    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-101 Pipework from: D-0101

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    1.5-HC-01019-D3; 1.5-HC-01026-A2 ; 12-HC-01004-C3; 12-HC-01018-D3; 24-HC-01001-D3; 24-HC-01005-C3; 2-V-01020-D3

    Nace: Y

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: D-0102

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    9 Shear Wave

    UT

    120Scan 50% of potential locations defined in

    the corrosion study.

    01/01/1995 29/12/2004 Online

    External

    Deterioration

    9 VI-EXT 60100% Coverage 04/02/2009 04/02/2014 OnLine DVI/01

    Internal Corrosion 15 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    13/11/2008 13/11/2013 OnLine UT/01

    11 July 2011 Page 1 of 176

  • 7/28/2019 Piping Exam Spec

    2/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-101-1 Pipework from: D-0102

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    2-HW-01022-C3; 3-HC-01036-C3

    Nace:

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: PL-1801

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    9 Shear Wave

    UT

    120Scan 50% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 29/12/2004 OnLine

    External

    Deterioration

    2 VI-EXT 30100% Coverage 04/02/2009 05/08/2011 OnLine DVI/01

    Internal Corrosion 2 UT 0Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 50% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 01/01/1995 OnLine UT/01

    11 July 2011 Page 2 of 176

  • 7/28/2019 Piping Exam Spec

    3/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-102 Pipework from:

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    6-V-01013-C3; 6-V-01100-C3; 16-HC-1049-C3; 3-HC-1034-C3; 16-HC-01006-C3; 16-HC-03001-C3; 16-HC-03149-C3; 16-HC-03759-C3; 4-HC-22063-HC3; 3-V-03191-C3; 2-HC-03144-C3; 2-HC-

    03143-C3; 2-V-03147-C3; 2-HC-03145-B3; 1-HC-01048-C3; 16-HC-03760-C3; 3-V-03761-C3; 2-HC-03762-C3; 2-HC-03763-B3; 2-HC-03764-C3; 2-PG-03836-C3; 2-HC-03146-B3; 2-HC-03757-B3

    Nace: Y

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: D-0301

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    9 Shear Wave

    UT

    120Scan 50% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 29/12/2004 Online

    External

    Deterioration

    6 VI-EXT 60100% Coverage 13/02/2009 13/02/2014 OnLine DVI/01

    Internal Corrosion 6 UT 10Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 25% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    28/11/2008 28/09/2009 OnLine UT/01

    11 July 2011 Page 3 of 176

  • 7/28/2019 Piping Exam Spec

    4/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-103 Pipework from: D-0102

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    4-HC-01048-C3; 3-V-02073-C3; 3-HC-01003-C3; 3-HC-02008-B3; 3-HC-02009-B3; 3-HC-02070-C3; 4-LN-02310-D2

    Nace: Y

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: D-0201

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    9 Shear Wave

    UT

    120Scan 50% of potential locations defined in

    the corrosion study.

    01/01/1995 29/12/2004 Online

    External

    Deterioration

    2 VI-EXT 30100% Coverage 25/03/2009 25/03/2009 OnLine DVI/01

    Internal Corrosion 2 UT 6Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 50% of Potential locations by Location

    Category.

    10/11/2008 10/11/2008 OnLine UT/01

    11 July 2011 Page 4 of 176

  • 7/28/2019 Piping Exam Spec

    5/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-1801 Pipework from:

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    8-V-06045-A1; 8-V-03643-A1; 6-V-22056-A1; 6-HC-07252-A1; 3-V-05065-A1; 3-V-02039-A1; 3-AG-04815-A1; 2-V-06081-A1; 2-V-06049-A1; 1-V-07313-A1; 1-V-01031-A1; 16-HC-18100-A1; 8-

    V-07302-A1; 6-V-07328-A1; 1-V-07329-B1; 6-V-07331-A1; 1-V-07332-B1; 3-V-07334-A1; 1-V-07335-A5A; 8-V-07350-A5A; 1-V-07316-B1; 1-V-07354-B1; 1-V-08008-C1; 1.5-HC-01026-A2 ; 1.5-

    HC-01019-A1; 0.75-V-02205-A1; 10-HC-07356-A1; 10-V-07255-A1; 10-V-07265-A1; 10-V-07266-A1; 10-V-18027-A1; 12-HC-07092-A1; 12-V-01101-A1; 12-V-03419-A1; 12-V-03501-A1; 12-V-

    03604-HA1; 12-V-03609-HA1; 12-V-03660-HA1; 12-V-03661-HA1; 12-V-03700-HA1; 12-V-03702-HA1; 12-V-18080-A1; 14-HC-18100-A1; 14-V-02101-A1; 14-V-18063-A1; 14-V-18090-A1; 16-

    HC-07095-A1; 16-V-03546-A1; 16-V-03662-HA1; 1-HC-02071-A1; 1-HC-02072-A1; 1-HC-07352-A1; 1-V-03203-A1; 1-V-03205-A1; 1-V-03207-A1; 1-V-03514-B3; 1-V-03516-C3; 1-V-03635-C3;

    1-V-03671-A1; 1-V-03754-B3; 1-V-03756-C3; 1-V-05095-C1; 1-V-18051-A1; 1-V-18058-A1; 20-NI-07017-A1; 20-V-18001-A1; 20-V-18065-A1; 24-V-18007-A1; 2-HC-02062-A1; 2-HC-02068-A1;

    2-HC-03543HA3; 2-HW-01010-A2; 2-HW-02017-A2; 2-HW-07243-A2; 2-HW-22004-A2; 2-V-01030-A1; 2-V-02093-A1; 2-V-03148-A1; 2-V-03195-A1; 2-V-03197-A1; 2-V-03755-A1; 2-V-03758-

    A1; 2-V-05054-A1; 2-V-05056-A2; 2-V-06007-A1; 2-V-06011-A1; 2-V-06037-A1; 2-V-06039-A1; 2-V-06047-A1; 2-V-06249-A1; 2-V-18029-A1; 2-V-18049-A1; 2-V-22145-HA1; 2-V-22147-HA1; 3-

