Planning and Environment Act 1987 - … and Environment Act 1987 ... Ocean Beach Road, Sorrento 29...

55
Planning and Environment Act 1987 Panel Report Mornington Peninsula Planning Scheme Amendment C204 Ocean Beach Road, Sorrento Front page 29 May 2017

Transcript of Planning and Environment Act 1987 - … and Environment Act 1987 ... Ocean Beach Road, Sorrento 29...

Planning and Environment Act 1987 

Panel Report 

Mornington Peninsula Planning Scheme Amendment C204 

Ocean Beach Road, Sorrento  

 

Front page  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

29 May 2017 

    

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Planning and Environment Act 1987 

Panel Report pursuant to section 25 of the Act 

Mornington Peninsula Planning Scheme Amendment C204 

Ocean Beach Road, Sorrento 

29 May 2017 

 

   

Trevor McCullough, Chair  Rachael O’Neill, Member 

 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

  

 

Contents   Page 

1  Introduction ................................................................................................................ 1 

1.1  The Amendment ...................................................................................................... 1 1.2  Background to the proposal .................................................................................... 2 1.3  Summary of issues raised in submissions ............................................................... 2 1.4  Issues dealt with in this report ................................................................................ 3 

2  Planning context ......................................................................................................... 4 

2.1  Policy framework ..................................................................................................... 4 2.2  Planning scheme provisions .................................................................................... 8 2.3  Ministerial Directions and Practice Notes ............................................................... 9 2.4  Discussion and conclusions ................................................................................... 10 

3  Are additional controls needed? ............................................................................... 11 

3.1  The issue ................................................................................................................ 11 3.2  Submissions ........................................................................................................... 11 3.3  Discussion .............................................................................................................. 13 3.4  Conclusions ............................................................................................................ 14 

4  Assessment against PPN59 ‐ Mandatory controls ..................................................... 15 

4.1  The issues .............................................................................................................. 15 4.2  Introduction ........................................................................................................... 15 4.3  Is the mandatory provision strategically supported? ........................................... 15 4.4  Is the mandatory provision appropriate to the majority of proposals? ............... 17 4.5  Do the mandatory provisions provide for the preferred outcome? ..................... 18 4.6  Will  the majority  of  proposals  not  in  accordance with  the mandatory 

provision be clearly unacceptable? ....................................................................... 20 4.7  Will the mandatory provision reduce administrative cost? .................................. 21 4.8  Do the proposed controls provide adequate flexibility of design? ....................... 21 4.9  Conclusions ............................................................................................................ 24 4.10  Finding ................................................................................................................... 25 

5  Assessment against PPN60 – Activity Centres ........................................................... 26 

5.1  The issue ................................................................................................................ 26 5.2  Introduction ........................................................................................................... 26 5.3  Submissions ........................................................................................................... 26 5.4  Discussion .............................................................................................................. 28 5.5  Conclusions ............................................................................................................ 30 

6  The proposed DDO Schedule 28 ................................................................................ 31 

6.1  The issue ................................................................................................................ 31 6.2  Precinct and sub‐precinct borders ........................................................................ 31 6.3  Interpreting building height .................................................................................. 31 6.4  Other form and content issues ............................................................................. 32 6.5  Is DDO28 appropriate with discretionary controls? ............................................. 33 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

  

 

6.6  Conclusions ............................................................................................................ 35 6.7  Recommendations ................................................................................................ 36 

 

Appendix A  Submitters to the Amendment 

Appendix B  Document list 

Appendix C  Council proposed changes to DDO28 

Appendix D  Summary of approved developments in Ocean Beach Road 

 

List of Tables Page 

Table 1  Summary of approved developments in Ocean Beach Road .................................. 1 

Table 2  An assessment of the development potential of properties owned by TYAS Super Pty Ltd and Coastal Corner Pty Ltd ................................................ 22 

 

List of Figures   Page 

Figure 1  The subject area showing the proposed DDO28 .................................................... 1 

Figure 2  The  four  sub‐precincts  identified  in  the  Ocean  Beach  Road Commercial Precinct Heritage Policy ...................................................................... 8 

Figure 3  Current zone map .................................................................................................... 9 

 

List of Abbreviations  

The Act  Planning and Environment Act 1987  

CFA  Country Fire Authority 

DDO  Design and Development Overlay 

HO   Heritage Overlay 

LPPF  Local Planning Policy Framework 

PPN  Planning Practice Note 

SPPF  State Planning Policy Framework 

VCAT  Victorian Civil and Administrative Tribunal    

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

  

 

Overview  

Amendment Summary    

The Amendment  Mornington Peninsula Planning Scheme Amendment C204 

Common name   Ocean Beach Road, Sorrento 

Brief description  The Amendment proposes to apply permanent design and development provisions (Design and Development Overlay Schedule 28) to Ocean Beach Road, Sorrento 

Subject site  The Ocean Beach Road commercial precinct, Sorrento 

The Proponent  Mornington Peninsula Shire Council 

Planning Authority  Mornington Peninsula Shire Council 

Authorisation   A03427 authorised on 27 September 2016 

Exhibition  15 November 2016 to 13 January 2017 

Submissions  Number of Submissions: 14   Opposed: 10 

A list of submitters is attached as Appendix A 

 

Panel Process    

The Panel  Trevor McCullough (Chair), Rachael O’Neill 

Directions Hearing  Mornington Peninsula Council offices, Rosebud 21 March 2017 

Panel Hearing  Mornington Peninsula Council offices, Rosebud 11 April 2017 

Site Inspections  Unaccompanied, 21 March 2017, 23 April 2017 

Appearances  Mornington Peninsula Shire Council represented by Mr John Rantino of Maddocks Lawyers 

Sorrento OB (DeGroup) Pty Ltd represented by Ms Teresa Bisucci of Best Hooper 

Tyas Super Pty Ltd and Coastal Corner Pty Ltd represented by Ms Julia Bell of David Lock and Associates 

Tixxis Pty Ltd represented by Mr Peter Soding 

Nepean Conservation Group represented by Mr Barend Frielink and Mr Gary Naughton 

Nepean Historical Society represented by Mr Frank Hindley 

Date of this Report  29 May 2017 

 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

 

Executive Summary 

(i) Summary 

Mornington  Peninsula  Planning  Scheme  Amendment  C204  (the  Amendment)  seeks  to introduce Schedule 28 to the Design and Development Overlay (DDO28)  into the Scheme to apply to land within the heritage precinct known as the Ocean Beach Road Commercial Precinct, Sorrento. 

As  exhibited,  DDO28  includes:  design  objectives;  application  requirements;  mandatory height and setback requirements; and decision guidelines. 

Council submitted that the Amendment  is required to  limit the height and scale of future development  within  the  commercial  precinct  of  Sorrento; manage  the  ever  increasing development pressure on Ocean Beach Road; and ensure  that  the historical  significance and coastal village character of the township  is not  lost through the cumulative  impact of inappropriate development. 

An  interim DDO28  currently applies  to  the  land.   The  interim  control applies mandatory setback and height requirements.   The Amendment seeks to  implement the Ocean Beach Road Commercial Precinct Sorrento Heritage Policy (HLCD Pty Ltd 2015) via the permanent introduction of the proposed DDO28. 

Objecting submitters raised the following key issues: 

The strategic justification for using mandatory controls. 

Whether  existing  planning  policy  provides  adequate  guidance  for  built  form outcomes. 

Whether the application of mandatory controls precludes site responsive designs. 

The appropriateness of the proposed precinct boundaries. 

Whether  lift‐overrun  and balustrading  are part of  a building  for  the purpose of calculating a maximum building height and applying height controls in the DDO28. 

The Panel has considered all written submissions along with presentations made to it at a public Hearing held on 11 April 2017. 

Although the Panel was not convinced that there  is a high  level of existing  ‘development pressure’,  or  that  the  built  form  of  recent  developments  is  overwhelming  or  out  of character, on balance the Panel supports the need for additional controls over and above local policy. 

The  Panel was  not  convinced  that  the  proposed mandatory  nature  of  the  setback  and height controls meets the criteria of Planning Practice Notes 59 or 60, and concludes that discretionary  controls  could  achieve  the  built  form  outcomes  sought  by  Council whilst maintaining the design flexibility inherent in a performance based system. 

The  Panel  recommends  that  the  Amendment  proceed,  subject  to  the  replacement  of mandatory  controls with  discretionary  controls,  and  a  number  of  other  changes  to  the proposed DDO28. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

 

(ii) Recommendations 

The Panel  recommends  that Mornington Peninsula Planning Scheme Amendment C204 be adopted as exhibited,  subject  to  the  following changes  to Design and Development Overlay Schedule 28: 

Adopt the changes to the Schedule proposed by Council post‐Hearing as shown 1.in Appendix C to this report, subject to the further changes set out below: 

a  Amend ‘Design objectives’ to include: 

a clearly defined vision for the commercial centre 

require  that  a  development  is  compatible  with  and makes  a  positive contribution to the low scale and character of the precinct 

emphasise  the  need  for  development  to  achieve  excellence  in architecture and design 

includes a  requirement  that views of  significant heritage buildings  (and identify which buildings) are protected 

delete reference to the HLCD report. 

b  Amend ‘Buildings and works’ to: 

remove mandatory requirements 

include discretionary requirements 

include a requirement to the effect of ‘that an application to exceed the maximum building height must be accompanied by a  site analysis plan and a written urban context  report documenting how  the development will achieve the design objectives and outcomes of this schedule’. 

c  Amend ‘Table’ to: 

remove references to storeys 

remove the mandatory height requirements 

remove the mandatory setback requirements 

remove setback requirement for east sub‐precinct 

include a note to the effect that ‘the setback does not relate to unnamed lanes’. 

d  Amend ‘Notes’ to: 

delete notes relating to mandatory controls and storeys 

delete  the words  ‘not  from  the  title boundary’ as  it  relates  to  setbacks from the third storey. 

e  Include  a  separate  heading  of  ‘Application  requirements’  and  include  the following: 

A site context analysis and design response. 

Detailed plans, including palette of materials and finishes. 

A  planning  report  demonstrating  that  the  development  will  achieve design objectives of the schedule. 

A perspective or photomontage detailing how the proposed development will sit within the streetscape. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

 

As appropriate, sightlines to demonstrate that a proposed development does not obstruct views of significant heritage places. 

f  Amend ‘Decision guidelines’ to: 

delete reference to the HLCD report. 

 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 1 

 

1 Introduction 

1.1 The Amendment  

(i) Amendment description 

Mornington  Peninsula  Planning  Scheme  Amendment  C204  (the  Amendment)  seeks  to introduce  new  design  and  development  restrictions  into  the  Mornington  Peninsula Planning Scheme to apply to  land within the heritage precinct known as the Ocean Beach Road Commercial Precinct, Sorrento. 

More specifically the Amendment introduces Schedule 28 to the Design and Development Overlay (DDO28) and applies it to the subject area. 

As exhibited, DDO28 includes: 

design objectives 

application requirements: - all  development  applications  within  the  Ocean  Beach  Road  commercial 

precinct  must  be  accompanied  by  a  site  context  analysis  and  design response  report  demonstrating  how  the  proposal  achieves  the  design objectives and requirements of DDO28; 

- an  application  for  development  exceeding  8 metres  in  height within  the Ocean Beach Road  commercial precinct, must  include a  sightline diagram demonstrating general compliance with the sightlines shown  in Diagram 1 at DDO28 

mandatory height and setback requirements (see Table in DDO28), and 

decision guidelines. 

(ii) The subject area 

The Amendment applies to land shown in Figure 1. 

 

Figure 1  The subject area showing the proposed DDO28 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 2 

 

(iii) Purpose of the Amendment 

Council submitted that: 

The  Amendment  is  required  to  limit  the  height  and  scale  of  future development within  the  commercial  precinct  of  Sorrento.    The  precinct  is arguably the most sensitive area of Sorrento.   As set out earlier, mandatory height  controls  currently  apply  to  all  residential  areas  surrounding Ocean Beach Road and  to  some pockets of  the commercial  zoned  land within  the precinct.   However,  they do not apply  to  the majority of  the precinct.   This represents  a  significant  gap  in  the  current  planning  framework  and  a significant threat to the significance of the heritage place  including  its  low‐scale coastal village character. 

