Planning and Tracking Project Effectively Use MS Project

download Planning and Tracking Project Effectively Use MS Project

of 65

Transcript of Planning and Tracking Project Effectively Use MS Project

  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    1/65

  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    2/65

    Content Outline

    Part I. Initiate projectschedule

    Part II. Planning

    Part III. Tracking Project

    Progress Part IV. Manage multipleprojects

    Part I. Initiate projectschedule

    Part II. Planning

    Part III. Tracking Project

    Progress Part IV. Manage multipleprojects

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    3/65

    Part I. Initiate project schedule

    Set the project start date

    Set Holidays and Days Off

    Define time units

    Set the project start date

    Set Holidays and Days Off

    Define time units

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    4/65

    Note: Project Start Date is used to calculate the project finish date based onyour entered start date and assigns the default constraint of As Soon AsPossible (ASAP). Task durations, dependencies, constraints, and otherscheduling factors are also scheduled from the start date.

    1. Set the project start date

    1. Go to File->Properties

    2. Enter the start date

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    5/65

    2. Set Holidays and Days Off

    1. Go to Tools -> Change WorkingTimes

    2. Select a date or range of date

    3. In Exception tab, enter reasonand time for days off, holidays

    4. Select Work Weeks tab forworking overtime on Sat or Sun

    Set days off, vacations, and holidays within Project

    Set Working overtime on Sat or Sun

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    6/65

    3. Define time units

    1. Go to Tools -> Options

    2. Select Calendar tab

    3. Click Set as Default button

    Note: You can adjust the Days permonth to 21

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    7/65

    Part II. Planning

    1. Scheduling tasks

    2. Assigning resources

    3. Checking and Adjusting the Project

    Plan

    1. Scheduling tasks

    2. Assigning resources

    3. Checking and Adjusting the Project

    Plan

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    8/65

    1. Scheduling tasks

    Major steps to create project schedule

    1. List down all milestones

    Deliver/Commitments Made to Customer

    Deliver/Commitments Made by Customer

    2. List down all Deliverables (includes internal deliverables)

    3. Create dependencies between deliverable and milestones

    4. For each deliverables, define tasks to achieve it

    5. Create dependencies between tasks in deliverables

    6. Set a deadline reminder for deliverables

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    9/65

    1.1 Milestone Deliverable - Phase

    Deliverable.

    Item that must be produced to mark the completion of a project or a project phase.Often, the deliverable is subject to approval by the project sponsor or customer.

    Milestone.A significant event in the project, often the completion of a major deliverable orphase. Milestones are represented as part of a project's task list.

    Phase.A grouping of tasks that represents a major stage in the life cycle of the project. Theoutcome of a phase is typically a major deliverable.

    Deliverable

    Milestone

    s

    Tasks

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    10/65

    1.2 Create dependencies between deliverable

    and milestones

    1. Select the Deliverable task (ex. SRS s deliverable)

    2. Hold down the Ctrl key, select the milestone (DeliverSRS)

    3. Choose Edit Link Tasks on menuNotes:

    You can link more than one deliverable to a milestone

    You should set deadline on milestones and deliverables

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    11/65

    1.3 Set a deadline reminder for deliverables,

    tasks or milestones

    If the task finishes afterthe deadline date, anindicator appears next tothe task, notifying youthat the task is scheduledto finish after its deadline.