    V-01021-A1; 3-V-03193-A1; 3-V-03679-A1; 3-V-03822-A1; 8-V-05066-A1; 3-V-05068-A1; 3-V-18062-HA1; 3-V-18073-HA1; 3-V-22146-HA1; 4-AM-03606-A5A; 4-V-02043-A1; 4-V-02055-A1; 4-

    V-02095-A1; 4-V-02099-A1; 4-V-02112-A1; 4-V-03199-A1; 4-V-03201-A1; 4-V-03217-A1; 4-V-03417-A1; 4-V-03510-A1; 4-V-03611-HA1; 4-V-03617-HA1; 4-V-03675-HA1; 4-V-03677-HA1; 4-V-03817-A1; 4-V-05090-A1; 4-V-05111-A1; 4-V-06061-HA1; 4-V-06067-HA1; 4-V-06077-A1; 4-V-07252-A1; 4-V-18021-A1; 4-V-18058-A1; 4-V-18081-A1; 4-V-22142-HA1; 6-HC-07252-A1; 6-V-

    01025-A1; 6-V-02041-A1; 6-V-02097-A1; 6-V-03156-A1; 6-V-03209-A1; 6-V-03606-HA1; 6-V-03643-A1; 6-V-03659-HA1; 6-V-03684-HA1; 6-V-03685-HA1; 6-V-05064-A1; 6-V-07602-HA1; 6-V-

    22005-A1; 6-V-22040-A1; 6-V-22073-HA1; 6-V-22074-HA1; 6-V-22078-HA1; 6-V-22079-HA1; 8-HC-06058-A1; 8-V-01014-A1; 8-V-01015-A1; 8-V-03674-A1; 8-V-05058-A1; 8-V-06041-A1; 8-V-

    06043-A1; 8-V-06066-HA1; 8-V-07263-A1; 8-V-07264-A1; 8-V-07315-A1

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: PK-1801

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    18 Shear Wave

    UT

    120Scan 25% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 29/12/2004 Online

    External

    Deterioration

    18 VI-EXT 60100% Coverage 04/03/2009 04/03/2019 OnLine DVI/01

    Internal Corrosion 22 UT 120Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category.

    25/11/2008 25/11/2018 OnLine UT/01

    11 July 2011 Page 5 of 176

  • 7/28/2019 Piping Exam Spec

    6/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-1801-1 Pipework from: D-0401

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    16-V-04026-DO

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: PL-1801

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    14 Shear Wave

    UT

    120Scan 25% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 29/12/2004 Online

    External

    Deterioration

    14 VI-EXT 60100% Coverage 01/01/1995 31/12/1999 OnLine DVI/01

    Internal Corrosion 18 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 31/12/1999 OnLine UT/01

    11 July 2011 Page 6 of 176

  • 7/28/2019 Piping Exam Spec

    7/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-1802 Pipework from: D-1802

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    4-HC-18009-A2; 2-HC-18011-A2; 3-HC-18010-A2; 4-HC-18008-A2

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: PL-210

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    4 VI-EXT 30100% Coverage 28/10/2009 28/10/2019 OnLine DVI/01

    Internal Corrosion 4 UT 30Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category.

    01/09/2004 01/09/2014 OnLine UT/01

    11 July 2011 Page 7 of 176

  • 7/28/2019 Piping Exam Spec

    8/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-1803 Pipework from:

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    1-V-07180-A1; 1-V-07181-A1; 1-V-07182-A1; 1-V-07183-A1; 1-V-07184-A1; 1-V-07185-A1; 1-V-07199-A1; 1-V-07308-A1; 2-HC-05028-A2; 4-HC-02100-A1

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: PK-1801

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    19 VI-EXT 60100% Coverage 04/08/2009 04/08/2014 OnLine DVI/01

    Internal Corrosion 19 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    15/09/2008 15/09/2013 OnLine UT/01

    11 July 2011 Page 8 of 176

  • 7/28/2019 Piping Exam Spec

    9/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-1803-1 Pipework from: Analyser AH-1

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    2-HC-18041-DO

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: PL-1803

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    18 VI-EXT 60100% Coverage 01/01/1995 31/12/1999 OnLine DVI/01

    Internal Corrosion 18 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 31/12/1999 OnLine UT/01

    11 July 2011 Page 9 of 176

  • 7/28/2019 Piping Exam Spec

    10/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-1805 Pipework from:

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    6-HC-07619-A30D; 4-V-07659-A30D; 4-V-07661-A30D; 2-V-07279-N0; 4-V-07596-HN0; 4-V-07108-N0; 4-V-07594-HN0; 4-V-07150-N0; 4-V-07592-HN0; 4-V-07106-N0; 1-V-07273-N0; 3-V-

    07277-N0; 1-HC-18068-N0; 1-HC-18054-N0; 1-V-18067-N0; 1-V-18071-N0; 2-V-07144-N0; 1-V-18074-N0; 4-V-18039-N0; 1-V-07203-N0; 1-V-07204-N0; 0.75-HC-07720-A1; 0.75-HC-18061-

    N0; 0.75-V-18072-N0; 0.75-V-18073-N0; 1.5-HC-07018-N0; 1.5-HC-07019-N0; 1.5-V-07492-HN0; 1.5-V-07493-HN0; 1.5-V-07512-HN0; 10-V-07140-N0; 10-V-18035-N0; 10-V-18037-N0; 16-V-

    07257-N0; 1-NI-18033-N0; 1-NI-18057-N0; 1-V-07145-N0; 1-V-07202-N0; 2-HC-07146-N0; 2-HC-07205-N0; 2-HC-07558-HN0; 2-HC-07573-HN0; 2-HC-07574-HN0; 2-HC-07575-HN0; 2-HC-

    18053-N0; 2-V-07033-N0; 2-V-07125-N0; 2-V-07126-N0; 2-V-07201-N0; 2-V-18002-N0; 2-V-18070-N0; 30-V-18028-N0; 3-V-07247-N0; 3-V-07563-HN0; 3-V-07565-HN0; 3-V-07584-HN0; 3-V-