The Amendment (and proposed design and development control) is required to manage the ever  increasing development pressure on Ocean Beach Road and  ensure  that  the historical  significance and  coastal  village  character of the  township  is  not  lost  through  the  cumulative  impact  of  inappropriate development.  The Amendment will also provide much needed certainty to all stakeholders  (i.e.  residents,  community  groups  and  developers)  about Council’s  expectations  and  requirements  for  the  scale  and  form  of  future development in the precinct. 

1.2 Background to the proposal 

The subject area  is zoned Commercial 1 Zone  (with  the exception of 52 and 48A Kerferd Avenue, which  is  located  in  the Public Use Zone 6), and  is  subject  to an  interim DDO28 applied through Amendment C203 approved by the Minister under section 20(4) of the Act and gazetted on 15 December 2016. 

Council advised that the strategic ground‐work for the current Amendment commenced in early 2015 when Council commissioned heritage consultants, HLCD Pty Ltd to prepare the Ocean Beach Road Commercial Precinct Sorrento Heritage Policy for Planning Applications for Places in the Heritage Overlay. 

The  Amendment  seeks  to  implement  the  Policy  via  the  permanent  introduction  of  the proposed DDO28. 

1.3 Summary of issues raised in submissions 

The key  issues raised  in the submissions of  the various parties are briefly summarised as follows: 

(i) Planning Authority 

The key issues for the Council were: 

The strategic justification for using mandatory controls 

Whether  existing  planning  policy  provides  adequate  guidance  for  built  form outcomes? 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 3 

 

(ii) Relevant agencies 

Heritage Victoria did not oppose the Amendment, and requested two very minor changes to a background report. 

The Country Fire Authority supported the Amendment. 

(iii) Individual submitters or groups of submitters 

Objecting submitters raised the following key issues: 

The strategic justification for using mandatory controls. 

Whether  existing  planning  policy  provides  adequate  guidance  for  built  form outcomes. 

Whether the application of mandatory controls precludes site responsive designs. 

The appropriateness of  the proposed DDO and precinct boundaries, particularly relating to: 

- the location of the land at 80‐98 Ocean Beach Road in two precincts - the exclusion of the Koonya Hotel and Morgans Bar from the DDO and the 

eastern sub‐precinct - the inclusion within the DDO and precinct of properties with no recognised 

heritage  significance  including  45  and  47  Kerferd Avenue  and  3293‐3295 Point Nepean Road, Sorrento 

- the inclusion of 60 Kerferd Avenue within the central precinct. 

Whether  lift‐overrun  and balustrading  are part of  a building  for  the purpose of calculating a maximum building height and applying mandatory height control  in the DDO28. 

1.4 Issues dealt with in this report 

The Panel  considered  all written  submissions made  in  response  to  the exhibition of  the Amendment; as well as  further submissions, evidence and other material presented  to  it during the Hearing, and observations from site visits. 

The  Panel  has  reviewed  a  large  volume  of material.   A  list  of  documents  tabled  at  the Hearing  is attached as Appendix B.   The Panel has had  to be selective  in referring  to  the more relevant or determinative material in the report.  All submissions and materials have been considered by  the Panel  in reaching  its conclusions,  regardless of whether  they are specifically mentioned in the report. 

This report deals with the issues under the following headings: 

Planning context 

Are additional controls needed? 

Assessment against PPN59 ‐ Mandatory controls 

Assessment against PPN60 – Activity Centres 

The proposed DDO Schedule 28. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 4 

 

2 Planning context 

Council  provided  a  response  to  the  Strategic  Assessment  Guidelines  as  part  of  the Explanatory Report. 

The Panel has reviewed Council’s response and the policy context of the Amendment, and has made a brief appraisal of  the  relevant  zone and overlay controls and other  relevant planning strategies. 

2.1 Policy framework 

(i) State Planning Policy Framework 

The  state  planning  policy  provisions were  updated  on  31 March  2017  via  Amendment VC134.    As  amended,  Council  submitted  that  the  following  state  planning  policies  are relevant to the Panel’s consideration of the Amendment: 

11‐ Settlement 

11.03‐2 – Activity Centres 

11.05‐1 – Coastal settlements 

11.05‐2 – Distinctive areas of state significance 

11.06‐4 – Place and Identity 

12.02‐1 – Protection of coastal areas 

15.03‐1 – Heritage Conservation 

17.01‐1 – Business 

17.03‐1 – Facilitating Tourism. 

Council submitted that the following clauses were of particular relevance: 

Broad  activity  centre  policy  at  clause  11.03‐2  encourages  the  concentration  of major  retail,  residential,  commercial,  administrative, entertainment  and  cultural developments  into activity centres which provide a variety of  land uses and are highly accessible to the community. 

For  coastal  settlements  such  as  Sorrento,  clause  11.05‐1,  state  planning  policy encourages urban  renewal and  redevelopment opportunities within  the existing settlement  to  reduce demand  for urban  sprawl.    The overall objective  for  such settlements is to achieve sustainable coastal development. 

Clause  11.05‐2  (Distinctive  Areas  of  State  significance)  recognises  and  seeks  to protect  and  enhance  the  valued  attributes  of  five  distinctive  areas  in  Victoria, including the Mornington Peninsula. 

Clause 11.06‐4 (Place and  identity) also promotes urban design excellence  in the built environment and clause 15 of  the Scheme offers  some guidance on how a high standard of urban design and amenity might be achieved.  It sets out various urban  design  principles  intended  to  achieve  “architectural  and  urban  design outcomes  that  contribute  positively  to  local  urban  character  and  enhance  the public realm while minimising detrimental impact on neighbouring properties”. 

For coastal areas, more specific urban design policy is set out at clause 12.02‐1.  It seeks  to ensure potential development  is sensitively sited and designed so as  to respect the valued character of coastal settlements. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 5 

 

State planning policy relating to heritage conservation at clause 15.03  (Heritage) of the Scheme includes various strategies directed to ensuring the conservation of places of heritage significance.  Relevantly, the strategies include to: 

- identify,  assess  and  document  places  of  natural  and  cultural  heritage significance as a basis for their inclusion in the planning scheme 

- provide for the conservation and enhancement of heritage value - encourage  appropriate  development  that  respects  places with  identified 

heritage values - ensure an appropriate setting and context for heritage places is maintained 

or enhanced. 

(ii) Local Planning Policy Framework 

Council submitted that the Amendment supports the following local planning objectives: 

21.07‐2 – Local Area Character 

22.02 – Activity Centres 

22.04 – Heritage Places and Abutting Land 

22.05 – Aboriginal Cultural Heritage 

22.13 – Township Environment 

22.17 ‐ Sorrento Historic Precinct Policy. 

Council submitted that the following policies are particularly relevant: 

Council's  general  heritage  policy,  'Heritage  Places  and  Abutting  Land'  at  clause 22.04 seeks  to conserve and appropriately manage  identified heritage places.    It includes  a  policy  to  require  new  development  to  retain  the  significance  of  a heritage place such as through: 

- being  visually  recessive  and  compatible  in  terms  of  scale,  siting,  design, form and materials with the historic character and significance of the place 

- responding  positively  to  special  features  such  as  views,  vistas,  mature vegetation and landmarks. 

Council  also  has  a  heritage  policy  specifically  tailored  to  the  Sorrento  Historic Precinct at clause 22.17 of the Scheme.  It applies to all land in HO1 including the Subject  Land  (other  than  the Continental Hotel  and Athenaeum heritage places which are on the Victorian Heritage Register). 

It includes 'general' objectives to: - protect  and  enhance  vistas  of  both  natural  and  man‐made  historical 

significance, views and landmarks - ensure  new  development  is  complementary  to  the  significance  and 

character of the Precinct - conserve and enhance the significance of heritage places in the Precinct; - conserve  and  enhance  the  streetscapes  of  the  Precinct  and  in  particular 

Ocean Beach Road - ensure  that  new  development  is  compatible  with  the  height,  scale  and 

siting of existing development in various parts of the Precinct. 

Complementary to those objectives are the following 'general' policies to: 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 6 

 

- ensure that new development does not have an adverse impact on existing vistas, views and landmarks 

- ensure new development responds positively to the location, height, mass, materials and external appearance of existing development in the Precinct;  

- require new development to respect the height, scale and siting of existing development in the various parts of the Precinct 

- consider  the  cultural  significance  of  a  heritage  place,  including  any statement of significance, when assessing proposals to develop or demolish the heritage place. 

The Sorrento Historic Precinct Policy also  includes a sub‐policy applying to all the land  in  the Ocean Beach Road Area as defined  in  the Policy, which  includes  the Subject Land (other than the Continental Hotel and Athenaeum heritage places). 

According  to  the  Policy,  the  Ocean  Beach  Road  Area  is  of  significance  for  its important  concentration  of  commercial  premises  of  high  historical  significance and also for the landmark qualities of the Continental Hotel and Stringers Store.  It is  also  described  as  being  of  aesthetic  and  architectural  significance  because  it demonstrates a number of changing methods of construction and design over the years including many buildings of limestone construction. 

The character of the Ocean Beach Road area is described in the Policy as: 

… that of an historic seaside village with a wide promenade type indigenous tree  lined main street with clear views to both the Bay and the back beach sand dunes and comprising mainly low rise commercial development and low density housing … 

Relevant policy objectives in relation to the Ocean Beach Road area include: - To  retain  the  historical  integrity  of  the  Continental  Hotel  and  Stringers 

Stores as landmark features at the entry to the main commercial area. - To  create  an  entrance  to  Sorrento’s main  street  at  the  corner  of  Point 

Nepean Road  and  Esplanade which  recognises  the heritage  values of  the Precinct. 

Related to these objectives, where a permit is required for development of land it is policy to: 

- Discourage the erection of buildings that exceed eight metres in height - Encourage buildings which incorporate the following design characteristics: 

- Typical form and elements of a Victorian or Edwardian shopfront, where appropriate 

- Original Victorian and Edwardian shopfronts - Reinforcement of the existing built form - Restorative alterations to significant heritage places - Roof pitch of not less than 22 degrees. 

- Require development at the corner of Point Nepean Road and Esplanade to recognise the special significance of the corner as an entrance to Sorrento’s main  street  and  to  complement  the  Koonya  Hotel/Stringers  Corner redevelopment, with special emphasis on building setbacks, landscaping, car parking away from Point Nepean Road and sight distances for traffic. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 7 

 

(iii) Other planning strategies or policies used in formulating the Amendment 

Ocean Beach Road Commercial Precinct Heritage Policy 

The Policy was adopted by Council on 22 September 2015. 

Council  submitted  that  the  commercial  precinct  in Ocean  Beach  Road  and  Point Nepean Roads, Sorrento has been identified in the Scheme as a valued heritage place for many years.  It  has  been  located  within  the  Heritage  Overlay  (HO1)  since  the  New  Format  Planning Scheme commenced on 6 May 1999. 

The stated aim of the Policy is: 

…to  provide  guidance  for  the  future  conservation  and  development  of  this area  to  protect  the  cultural  heritage  significance  of  the Ocean  Beach  Road Commercial  Heritage  precinct.    The Ocean  Beach  Road  Heritage  Policy  has been written to assist owners undertaking works and Council officers assessing planning approvals for new development or alterations to existing properties. 

The purpose of the Policy is “to retain the special qualities in the physical environment that arise from the history of development in Ocean Beach Road.” 

Council  submitted  that  the  Policy  was  prepared  with  reference  to  key  relevant  cultural documents  in  Australia  including  the  Burra  Charter  and with  regard  to  Planning  Practice Note 01: Applying the Heritage Overlay. 

The Policy includes a statement of cultural significance for the broad study area or precinct, which is recited at the commencement of each sub‐precinct policy. 

The Policy describes the broad Precinct as being of importance to residents and visitors at a local significance  level “for  its character as a historic seaside village  in a  landscaped setting with views to natural and historic features because of  its historical significance,  its rarity,  it representativeness, its aesthetic significance and its strong or special associations”. 

