PM PLANS 0d PM1010, PM1006, PM1009,

    PM1007, PM1008, PQP1010

    MILESTONE1050, CONST1000, CONST1060

    MILESTONE1020 QHSE DOCUMENTS APPROVED 0d QHSE1030, QHSE1050,QHSE1040, QHSE1070,QHSE1125

    MILESTONE1050, CONST1000, CONST1060

    MILESTONE1030 Method Statements Approved 0d MS1011, MS1007, MS1013,MS1015, MS1019, MS1009,MS1001, MS1003, MS1005,MS1017

    MILESTONE1050, CONST1000, CONST1060

    MILESTONE1040 DESIGN DELIVERABLE LIST 0d ENG1160, ENG1290,ENG1180, ENG1190,ENG1200, ENG1210,ENG1220, ENG1230,ENG1240, ENG1250,ENG1260, ENG1140

    CONST1000, CONST1060, CONST1120

    MILESTONE1050 CONSTRUCTION START 0d MILESTONE1010,MILESTONE1020,

    MILESTONE1060 Final Hand Over 0d COMM1040, COMM1015, C

    PRELIMINARI

    PRELIMINARIES 24d

    PRELIM1000 Recipt of Letter of Award ( LOA) 1d MILESTONE1000 PRELIM1010

    PRELIM1010 Letter of Acknowledgement 1d PRELIM1000 PRELIM1020PRELIM1020 Letter of Assistance 10d PRELIM1010 PRELIM1030

    PRELIM1030 Secrurity & Refinery Pass 10d PRELIM1020 PRELIM1040

    PRELIM1040 Kick Off Meeting for the Project 1d PRELIM1030 PM1001, PM1004, PM1002, PQP1000, ENG1001,PM1005, PM1003, PM1000, MS1010, MS1006,MS1012, MS1014, MS1018, MS1008, MS1000,MS1002, MS1004, MS1016, QHSE1000,QHSE1010, QHSE1020, QHSE1060, QHSE1100

    PROJECT MA

    PROJECT MANAGEMENT 32d

    PM1000 Mobilization of Project team 20d PRELIM1040 ENG1001

    SUBMISSION

    SUBMISSION 20d

    PM1001 Sumbission of Project Execution Plan 20d PRELIM1040 PM1006

    PM1002 Submission of Organization Chart 7d PRELIM1040 PM1007

    PM1003 Submission of Project Co-Ordination Register 7d PRELIM1040 PM1008

    PM1004 Submission of Project Procurement Plan 7d PRELIM1040 PM1009

    PM1005 Submission of Document Deliverables Register 7d PRELIM1040 PM1010

    APPROVAL

    APPROVAL 25d

    PM1006 Approval Project Execution Plan 12d PM1001 MILESTONE1010

    PM1007 Approval of Organization Chart 12d PM1002 MILESTONE1010

    PM1008 Approval of Project Co-ordination Register 12d PM1003 MILESTONE1010

    PM1009 Approval of Project Procurement Plan 12d PM1004 MILESTONE1010

    PM1010 Approval Of Document Deliverable Register 12d PM1005 MILESTONE1010

    CHEMICAL INJECTION FACILITIES AT ADRD

    Engr Nouman Zia

  • 7/27/2019 PM With Comments 12october

    2/8

    Activity ID Activity Name OriginalDuration

    Predecessors Successors

    PROJECT QU

    PROJECT QUALITY PLAN 17d

    PQP1000 Submission of Project Quality Plan ( PQP) 5d PRELIM1040 PQP1010

    PQP1010 Approval of Project Quality Plan 12d PQP1000 MILESTONE1010

    QHSE DOCU

    QHSE DOCUMENTATION 45d

    HSE PLAN

    HSE PLAN 15dSUBMISSION

    SUBMISSION 5d

    QHSE1000 Submission of HSE Plan 5d PRELIM1040 QHSE1030

    QHSE1010 Submission of TRA 5d PRELIM1040 QHSE1040

    QHSE1020 Submission of Emergency Rescue Plan 5d PRELIM1040 QHSE1050

    APPROVAL

    APPROVAL 10d

    QHSE1030 Approval of HSE Plan 5d QHSE1000 MILESTONE1020

    QHSE1040 Approval of TRA 10d QHSE1010 MILESTONE1020

    QHSE1050 Approval of Emergency Rescue Plan 10d QHSE1020 MILESTONE1020

    INSPECTION T

    INSPECTION TEST REPORT 15d

    QHSE1060 Submission Of ITP 5d PRELIM1040 QHSE1070

    QHSE1070 Approval Of ITP 10d QHSE1060 MILESTONE1020

    WELDER PRO

    WELDER PROCEDURE SPECIFICATION 15d

    QHSE1100 Submission Of WPS 5d PRELIM1040 QHSE1105

    QHSE1105 Approval Of WPS 10d QHSE1100 QHSE1110

    PROCEDURE

    PROCEDURE QUALIFICATION REPORT 15d

    QHSE1110 Submission Of PQR 5d QHSE1105 QHSE1115

    QHSE1115 Approval Of PQR 10d QHSE1110 QHSE1120

    WELDER QUA

    WELDER QUALIFICATION TEST 15d

    QHSE1120 Submission Of WQT 5d QHSE1115 QHSE1125QHSE1125 Approval Of WQT 10d QHSE1120 MILESTONE1020

