Planning and Execution of Ground Mount Solar Projects ... · 01 basics of ground mount solar...
Transcript of Planning and Execution of Ground Mount Solar Projects ... · 01 basics of ground mount solar...
your logo
prepared forgeneral audience
Planning and Execution of Ground Mount Solar Projects(“Solar 101”)
your logo
intropurpose
page02
This presentation provides an overview of key concepts related to the planning, design and construction of ground mount solar projects intended for a non-technical audience.
your logo
introoverview
page03
01 basics of a ground mount solar project 02 project planning
01 basics of groundmount solar projects
your logo
basicsunits of electricity
page05
• Voltage, V (measured in Volts, V)• potential difference between two
points
• Current, I (measured in Amps, A)• rate of flow of electrons
• Resistance, R (measured in Ohms, Ω)• resistance to electron flow of a
material
V = I x R
Image Source: https://learn.sparkfun.com/tutorials/voltage-current-resistance-and-ohms-law
Water analogy:
your logo
basicsunits of electricity
page06
• Voltage is either AC (Alternating Current) or DC (Direct Current).
• In a solar project, the inverters convert from the DC output of the solar panels to AC for use by the grid.
• AC can be single phase or 3 phase.
Image Source: https://learn.sparkfun.com/tutorials/alternating-current-ac-vs-direct-current-dc
your logo
basicsunits of electricity
page07
• Power, P (measured in Watts, W)• rate of transfer of electrical energy
• Power losses depend on the current and resistance of a circuit.
For DC systems:
P = I x V Ploss = I2 x R
• Losses can be decreased by using bigger cables (lower resistance) or higher voltage (lower current).
• Transformers change AC voltage for transmission of power over long distances.
your logo
basicsunits of electricity
page08
• In AC systems, power can be • Apparent Power, S (measured in Volt-
Amperes, VA)• Real Power, P (measured in Watts, W)• Reactive Power, Q (measured in
reactive Volt-Amperes, VAR)
• Power (P) is what generates kWh ($$$).• But electrical equipment (inverters,
transformers) is rated for the Apparent Power (S), which determines current.
For 3-Phase AC Systems:
S = √3 I x V, Ploss = 3 I2 x R
your logo
basicsunits of electricity
page09
• Power Factor, pf, is the ratio of Real Power to Apparent Power.
• Power Factor can be positive (“lagging”) or negative (“leading”) depending on the relationship between the current and voltage.
• Utilities typically specify the power factor for a solar generator while requiring capability to change power factor within a specified range, for example, from -0.95 to +0.95.
• Power factor control is done by the inverters or by power factor correction equipment installed at the substation.
Image By Wikieditor4321 - Own work, CC BY-SA 4.0, https://commons.wikimedia.org/w/index.php?curid=45518724
pf = P / Spf = cos (θ)
your logo
basicssimple schematic
page010
.
.
.
RecombinerBox
CombinerBoxes
Intermediate Transformer
InverterStrings of Solar Panels
.
.
.
. . .
. . .
DC Collector
AC Collector
MMain Step-Up Transformer
Protections, Controls, and Communications
Connection to Grid
Inverter Stations
your logo
basicssimple schematic
page011
.
.
.
RecombinerBox
CombinerBoxes
Intermediate Transformer
InverterStrings of Solar Panels
.
.
.
. . .
. . .
DC Collector
AC Collector
MMain Step-Up Transformer
Protections, Controls, and Communications
Connection to Grid
Inverter Stations
Each panel generates ~40V, 8.5A. They are connected in series to form “strings”
your logo
basicssimple schematic
page012
.
.
.
RecombinerBox
CombinerBoxes
Intermediate Transformer
InverterStrings of Solar Panels
.
.
.
. . .
. . .
DC Collector
AC Collector
MMain Step-Up Transformer
Protections, Controls, and Communications
Connection to Grid
Inverter Station
Output of strings is combined in parallel at combiner boxes and recombiner boxes.
your logo
basicssimple schematic
page013
.
.
.
RecombinerBox
CombinerBoxes
Intermediate Transformer
InverterStrings of Solar Panels
.
.
.
. . .
. . .
DC Collector
AC Collector
MMain Step-Up Transformer
Protections, Controls, and Communications
Connection to Grid
Inverter Station
Maximum Power Point Inverters have two functions
• Convert the dc power into ac.• Control the dc voltage from
the solar array to track the “maximum power point” or curtail the power.
your logo
basicssimple schematic
page014
.
.
.
RecombinerBox
CombinerBoxes
Intermediate Transformer
InverterStrings of Solar Panels
.
.
.
. . .
. . .
DC Collector
AC Collector
MMain Step-Up Transformer
Protections, Controls, and Communications
Connection to Grid
Inverter Stations
Larger projects have multiple subarrays each connected to its own inverter station. Multiple inverter stations are connected to form a “collector system”.
your logo
basicssimple schematic
page015
.