    Note: You should set taskdeadline on importanttask: milestones, phases

    1. Double click on the task

    2. Select Advanced tab3. In Deadline box, enter the

    deadline date

    4. Click OK

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    12/65

    1.4 Some tips when entering tasks

    Use Task form view

    The task information is viewed in more detail

    1. Select View More Views from the menu

    2. Select Task Entry and click Apply

    Or

    1. Select Windows Split

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    13/65

    1.5 Some tips when entering tasks (Cont.)

    Use abbreviations when you enter durations

    1. Select a task

    2. Type as below in duration or effort column

    For Enter Example

    Minutes m 30m

    Hours h 2h

    Days d 4d

    Weeks w 6w

    Months mo 1mo

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    14/65

    2. Assigning resources

    Build project team

    Define working time for resources

    Assign resource to tasks

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    15/65

    2.1 Build project team

    1. Select View Resource Sheet

    2. Enter name in Resource Namecolumn

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    16/65

    2.2 Change working times, days off, and

    vacations for individual resources

    1. Select View Resource Sheet

    2. Double click on a resource name

    3. Select a date or range of date

    4. In Exception tab, enter reason andtime for days off, holidays

    5. Select Work Weeks tab forworking overtime on Sat or Sun

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    17/65

    2.3 Assign resource to tasks

    1. Select a task

    2. Select Tool Assign Resources (Alt+F10)

    3. Select a resource

    4. Click Assign button

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    18/65

    3. Checking and Adjusting the Project Plan

    Concepts

    Identifying the Resource Overallocation

    Balancing the Resource Overallocation

    Check the project total efforts

    Review the Critical Path and Critical Tasks

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    19/65

    3.1 Concepts

    Duration? Work? Resource Units?

    Duration WorkResource Units relationship

    Task types

    Effort-Driven feature

    Overallocated Resource Changing task types

    Sample (Fixed Unit, Fixed Work and FixedDuration)

    Notes when using effort driven and task types

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    20/65

    3.1.1 Duration? Work? Resource Units?

    Duration is the length of working timebetween the start and finish of a task.

    Work is the amount of effort, measuredin time units (like hours or days), that aresource needs to complete the task.

    Resource Units indicate how much of aresource's available time, according tothe resource calendar, is being used towork on a particular task

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    21/65

    3.1.2 Duration WorkResource Units

    relationship

    Duration = Work / Unit

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    22/65

    3.1.3 Task types

    Fixed Units Fixed Duration

    Fixed Work

    If you change one variable, one of the othertwo variables will be recalculated, dependingon what task type has been selected for that

    task.

    Objective of each fixed type

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    23/65

    3.1.4 Effort-Driven feature

    When you assign or remove people from a task:

    Project lengthens or shortens the duration of the taskbased on the amount of resource units assigned to it

    It doesn't change the total amount of work for the task.

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    24/65

    3.1.5 Task type and effort-driven relationship

    Fixed Units With effort-driven schedulingturned on, the more resources you add to a

    task, the shorter the duration becomes

    Fixed Duration With effort-driven schedulingturned on, adding more resources decreasesthe time units each resource will have to workon the task.

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    25/65

    3.1.6 Notes when using effort driven and task

    types

    The default task type is Fixed Unit

    Effort driven feature is turned on by default

    Effort-driven calculations are applied only afterthe firsttime one or more resources is assigned to the task.

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    26/65

    3.1.7 Overallocated Resource

    A resource is overallocated when it is assigned toomuch work to complete within the resource'savailable time.

    A resource overallocation can be caused by:

    A resource assigned to work full-time on more than onetask at the same time

    A resource assigned to a summary task

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    27/65

    3.1.8 Changing task types

    Changing task type1. Double click on the Task

    2. Choose the Advanced tab

    3. Change the Task type

    Enable or disable effort driven feature

    1. Double click on the Task2. Choose the Advanced tab

    3. Select or deselect Effort driven checkbox

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    28/65

    3.2 Identifying the Resource Overallocation

    1. Select View Resource Usage (or resourcesheet, resource allocation, resource graph)

    2. Find the resources highlighted in red.

    Note Overallocated resources are always highlightedin red

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    29/65

    3.3 Balancing the Resource Overallocation

    Adjusting AssignmentsAdding More Resources to Tasks

    Replacing Overallocated Resources

    Delaying tasks

    Splitting Tasks Using Leveling resource feature

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    30/65

    3.3.1 Adjusting Resource Availability (Adjust %

    Unit)