    18038-N0; 4-HC-18046-N0; 4-V-07598-N0; 4-V-07600-HN0; 4-V-18004-N0; 4-V-18036-N0; 4-V-18044-N0; 6-V-07107-N0; 6-V-07120-N0; 6-V-18012-N0; 8-V-07132-N0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: E-1801

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    18 VI-EXT 60100% Coverage 04/08/2009 04/08/2014 OnLine DVI/01

    Internal Corrosion 18 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    01/01/1995 01/01/2000 OnLine UT/01

    11 July 2011 Page 10 of 176

  • 7/28/2019 Piping Exam Spec

    11/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2003 Pipework from: PK-2001A/B

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    2-PA-21004-B1; 2-PA-21011-B1; 2-PA-21012-B1; 3-PA-21005-B1

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: PL-2003-1

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    CUI 16 CUI

    Inspection-

    Visual

    6010% of potential CUI Locations by category. 01/06/2009 31/05/2014 Shutdown DVI/01

    External

    Deterioration

    11 VI-EXT 60100% Coverage 04/10/2009 03/10/2014 OnLine DVI/01

    Internal Corrosion 11 UT 12Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 25% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 01/01/1996 OnLine UT/01 Frequency changed by

    the ICP. the interval can

    be increase after 3

    inspections.

    11 July 2011 Page 11 of 176

  • 7/28/2019 Piping Exam Spec

    12/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2003-1 Pipework from: PL-2003

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    2-PA-20013-E0; 2-PA-20014-E0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: E2101

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    11 Remove ins

    and dye pen

    120Chloride Stress Corrosion Cracking expected

    on Circuit - consult with Materials Engineer.

    01/01/1995 29/12/2004 Shutdown DP/01

    External

    Deterioration

    11 VI-EXT 60100% Coverage 01/01/1995 31/12/1999 OnLine DVI/01

    Internal Corrosion 25 UT 120Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 29/12/2004 OnLine UT/01

    11 July 2011 Page 12 of 176

  • 7/28/2019 Piping Exam Spec

    13/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-201-1 Pipework from: PL-103

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    6-LN-02311-D2

    Nace:

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: D-0207

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    15 Shear Wave

    UT

    120Scan 25% of potential locations defined in

    the corrosion study.

    01/06/2009 30/05/2019 Online

    External

    Deterioration

    15 VI-EXT 60100% Coverage 01/03/2010 01/03/2015 OnLine DVI/01

    Internal Corrosion 19 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    01/03/2010 01/03/2015 OnLine UT/01

    11 July 2011 Page 13 of 176

  • 7/28/2019 Piping Exam Spec

    14/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-202 Pipework from: D-0207

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    4-GN-02312-B2

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: PL-212

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    15 Shear Wave

    UT

    120Scan 25% of potential locations defined in

    the corrosion study.

    01/06/2009 30/05/2019 Online

    External

    Deterioration

    15 VI-EXT 60100% Coverage 01/03/2010 01/03/2015 OnLine DVI/01

    Internal Corrosion 15 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    01/03/2010 01/03/2015 OnLine UT/01

    11 July 2011 Page 14 of 176

  • 7/28/2019 Piping Exam Spec

    15/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-203 Pipework from: D-0207

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    6-LN-02341-B2; 6-LN-02344-B2; 6-LN-02346-B2

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: F-0201

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    15 Shear Wave

    UT

    120Scan 25% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/06/2009 30/05/2019 Online

    External

    Deterioration

    15 VI-EXT 60100% Coverage 01/03/2010 01/03/2015 OnLine DVI/01

    Internal Corrosion 19 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    01/03/2010 01/03/2015 OnLine UT/01

    11 July 2011 Page 15 of 176

  • 7/28/2019 Piping Exam Spec

    16/176

  • 7/28/2019 Piping Exam Spec

    17/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-206 Pipework from: D-0208

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    2-HC-02365-B1

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: PL-206-1

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    19 VI-EXT 60100% Coverage 01/03/2010 01/03/2015 OnLine DVI/01

    Internal Corrosion 19 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    01/03/2010 01/03/2015 OnLine UT/01

    11 July 2011 Page 17 of 176

  • 7/28/2019 Piping Exam Spec

    18/176

  • 7/28/2019 Piping Exam Spec

    19/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-207-1 Pipework from: PL-203

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    8-LN-02347-B2

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: T-0202

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    18 Shear Wave

    UT

    120Scan 25% of potential locations defined in

    the corrosion study.

    01/06/2009 30/05/2019 Online

    External

    Deterioration

    18 VI-EXT 60100% Coverage 01/03/2010 01/03/2020 OnLine DVI/01

    Internal Corrosion 22 UT 120Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category.

    01/03/2010 01/03/2020 OnLine UT/01

    11 July 2011 Page 19 of 176

  • 7/28/2019 Piping Exam Spec

    20/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-208 Pipework from: T-0202

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    4-HC-02023-A3; 6-HC-02354-A1

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: E-0205

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    CUI 19 CUI

    Inspection-

    Visual

    6010% of potential CUI Locations by category. 01/06/2009 31/05/2014 OnLine DVI/01

    External

    Deterioration

    19 VI-EXT 60100% Coverage 01/06/2009 31/05/2014 OnLine DVI/01

    Internal Corrosion 19 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    01/06/2009 31/05/2014 OnLine UT/01

    11 July 2011 Page 20 of 176

  • 7/28/2019 Piping Exam Spec

    21/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-208-1 Pipework from: E-0205

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    6-HC-02355-A1; 6-HC-02356-A1; 6-HC-02357-A1

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: E-0204

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    CUI 15 Profile RT 12010% of potential CUI Locations by category.

    External

    Deterioration

    19 VI-EXT 60100% Coverage 01/03/2010 01/03/2015 OnLine DVI/01

    Internal Corrosion 19 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    01/03/2010 01/03/2015 OnLine UT/01

    11 July 2011 Page 21 of 176

  • 7/28/2019 Piping Exam Spec

    22/176

  • 7/28/2019 Piping Exam Spec

    23/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-210 Pipework from: T-0202

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    10-HC-02353-A1

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: H-0203

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    CUI 19 CUI

    Inspection-

    Visual

    60Strip 10% of potential CUI Locations by

    category.