    METHOD STAT

    METHOD STATEMENTS 15d

    CIVIL WORKS

    CIVIL WORKS 15d

    MS FOR FO

    MS FOR FOUNDATION FOR SKIDS 15d

    MS1010 Submission of MS for the Foundations for Skids 5d PRELIM1040 MS1011

    MS1011 Approval of MS for the Foundation for Skids 10d MS1010 MILESTONE1030

    MS FOR CO

    MS FOR CONSTRUCTION OF DUCT BANKS IN ROAD CROSSING 15d

    MS1006 Submission of MS for the construction of Ducts Banks in Road Crossing 5d PRELIM1040 MS1007

    MS1007 Approval of of MS for the construction of Ducts Banks in Road Crossing 10d MS1006 MILESTONE1030

    METHOD STAT

    METHOD STATEMENTS FOR MECHANICAL WORKS 15dMS FOR INS

    MS FOR INSTALLATION OF EQUIPMENT 15d

    MS1012 Submission Of MS For Equipment 5d PRELIM1040 MS1013

    MS1013 Approval For MS For Equipment 10d MS1012 MILESTONE1030

    MS FOR INS

    MS FOR INSTALLATION OF PIPING 15d

    MS1014 Submission Of MS For Installation Of Piping 5d PRELIM1040 MS1015

    MS1015 Approval For MS For Installation Of Piping 10d MS1014 MILESTONE1030

    MS FOR INS

    MS FOR INSTALLATION OF VALVES 15d

    MS1018 Submission Of MS For Installation Of Valves 5d PRELIM1040 MS1019

    MS1019 Approval For MS For Installation Of Valves 10d MS1018 MILESTONE1030

    MS FOR SA

    MS FOR SANDBLASTING & PAINTING 15d

    MS1008 Submission of MS for Sandblasting & Painting 5d PRELIM1040 MS1009

    MS1009 Approval of MS for Sandblasting & Painting 10d MS1008 MILESTONE1030

    ELECTRICAL &

    ELECTRICAL & INSTRUMENTATION WORKS 15d

    CHEMICAL INJECTION FACILITIES AT ADRD

    Engr Nouman Zia

  • 7/27/2019 PM With Comments 12october

    3/8

  • 7/27/2019 PM With Comments 12october

    4/8

  • 7/27/2019 PM With Comments 12october

    5/8

  • 7/27/2019 PM With Comments 12october

    6/8

    Activity ID Activity Name OriginalDuration

    Predecessors Successors

    PROC1330 Submission of submittals of Flow Transmitter 1d ENG1220, ENG1230,ENG1240, ENG1250,ENG1260

    PROC1340

    PROC1340 Approval of Flow Transmitter 5d PROC1330 PROC1350

    PROC1350 PO for Flow Transmitter 1d PROC1340 PROC1360PROC1360 Delivery at Site 52d PROC1350 INST1000

    CONSTRUCTICONSTRUCTION 174d

    CIVIL WORKSCIVIL WORKS 155d

    FOUNDATION FFOUNDATION FOR ANTI STATIC SKID 5122-L 22d

    CONST1000 Excavation For Skid Foundtion 5122-L 7d PROC1030,MILESTONE1010,

    CONST1010, MECH1040

    CONST1010 Compaction 2d CONST1000 CONST1020

    CONST1020 Steel Reinforcement 3d CONST1010 CONST1030

    CONST1030 Shuttering Fixing 3d CONST1020 CONST1040

    CONST1040 Concrete Pouring 1d CONST1030 CONST1050

    CONST1050 Curing For Skid Foundtion 5122-L 7d CONST1040 MECH1010, MECH1020, MECH1170

    FOUNDATION FFOUNDATION FOR LUBRICITY IMPROVER 7006-L 24d

    CONST1060 Excavation For Skid Foundtion 7006-L 7d PROC1430,MILESTONE1010,

    CONST1070

    CONST1070 Compaction 2d CONST1060 CONST1080

    CONST1080 Steel Reinforcement 3d CONST1070 CONST1090

    CONST1090 Shuttering Fixing 3d CONST1080 CONST1100

    CONST1100 Concrete Pouring 1d CONST1090 CONST1110

    CONST1110 Curing For Skid Foundtion 5122-L 9d CONST1100 MECH1240, MECH1025EXCAVATION FEXCAVATION FOR CABLE TRENCHES 9d

    CONST1120 Excavation for Cable Trenches 7d MILESTONE1040,PROC1200, PROC1240

    CONST1130

    CONST1130 Laying of Cable Trenches 1d CONST1120 CONST1140

    CONST1140 Backing Filling 1d CONST1130

    MECHANICALMECHANICAL WORKS 130d

    MECH1010 Installation of Safety Sign & Emergency Procedure Board Near Anti Static inj Facility 5d CONST1050 COMM1012