The reasons the Precinct is identified as being significant include: 

Because of  its  intactness and ability  to demonstrate  the  two  key periods of development  (the  1870’s  and  1890’s  and  the  resort  boom  of  the  1890’s  to 1920’s), through its early buildings and setting; 

Because  it  demonstrates  principal  characteristics  of  the  1870’s  and  1880’s period of development,  including the  low scale of a seaside village, following the natural topography and creating a main street.1 

The  Policy  divides  the  study  area  into  four  sub‐precincts,  based  on  the  different characteristics within  the precinct  and provides  an  individual policy  for  each  sub‐precinct appropriate to its characteristics as shown in Figure 2. 

                                                       1  See Section 4.2, page 3 of the Policy. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 8 

 

 

Figure 2  The four sub‐precincts identified in the Ocean Beach Road Commercial Precinct Heritage Policy 

For  each  sub‐precinct,  the  Policy  provides  guidance  in  relation  to  additions  and  infill.    In relation  to building heights and  setbacks,  it provides quite  specific guidance  for each  sub‐precinct. 

2.2 Planning scheme provisions 

(i) Zones 

As shown in Figure 3, the subject area is zoned Commercial 1 Zone with the exception of the land at 52 and 48A Kerferd Avenue, which is located in the Public Use Zone 6. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 9 

 

Figure 3  Current zone map 

No changes to zones are proposed as part of the Amendment. 

(ii) Overlays 

The Heritage Overlay Schedule 1 (HO1) applies to all of the subject land except: 

1‐21A Ocean Beach Road  (Continental Hotel) which  is subject  to Heritage Overlay Schedule 257 (HO257) 

36‐38  Ocean  Beach  Road  (Athenaeum)  which  is  subject  to  Heritage  Overlay Schedule 408 (HO408). 

Environmental Significance Overlay Schedule 25 (ESO25) applies to 3293‐3295 Point Nepean Road. 

2.3 Ministerial Directions and Practice Notes 

(i) Ministerial Directions 

Council  submitted  that  the Amendment meets  the  relevant  requirements of  the  following Ministerial Directions:  

Ministerial Direction – The Form and Content of Planning Schemes under s7(5) of Act 

Ministerial Direction No 9 – Metropolitan Strategy under s12(2)(a) of the Act 

Ministerial Direction No 11 – Strategic Assessment of Amendments under s12(2)(a) of the Act 

Ministerial Direction No 17 – Localised Planning Statements under s12(2)(a) of the Act. 

(ii) Planning Practice Notes (PPN) 

PPN59 The role of mandatory provisions in planning schemes, June 2015 applies because the Amendment  proposes  to  apply  mandatory  height  and  setback  controls  in  DDO28.  Assessment against PPN59 is discussed in Chapter 4 of this report. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 10 

 

PPN60 Height and setback controls for activity centres also applies, and this  is discussed  in Chapter 5. 

2.4 Discussion and conclusions 

The Panel accepts that the Amendment  is broadly consistent with State and  local planning policy frameworks, and complies with the relevant ministerial directions. 

The Panel notes the substantial body of heritage policy and planning controls that apply to individually significant sites and the Precinct more broadly. 

The questions of whether additional controls are justified, whether mandatory controls are justified, and compliance with the relevant PPNs are discussed in the following chapters. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 11 

 

3 Are additional controls needed? 

3.1 The issue 

Do the existing policies in the planning scheme achieve the desired built form outcomes? 

Some submitters questioned whether the proposed controls were needed, arguing that the existing policies have not created undesirable built form outcomes. 

3.2 Submissions 

Mr Rantino, appearing for Council, submitted that the Amendment was required to fill a gap in the current planning framework to: 

limit the height and scale of future development within the commercial precinct of Sorrento 

to  manage  what  he  described  as  an  “ever  increasing  development  pressure  on Ocean Beach Road” 

to provide certainty  to all  stakeholders with  respect  to  the Council’s expectations and  requirements  for  the  scale  and  form  of  development  allowable  within  the precinct. 

In relation to the first point, Mr Rantino advised that mandatory controls currently apply to all residential areas surrounding Ocean Beach Road and to some pockets of the commercial zoned  land within the precinct.   He submitted that the gap  in mandatory controls posed a “significant  threat  to  the  significance  of  the  heritage  place  including  its  low‐scale  coastal village character”.  In relation to the threat of development pressure, he submitted that the controls  were  required  to  “ensure  that  the  historical  significance  and  coastal  village character  of  the  township  is  not  lost  through  the  cumulative  impact  of  inappropriate development”. 

In support of the assertion that the existing policy was deficient, Mr Rantino submitted2: 

The  existing  local  planning  policy  for  the  precinct  at  clause  22.17  (Sorrento Historic Precinct) provides  some guidance  for height,  scale and  setbacks  for new  development  in  the  precinct  but  is  not  terribly  sophisticated.    For example,  it  discourages  the  erection  of  buildings  that  exceed  8  metres  in height without providing any related guidance on the circumstances  in which the 8 metre height may be varied.   For example, having regard to the size of the site and the setback of the part of the building above 8 metres  from the site boundaries.  Also, being discretionary, there is no certainty that the policy will be applied consistently and rigorously. 

Related to this, historical reliance on planning policy to achieve an appropriate outcome  has  resulted  in multiple  developments  being  approved  that  have been  at  odds  with  the  valued  low‐scale  coastal  village  character  of  the Precinct.    These  developments  would  and  could  not  be  approved  if  the proposed mandatory height controls were introduced. 

                                                       2   Council Part A submission para 112. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 12 

 

Ms Bisucci, appearing for Sorrento OB (DeGroup) Pty Ltd (Submission 6) was critical of the strategic  justification for the Amendment and submitted that built form controls should be strategically  justified  from  a  policy  and  physical  context.    She  submitted  that  the Amendment: 

is not based on any vision which supports urban renewal having regard to the physical context but rather on the basis that there  is  increasing development pressure … tighter controls must be placed ….to limit height and scale … 

She further submitted that the: 

Amendment  is  a  reactive  response  which  implies  that  either  the  current controls and policy framework is inadequate or that the decision makers have got it wrong. 

Ms Bisucci submitted that there is ample: 

specific  and  dedicated  existing  policy  for  the  Sorrento  Township  which provides  appropriate  design  and  development  guidance  to  ensure  that  any development  is  respectful of and complementary  to  the coastal  location and the heritage significance of the area. 

The  Nepean  Conservation  Group  (Submission  14)  and  the  Nepean  Historical  Society (Submission  13) were  supportive  of  the  intent  of  the  Amendment  and,  in  particular,  the Historical Society submitted that it agreed: 

with  the Council assessment  that an Amendment  is  required  to manage  the increasing development pressure  on Ocean Beach Road, and  to  ensure  that the historical significance and coastal village character of the town is not lost through inappropriate development. 

Both groups were critical of the recent development that had occurred within the town, the uncertainty provided  through  the existing controls  that  resulted  in Council decisions being challenged, and the cost associated with VCAT appeals borne by all parties.  They were also critical of  the  change  in  the nature of  land use,  submitting  that  the  recent developments were focused on residential rather than commercial. 

Ms Bell, appearing for Coastal Corner Pty Ltd (Submission 1), was critical of the Amendment and submitted that  it was not based on a sound strategic rationale.   She further submitted that  the  controls  give  little  consideration  to  the  existing  physical  conditions,  which  she observed was  due  to  the  lack  of  testing  of  appropriate  built  form  outcomes,  based  on  a rigorous analysis.    In her review of the existing planning policy context, Ms Bell noted that Plan Melbourne 2017 no  longer referred to protecting Melbourne’s neighbourhood centres with mandatory controls. 

Mr Soding  (submission 11)  submitted  that  the heritage values of  the precinct are already protected  by  the  presence  of  the Heritage Overlay  and what  he  described  as  “extensive policy” in the Local Planning Policy Framework (LPPF).  He submitted that: 

a DDO with a vice grip on heights and  setbacks  is not needed.   The existing policy within the SPPF and LPPF would give the outcomes sought.  In respect to the  setbacks  proposed,  the  proposal  to  setback  the  third  and  upper  level  a 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 13 

 

minimum of 8 metres from the front may lead to a worse planning and design outcome as  it advocates a stepping of the building where site conditions and view lines may not require such a step in the building. 

3.3 Discussion 

Mr Rantino provided the Panel with a folder containing copies of all recent applications for planning permits,  including permits  issued, endorsed plans and VCAT decisions.   The folder also contained one application for planning permit and plans that have formed the basis of pre‐application discussions.   Having  reviewed  the approvals,  the Panel  is of  the view  that there  has  not  been  a  high  number  of  applications  that  would  constitute  ‘development pressure’ or at a level that seems overwhelming for an activity centre.  The Panel notes that the  details  of  the  approval  at  68‐70 Ocean  Beach  Road were  not  included  in  the  folder provided to the Panel, and that this is evidently a recent development and one referred to in submissions. 

The Panel observes  that  the  approvals  range over  a  ten  year period  and  that  the overall height of developments that have been approved are generally consistent with the heights referenced in the Amendment, although setbacks differ across the approved developments.  The number of storeys achieved within the overall heights also differ. 

Having  inspected the subject area, the Panel  is of the view that the new developments sit comfortably within the streetscape and do not visually dominate or overwhelm it.  The Panel observes that to date the historical significance and coastal village character of the township has not been lost or eroded.  The Panel is of the view that the developments that have been approved but not yet constructed will not alter that outcome. 

A summary of the approvals to date and the Panel’s observations is provided in Appendix D. 

Mr Rantino  tabled an Urban Design Analysis Package, prepared by Hansen Partnership, at the commencement of the Hearing.  This was amended and provided to the Panel following the Hearing.  Whilst not the subject of evidence or cross‐examination, the Panel considered the document  to be of assistance  in detailing context,  lot  size,  land use and development potential. 

On  the  basis  of  the  Panel’s  review  of  approvals  and  the  existing  policy  context,  and  the Panel’s  inspection of the commercial precinct, the Panel  is of the view that approvals have been clearly influenced by existing policy.  It is clear that VCAT and parties in applications for review  have  given  due  consideration  to  the  various  planning  provisions  and  policies, including those relating to activity centres and heritage.  The Panel does not agree with the submission advanced on behalf of the Council by Mr Rantino that: 

historical reliance on planning policy  to achieve an appropriate outcome has resulted in multiple developments being approved that have been at odds with the valued low‐scale coastal village character of the Precinct. 

The  Panel  understands  and  accepts  Council’s  preference  (and  indeed  that  of  other submitters)  that  it  is  desirable  and  fair  to  have  a  more  precise  control  that  guides appropriate scale and form of development within the commercial centre.  On balance, the Panel agrees that a more specific level of control in the form of a DDO is appropriate for the centre.   The Panel accepts that there  is benefit  in clearly articulating the desired built form 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 14 

 

outcomes for the centre.   The question of whether these controls should be mandatory or discretionary is discussed in the next Chapter. 

3.4 Conclusions 

The Panel concludes: 

There  has  not  been  a  high  number  of  applications  that  would  constitute ‘development pressure’ or at a level that seems overwhelming for an activity centre. 

The  overall  height  of  developments  that  have  been  approved  are  generally consistent with  the heights  referenced  in  the Amendment, although setbacks and numbers of storeys vary. 

The new developments sit comfortably within  the streetscape and do not visually dominate  or  overwhelm  it,  and  the  historical  significance  and  coastal  village character of the township has not been lost or eroded. 

Approvals have been clearly influenced by existing policy. 

The Panel does not agree  that  recent developments are “at odds with  the valued low‐scale coastal village character of the Precinct”. 

On balance, a more specific level of control in the form of a DDO is appropriate for the centre. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 15 

 

4 Assessment against PPN59 ‐ Mandatory controls 

4.1 The issues 

The Amendment proposes mandatory height and  setback controls  in  the  table  to DDO28.  The  issue  is whether mandatory height  and  setback  controls proposed  in  the DDO28  are justified. 

If it is determined that mandatory controls are not strategically justified, then a further issue is whether DDO28 remains appropriate in the context of discretionary controls.  This issue is discussed in Chapter 6. 

4.2 Introduction 

Planning Practice Note 59 (PPN59) is relevant to the consideration of mandatory controls.  In its  introduction PPN59 notes that the Victoria Planning Provisions (VPP) are predominantly performance based.  It notes that mandatory provisions in the VPP are the exception.  It also notes that the: 

VPP process is primarily based on the principle that there should be discretion for  most  developments  and  that  applications  are  to  be  tested  against objectives  and  performance  outcomes  rather  than  merely  prescriptive mandatory requirements. 