    DVI/01

    External

    Deterioration

    19 VI-EXT 60100% Coverage 01/03/2010 01/03/2015 OnLine DVI/01

    Internal Corrosion 19 UT - Offline 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    01/06/2009 31/05/2014 OnLine UT/01

    11 July 2011 Page 23 of 176

  • 7/28/2019 Piping Exam Spec

    24/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2101 Pipework from: PK-2103

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    2-IA-21276-SO; 2-IA-21103-SO; 1-IA-21179-SO; 1.5-HW-21050-SO; 1.5-IA-07535-HSO; 1.5-IA-07538-HSO; 1.5-IA-21139-SO; 1.5-IA-21140-SO; 1-IA-01040-SO; 1-IA-20001-SO; 1-IA-20009-SO; 1-

    IA-20024-SO; 1-IA-21043-SO; 1-IA-21044-SO; 1-IA-21090-SO; 1-IA-21095-SO; 1-IA-21138-SO; 1-IA-21148-SO; 1-IA-21158-SO; 1-IA-21159-SO; 1-IA-21162-SO; 1-IA-21189-SO; 1-IA-21190-SO; 1-

    IA-21191-SO; 1-IA-21192-SO; 1-IA-21193-SO; 1-IA-21194-SO; 1-IA-21196-SO; 1-IA-21206-SO; 1-IA-21210-SO; 1-IA-21211-SO; 1-IA-21212-SO; 1-IA-21213-SO; 1-IA-21214-SO; 1-IA-21222-HSO;

    1-IA-21248-SO; 1-IA-21249-SO; 1-IA-21250-SO; 1-IA-21251-SO; 2-IA-21300-SO; 1-IA-21311-SO; 2-IA-07546-HSO; 2-IA-21048-SO; 2-IA-21049-SO; 2-IA-21079-SO; 2-IA-21080-SO; 2-IA-21081-

    SO; 2-IA-21089-SO; 2-IA-21091-SO; 2-IA-21092-SO; 2-IA-21093-SO; 2-IA-21094-SO; 2-IA-21098-SO; 2-IA-21099-SO; 2-IA-21125-SO; 2-IA-21126-SO; 2-IA-21128-SO; 2-IA-21146-SO; 2-IA-21147-

    SO; 2-IA-21163-SO; 2-IA-21179-SO; 2-IA-21185-SO; 2-IA-21186-SO; 2-IA-21197-SO; 2-IA-21229-HSO; 2-IA-21230-SO; 2-IA-21235-A023; 2-IA-21243-SO; 2-IA-21244-SO; 2-IA-21260-SO; 2-IA-

    21266-SO; 2-IA-21267-SO; 2-IA-21268-SO; 2-IA-21275-SO; 2-IA-21310-SO; 3-IA-21009-SO; 3-IA-21010-SO; 3-IA-21164-SO; 3-IA-21218-S0

    Nace: Y

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: Plant air to dist header

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    25 VI-EXT 120100% Coverage 22/10/2009 22/10/2019 OnLine DVI/01

    Internal Corrosion 25 UT 120Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category.

    01/01/1995 01/01/2005 OnLine UT/01

    11 July 2011 Page 24 of 176

  • 7/28/2019 Piping Exam Spec

    25/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2102 Pipework from:

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    1-PA-21058-L1; 1-PA-21063-L1; 1-PA-21174-L1; 1-PA-21221-L1; 1.5-HW-21013-L1; 1.5-PA-21117-L1; 1.5-PA-21118-L1; 1-PA-21055-L1; 1-PA-21057-L1; 1-PA-21059-L1; 1-PA-21062-L1; 1-PA-

    21065-L1; 1-PA-21068-L1; 1-PA-21069-L1; 1-PA-21070-L1; 1-PA-21073-L1; 1-PA-21075-L1; 1-PA-21076-L1; 1-PA-21078-L1; 1-PA-21096-L1; 1-PA-21097-L1; 1-PA-21110-L1; 1-PA-21112-L1; 1-

    PA-21113-L1; 1-PA-21115-L1; 1-PA-21116-L1; 1-PA-21121-L1; 1-PA-21122-L1; 2-PA-21123-L1; 1-PA-21145-L1; 1-PA-21157-L1; 1-PA-21161-L1; 1-PA-21166-L1; 1-PA-21168-L1; 1-PA-21169-L1;

    1-PA-21171-L1; 1-PA-21172-L1; 1-PA-21175-L1; 1-PA-21176-L1; 1-PA-21177-L1; 1-PA-21178-L1; 1-PA-21183-L1; 1-PA-21209-L1; 1-PA-21239-L1; 1-PA-21240-L1; 1-PA-21253-L1; 1-PA-21254-

    L1; 1-PA-21255-L1; 1-PA-21304-L1; 2-PA-21001-L1; 2-PA-21052-L1; 2-PA-21053-L1; 2-PA-21056-L1; 2-PA-21060-L1; 2-PA-21061-L1; 2-PA-21064-L1; 2-PA-21067-L1; 2-PA-21074-L1; 2-PA-

    21106-L1; 2-PA-21107-L1; 2-PA-21108-L1; 2-PA-21111-L1; 2-PA-21114-L1; 2-PA-21119-L1; 2-PA-21120-L1; 2-PA-21137-L1; 2-PA-21144-L1; 2-PA-21165-L1; 2-PA-21167-L1; 2-PA-21173-L1; 2-

    PA-21228-HL1; 2-PA-21242-L1; 2-PA-21252-L1; 2-PA-21259-L1; 2-PA-21262-L1; 2-PA-21263-L1; 2-PA-21264-L1; 2-PA-21265-L1; 2-PA-21269-L1; 2-PA-21270-L1; 2-V-21002-L1; 3-PA-21006-L1;

    3-PA-21007-L1; 3-PA-21051-L1; 3-PA-21066-L1; 3-PA-21070-L1; 3-PA-21071-L1; 3-PA-21182-L1; 3-V-21003-L1

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: Plant air to dist header

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    25 VI-EXT 120100% Coverage 13/04/2009 13/04/2019 OnLine DVI/01

    Internal Corrosion 25 UT 120Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category.