    Tip: Use Resource Allocation view

    1. Select view more views from the menu.

    2. Select the resource allocation view and click apply

    3. Select the resource with red highlight4. Adjust the hour on top-right table

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    31/65

    3.3.2 Adjusting Assignments Adding More Resources

    to Tasks Replacing Overallocated

    Resources

    Use Assign Resources dialog box

    1. Go to Resource Allocation view

    2. Select the resource with red highlight

    3. Select a task in bottom-right table

    4. Select Tool Assign Resources (Alt+F10)

    5. Select a resource

    6. Click Assign for adding more resources

    7. Click Replace for replacing overallocatedresources

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    32/65

    3.3.3 Leveling resource

    Leveling resource is a MS Project feature that automatically: Delaying a task until the assigned resource has time to work on it

    Splitting a task so that part of a task is done when planned, andthe rest of it is done later when the assigned resource has time

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    33/65

    3.3.4 Factors effect leveling resources

    Available slack

    Task duration

    Task constraints

    Task ID

    Task priority Task dependencies

    Scheduling dates

    Resource availability as show in working timecalendar

    Resource availability as show by maximum units Resource assignment units on the task

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    34/65

    3.3.5 Resource Leveling feature

    1. Go to Resource Allocation view

    2. Select the resource with red highlight3. Select Tool Level resources

    4. Use default value

    5. Click Level Now button

    6. Select Selected resources

    7. Click OK

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    35/65

    3.3.5 Resource Leveling feature (Cont.)

    Options Description

    Automatic level resources whenever you make a change that affectsscheduling

    Manual resources leveled only when you give the Level Now command

    Level entire project Specifies that overallocated resources should be leveled overthe entire duration of the project

    Level From and To Specifies the date range in which to level resources

    Level only withinavailable slack

    Prevents the finish date of your project from being delayed

    Level order With this levelingorder

    These fields are examined

    Standard These fields are examined: Taskrelationships, Slack, Start date, Priority,Constraint

    ID Only Task IDPriority, Standard Priority, Task relationships, Slack, Start

    date, Constraint

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    36/65

    3.4 Check the project total efforts

    Use Project Statistics dialog box

    Review the effort reported by MS Project vs. effortin estimation sheet

    1. Click Project Project Information

    2. In the Project Information dialog box, click theStatistics button

    3. Focus on work column

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    37/65

    3.5 Review the Critical Path and Critical Tasks

    Use Tracking Gantt view

    1. Go to View Tracking Gantt

    2. The critical path is highlighted in red color in thechart

    Use Detail Gantt v iew

    1. Go to View More Views

    2. Choose Detail Gantt

    3. Click Apply

    Critical Path

    You may wonder, "what ultimately determines the length of myproject?" The answer is the critical path

    The critical path is the series of tasks (or even a single task) that effectthe finish date of the project

    All tasks on critical path must be review carefully, these tasks shouldbe assigned by dedicated people

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    38/65

    3.5 Review the Critical Path and Critical Tasks

    (Cont.)

    How do I shorten the critical path?

    Shorten the duration or work on a task on the critical path.

    Break a critical task into smaller tasks that can be worked onsimultaneously by different resources.

    Revise task dependencies to allow more scheduling flexibility.

    Set lead time between dependent tasks where applicable.

    Schedule overtime.

    Assign additional resources to work on critical path tasks.

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    39/65

    Part III. Tracking project progress

    1. About planned, scheduled, and actual

    information2. Saving Original Plan Information byusing Baseline

    3. Updating actual At task level

    At assignment level

    4. Rescheduling the Project5. Reviewing progress

    6. How team member enter actual work

    1. About planned, scheduled, and actual

    information2. Saving Original Plan Information byusing Baseline

    3. Updating actual At task level

    At assignment level

    4. Rescheduling the Project5. Reviewing progress

    6. How team member enter actual work

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    40/65

    1. About planned, scheduled, and actual

    information

    Planned or baseline information When you build and refine your project to the point where you're confident

    you can start the project, you have a good beginning point, or baseline.

    Scheduled information Scheduled information is the current, most up-to-date task information.

    Actual information Actual information reflects how the task was finally accomplished. You

    started with the planned projection of duration, work, cost, and start andfinish dates. You enter progress information, or actuals, for tasks, and endup with the real picture of the completion of the task.