PPN59  notes  that  there will  be  circumstances where  a mandatory  provision will  provide certainty and ensure a preferable and efficient outcome. 

PPN59 states  that mandatory provisions will only be considered  in circumstances where  it can be clearly demonstrated that discretionary provisions are insufficient to achieve desired outcomes.  It lists criterion that should be used to assess whether the benefits of mandatory controls  outweigh  any  loss  of  opportunity  or  flexibility  inherent  in  a  performance  based system: 

Is the mandatory provision strategically supported? 

Is the mandatory provision appropriate to the majority of proposals? 

Does the mandatory provision provide for the preferred outcome? 

Will the majority of proposals not  in accordance with the mandatory provision be clearly unacceptable? 

Will the mandatory provision reduce administrative costs? 

The views of the submitters differed as to whether mandatory controls were appropriate for the centre.  These submissions and the PPN59 criteria are discussed below. 

4.3 Is the mandatory provision strategically supported? 

(i) Submissions 

Mr Rantino submitted that the special characteristics of the subject land and its location on the Mornington  Peninsula  is  “key  to  the  strategic  basis  for  using mandatory  height  and setback provisions”.   He noted that the significance of the Peninsula was  identified  in State 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 16 

 

planning  policy  and  the Mornington  Peninsula  Localised  Planning  Statement,  2014.    He advised that: 

Most  relevantly,  the  Statement  identifies  the  establishment of a  strong and consistent overall planning framework for future land use and development on the  Peninsula  as  being  ‘essential’  given  the  particular  pressures  on  the Peninsula’s  rural  landscapes,  coasts,  towns  and  villages,  and  the  risk  of unintended and unplanned change, through cumulative  impacts.    It expressly anticipates  the  use  of  mandatory  controls  and  standards  in  the  planning framework where necessary to achieve this objective. 

Mr  Rantino  also  referred  to mandatory  controls  that  had  been  applied  in  the  villages  of Flinders,  Shoreham  and  McCrae.    He  advised  that  the  DDOs  applied  to  these  centres prescribe  a mandatory maximum  building  height  of  8.5 metres with  no more  than  two storeys above natural ground  level.   He  tabled a copy of  the Panel report  for Amendment C101 to the Mornington Peninsula Planning Scheme (Flinders).  Mr Rantino submitted that: 

the  Sorrento  village  centre,  like  the  Flinders  village  centre,  warrants mandatory  height  controls  to  preserve  the  existing  scale,  character  and heritage values and setting of the Sorrento centre. 

In relation to  implementing policy, Mr Rantino submitted that the proposed control would implement  the purpose of  the Ocean Beach Road Commercial Precinct  Sorrento Heritage Policy (the HLCD report); would achieve two objectives of Clause 22.17; and would assist in achieving  policy  objectives  of  Clause  22.02  of  the  planning  scheme.    In  summary,  he submitted that the controls would: 

achieve the policy relating to height and setbacks of the Ocean Beach Road policy 

ensure the retention of the existing streetscape character of the area 

ensure  that  commercial  development  contributes  to  the  scale  and  urban  design quality of the centre, enhance the public realm and respect heritage values 

maintain  consistent  standards  for  development  in  relation  to  height  and landscaping. 

Conversely, Ms Bisucci submitted that the Amendment does not meet this criteria of PPN59.  She  submitted  that  the  Heritage  Overlay,  Clause  22.04  and  Clause  22.17  are  the more appropriate mechanism  to  guide  development  and  respond  to  the  heritage  value  of  the streetscape.  Further, she submitted that: 

rather  than  add  another  layer  of  control,  it  is  considered more  appropriate that  the Council consider amending  the current performance based planning provisions if they are deficient. 

Ms Bell  included a comprehensive summary of the relevant State and  local planning policy framework relevant to the Amendment.  She submitted that the Amendment does not have a sound strategic basis: 

The application of a design control of this nature over the extent of an activity centre requires analysis and testing of the existing and future built form along with  its  capacity  to  accommodate  housing  growth,  given  the  limited opportunities  in  the  residential  hinterland  surrounding.    The  DDO  schedule 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 17 

 

should be informed by the preparation of an urban design report justifying the heights and setbacks across each precinct. 

Mr  Soding was  also  of  the  view  that  the  existing  State  and  local  planning  policy would provide the outcomes sought by the proposed controls. 

(ii) Discussion 

The Panel acknowledges the objectives and strategies of the Mornington Peninsula Localised Planning  Statement,  including  those  to maintain  and  enhance  the  character  and  role  of towns in the Peninsula and to effectively manage future change.  It is evident that the extent of change  is unlikely to be as significant as other activity centres, particularly those outside of the Peninsula. 

The Panel, however, also acknowledges that there is clear policy direction in Plan Melbourne 2017,  including  that detailed at Policy 1.2.1 which notes  that all activity  centres have  the capacity to continue to grow and diversify the range of activities they offer.  Plan Melbourne 2017 also notes that “to capture and to accommodate  future growth opportunities activity centres will need greater flexibility  in planning controls than surrounding residential areas”.  This  is  contrasted  with  the  policy  objectives  relating  to  residential  areas  where  Plan Melbourne notes that there has been a strengthening of mandatory controls in the review of the residential zones. 

It  is clear that the Localised Planning Statement seeks to encourage the establishment of a strong  policy  framework.    Plan  Melbourne  also  promotes  such  an  approach  where  it identifies  that “local plans undertaken  in consultation with  the community will  identify  the scope and nature of future growth within each activity centre”. 

The differentiation between  the  two documents  seems  to be  the  reference  to  the use of mandatory controls.  The Localised Planning Statement states that it may be appropriate to use mandatory controls where necessary due to particular pressure on towns and the risk of unintended and unplanned  change  through  cumulative  impacts.   The Panel  is of  the view that  this  is  a  situation  where  the  imposition  of mandatory  controls  is  not  necessary  to facilitate appropriate development and growth within the Sorrento commercial centre.   As discussed  in the previous Chapter, the Panel does not agree with submissions advanced by Council  that  there  has  been  development  pressure  on  the  town  or  indeed  that  the development undertaken has resulted in intended or unplanned change. 

The Panel  is of the view that the policy framework does not support the use of mandatory controls.  It is of the view that objectives and strategies relating to retaining the character of the streetscape and ensuring that development  is appropriately designed and sited can be readily achieved through the use of discretionary controls. 

4.4 Is the mandatory provision appropriate to the majority of proposals? 

(i) Submissions 

Mr  Rantino  submitted  that  Council  had  given  careful  consideration  to  the  scope  of  the proposed mandatory controls to ensure that they would be appropriate in the vast majority of cases.   He advised  that  the Council engaged Hansen Partnership  to undertake an urban 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 18 

 

design analysis to road test the proposed controls.  He advised that Hansen had identified a number of sites within the commercial precinct that were vacant/underutilised and likely to be  developed.    He  also  observed  that  whilst  submitters  had  raised  concerns  with  the constraints  imposed  as  a  result  of  the  proposed  controls,  none  had  suggested  that  the proposed DDO28 would result in inappropriate development or present financially unviable development of their properties. 

Ms Bisucci submitted that,  in the absence of a comprehensive built form analysis prepared as part of  the Amendment,  it  is difficult  to determine  the visual and amenity  impacts  the proposed controls would have on the commercial precinct and what type of  influence this would have taking  into account consideration of  land use outcomes and economic growth.  She submitted that this was a major flaw. 

Contrary  to  the  position  advanced  by Mr  Rantino, Ms  Bell  submitted  that  the  proposed controls  “would  limit  the  unnecessary  loss  of  flexibility  and  opportunity  available  in  the performance based controls”.  She submitted that the scope of the mandatory controls had not been carefully considered to ensure that they would be appropriate in the vast majority of cases.  She also submitted that, of the 60 properties fronting Ocean Beach Road, only 23 are  identified  as  being  individually  significant within  the  Ocean  Beach  Road  Commercial Precinct Sorrento Heritage Policy.   She concluded that, given the  lack of  individual heritage significance, performance based controls are more appropriate to deliver flexibility in design. 

(ii) Discussion 

As  noted  in  Chapter  3  of  this  report,  Mr  Rantino  tabled  the  Hansen  work  at  the commencement of the Hearing.  It was not publicly available prior to the Hearing.  The Panel notes that the Hansen work was not presented as expert evidence during the Hearing, and it has not been subjected to critical review. 

Having now had  the benefit of  reviewing  the Hansen work,  the Panel notes  that whilst  it documents  ‘built  form  envelopes’,  in  some  cases  these  do  not  correlate  with  the identification  of  ‘contributory’  heritage  buildings,  or  sites  that  have  been  recently redeveloped, or  indeed sites that have been  identified as  ‘unlikely to develop’.   Whilst the Hansen  report provides  some useful  context and analysis,  it has not been presented as a detailed impact analysis from which definitive conclusions could be drawn. 

The Panel  is not  convinced  that  the proposed mandatory  controls  are  appropriate  to  the majority of proposals.  The Panel believes that proposals that do not strictly comply with the proposed mandatory controls could still be acceptable provided that they meet the design objectives of DDO28.  This is evidenced by some of the existing developments that may not meet the proposed mandatory standard, but nevertheless provide acceptable outcomes. 

4.5 Do the mandatory provisions provide for the preferred outcome? 

(i) What are the considerations? 

PPN59  lists  the  following  three  criteria  be  used  to  assess whether  or  not  the mandatory provisions provide for the preferred outcome: 

Does  a  proposed  mandatory  provision  resolve  divergent  opinions  within  the community as to a preferred outcome when a consistent outcome is necessary? 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 19 

 

Does  a  proposed  mandatory  provision  avoid  the  risk  of  adverse  outcomes  in circumstances  where  there  is  likely  to  be  constant  pressure  for  development inconsistent with planning policy? 

Is there real evidence of development exceeding the proposed control? 

(ii) Submissions 

Mr Rantino  submitted  that  the proposed  controls would  facilitate  the Council’s preferred outcome  of  ensuring  that  development maintains  the  low  scale  of  development  in  the centre.    He  also  submitted  that  the  mandatory  controls  would  clearly  articulate  to developers what was an appropriate level of development, and what was ultimately sought by residents and visitors to the area who value the low scale character of the village centre.  He submitted that: 

The proposed mandatory controls will avoid  the  risk of adverse outcomes  in circumstances where, because of  the high  level of discretionary spend  in  the activity centre, the tourism of the area and the high land values, there is likely to  be  constant  pressure  by  developers  seeking  to  develop  land  at  building heights  inconsistent  with  local  planning  policy,  in  order  to  maximise  the development potential (and profit) within the precinct. 

Mr  Rantino  submitted  that  the  mandatory  controls  are  necessary  to  avoid  “further development being approved  that  is at odds with  the valued  low scale village character of the Precinct”.  He then listed a summary of examples of approved development that exceed the  limits of  the proposed controls.   He submitted  that  these developments would not be approved  if  the  proposed mandatory  height  controls were  introduced.    The  Panel  noted that, apart from one example, being at the rear of the Continental Hotel, the overall height of  the  developments  was  below  the  proposed  11 metre  height  control,  and  it was  the setback at the second storey that encroached into the proposed setback.  The Panel put this observation to Mr Rantino and he confirmed that this was the case. 

The Nepean Conservation Group and the Nepean Historical Society were of the view that the proposed mandatory  provisions  would  resolve  divergent  opinions  as  they  would  clearly articulate  acceptable  built  form  outcomes  for  the  centre.    These  groups  were  very concerned about the extent of redevelopment that had occurred recently in the centre and the adverse impacts these had on the character of the precinct. 

Mr Soding advised the Panel that he had reviewed VCAT decisions in the precinct since 2006, and on the basis of this review he had form the view that the three reviews (two of which had been against conditions) “is hardly in our view significant pressure”. 

(iii) Discussion 

The  Panel  understands  the  Council’s  and  other  submitters’  preference  for  mandatory provisions on  the basis  that applicants  for planning permits and  the  community will have clearly defined parameters of the extent of development deemed acceptable by the Council; however, the Panel does not agree that a consistent outcome  is necessary.   That  is, whilst the Panel accepts that it is appropriate to establish development objectives for the precinct, it does not accept that it is necessary to achieve a consistent outcome in terms of absolute 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 20 

 

overall heights,  setbacks or  storeys.    It  is possible  to achieve development  that  is broadly consistent  with  design  objectives  but  that  allows  for  variation  in  height  or  setback  to encourage differentiation between buildings and visual interest without uniformity. 