    01/01/1995 01/01/2005 OnLine UT/01

    11 July 2011 Page 25 of 176

  • 7/28/2019 Piping Exam Spec

    26/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2103 Pipework from: PK-2103

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    1.5-NI-07533-HA1; 1.5-NI-07576-HA1; 1-NI-07534-HA1; 8-NI-07607-HA1; 8-NI-07608-HA1; 8-NI-07609-HA1; 3-V-07603-HA1; 1.5-NI-07536-HA1; 1-NI-07537-HA1; 1.5-NI-07577-HA1; 3-V-

    07604-HA1; 1.5-NI-07539-HA1; 1-NI-07540-HA1; 1.5-NI-07578-HA1; 3-V-07605-HA1; 1-NI-18055-A1; 2-NI-03260-A1; 2-NI-03336-A1; 3-NI-03329-A1; 4-NI-03337-A1; 4-NI-03104-A2; 1.5-NI-

    03101-A2; 1.5-NI-03102-A2; 1-NI-05037-A2; 1-NI-21305-A1; 2-NI-21306-A1; 1-NI-23167-A1; 1-NI-23168-A1; 1-NI-23169-A1; 1-NI-23170-A1; 1-NI-23171-A1; 1-V-23180-A1; 2-V-23181-A1; 1-

    NI-01037-A1 ; 0.5-HW-21207-A1; 0.75-HW-21215-A1; 1.5-HW-21136-A1; 1.5-NI-21025-A1; 1.5-NI-21026-A1; 12-NI-03158-A1; 12-NI-03358-A1; 16-NI-07115-A1; 16-NI-07116-A1; 1-NI-

    07533-HA1; 1-NI-07536-HA1; 1-NI-07539-HA1; 1-NI-18043-A1; 1-NI-18054-A1; 1-NI-18056-A1; 1-NI-18091-A1; 1-NI-21014-A1; 1-NI-21017-A1; 1-NI-21019-A1; 1-NI-21022-A1; 1-NI-21023-

    A1; 1-NI-21024-A1; 1-NI-21030-A1; 1-NI-21031-A1; 1-NI-21032-A1; 1-NI-21033-A1; 1-NI-21034-A1; 1-NI-21035-A1; 1-NI-21045-A1; 1-NI-21134-A1; 1-NI-21141-A1; 1-NI-21150-A1; 1-NI-

    21151-A1; 1-NI-21152-A1; 1-NI-21153-A1; 1-NI-21154-A1; 1-NI-21155-A1; 1-NI-21180-A1; 1-NI-21181-A1; 1-NI-21188-A1; 1-NI-21198-A1; 1-NI-21199-A1; 1-NI-21200-A1; 1-NI-21201-A1; 1-

    NI-21202-A1; 1-NI-21203-A1; 1-NI-21205-A1; 1-NI-21220-A1; 1-NI-21256-A1; 1-NI-21257-A1; 1-NI-21258-A1; 1-NI-21301-A1; 1-NI-21303-A1; 20-NI-07013-A1; 20-NI-07510-HA1; 2-NI--03060-

    A1; 2-NI-03136-A1; 2-NI-07562-HA1; 2-NI-21015-A1; 2-NI-21016-A1; 2-NI-21028-A1; 2-NI-21042-A1; 2-NI-21100-A1; 2-NI-21127-A1; 2-NI-21128-A1; 2-NI-21129-A1; 2-NI-21130-A1; 2-NI-

    21131-A1; 2-NI-21132-A1; 2-NI-21133-A1; 2-NI-21135-A1; 2-NI-21143-A1; 2-NI-21149-A1; 2-NI-21160-A1; 2-NI-21195-A1; 2-NI-21217-A1; 2-NI-21245-A1; 2-NI-21246-A1; 2-NI-21247-A1; 2-

    NI-21261-A1; 2-NI-21305-A1; 2-NI-27010-A1; 2-V-21208-A1; 3-NI-03129-A1; 3-NI-03816-A1; 3-NI-03817-A1; 3-NI-03891-A1; 3-NI-21020-A1; 3-V-25016-A2; 3-V-25017-A2; 4-NI-07014-A1; 4-

    NI-21014-A1; 4-NI-21021-A1; 4-NI-21027-A1; 4-NI-21039-A1; 2-UT-35116-CS-; 0.5-UT-35330-SST-; 10-UT-35331-SST-; 10-UT-35332-SST-; 2-UT-35333-CS-

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: H P nitrogene to dist header

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    25 VI-EXT 120100% Coverage 14/04/2009 14/04/2019 OnLine DVI/01

    Internal Corrosion 25 UT 120Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category.

    01/01/1995 01/01/2005 OnLine UT/01

    11 July 2011 Page 26 of 176

  • 7/28/2019 Piping Exam Spec

    27/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-211 Pipework from: T-0202

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    6-GN-02359-A2; 6-GN-02360-A2

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: PL-2204

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    18 Shear Wave

    UT

    120Scan 25% of potential locations defined in

    the corrosion study.

    01/06/2009 30/05/2019 Online

    External

    Deterioration

    18 VI-EXT 60100% Coverage 01/03/2010 01/03/2020 OnLine DVI/01

    Internal Corrosion 22 UT 120Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category.

    01/03/2010 01/03/2020 OnLine UT/01

    11 July 2011 Page 27 of 176

  • 7/28/2019 Piping Exam Spec

    28/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-212 Pipework from: PL-205/PL202

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    4-GN-02370-B1

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: PL-2213

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    15 Shear Wave

    UT

    120Scan 25% of potential locations defined in

    the corrosion study.