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    41/65

    2. Saving Original Plan Information by using

    Baseline

    BaselineBaseline is used in case you want to compare the original plan (orapprovedplan) with the current plan to analyze your progress and performance

    To save a baseline plan

    1. Select tools tracking Set baseline

    2. Select Set baseline and Entire project

    3. Click ok

    To clear a Baseline

    1. Click Tools Tracking Clear Baseline

    2. Select the Clear Baseline Plan option

    3. Select the Entire Project option

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    42/65

    3. Updating actual

    At task level Updating the Project as Scheduled

    Updating Task Completion Percentage

    Updating Task Actual Values

    At assignment level Updating Percent Work Complete, Actual Work Complete and

    Remaining Work

    Updating actual work by timephased (the same as timesheet)

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    43/65

    1/20/2011Confidential 43

    Updating the Project as Scheduled

    Updating the Project as ScheduledIf everything is going along smoothly and there are no problems ordelays, the easiest way to track progress is simply to report thatthe project is proceeding as planned.

    1. Select tools tracking update project from the menu

    2. Make sure that the Update Work As Complete Throughoption isselected.

    3. Enter the complete through date in the box

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    44/65

    1/20/2011Confidential 44

    Updating the Project as Scheduled (Cont.)Notes:

    Set 0% - 100%:

    Updates the scheduled progress on all tasks within the given timeframe

    Set 0% or 100% complete only:

    Only updates tasks as not started (0%) or finished (100%). Does notupdate progress on tasks that have started but are not finished.

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    45/65

    1/20/2011Confidential 45

    Updating Task Actual Values

    Updating Task Actual ValuesSome tasks in your project will not fall within their scheduled timeframe; some tasks may end faster or slower than scheduled. In theseinstances, you should update what actually happens in the project.

    1. Select the task you want to update

    2. Select tools tracking update tasks from the menu

    3. Enter the task actual values in the dialog box

    4. Click ok

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    46/65

    3.1 Updating Percent Work Complete, Actual

    Work Complete and Remaining Work

    1. Display a task sheet, such as the Task Usage view or Tracking Gantt

    2. Click View Table Work

    3. In the Actual (work) field of the task you want to update, enter the actual work value.

    The values in the Remaining (work) and % W. Comp fields are recalculated.

    Tip: Update actual work in the Assignment Information dialog box

    1. Double-click the assignment to open the Assignment Information dialog box.

    2. Click the Tracking tab.

    3. Update the value in the Actual Work box.

    This is also a good method of updating actual work for multiple assignments if they allhave the same value

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    47/65

    3.2 Updating actual work by timephased

    If you need to track how much work each resource has performed on a

    task during a specific time period (for example, daily), you can enterthe timephased information for actual work for each assignedresource.

    1. Select view task usage

    2. Select format details actual work

    3. Click the act. work field under the date youwant to update.

    Make sure you select the act. work field forthe task or resource you want to update.

    4. Enter the actual amount of work completedand press enter

    Note: When you fill the 0 value toAct. Work, thetask will be spitted

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    48/65

    4. Rescheduling the Project If you want to continually work on uncompleted tasks after your team's

    efforts redirected onto a different urgent priority. What do you do withyour project plan?

    1. Select tools tracking update project

    2. Select the Reschedule UncompletedWork To Start After option

    3. Enter the start after date in the box

    Tip: Use Reschedule work icon on Trackingtoolbar

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    49/65

    5. Reviewing progress

    View task progress with progress lines

    Check for tasks that are behind schedule

    Compare current work amounts with your original plan

    Reviewing Overall Schedule Progress

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    50/65

    5.1 View task progress with progress lines

    You can add progress lines to your Gantt Chart that provide a graphicmeans of seeing whether tasks are ahead of schedule, behindschedule, or exactly on time

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    51/65

    5.1 View task progress with progress lines

    (Cont.)