Further, the Panel does not accept that mandatory provisions will necessarily avoid the risk of adverse outcomes.   Firstly, the Panel does not accept that there has been, or that there will be, likely constant pressure for development that is inconsistent with planning policy.  It is also of  the view  that  there  is no  real evidence of development exceeding  the proposed control, indeed as noted above, all but one of the developments are less than 11 metres in overall  height.    Secondly,  the  Panel  is  of  the  view  that  discretionary  controls  can  be satisfactorily used  to guide appropriate built  form outcomes.   Thirdly, mandatory controls are no guarantee of quality architectural outcomes or design responses. 

4.6 Will the majority of proposals not  in accordance with the mandatory provision be clearly unacceptable? 

(i) Submissions 

Mr Rantino submitted  that  the cumulative  impact of developments  that were  inconsistent with the proposed controls would result in an unacceptable outcome. 

Ms Bell submitted  that  the proposed height controls do not achieve  the outcomes sought within the design objectives of proposed DDO28. 

(ii) Discussion 

The design objectives of the proposed DDO28 seek to: 

ensure that development  is respectful of and makes a positive contribution to the low scale character of the streetscape 

provide for a graduated building height from Ocean Beach Road and Morce Avenue 

promote design excellence 

ensure  that development exceeding eight metres  in height  is generally not visible from eye level directly opposite 

ensure  that development has adequate regard  for  the design requirements  in  the HLCD report. 

Mr  Rantino  advised  the  Panel  that  the  sightline  objective  was  drafted  as  an  important application requirement, but was not a mandatory provision. 

Given the presence of the Heritage Overlay and contributory buildings; the need to comply with the requirements of the overlay and policy; coupled with the fact that some sites are unlikely to be redeveloped,  it  is the Panel’s observation that there would not be a majority of proposals that would not accord with the requirements.   Further, should a proposal not accord with the requirements, it is not clear that this would necessarily be an unacceptable outcome.    It  is  the Panel’s  view  that well drafted design objectives  and detailed decision guidelines can satisfactorily achieve appropriate built form outcomes. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 21 

 

4.7 Will the mandatory provision reduce administrative cost? 

(i) Submissions 

Mr  Rantino  submitted  that  the  proposed  mandatory  controls  would  be  highly  likely  to reduce the costs that Council currently  incurs as there would be greater certainty afforded by the controls and in turn fewer appeals. 

The Nepean Conservation Group also submitted that the mandatory controls were required as the VCAT process is expensive for Council and other parties. 

(ii) Discussion 

The Panel accepts that the application of mandatory controls could result  in a reduction of costs.   However, given  the  limited number of applications  for  redevelopment, and noting that several planning permits were granted by the Council without the need for an appeals process,  indicates to the Panel that the costs do not significantly outweigh the benefit of a performance based provision. 

4.8 Do the proposed controls provide adequate flexibility of design? 

(i) Introduction 

Whilst ‘flexibility of design’ is not in itself a criterion, PPN59 says that the criteria “should be used  to assess whether or not  the benefits of any proposed mandatory provision outweigh any  loss of opportunity and  the  flexibility  inherent  in a performance based  system”  (Panel emphasis). 

The Panel believes  it  is worthwhile examining whether mandatory controls would provide for adequate flexibility of design. 

(ii) Submissions 

Two of the submitters undertook an analysis on the effect of the proposed controls on their clients’  properties.    The  Panel  considers  it  appropriate  to  provide  the  details  of  these submissions as they have assisted in providing an understanding of the actual impact on the development  potential  of  properties  and  informed  its  view  as  to  the  appropriateness  of imposing mandatory controls. 

Mr Rantino advised at the commencement of the Hearing that Council had: 

agreed  to  remove  the  requirement  for  side  setbacks  and  setbacks  from  the  rear building line within the north‐west precinct 

amended  the  requirement  at  column  2  of  the  table  in  the  Schedule  to  refer  to “maximum building height at road frontage” 

included  an  additional  requirement  in  the  central,  north‐west  and  south‐west precincts that required “where the site is on a corner with a named road or lane, a minimum of 3 metres from the side street building line or the second storey below.” 

In closing, Mr Rantino submitted  that he did not accept  the proposition put by Mr Soding that mandatory controls result in “dumbed down” architecture.  He observed that there are 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 22 

 

many excellent examples of quality architecture up and down  the coast  that are designed responding to mandatory controls. 

Ms Bisucci observed that the HLCD report does not talk about a vision “but provides details of what  is  there and why  the Council wants  to keep  it”.   She  submitted  that a DDO  is an appropriate tool to guide built form, but it was the issue of mandatory controls that was of concern.   She added  that  “eight metres  is not  the magic number”  for  front  setbacks.   Ms Bisucci requested that the Panel set design criteria in DDO28 where additional height can be achieved, for instance on large sites, sites that do not contain or abut contributory buildings. 

Ms  Bell  detailed  the  proposed  controls  relevant  to  the  various  properties  owned  by  her client,  and  the  development  outcomes  that  could  be  achieved.    A  summary  of  her submission in relation to these properties is detailed in Table 1 below. 

Table 1  An assessment of the development potential of properties owned by TYAS Super Pty Ltd and Coastal Corner Pty Ltd 

Address  Submission 

172 Ocean Beach Road 

Not identified as a contributory property and it is not sited adjacent to contributory heritage properties. 

The frontage of properties 170, 172 and 174 Ocean Beach Road are misaligned with the balance of the street, set back approximately 6 metres.  DDO28 requires a 5 metre setback from Ocean Beach Road.  It is unclear from the controls as to whether the 5 metre setback is required from the front of the allotments adjacent or from the main boundary alignment along Ocean Beach Road. 

The site has a depth of approximately 25 metres.  Any third storey must be set back 8 metres from the front, making the third storey unviable. 

85‐89 Ocean Beach Road 

Not identified as a contributory property and it is not sited adjacent to contributory heritage properties. 

The setback of the third storey is to be measured from the front wall of the second storey of the building, not from the front title boundary. 

As the client is considering adding an additional storey to the existing building, due to the existing front setback, the upper level setbacks required from the second storey (which is also recessed) below leaves a developable area of 5 metres, making the third storey unviable. 

45‐47 Kerferd Avenue 

Questionable whether the controls apply to this property given the reference to building heights at Ocean Beach Road frontage. 

3293‐3295 Point Nepean Road 

Not identified as a contributory property.  Development of the site should not block views of Quamby or the tower of the Continental Hotel.  Development should follow the slope of the land and maintain the 8 metre height limit at any given point so views are still maintained over the tops of buildings. 

DDO28 proposes a mandatory front setback that must match the setback of the building on the adjoining lot or the average of the setback of the buildings on either side of the lot. 

In this case, the property directly to the west is vacant.  The property to the south has no front setback and rises to a height greater than 8 metres, the 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 23 

 

mandatory height limit. 

As such, it would be a gross underdevelopment of the site to limit it to 8 metres. 

If the key measure to height is views to Quamby or the tower of the Continental Hotel, DDO28 should provide a clear sightline diagram confirming the maximum allowable heights through the site. 

Mr Soding made submissions on the effect of the proposed controls on his client’s property at  101  Ocean  Beach  Road.    He  noted  that  there  were  no  properties  in  the  south‐west precinct that were of contributory heritage significance, however despite this, the proposed height  and  setback  controls were  the  same  as  proposed  for  other  precincts.   Mr  Soding tabled a plan of subdivision for his client’s property that showed its abuttal to Darling Road and  a  ‘road’  to  the  rear.   He queried  the effect of  the proposed  controls on  the  setback required from the ‘road’. 

(iii) Discussion 

The  submissions  of  parties  in  relation  to  the  development  potential  of  land  within  the precinct  highlights  to  the  Panel  the  inherent  difficulties  and  constraints  in  imposing mandatory  controls.   Mandatory  controls  do  not  promote  or  encourage  a  detailed  site analysis to inform the design constraints and opportunities of a particular site.  They do not take  into  account  lot  sizes,  irregular  siting  of  buildings  or  street  alignment,  topography, heritage significance or the like. 

The Panel is of the view that there can be unintended outcomes that impact on properties or constraints  that  unnecessarily  limit  the  development  potential  of  a  property.    This  is highlighted in the submissions made by the parties.  In relation to each of the properties, the Panel notes the following: 

80‐89 Ocean Beach Road – this is a large landholding, of some 2,500 square metres, that  has  frontage  to  both  Ocean  Beach  Road  and Morce  Avenue.    The  current application  for  planning  permit  details  a  two  storey  building, with  a  street wall height of 4.9 metres to Ocean Beach Road and a height of 12.6 metres to the Morce Avenue frontage.   Not only would the overall height of the building be prohibited, but  on  the  basis  of  the  change  to  the  heading  at  column  2  in  the  table  to  the Schedule where it now references “a maximum building height at road frontage”, it means  that  the  proposed  setback  would  be  prohibited.    The  provision  of  two storeys  in  a  height  exceeding  11 metres  also  highlights  that  it  is  unnecessary  to impose a limitation on overall height and number of storeys.  This is also highlighted in  the  fact  that  the  developments  referenced  by  Mr  Rantino  were  below  the proposed  height  limits  but  contained  4  levels.    It  is  the  Panel’s  view  that  the principal  consideration  as  to  the  appropriateness  or  otherwise  of  proposed  built form  in  a  streetscape  is  the  overall  form  and  scale,  not  of  how many  levels  are contained  in  it.    Noting  of  course,  that  the  number  of  floors  will  follow  from requirements relating to floor to ceiling heights and internal amenity. 

172 Ocean Beach Road – this  is a shallow block with a depth of approximately 25 metres,  it  abuts  an  accessway  to  the  rear  and  is  at  the  end  of  the  commercial precinct.    Compliance  with  the  setback  requirement  would  likely  render  the 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 24 

 

opportunity for a third floor not possible, but there may be other design options or considerations.   The Panel accepts that reference to the road frontage  in the table to  the  Schedule  would  take  into  account  the  varied  street  alignment  of  this property. 

85‐99 Ocean Beach Road  –  The  Panel  notes  that Mr Rantino  confirmed  that  the requirement,  as  drafted,  requires  setbacks  from  the  level  below,  not  the  street frontage.    Therefore,  given  that  the  existing  building  is  set  back  from  the  street alignment, any third floor would have a setback well in excess of eight metres from the street.  This is a wide block with a frontage in the order of 36 metres, but as the Panel understands it, would not be able to accommodate a third level based on the proposed controls. 

45‐47 Kerferd Avenue – the change to the heading of column 2 of the table to the Schedule means that the controls apply to this property. 

3293‐3295  Point  Nepean  Road  –  this  is  an  isolated  site  in  the  context  of  the commercial precinct.  The proposed control is eight metres.  It appears to the Panel that the key consideration relevant to this property  is the  impact on any views to either Quamby  or  the  Continental  Hotel.    In  the  absence  of  a  detailed  analysis, including site lines, this appears as an arbitrary limit. 

101 Ocean Beach Road – The Panel notes Mr Rantino’s submission that Council did not  regard  abuttals  to  unnamed  lanes  as  a  frontage  and  that  this  could  be addressed  as  a  note  in  the  Schedule.    This  again  highlights  to  the  Panel  the unintended outcomes that may arise by virtue of mandatory controls. 

The  Panel  is mindful  that  this  assessment  is  only  of  a  handful  of  properties  within  the commercial precinct, however, considers that  it highlights why mandatory controls are not the answer.  The Panel concludes that the benefits of the proposed mandatory provisions do not outweigh the flexibility inherent in a performance based system. 

4.9 Conclusions 

The Panel draws the following conclusions in relation to the proposed mandatory controls: 

The  Panel  is  of  the  view  that  the policy  framework  does  not  support  the  use  of mandatory  controls.    It  is  of  the  view  that  objectives  and  strategies  relating  to retaining  the  character  of  the  streetscape  and  ensuring  that  development  is appropriately  designed  and  sited  can  be  readily  achieved  through  the  use  of discretionary controls. 