    01/06/2009 30/05/2019 Online

    External

    Deterioration

    15 VI-EXT 60100% Coverage 01/03/2010 01/03/2015 OnLine DVI/01

    Internal Corrosion 15 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    01/03/2010 01/03/2015 OnLine UT/01

    11 July 2011 Page 28 of 176

  • 7/28/2019 Piping Exam Spec

    29/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2204 Pipework from: PL 207

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    2-V-22148-HA3; 1-V-03111-A3; 1-V-03311-A3; 2-FG-22024-A3; 2-FG-22027-A3; 2-FG-22047-A3; 2-FG-22048-A3; 2-FG-22151-A3; 2-FG-22052-A3; 2-FG-22084-A3; 2-FG-22143-HA3; 2-FG-

    35161-CS 150-; 2-FG-35164-CS 150-; 2-HC-22042-A3; 3-FG-22026-A3; 3-FG-22029-A3; 3-FG-22031-A3; 3-FG-22053-A3; 3-FG-22087-A3; 3-FG-22088-A3; 3-FG-22089-A3; 3-FG-22090-A3; 4-FG-

    22019-A3; 4-FG-22021-A3; 4-FG-22025-A3; 4-FG-22049-A3; 6-FG-22068-A3; 4-FG-22069-A3; 4-FG-22085-A3; 4-FG-22086-A3; 4-FG-35161-CS 150-; 4-HC-22043-A3; 4-HC-22062-HA3; 4-HC-

    22081-HA3; 6-FG-22014-A3; 6-FG-22023-A3; 6-FG-22071-HA3; 6-FG-22072-HA3; 6-FG-22076-HA3; 6-FG-22077-HA3; 6-FG-22083-HA3; 8-FG-22003-A3; 8-FG-22017-A3; 8-FG-22041-A3; 8-HC-

    22001-A3; Unkn0wn size--35163--

    Nace: Y

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: D-1804

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    14 Shear Wave

    UT

    120Scan 25% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 29/12/2004 Online

    External

    Deterioration

    4 VI-EXT 30100% Coverage 15/06/2009 14/12/2011 OnLine DVI/01

    Internal Corrosion 4 UT 12Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category.

    14/01/2009 14/01/2010 OnLine UT/01 Inspect annually for 3

    years. Then detemine

    corrosion rate based on

    the 3 inspections.

    11 July 2011 Page 29 of 176

  • 7/28/2019 Piping Exam Spec

    30/176

  • 7/28/2019 Piping Exam Spec

    31/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2213A Pipework from: D-2202

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    2-HC-22010-B3; 2-HC-22153-B3

    Nace: Y

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: PL-203

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    4 VI-EXT 30100% Coverage 15/06/2009 14/12/2011 OnLine DVI/01

    Internal Corrosion 4 UT 30Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    14/01/2009 15/07/2011 OnLine UT/01

    11 July 2011 Page 31 of 176

  • 7/28/2019 Piping Exam Spec

    32/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2221 Pipework from: H-2203

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    3-HC-22140-HB3-1"-H; 4-HC-22064-HC3-1"-H; 4-HC-22065-HB3-1"-H; 3-HC-22141-HB3; 3-HC-22082-HB3

    Nace:

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: PK-1803

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    CUI 15 CUI

    Inspection-

    Visual

    6010% of potential CUI Locations by category. 01/06/2009 31/05/2014 OnLine DVI/01

    Environmental

    Cracking

    15 Shear Wave

    UT

    120Scan 50% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/2007 29/12/2016 Online

    External

    Deterioration

    15 VI-EXT 60100% Coverage 01/01/2007 31/12/2011 OnLine DVI/01

    Internal Corrosion 15 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 25% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/06/2009 31/05/2014 OnLine UT/01

    11 July 2011 Page 32 of 176

  • 7/28/2019 Piping Exam Spec

    33/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2301 Pipework from: Water treating pakage

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    4-TW-23024-G1; 4-TW-23016-G1; 3-TW-23110-HDPE; 2-TW-23252-G1; 2-TW-23200-G1; 2-TW-23131-G1; 2-TW-23091-G1; 2-TW-23060-G1; 1-V-23070-S0; 1-V-23068-S0; 1-TW-23165-G1; 1-

    TW-23069-S0; 1-TW-23067-S0; 1-TW-23030-S0; 1-TW-23031-S0; 1-TW-23085-G1; 1-TW-23090-G1; 1-TW-23092-G1; 1-TW-23093-G1; 1-TW-23094-G1; 1-TW-23095-G1; 1-TW-23098-G1; 1-

    TW-23099-G1; 1-TW-23101-G1; 1-TW-23105-G1; 1-TW-23106-G1; 1-TW-23107-G1; 1-TW-23109-G1; 1-TW-23117-HDPE; 1-TW-23118-HDPE; 1-TW-23126-G1; 1-TW-23127-G1; 1-TW-23189-

    HDPE; 1-TW-23191-HDPE; 1-TW-23194-G1; 1-TW-23196-G1; 1-TW-23197-G1; 1-TW-23198-G1; 1-TW-23199-G1; 1-TW-23201-G1; 1-TW-23202-G1; 1-TW-23203-G1; 1-TW-23204-G1; 1-TW-

    23205-G1; 1-TW-23220-G1; 1-TW-23221-G1; 1-TW-23222-G1; 1-TW-23223-G1; 1-TW-23229-G1; 1-TW-23230-G1; 1-TW-23235-G1; 1-TW-23273-HDPE; 1-TW-23279-S0; 1-TW-23280-S0; 1-

    TW-23281-S0; 1-TW-23300-G1; 2-TW-23022-AL0; 2-TW-23029-HDPE; 2-TW-23033-HDPE; 2-TW-23050-D0; 2-TW-23064-G1; 2-TW-23084-G1; 2-TW-23097-G1; 2-TW-23100-G1; 2-TW-23102-

    G1; 2-TW-23104-G1; 2-TW-23115-HDPE; 2-TW-23116-HDPE; 2-TW-23121-HDPE; 2-TW-23122-HDPE; 2-TW-23147-HDPE; 2-TW-23156-G1; 2-TW-23157-HDPE; 2-TW-23164-G1; 2-TW-23166-

    G1; 2-TW-23195-G1; 2-TW-23209-H2; 2-TW-23219-G1; 2-TW-23226-HDPE; 2-TW-23236-HDPE; 2-TW-23239-G1; 2-TW-23251-HDPE; 2-TW-23253-G1; 2-TW-23275-HDPE; 2-TW-23278-S0; 2-