.
.
RecombinerBox
CombinerBoxes
Intermediate Transformer
InverterStrings of Solar Panels
.
.
.
. . .
. . .
DC Collector
AC Collector
MMain Step-Up Transformer
Protections, Controls, and Communications
Connection to Grid
Inverter Stations
One or more transformers step up the voltage to grid level.
your logo
basicssimple schematic
page016
.
.
.
RecombinerBox
CombinerBoxes
Intermediate Transformer
InverterStrings of Solar Panels
.
.
.
. . .
. . .
DC Collector
AC Collector
MMain Step-Up Transformer
Protections, Controls, and Communications
Connection to Grid
Inverter Station
A substation contains the main transformer together with protections and controls equipment required to connect the project safely to the grid.
A substation without a transformer is called a “switching station”.
your logo
basicspiles
page017
• Different types• Driven piles• Helical piles (1 or more helixes)• Ground screws• Caisson piles• Rock anchors• Or none at all (ballasted system)
• Selection depends on• Frost depth• Presence of boulders• Type of soil / presence of bedrock
• Subsurface risk can impact project cost and schedule.
your logo
basicsgrid interconnection
page018
• Point of Common Coupling (PCC) is where the ownership changes from customer to utility. • Point of Interconnection (POI) is where the project connects to the existing grid.• PCC and POI can be in different locations if a new utility-owned line is required to connect the project.
Image Source: Hydro One, Form B, Connection Impact Study Application
02 project planning
your logo
planning key principles
page020
• The best practice for engineering of large capital projects involves a phased approach that begins with Front End Engineering Design or FEED, also called Front End Loading.
• The work completed in each phase is just enough to allow decisions to be made and the project advanced.
FEL1Conceptual
Gate Review
FEL2Pre-
FeasibilityGate
ReviewFEL3
FeasibilityGate
ReviewFEL4
ExecutionStart Up and Operations
Value Identification Value Realization
your logo
planningkey principles
page021
• In each phase, uncertainty decreases and so does project risk.
• As uncertainty decreases, precision of estimates improves (project yield, CAPEX, OPEX)
Image source: http://wiki.iploca.com/display/rtswiki/2.2+Key+points+to+address+during+FEL
your logo
planningkey principles
page022
• A gate review is completed after each phase to determine whether to move forward to the next phase.
• The gate review is linked to a spending decision.
Image source: http://www.chem.info/article/2013/12/right-tools-job-front-end-loading
your logo
planningFEL 1 - concept
page023
Typical tasks:
• Land constraints → Environmental constraints → Available Area→ Estimate DC capacity
• Off-taker constraints• Interconnection availability→ Estimate maximum AC capacity
→ Ballpark energy production→ Ballpark CAPEX, OPEX estimates
→ Preliminary financial analysis
Go / No Go Decision
CAPEX~ $/W
Capacity ~MW/ha
Yield ~kWh/kW
your logo
planningFEL 2 – pre-feasibility
page024
Typical tasks:
• Environmental site investigation(s)• Desktop geotechnical• Develop layout• Develop single line diagram• Choice and budgetary quotations for
major equipment• PV Modules• Racking• Inverters
→ More precise energy yield and cost estimates
→ More precise financial analysis
Go / No Go Decision
your logo
planningFEL 3 - feasibility
page025
Typical tasks:
• Off-take agreements awarded / final.• Interconnection studies.→ Interconnection agreement• Site work, studies and consultations.→ Environmental & regulatory permits.• Geotechnical investigation.
• Prepare EPC contract designs and specifications.
→ Request for proposals.→ Bid analysis and selection.
→ More precise energy yield and cost estimates
→ More precise financial analysis
Go / No Go Decision
your logo
planningFEL 4 - execution
page026
Typical tasks:
• Project finance review and credit agreement execution.
• Kick-off with EPC Contractor.• Construction planning (safety, quality,
staffing).• Detailed design & engineering (50%,
90%, Issued for Construction).→ Building permits.
• Procurement.• Construction.• Testing & commissioning.• Project start-up.
Operations.
your logo
planninga brief word on energy storage…
page027
• An energy storage system has both a Power rating (Watts) and Energy rating (Watt-hours or Wh)
• Multiples types of energy storage might be appropriate for the same application.
• To select and optimize the energy storage device, first you need to develop specifications.
Image source: http://www.sandia.gov/ess/publications/SAND2013-5131.pdf
your logo
• Consider:• Stakeholder objectives• System requirements• Load/generation profile• Costs (capital + operational)
vs benefits• Operational requirements• Replacement frequency• Technology risk• Environmental risk• And more
planninga brief word on energy storage…
page028Image source: http://www.sandia.gov/ess/publications/SAND2013-5131.pdf
thank you.