The Panel  is not convinced that the proposed mandatory controls are appropriate to the majority of development proposals. 

The  Panel  accepts  that  the mandatory  provisions may  provide  for  the  outcomes preferred by Council, and agrees that it may resolve divergent opinions on issues of height and setback. 

The  Panel  is  not  convinced  that  there  is  evidence  of  significant  development pressure  for  outcomes  outside  planning  policy  or  evidence  that  approved developments are clearly exceeding the proposed control. 

Given the presence of the Heritage Overlay and contributory buildings; the need to comply with the requirements of the overlay and policy; coupled with the fact that 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 25 

 

some sites are unlikely  to be redeveloped,  it  is  the Panel’s observation  that  there would not be a majority of proposals that would not accord with the requirements. 

The Panel accepts Council’s advice that the application of mandatory controls could result in a reduction in administrative costs. 

Mandatory controls do not promote or encourage a detailed site analysis to inform the  design  constraints  and  opportunities  of  a  particular  site,  and  the  Panel concludes that the benefits of the proposed mandatory provisions do not outweigh the flexibility inherent in a performance based system. 

4.10 Finding 

The  Panel  finds  that  DDO28  should  be  amended  to  include  discretionary  rather  than mandatory controls.  This is discussed further in Section 6.5. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 26 

 

5 Assessment against PPN60 – Activity Centres 

5.1 The issue 

Does the Amendment meet the requirements set out in PPN60? 

5.2 Introduction  

Planning  Practice  Note  60  (PPN60)  provides  guidance  on  the  preferred  approach  to  the application of height and setback controls for activity centres.  The Practice Note is relevant to this Amendment because of the proposed mandatory height and setback controls. 

The  parties made  competing  submissions  in  relation  to  the  Amendment when  assessed against PPN60.  These submissions are detailed below. 

5.3 Submissions 

Mr  Rantino  submitted  that  PPN60  professes  to  apply  to  all  activity  centres  and  that  no distinction  is  drawn  between  different  scales  or  characteristics  of  an  activity  centre.   He noted  that  it  would  apply  equally  to  Camberwell  Junction  (as  a  metropolitan  principal activity centre) as  it does to Sorrento (a small township centre).   He submitted that on this basis,  it  is  important  that PPN60  is not applied  indiscriminately as  though one principle or guideline applies equally to all centres. 

Mr  Rantino  noted  that whilst  Council  does  not  claim  to  have  undertaken  a  full  suite  of strategic work, such as a Housing Strategy or Economic Strategy,  it has “undertaken a very comprehensive assessment of the heritage and streetscape attributes of the Sorrento town centre and made a decision with  respect  to  that assessment  commensurate with  the  role function and setting of the centre”. 

On this basis, he submitted that the type of ‘exceptional circumstances’ that might need to be applied  to a principal or major activity centre  (to  justify mandatory height and setback controls) might not need to be ‘exceptional’ in a smaller neighbourhood centre.  In relation to the  list of  ‘exceptional circumstances’  listed  in the Practice Note, Mr Rantino submitted that: 

Council  is  firmly  convinced  that  the  Sorrento  town  centre  is  one  of  those “significant  heritage  places  where  other  controls  are  demonstrated  to  be inadequate to protect unique heritage places”.    It  is satisfied  that  the centre can, within the parameters of the proposed DDO28, deliver on  its role within the activity centre hierarchy in a manner which secures the centre’s long term viability. 

Ms  Bisucci  also made  submissions  in  relation  to  PPN60.    It was  her  submission  that  the absence of a comprehensive built form analysis was a major flaw  in the preparation of the Amendment.  She submitted that in the absence of this work, “it is difficult to determine the visual and amenity  impacts the proposed controls will have on the commercial precinct and what  type  of  influence  this would  have  taking  into  consideration  land  use  outcomes  and economic growth – both of which are important elements of activity centres”. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 27 

 

Ms Bisucci submitted that the proposed built form objectives or outcomes proposed under DDO28  lack  the  appropriate  strategic  justification.    She  submitted  that  the  HLCD  report could not be relied on to provide such strategic  justification.   She was of the view that the HLCD  report  focuses  on  the  cultural/heritage  significance  of  the  precinct  and  provides guidelines  for more  conservative design and development.   She  submitted  that  there had been  no  justification  for  the  proposed  mandatory  controls  and  that  the  Panel  should recommend that the height and setback controls be discretionary. 

The  Nepean  Conservation  Group  submitted  that  restrictions  in  the  form  of  mandatory controls were required for the following reasons: 

Recent  inappropriate  developments  as  a  result  of  lack  of  mandatory standards and controls 

Council decisions often challenged 

Need  to  go  to  VCAT,  which  is  an  expensive  process  for  Council  and developers alike 

Tendency for VCAT to ignore Council policies. 

Mr Frielink also submitted there are many international examples where mandatory controls existed, including in Holland and Paris, and that they are accepted and understood. 

The  Nepean  Historical  Society  submitted  that  controls  were  required  because  recent developments  that  had  been  approved  or  undertaken  in  the  town  centre  have  paid inadequate attention  to  the neighbourhood character and heritage.    It submitted  that  the Society agrees with the Council’s assessment that an Amendment is required: 

to manage the increasing development pressure on Ocean Beach Road, and to ensure that the historical significance and coastal village character of the town is not lost through inappropriate development. 

Ms  Bell  acknowledged  that  Sorrento  satisfied  two  ‘exceptional  circumstances’  listed  in PPN60, being: 

Sensitive  coastal environments where exceeding an  identified height  limit will unreasonably detract from the significance of the coastal environment 

Significant  heritage  places where  other  controls  are  demonstrated  to  be inadequate to protect unique heritage values. 

However, in her submission, there was no strategic justification for mandatory controls.  She too was critical of the Council’s reliance on the HLCD report to  justify the Amendment and submitted  that  the  Amendment  documentation  “does  not  refer  to  any  capacity  or constraints analysis or  identification of key sites within each centre that can accommodate more  intense  development  when  compared  to  the  remainder  of  the  centre.    Ms  Bell submitted that the Amendment should be abandoned to allow further strategic work to be undertaken  to  “build  an  urban  design  rationale  for  the  proposed  built  form  heights  and setbacks”. 

Mr Soding was also critical of the proposed controls.  In relation to his client’s property, he submitted that despite the HLCD report noting that there are no properties of contributory heritage significance  in  the south west precinct,  the proposed height and setback controls 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 28 

 

were  the  same  as  those  being  applied  in  other  precincts  (other  than  the  Central  sub precinct).  He also submitted that: 

height  limits are a blunt  tool  that can  lead  to poor design outcomes  that  in themselves can do more harm to the area as the architect seeks/needs to fit all of  the building within  the mandated  limit  (such as building  lift overruns, balconies stairs and services to the building). 

Mr Soding submitted that there was no strategic justification to support mandatory controls and that the Amendment should be abandoned. 

5.4 Discussion 

PPN60 identifies that state planning policy directs the future expansion of services, including commercial, retailing, employment, community, transport, entertainment and other services as well as being ideally placed to provide for growth in housing.  It notes that strategy seeks to build up activity centres to: 

accommodate  ongoing  investment  and  change  in  retail,  office,  service  and residential markets 

have  a mix  of  activities  that  generate  high  numbers  of  trips  including  business, retail, services and entertainment 

have the potential to grow sustainably and support intensive housing developments without conflicting with surrounding land uses 

provide for services and infrastructure to support population growth 

identify areas for urban renewal. 

The  Practice  Note  identifies  the  role  that  height  and  setback  controls  play  in managing change  in  and  around  activity  centres  and  sets  out  how  these  are  to  be  used,  including through structure plans.  It notes that height and setback controls can be appropriate as long as they are not aimed at restricting built form, but at facilitating good design outcomes. 

The  Practice  Note  states  that  a  Council will  need  to  demonstrate  that  proposed  height controls are based on identifiable objectives or outcomes.  Proposed height controls must be selected through a comprehensive built form analysis that achieves the following: 

Identifies significant opportunities for change within an activity centre. 

Explores  alternative  built  form  objectives  and  outcomes  to  accommodate  this change.  This should include an analysis of visual and amenity impacts. 

Selects  appropriate  heights  and  built  form  outcomes  at  a  precinct  level  through evaluation  of  built  form  objectives,  land  use  outcomes  and  economic  growth consistent with State policy. 

The Panel  acknowledges  that  there has not been  a built  form  analysis  in  a  form  typically seen,  that  is undertaken by urban designers,  apart  from  the work undertaken by Hansen Partnership.    The  Panel  accepts  that  the HLCD  report  identifies  opportunities  for  change within  the  centre;  and  selects what  it  considers  to be  appropriate heights  and built  form outcomes  through  evaluation  of  built  form  objectives.    It  does  not  identify  land  use outcomes or economic growth objectives or address issues of amenity. 

The premise  for  the built  form controls  is  to provide guidance  for  the  future conservation and development of the centre and to protect its cultural and heritage significance. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 29 

 

Whilst  change  in  and  around  activity  centres  is  anticipated  and  encouraged  by  planning policy,  it  is also policy to manage change.    It  is clear to the Panel that the existing scale of development within the centre, and indeed the likely future character, is one of typically low scale, particularly at the street wall, with modest opportunities for additional height that  is set  back  from  the  street.   Despite  recent  development  and  the  presence  of  larger  retail chains as tenants, the centre retains its coastal feel.  It has a sense of space because of the road and pavement widths and quality urban design features, including street planting. 

The Panel accepts that the proposed height controls are consistent with state policy  in the sense that they anticipate a higher scale of development than currently exists. 

However,  the  Panel  is  of  the  view  that  there  are  no  ‘exceptional  circumstances’  for  the precinct, and therefore no cause to warrant mandatory controls.  Whilst there are significant heritage places,  these have been  identified and  included  in  site  specific heritage overlays.  There are contributory buildings within  the  land subject  to  the Amendment; however,  the number  is modest within  the overall  centre.   Given  the presence of  the existing Heritage Overlay  and Clause 22.17,  the Panel  is of  the  view  that  there are other  controls  that  are adequate to protect the heritage values.  Policy in Clause 22.17 includes: 

Encourage  development  to  be  compatible  with  the  scientific,  aesthetic, architectural, historic and cultural significance of the Precinct 

Require infill buildings to complement the existing streetscape 

Ensure that new development does not have an adverse impact on existing vistas, views and landmarks 

Ensure  that new development  responds positively  to  the  location, height, mass and materials and external appearance of existing development in the Precinct 

Require  that  new  development  respects  the  height,  scale  and  siting  of existing development in the various parts of the Precinct 

Discourage the erection of buildings that exceed eight metres in height. 

Further, the Panel notes that the Practice Note states that “where mandatory controls are proposed  it  will  need  to  be  demonstrated  that  discretionary  controls  could  result  in  an unacceptable  built  form  outcome”.    The  Panel  is  of  the  view  that  the  Council  did  not demonstrate such an outcome.    Indeed, as detailed  in Chapter 4, whilst Council sought  to rely on approvals for development within the centre to support  its position that there was development pressure that would erode the features and character of the centre, the Panel did  not  agree with  that  position.    Having  the  benefit  of  inspecting  the  centre,  including recently constructed developments, the Panel notes that even in the absence of mandatory controls, based on specific site analysis for each proposal, the eventual built form in terms of height is generally consistent with that sought through the Amendment.  The differences are the  number  of  stories  achieved within  the  overall  height  and  the  setbacks  of  the  upper levels.   As noted previously,  the Panel  is of  the view  that  the developments are generally respectful  of  the  lower  scale  streetscape  character  and  that  the  upper  levels  read  as recessive elements. 

PPN60  also  requires  that  where  blanket  mandatory  height  and  setback  controls  are proposed, that rigorous strategic justification has to be provided.  Whilst the Panel has noted 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 30 

 

that  it accepts  the HLCD  report  includes a built  form analysis of  the centre,  there has not been  any  further  strategic work undertaken  in  the  form  that  is  called  for by  the Practice Note, including a housing strategy, an economic strategy, a capacity and constraints analysis, or an identification and analysis of key sites within the centre which can accommodate more intense development. 