    MECH1020 Installation Of Safety Shower & Eyewash Facility For 5122-L 5d CONST1050, PROC1120 MECH1030

    MECH1025 Installation Of Safety Shower & Eyewash Facility For 7006-L 5d PROC1710, CONST1110 MECH1035

    MECH1030 Laying Of Water Supply line & Tie in to Nearest Potable water system For 5122-L 5d MECH1020 COMM1012

    MECH1035 Laying Of Water Supply line & Tie in to Nearest Potable water system For 7006-L 5d MECH1025 COMM1012

    MECH1040 Removal Of 4'' Existing Redundant Water Pipeline & Gas Oil Flushing 7d CONST1000 MECH1110

    PIPE FABRICAPIPE FABRICATION 130d

    SHOP FABRISHOP FABRICATION 39d

    MECH1050 Marking & Cutting Of Pipes as Per Isometeric Drawing 5d PROC1510, PROC1450,PROC1470, PROC1550,PROC1080, PROC1590,PROC1630, PROC1160,PROC1670

    MECH1060

    MECH1060 Preparation of Fitups 3d MECH1050 MECH1070

    MECH1070 Welding Of Pipe Spools 10d MECH1060 MECH1080

    MECH1080 RT Of Pipe Spools 4d MECH1070 MECH1090

    MECH1090 Hydrotesting of Pipe Spools 3d MECH1080 MECH1100

    CHEMICAL INJECTION FACILITIES AT ADRD

    Engr Nouman Zia

  • 7/27/2019 PM With Comments 12october

    7/8

  • 7/27/2019 PM With Comments 12october

    8/8

    Activity ID Activity Name OriginalDuration

    Predecessors Successors

    ELECTRICALELECTRICAL WORKS 18d

    POWER & SIGPOWER & SIGNAL CABLE INSTALLATION 18d

    CHEMICAL ICHEMICAL INJECTION SKID 7006-L 18d

    ELECT1020 Installation of All Power & Control Cables in New cable Trays From substation 70 to 2 nosInj Pump Motors

    3d PROC1200, PROC1240 ELECT1030

    ELECT1030 Installation of All Power & Control Cables in New cable Trays From substation 70 to 1 no 3d ELECT1020 ELECT1040

    ELECT1040 Installation Of Earth/ Grounding cables, fittings & Accessories to Existing Earth Grid 3d ELECT1030 ELECT1050

    ELECT1050 Installation of All Power & Control Cables in below ground Tranches 3d ELECT1040 ELECT1055

    ELECT1055 Termination of Cables with the Skid 3d ELECT1050 ELECT1065

    ELECT1065 Installation of Junction Boxes 3d ELECT1055 COMM1015

    CHEMICAL ICHEMICAL INJECTION SKID 5122-L 18d

    ELECT1000 Installation of All Power & Control Cables in New cable Trays From substation 21 to 1 nosTransfer Pump Motor

    3d PROC1200, PROC1240 ELECT1010

    ELECT1010 Installation of All Power & Control Cables in New cable Trays From substation 21 to 2 no 3d ELECT1000 ELECT1060

    ELECT1060 Installation Of Earth/ Grounding cables, fittings & Accessories to Existing Earth Grid 3d ELECT1010 ELECT1070

    ELECT1070 Installation of All Power & Control Cables in below ground Tranches 3d ELECT1060 ELECT1090

    ELECT1090 Termination of Cables with the Skid 3d ELECT1070 ELECT1110

    ELECT1110 Installation of Junction Boxes 3d ELECT1090 COMM1015

    INSTRUMENTAINSTRUMENTATION & CONTROLS WORKS 8d

    INST1000 Installation of Flow transmitter 2d PROC1360 INST1005

    INST1005 Installation of Flow Element 2d INST1000 INST1015

    INST1015 Installation Of Instrumentation Control System 2d PROC1280, INST1005 INST1020

    INST1020 Configuration of DCS 2d INST1015 COMM1015

    TESTING & CTESTING & COMMISSIONING 54d

    COMM1012 Commissioning of Chemical Injection Skids 7d MECH1160, MECH1300,MECH1230, MECH1470,MECH1010, MECH1030,MECH1410, MECH1035

    ENG1170, COMM1015, COMM1040,MILESTONE1060

    COMM1015 Commissioning Of Instruments 7d ELECT1065, ELECT1110,INST1020, COMM1012

    COMM1020, COMM1040, MILESTONE1060

    COMM1020 Demobilization 7d ENG1172, COMM1015 COMM1050

    COMM1040 Training Of Personnel 4d COMM1012, COMM1015 COMM1050, MILESTONE1060

    COMM1050 Project Close Out Report 10d COMM1040, COMM1020

    CHEMICAL INJECTION FACILITIES AT ADRD

    Engr Nouman Zia