    TW-23284-S0; 2-TW-23287-G1; 2-TW-23287-S0; 2-TW-23288-S0; 2-TW-23289-S0; 2-TW-23290-S0; 3-TW-23002-AL0; 3-TW-23015-HDPE; 3-TW-23016-HDPE; 3-TW-23021-G1; 3-TW-23021-

    HDPE; 3-TW-23022-HDPE; 3-TW-23023-HDPE; 3-TW-23025-HDPE; 3-TW-23026-HDPE; 3-TW-23027-HDPE; 3-TW-23028-HDPE; 3-TW-23032-HDPE; 3-TW-23033-HDPE; 3-TW-23034-HDPE; 3-

    TW-23087-HDPE; 3-TW-23103-HDPE; 3-TW-23110-HDPE; 3-TW-23111-HDPE; 3-TW-23112-HDPE; 3-TW-23113-HDPE; 3-TW-23185-HDPE; 3-TW-23228-HDPE; 3-TW-23247-HDPE; 4-TW-

    23017-H2PE; 4-TW-23018-G1; 4-TW-23019-HDPE; 4-TW-23020-HDPE; 4-TW-23057-G1; 4-TW-23151-HDPE

    Nace:

    Inspection plan

    Line list:

    Material: PP PP

    Pipework to: TK-2302

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    16 VI-EXT 120100% Coverage 04/06/2009 04/06/2019 OnLine DVI/01

    Internal Corrosion 16 UT 0Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 01/01/1995 OnLine UT/01

    11 July 2011 Page 33 of 176

  • 7/28/2019 Piping Exam Spec

    34/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2302 Pipework from: TK-2304

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    0.75-TW-23193-D0; 1-TW-23231-D0; 1-TW-23232-D0; 1-TW-23233-D0; 1-TW-23234-D0; 1-TW-23240-D0; 1-TW-23255-D0; 2-TW-03513-HF0; 2-TW-03633-HF0; 2-TW-03634-HF0; 2-TW-

    03678-HF0; 2-TW-03693-HD0; 2-TW-03694-HD0; 2-TW-03695-HD0; 2-TW-03696-HD0; 3-TW-23051-D0; 2-TW-23054-D0; 2-TW-23055-D0; 2-TW-23063-D0; 2-TW-23075-D0; 2-TW-23076-D0;

    2-TW-23077-D0; 2-TW-23079-D0; 2-TW-23096-D0; 2-TW-23108-D0; 2-TW-23125-D0; 2-TW-23150-D0; 2-TW-23210-D0; 2-TW-23254-HD0; 2-TW-23256-D0; 2-TW-23261-A023; 2-TW-23262-

    A023; 2-TW-23277-ND0; 3-TW-23052-D0; 3-V-03680-HD0; 3-V-03681-HD0; 3-V-03682-HD0; 3-V-03683-HD0; 2-TW-03054-D0; 2-TW-23159-D0; 2-TW-23001-D0; 1-TW-03897-D0; 1-TW-

    20002-D0; 1-TW-20010-D0; 1-TW-23124-D0; 1-TW-23192-D0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: Distribution

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    23 VI-EXT 120100% Coverage 04/06/2009 04/06/2019 OnLine DVI/01

    Internal Corrosion 23 UT 120Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category.

    01/01/1995 01/01/2005 OnLine UT/01

    11 July 2011 Page 34 of 176

  • 7/28/2019 Piping Exam Spec

    35/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2303 Pipework from: SEA

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    10-SW-23132-H2PE; 10-SW-23133-H2; 12-SW-23011-H2; 1-SW-23013-H2; 1-SW-23272-H2; 4-SW-23128-H2; 4-SW-23238-H2; 4-SW-23248-G1; 6-SW-23007-H2; 6-SW-23008-H2; 6-SW-

    23009-H2; 6-SW-23010-H2; 8-SW-23006-H2; 8-SW-23134-HDPE; 8-SW-23237-H2; 8-SW-23241-H2; 8-SW-23242-H2; 8-SW-23243-H2; 8-SW-23135-HDPE; 8-SW-23016-H2; 2-SW-23208-H2; 2-

    SW-23245-H2; 3-SW-23246-H2; 1-SW-23271-H2

    Nace:

    Inspection plan

    Line list:

    Material: HDPE PE3408

    Pipework to: Water treating pakage / TK

    2301

    Damagemechanisms

    Insp.Priority

    Insp. Method Freq.(months)

    Extent of Inspection Last insp.date

    Next insp.Due date

    Availability Guideline Comments

    External

    Deterioration

    23 VI-EXT 120100% Coverage 04/06/2009 04/06/2009 OnLine DVI/01

    Internal Corrosion 23 UT 0Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category.

    01/01/1995 01/01/1995 OnLine UT/01

    11 July 2011 Page 35 of 176

  • 7/28/2019 Piping Exam Spec

    36/176

  • 7/28/2019 Piping Exam Spec

    37/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2501-1 Pipework from:

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    1-AM-03528-HD0; 1-AM-03685-HD0; 0.75-AM-03523-HD0; 0.75-AM-03520-HD0; 0.75-AM-03524-HD0; 1.5-AM-03076-HD0; 1.5-AM-03157-D0; 1.5-AM-03547-HD0; 1.5-AM-03576-HD0; 1-

    AM-03139-D0; 1-AM-03141-D0; 1-AM-03183-D0; 1-AM-03184-D0; 1-AM-03185-D0; 1-AM-03188-D0; 1-AM-03189-D0; 1-AM-03341-D0; 1-AM-03383-D0; 1-AM-03384-D0; 1-AM-03385-D0; 1-

    AM-03388-D0; 1-AM-03389-D0; 1-AM-03533-HD0; 1-AM-03620-HD0; 1-AM-03624-HD0; 2-AM-03063-D0; 2-AM-03072-D0; 2-AM-03114-D0; 2-AM-03115-D0; 2-AM-03116-D0; 2-AM-03127-

    D0; 2-AM-03140-D0; 2-AM-03142-D0; 2-AM-03186-D0; 2-AM-03187-D0; 2-AM-03190-D0; 2-AM-03263-D0; 2-AM-03272-D0; 2-AM-03327-D0; 2-AM-03340-D0; 2-AM-03342-D0; 2-AM-03386-

    D0; 2-AM-03387-D0; 2-AM-03390-D0; 4-AM-03182-D0; 4-AM-03382-ND0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: D-2501

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    24 VI-EXT 120100% Coverage 04/07/2009 02/07/2019 OnLine DVI/01

    Internal Corrosion 24 UT 120Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category.