Moreover, the Panel is of the view that the proposed use of mandatory controls will restrict built form rather than facilitate or promote good design outcomes.   For these reasons, the Panel accepts the Council’s preference to provide statutory controls to  facilitate built form outcomes;  however  is  of  the  view  that  these  are  more  appropriately  in  the  form  of discretionary controls. 

5.5 Conclusions 

The Panel draws the following conclusions in relation to PPN60: 

The  Panel  is  of  the  view  that  there  are  no  ‘exceptional  circumstances’  for  the precinct, and therefore no cause to warrant mandatory controls. 

Given the presence of the existing Heritage Overlay and Clause 22.17, the Panel is of the  view  that  there  are other  controls  that  are  adequate  to protect  the heritage values. 

The  Panel  is  not  convinced  that  discretionary  controls  would  result  in  an unacceptable built form outcome. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 31 

 

6 The proposed DDO Schedule 28 

6.1 The issue 

In addition to the vexed issue of mandatory controls, various submissions dealt with specific requirements  of  the  proposed  DDO28.    The  Panel  has  considered  these  matters  in conjunction with  the  overall  provisions  in  forming  its  view  as  to whether  the  form  and content of the proposed DDO28 is appropriate. 

6.2 Precinct and sub‐precinct borders 

(i) Submissions 

Mr Rantino advised the Panel that Council accepted the submission from the property owner of 80‐98 Ocean Beach Road  that  the property should be wholly contained  in a single sub‐precinct, and more specifically, within the central sub‐precinct. 

He  also  advised  that  Council  did  not  support  the  creation  of  a  ‘south‐east  precinct’  to accommodate 60 Kerferd Avenue.   This was on  the basis  that  the DDO28 was developed having regard to existing development and the significance of the area.   He submitted that Council opposed the removal of properties from DDO28 that do not have frontage to Ocean Beach Road because they: 

are commercially zoned properties 

are the gateways to the centre from surrounding residential areas 

can influence the outcomes sought for the centre with inappropriate development. 

(ii) Discussion  

The Panel accepts Council’s position in relation to the inclusion of other commercially zoned properties within the DDO28.  It is a logical extension of the DDO28.  Accordingly, the Panel accepts Council’s submission regarding the inclusion of 60 Kerferd Avenue within the DDO28 as exhibited. 

The Panel also agrees  that  it  is appropriate  to  include all of  the property at 80‐98 Ocean Beach Road  in  the one  sub‐precinct and notes  that  this has been amended  in  the  revised version of the Schedule submitted to the Panel as shown in Appendix C. 

6.3 Interpreting building height 

(i) Submissions 

Mr Rantino advised the Panel that Council’s position  in relation to balustrades  is that they are to be included in the calculation of building height for the purposes of DDO28. 

Ms Bisucci referred to the decision by Deputy President Dwyer in Aitken Properties Pty Ltd v Hobsons Bay CC [2016] VCAT 1484  in relation to her submissions regarding building height.  Mr Rantino submitted that Council accepted that lift overruns are a form of building services and are therefore excluded from the measurement of height. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 32 

 

In  closing Mr  Rantino  advised  the  Panel  that  in  relation  to  balustrades  he  adopted  the findings  of  Deputy  President  Dwyer  that  it  was  “a  question  of  fact”.    That  is,  that  the ‘building height’ is defined and is a question of fact not a question of law. 

(ii) Discussion 

The Panel notes that the exemption relating to lift overruns has been included in the revised version of the Schedule submitted following the Hearing (See Appendix C). 

On the basis of the Panel’s findings in relation to the appropriateness of mandatory controls, it is of the view that where appropriate, features such as balustrades to roof terraces or the like  can  be  readily  dealt  with  through  an  assessment  against  the  design  objectives  and decision guidelines of DDO28. 

6.4 Other form and content issues 

(i) Submissions 

As noted above, Mr Rantino advised the Panel that the heading to column 2 of the table in DDO28  had  been  amended  to  apply  to  “road  frontage”  rather  than  as  in  the  exhibited version “Ocean Beach Road frontage”.  He advised that this was a correction and that it was necessary  to  apply  the  built  form  controls  to  those  properties  not  fronting Ocean  Beach Road “because of their visual and physical proximity to the Ocean Beach Road properties and the potential for their development to degrade the valued low scale coastal village character in Ocean Beach Road”.    It was also to ensure that they were  included  in a DDO, because  if they were excluded  it would result  in an anomaly within the planning  framework whereby DDO2 and DDO3 apply to surrounding land. 

The Nepean Conservation Group and the Nepean Historical Society took  issue with the  line of sight diagram included in proposed DDO28.  They submitted that it there were anomalies, firstly with the representation of the width of the road and secondly because views of the buildings  opposite  the  street  are  always  viewed  at  an  angle.    The  Nepean  Conservation Group submitted that a mandatory setback of 16 metres should be adopted to ensure that third storeys could not be seen from the other side of the street. 

They  also  submitted  that  DDO28  should  address  land  use  and  that  there  should  be  a mandatory  requirement  within  DDO28  that  a  planning  application  should  include  a perspective,  photomontage  or  video  showing  the  visual  impacts  of  the  proposed development. 

In  reply, Mr  Rantino  advised  the  Panel  that  there was  no  need  to  increase  the  setback requirement to 16 metres.  He also noted that the control deals with built form and cannot include restrictions on residential development.  He also advised that if the Panel was of the view that it was appropriate to require a perspective or similar that this could be included as a decision requirement. 

Mr Soding agreed  that good contemporary design  is  required  for  the precinct, however  it was his view that this requirement was not dealt with in the DDO28 requirements, except by reference to the HLCD report. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 33 

 

(ii) Discussion 

The Panel accepts the changes proposed to the Table to DDO28 to clarify setbacks for corner sites and deletion of the reference to ‘Ocean Beach Road’ from the heading at Column 2 of the  table  to  the  Schedule,  as  shown  in  Appendix  C.    The  Panel  also  accepts  the minor changes to the wording of the ‘Design objectives’ as shown in Appendix C. 

The Panel notes various submitters’ concerns with the HLCD report that forms the basis of the proposed DDO28.  The Panel notes that there is a requirement under ‘design objectives’ and  ‘decision  guidelines’  that  requires  that  development  respond  to  the  design requirements of the relevant sub‐precinct within the HLCD document.   The Panel  is of the view that it is not appropriate for a control to rely on a separate document and that salient requirements should be included in the DDO for greater clarity.  The DDO should be a stand‐alone  control,  thereby  providing  transparency  to  all,  including  developers  and  the community.  In relation to the HLCD report, the Panel accepts the submissions of Ms Bisucci and Mr  Soding  that  it  does  not  provide  guidance,  nor  set  a  clear  objective  to  promote pursuit of design excellence, or provide a vision  for  the  centre.   The Panel  considers  that these should be clearly articulated in the design objectives of DDO28. 

The Panel agrees with Mr Rantino’s submission in relation to the purpose of the DDO.  State planning  policy,  Plan  Melbourne  2017  and  the  local  policy  framework  all  promote  the expansion of activity centres and the facilitation of a mix of land uses. 

The Panel also agrees with the suggestion put forward by the Nepean Conservation Group and  the  Nepean  Historical  Society  that  requires  the  preparation  of  perspective, photomontage,  or  video  showing  the  visual  impacts  of  the  proposed  development.    The Panel notes Mr Rantino’s agreement to inclusion of such a requirement in the DDO28.  This could be included under the ‘application requirements’ section. 

The Panel does not accept  the  submissions  to  increase  the  setback  for upper  levels  to 16 metres.   The reference  to eight metres  in  the sightline diagram  is a reasonable setback  to achieve the design objective that  ‘applications exceeding 8 metres  in height above natural ground  level  is  generally  not  visible  from  standing  eye  level  directly  opposite  the  site’.  Having  said  that,  the  exhibited  DDO28  was  drafted  so  that  sightline  showed  general compliance with the sightline diagram.   The Panel  is of the view that the sightline diagram can remain and is a tool to guide the setbacks of upper levels, albeit the setbacks are to be discretionary. 

6.5 Is DDO28 appropriate with discretionary controls? 

(i) The issue 

On the basis that the Panel  is of the view that mandatory controls are not  justified  in this instance, it has turned its mind as to whether DDO28 as drafted remains appropriate in the context of discretionary controls. 

(ii) Discussion 

As  detailed  in  Chapter  4,  and  having  regard  to  submissions  relating  to  the  effect  of  the proposed  controls  on  specific  properties,  the  Panel  notes  the  inherent  difficulties  and 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 34 

 

constraints  in  imposing mandatory controls.   Put simply, they do not allow  for site specific constraints or opportunities  to be  taken  into account.   The Panel also made observations regarding the inclusion of reference to storeys in a height control and formed the view that it is not appropriate to include a limitation on the number of storeys. 

As detailed  in previous Chapters, the Panel acknowledges Council’s preference to preserve and  continue  to  enhance  the  heritage  and  coastal  features  of  the  Sorrento  commercial precinct,  including  reinforcing a predominant  street wall height and allowing  for  recessive upper  levels.    The  Panel  is  of  the  view  that  this  objective  can  be  achieved  through  the inclusion of discretionary controls. 

The Panel has reviewed DDO28 in some detail and is of the view that it can be redrafted to reference discretionary controls relating to height and setbacks.   So that the DDO does not become  a  transformation  of  the  exhibited  version,  the  Panel  is  of  the  view  that  DDO28 should  be  amended  to  require  that  where  an  application  exceeds  the  discretionary maximum building height it must be accompanied by a site analysis plan and written urban context  report documenting how  the development will achieve  the design objectives  and outcomes of DDO28.   This requirement differs  from the exhibited version of DDO28 which sought  to  require  a  site  context  analysis  and  design  response  demonstrating  compliance with  the objectives  for all applications.    In  the Panel’s view,  the distinction  can be drawn between proposals complying with  the preferred heights and setbacks  (where  it would be appropriate for the preparation and submission of a site analysis and design response with a report responding to the design objectives) with a proposal exceeding the preferred controls being  submitted  with  a  comprehensive  urban  context  analysis/report  demonstrating compliance with the objectives of the controls. 

The  intent  of  the  controls  is  also  to preserve  views of  existing  significant heritage  fabric, however, this has not been included within the control.  It is a requirement of other policy, and the Panel considers that it would be of assistance to include it as a design objective and application  requirement.    This  observation  is made  particularly  in  relation  to  the  eastern sub‐precinct where the height and setback control seeks to protect views.  The Panel accepts Ms  Bell’s  submissions  in  relation  to  the  proposed  requirements  relative  to  the  property included in this precinct and is of the view that the setback requirement be deleted from the control.   The proposed eight metre height control can remain as a discretionary  limit, with any proposals to exceed the height demonstrating compliance with the requirement relating to views. 

In relation to the reference to the HLCD report, as observed above the Panel  is of the view that  the  DDO  should  be  drafted  so  that  it  is  a  stand‐alone  control.    Whilst  the  Panel considers  that  the  HLCD  report  provides  for  an  analysis  of  the  historical  and  existing conditions and provides the framework for the proposed controls,  it  is of the view that the overlay should not rely on a reference to the report.  Whilst it has been adopted by Council, it is a reference document only and is not part of the planning scheme. 

If  Council  does  not  accept  the  Panel’s  recommendation  with  respect  to  discretionary controls  and  wishes  to  pursue  mandatory  controls,  the  Panel  is  of  the  view  that  this Amendment  should be abandoned, and Council  should undertake a  rigorous urban design analysis of the precinct before preparing a new amendment. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 35 

 

6.6 Conclusions 

The Panel draws the following conclusions in relation to the proposed DDO28: 

All of the property known as 80‐98 Ocean Beach Road should be contained within the  ‘central’  sub‐precinct  (Note  that  this  has  been  done  in  the  Council modified version at Appendix C). 

No  change  is  required  to  the  boundary  of  the  Ocean  Beach  Road  commercial precinct. 

No change is required to the sightline diagram. 

DDO28  is  appropriate,  subject  to  the  removal  of mandatory  controls  and  other changes as listed below to the post‐Hearing version tabled by Council and included as Appendix C to this report: 

- Amend ‘Design objectives’ to: - Include a clearly defined vision for the commercial centre - require  that  a  development  is  compatible with  and makes  a  positive 

contribution to the low scale and character of the precinct - emphasise  the  need  for  development  to  achieve  excellence  in 

architecture and design - include a requirement that views of significant heritage buildings (and 

identify which buildings) are protected - delete reference to the HLCD report. 