    1. Select View Tracking Gantt

    2. Select Tool Tracking Progress Lines

    3. In Progress Lines dialog box: Select Always display current progress line

    Select At current date

    4. Click OK button

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    52/65

    5.2 Check for tasks that are behind baseline

    If you want to review the differences between your original baseline planvalues and your currently scheduled values

    1. Select View Tracking Gantt

    2. Select View Table Variance

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    53/65

    5.3 Compare current work amounts with your

    original plan

    If you want to review the differences between your original baseline planvalues and your currently work values

    1. Select View Tracking Gantt

    2. Select View Table Work

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    54/65

    5.4 Reviewing Overall Schedule Progress

    1. Click Project Project Information

    2. In the Project Information dialog box, click the

    Statistics button

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    55/65

    6. How team member enter actual work

    Team size Suggestion Method

    7 -Break the project schedule into multiple project schedule.

    -Delegate updating progress of each separate schedule to a team leader

    -Each team leader will update project progress as above method (with team size < 7)

    -PM use master project schedule to monitor the status of whole project

    Note: In CSCV, updating progress by usingassignment level is recommended

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    56/65

    Part IV. Manage multiple projects

    Structuring Master Projects withSubprojects

    Consolidating Project Information

    Sharing Resources Using a ResourcePool

    Structuring Master Projects withSubprojects

    Consolidating Project Information

    Sharing Resources Using a ResourcePool

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    57/65

    1. Structuring Master Projects with Subprojects

    Scenario: You are a PM that manages a large project containing many

    phases or components for which other team leader are responsible.

    Solution: In Microsoft Office Project 2007, you can set up a master projectwith subprojects representing those subphases. You can keep an eye on theoverall picture while the team leader responsible for the individual phaseshave complete control over their pieces of the project.

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    58/65

    1.1 Create Master Projects with Subprojects

    1. Open the project that you wantto become the master project

    2. Select View Gantt chart

    3. Click the row below where youwant to insert the project

    4. Select Insert Project

    5. Browse to the drive and folder in

    which the subproject is stored

    6. Click the project file and thenclick the Insert button

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    59/65

    2. Sharing Resources Using a Resource Pool

    Scenario: You have three PM in the same organization. Although they managedifferent projects, they use many of the same resources. Sometimes, their projectsconflict with one another because of demands on the same resources at the sametime.

    Solution: In Microsoft Project, they can create a resource pool file that contains

    the resources they all use. They can then link their individual project files to that resource pool.

    The resource availability and usage information is available through that resource pool.

    When one project assigns tasks to a resource in the resource pool, the resource pool isupdated with that resource's allocation information.

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    60/65

    2. Sharing Resources Using a Resource Pool

    (Cont.)

    Setting Up a Resource Pool Linking a Project to Your Resource Pool

    Checking Availability of Resource Pool Resources

    Disconnecting a Resource Pool from a Project Plan

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    61/65

    2.1 Setting Up a Resource Pool

    Resource pools are easier to manage in the long run if you have a project file

    whose only job is to serve as the resource pool file

    1. Create a new project schedule2. Select View Resource sheet

    3. Enter resource information

    4. Save the project schedule file with aname as: ResPool

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    62/65

    2.2 Linking a Project to Your Resource Pool

    1. Open the resource pool file

    2. Open your project file that you want to shareresources from the resource pool.

    3. In this project file, select Tools ResourceSharing Share Resources

    4. Select the Use Resources option

    5. In the From list, click the name of the resource

    pool file6. Click OK

    7. Now all resource information in the resourcepool appears in your project file

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    63/65

    2.3 Checking Availability of Resource Pool

    Resources

    Using the Resource Usage view or the Resource Graph in the resourcepool file to check the availability of resources across all sharer projects.

    In these views, you can see all the assignments for all the resources in theresource pool.

    You can see the amount of time they're assigned, if they're overallocated, or ifthey have time available to take on more assignments

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    64/65

    2.4 Disconnecting a Resource Pool from a

    Project Plan

    If you no longer need the resource pool and the sharer file to be linked, youcan disconnect them, as follows

    1. Open both the resource pool and the sharer file

    2. Display the sharer file

    3. Select Tools Resource Sharing ShareResources

    4. Select the Use Own Resources option

    http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/http://www.docu-track.com/buy/
  • 8/11/2019 Planning and Tracking Project Effectively Use MS Project

    65/65

    Thank You