- Amend ‘Buildings and works’ to: - remove mandatory requirements - include discretionary requirements - include a  requirement  to  the effect of  ‘that  an  application  to exceed 

the maximum building height must be accompanied by a site analysis plan  and  a  written  urban  context  report  documenting  how  the development will achieve  the design objectives and outcomes of  this schedule’. 

- Amend ‘Table’ to: - remove references to storeys - remove the mandatory height requirements - remove the mandatory setback requirements - remove setback requirement for east sub‐precinct - include  a  note  to  the  effect  that  ‘the  setback  does  not  relate  to 

unnamed lanes’. - Amend ‘Notes’ to: 

- delete notes relating to mandatory controls and storeys - delete the words ‘not from the title boundary’ as it relates to setbacks 

from the third storey. - Include  a  separate  heading  of  ‘Application  requirements’  and  include  the 

following: - A site context analysis and design response - Detailed plans, including palette of materials and finishes - A  planning  report  demonstrating  that  the  development  will  achieve 

design objectives of the schedule 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 36 

 

- A  perspective  or  photomontage  detailing  how  the  proposed development will sit within the streetscape 

- As  appropriate,  sightlines  to  demonstrate  that  a  proposed development does not obstruct views of significant heritage places. 

- Amend ‘Decision guidelines’ to: - Delete reference to the HLCD report. 

The  Panel  has  not  attempted  to  re‐draft  DDO28  because  it  believes  that  Council  should carefully  review  the drafting  in conjunction with DELWP before  finalising  the Amendment.  That is not the role of the Panel. 

6.7 Recommendations 

The Panel recommends that Mornington Peninsula Planning Scheme Amendment C204 be adopted  as  exhibited,  subject  to  the  following  changes  to  Design  and  Development Overlay Schedule 28: 

Adopt the changes to the Schedule proposed by Council post‐Hearing as shown in 1.Appendix C to this report, subject to the further changes set out below. 

a  Amend ‘Design objectives’ to include: 

a clearly defined vision for the commercial centre 

require  that  a  development  is  compatible  with  and  makes  a  positive contribution to the low scale and character of the precinct 

emphasise the need for development to achieve excellence in architecture and design 

includes  a  requirement  that  views  of  significant  heritage  buildings  (and identify which buildings) are protected 

delete reference to the HLCD report. 

b  Amend ‘Buildings and works’ to: 

remove mandatory requirements 

include discretionary requirements 

include a  requirement  to  the effect of  ‘that an application  to exceed  the maximum building height must be accompanied by a site analysis plan and a written  urban  context  report  documenting  how  the  development will achieve the design objectives and outcomes of this schedule’. 

c  Amend ‘Table’ to: 

remove references to storeys 

remove the mandatory height requirements 

remove the mandatory setback requirements 

remove setback requirement for east sub‐precinct 

include a note to the effect that  ‘the setback does not relate to unnamed lanes’. 

d  Amend ‘Notes’ to: 

delete notes relating to mandatory controls and storeys 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Page 37 

 

delete  the words  ‘not  from  the  title  boundary’  as  it  relates  to  setbacks from the third storey. 

e  Include  a  separate  heading  of  ‘Application  requirements’  and  include  the following: 

A site context analysis and design response. 

Detailed plans, including palette of materials and finishes. 

A planning report demonstrating that the development will achieve design objectives of the schedule. 

A perspective or photomontage detailing how the proposed development will sit within the streetscape. 

As  appropriate,  sightlines  to  demonstrate  that  a  proposed  development does not obstruct views of significant heritage places. 

f  Amend ‘Decision guidelines’ to: 

delete reference to the HLCD report. 

 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Appendices 

 

Appendix A  Submitters to the Amendment  

No.  Submitter 

1  Coastal Corner Pty Ltd 

2  Mr David Moffatt 

3  Ms Gillian Loft 

4  Ms Christine Grainger 

5  Heritage Victoria 

6  Sorrento OB (DeGroup) Pty Ltd 

7  Tyas Super Pty Ltd 

8  Tyas Super Pty Ltd 

9  Tyas Super Pty Ltd 

10  Tyas Super Pty Ltd 

11  Tixxis Pty Ltd 

12  Country Fire Authority 

13  Nepean Historical Society 

14  Nepean Conservation Group Inc 

 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Appendices 

 

Appendix B  Document list 

No.  Date  Description  Tabled by 

1  11/04/2017  Council Part A submission  Mr Rantino 

2  11/04/2017  Revised DDO Schedule 28  Mr Rantino 

3  11/04/2017  Background Folder  Mr Rantino 

4  11/04/2017  Folder containing planning permits and endorsed plans for approved developments in Ocean Beach Road 

Mr Rantino 

5  11/04/2017  Council Part B submission  Mr Rantino 

6  11/04/2017  Mornington Peninsula Planning Scheme Amendment C101 panel report 

Mr Rantino 

7  11/04/2017  Mornington Peninsula Planning Scheme Amendment C84 panel report 

Mr Rantino 

8  11/04/2017  Queenscliffe Planning Scheme Amendment C7 panel report  Mr Rantino 

9  11/04/2017  Sorrento OB (DeGroup) Pty Ltd submission  Ms Bisucci 

10  11/04/2017  Nepean Conservation Group submission  Mr Frielink & Mr Naughton 

11  11/04/2017  Nepean Historical Society submission   

12  11/04/2017  Nepean Historical Society attachments  Mr Hindley 

13  11/04/2017  TYAS Super Pty Ltd and Coastal Corner Pty Ltd submission  Ms Bell 

14  11/04/2017  Aerial photograph showing client’s landholdings  Ms Bell 

15  11/04/2017  D and P A Elliot submission  Mr Soding 

16  11/04/2017  Plan of Subdivision for 101 Beach Road  Mr Soding 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Appendices 

 

Appendix C  Council proposed changes to DDO28 Pre‐Hearing changes are shown in brown. 

Post‐Hearing changes are shown in aqua. 

Map 1 shows the proposed precinct boundary changes to  include 80‐98 Ocean Beach Road within the Central sub‐precinct. 

 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Appendices 

 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Appendices 

 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Appendices 

 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Appendices 

 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Appendices 

 

Appendix D  Summary of approved developments in Ocean Beach Road 

Address  and VCAT Reference No. 

Summary of appeal  Panel Comments 

1‐21A Ocean Beach Road and 23 Constitution Hill Road  

VCAT Ref No. P2003/2016 

 

This was a review against two conditions imposed on a Notice of Decision to grant a Planning Permit.  The first condition related to the requirement to reduce the overall height of the proposed apartment building to RL37.05 and the second was against a requirement for a financial contribution.  Ultimately the Tribunal formed the view that it was not necessary to reduce the overall height, but in having regard to DDO28 the Tribunal noted that the reduced height of the apartment building supported by the council and respondent is appropriately 2 metres higher than what the sightline diagram encourages.   

The Panel notes that the Council was supportive of a development that did not accord with the requirements in DDO28.  In particular, were the controls mandatory, the proposal could not have been approved in either the form that the Tribunal approved it, or indeed had the height been reduced to that height sought by the Council.  The Panel also notes in the VCAT decision, that the Tribunal undertook a comprehensive review of the various planning policies applicable to the proposed development. 

142 Ocean Beach Road 

VCAT Ref No. P115/2016 

This review was against two conditions imposed in a Notice of Decision to grant a Planning Permit.  The Council’s planning officer recommended approval of the application and when approved by the Council, two additional conditions were imposed.  These conditions were the subject of the appeal and required the deletion of an apartment and increased setbacks at levels 2 and 3.  The setback to apartment 7 was 12.3 metres. 

The application was for a mixed‐use building comprising dwellings, shops and a medical centre.  It comprised partial demolition of the rear of the existing building. 

The building would have an overall height of 11.83 metres, with a height of 7.57 metres at Ocean Beach Road.  The Tribunal directed the deletion of the two conditions in dispute. 

The Panel observes that the site subject to this application is included in Design and Development Overlay, Schedule 10 and is not part of the centre subject to this Amendment. 

77 Ocean Beach Road 

This review was against the Council’s decision to refuse approval for a 

The Panel observes that this site is included in the south‐west sub 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Appendices 

 

VCAT Ref No. P343/2016 

three storey mixed use building. 

Agreement was reached during a Compulsory Conference and the Tribunal subsequently directed the grant of a planning permit. 

precinct as part of this Amendment.  As approved, it has a street wall height of 7.5 metres and an overall height of 9.8 metres.  The third floor is set back in the order of eight metres from the front of the building at the level below. 

Whilst complying with the proposed mandatory heights and setback at third floor level proposed as part of this Amendment, it would not satisfy the limitation on number of storeys.  However, the Panel notes that the overall height is not exceeded and the setback from the street frontage to the top level is 16 metres. 

61‐63 Ocean Beach Road 

The plans endorsed pursuant to planning permit (P12/0871) were issued on 2 April 2013.  The permit allowed the construction of a four storey mixed use building. 

The approved building had a street wall height of 7.8 metres and an overall height of 11.3 metres. 

The third floor is set back approximately 6.5 metres from the frontage and the fourth floor is set back 16 metres from the frontage. 

The subject site is included in the central sub precinct in the Amendment. 

As approved, the building complies with the overall heights, but exceeds the number of storeys and setback to the third floor proposed as part of this Amendment. 

This building has been constructed.  In the Panel’s view, the third and fourth levels are recessive to the streetscape. 

57‐59 Ocean Beach Road 

VCAT Ref No. P2240/2014 

This review was lodged against the Council’s decision to issue a notice of refusal to grant a planning permit for a four storey mixed use development. 

The overall height of the development was 8.95 metres at its east elevation and 10.5 metres at the west elevation.  The Tribunal considered the application against the policy context for a preferred eight metre height limit.  The Tribunal observed that a building that is between 1.9 metres and 2.5 metres above the policy preference at a distance of 18 metres from the Ocean Beach Road frontage was reasonable given the broad compliance with State and local activity centre policy.  In accepting that most buildings in the centre were of a two storey height, the 

The subject site is included in the central sub precinct in the Amendment.   

As approved, the façade marginally exceeds the height for the street wall but not of the overall height of 11 metres.  It exceeds the number of storeys and the setback to the third floor. 

Having reviewed the endorsed plans, the Panel observes that the top floor is a very recessive element. 

Mornington Peninsula Planning Scheme Amendment C204  Panel Report  29 May 2017 

 

Appendices 

 

Tribunal also observed that the maximum building height was not out of character for the centre. 

56‐58 Kerferd Avenue 

VCAT Ref No. P633/2010 

This review was lodged against the Council’s decision to issue a notice of refusal to grant a planning permit for a three mixed‐use development. 

In relation to the preferred height limit of eight metres found in the local policy, the Tribunal observed: 

The rigorous application of an 8 metre height limit is also at odds with the existing variability in building height and form.  The policy contact of an 8 metre height limit is more relevant to the scale and relationship between individual buildings or groups of buildings rather than a uniform height limit, particularly in view of Sorrento’s undulating terrain. 

The subject site is included in the central sub precinct in the Amendment. 

As approved, the building has an overall height of 9.9 metres, containing three storeys.  The setback of the third storey encroaches into the mandatory setback proposed as part of this Amendment. 

This development has been constructed.  Being in Kerferd Avenue it is viewed in a different context to that of Ocean Beach Road.  The Panel is of the view that this is an appropriately sited and designed building. 

1 Hayes Avenue 

VCAT Ref No. P1581/2006 

This review was lodged against the Council’s decision to issue a notice of refusal to grant a planning permit for a three storey residential development. 

Amended plans were circulated and during the course of the hearing consent were reached between the parties.  Accordingly, the Tribunal directed that a permit be granted. 

The subject site is included in the central sub precinct in the Amendment. 

As approved, the building has an overall height less than 8 metres.  The setback from the side street is less than 3 metres and would not comply with the mandatory requirement proposed as part of this Amendment. 

This development has been constructed.  Due to its location to the rear of the Country Fire Authority building, the Panel notes that it has limited visibility from Kerferd Avenue and is not visible within Ocean Beach Road.