    01/01/1995 29/12/2004 OnLine UT/01

    11 July 2011 Page 37 of 176

  • 7/28/2019 Piping Exam Spec

    38/176

  • 7/28/2019 Piping Exam Spec

    39/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2501U Pipework from: Amine sumps

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    6-AM-25036-A2; 6-AM-25018-A2; 6-AM-25009-A2; 6-AM-25007-A2; 6-AM-25003-A2; 6-AM-25001-A2; 6-AM-20624-A2; 4-AM-25046-HA2; 4-AM-25040-A2; 4-AM-25037-A2; 4-AM-25035-

    A2; 4-AM-25034-A2; 4-AM-25010-A2; 4-AM-25004-A2; 3-AM-25011-A2; 2-AM-25043-A2

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to:

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    17 VI-EXT 60100% Coverage 01/01/1995 31/12/1999 DVI/01

    Internal Corrosion 17 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 31/12/1999 OnLine UT/01 ICP recommends that

    BGT should ensure the

    external condition of the

    wrapping is effective,

    otherwise a CP system

    should be installed."

    11 July 2011 Page 39 of 176

  • 7/28/2019 Piping Exam Spec

    40/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2502A Pipework from: glycol sumps

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    0.5-V-05086-A1; 0.5-V-05087-A1; 0.75-GL-05101-A2; 0.75-GL-05102-A1; 1-HC-05063-A1; 1-HC-05077-A1; 1-HC-05078-A1; 1-HC-05083-A1; 1-HC-05084-A1; 1-V-05060-A2; 1-V-05062-A2; 1-V-

    05074-A2; 1-V-05075-A2; 1-V-05097-HA1; 6-GL-05069-A2; 2-GL-05089-A2; 2-HW-25023-A2; 2-HW-25041-A2; 2-V-05096-HA1; 4-V-25027-A2; 4-V-25028-A2; 4-V-25033-A2

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: TK-2501

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    11 VI-EXT 60100% Coverage 08/04/2009 07/04/2014 OnLine DVI/01

    Internal Corrosion 11 UT 0Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 25% of Potential locations by Location

    Category.

    25/12/2008 25/12/2008 OnLine UT/01

    11 July 2011 Page 40 of 176

  • 7/28/2019 Piping Exam Spec

    41/176

  • 7/28/2019 Piping Exam Spec

    42/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2701 Pipework from:

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    2-HW-06009-C1; 1-HW-05026-A2; 1-HW-27015-A2; 2-AM-25038-A2; 2-HC-03118-A2; 2-HC-03318-A2; 2-HW-06010-A1; 2-HW-06054-A1; 2-HW-06055-A1; 2-HW-27014-A2; 3-HC-18031-A2

    Nace:

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: PL-2702

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    11 VI-EXT 60100% Coverage 21/05/2009 20/05/2014 OnLine DVI/01

    Internal Corrosion 11 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category.

    14/11/2008 13/11/2013 OnLine UT/01

    11 July 2011 Page 42 of 176

  • 7/28/2019 Piping Exam Spec

    43/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-2702 Pipework from: waste water drains

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    1-HW-23158-D0; 1-CD-35114-SST-; 1-CD-35115-SST-; 1-CD-35119-SST-; 1-CD-35120-SST-; 1-HW-23254-D0; 1-HW-27003-D0; 1-HW-27004-D0; 1-HW-27005-D0; 2-HW-03734-D0; 2-HW-

    04011-D0; 2-HW-23149-D0; 2-HW-27001-D0; 2-HW-27002-D0; 2-HW-27006-D0; 2-HW-27007-D0; 3-HW-27008-D0; 3-HW-27009-D0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: TK-2701

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    23 VI-EXT 120100% Coverage 21/05/2009 21/05/2019 OnLine DVI/01

    Internal Corrosion 23 UT 120Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category.

    01/01/1995 01/01/2005 OnLine UT/01

    11 July 2011 Page 43 of 176

  • 7/28/2019 Piping Exam Spec

    44/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-301A Pipework from: D-0301

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    2-HC-03003-C3; 2-HC03004-B3

    Nace: Y

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: PL-0103

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    14 Shear Wave

    UT

    120Scan 25% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 29/12/2004 OnLine

    External

    Deterioration

    4 VI-EXT 30100% Coverage 01/01/1995 01/07/1997 OnLine DVI/01

    Internal Corrosion 4 UT 12Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 50% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 01/01/1996 OnLine UT/01 Frequency changed by

    the ICP. the interval can

    be increase after 3

    inspections.

    11 July 2011 Page 44 of 176

  • 7/28/2019 Piping Exam Spec

    45/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-302 Pipework from: E-0301

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    16-HC-03006-C3; 4-V-03155-C3; 2-V-03196-C3; 16-HC-03751-C3; 3-V-03824-C3; 2-PG-03838-C3; 16-HC-03752-C3; 2-HC-03765-B3; 2-HC-03753-B3; 2-HC-03152-B3; 2-HC-03153-B3

    Nace: Y

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: F-0301

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    9 Shear Wave

    UT

    120Scan 50% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 29/12/2004 OnLine

    External

    Deterioration

    6 VI-EXT 60100% Coverage 02/02/2009 01/02/2014 OnLine DVI/01

    Internal Corrosion 6 UT 12Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 25% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    03/10/2008 03/10/2009 OnLine UT/01 Frequency changed by

    the ICP. the interval can

    be increase after 3

    inspections.

    11 July 2011 Page 45 of 176

  • 7/28/2019 Piping Exam Spec

    46/176

  • 7/28/2019 Piping Exam Spec

    47/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-302B Pipework from: HC-03025

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    12-HC-03027-C3; 16-HC-03025-C3

    Nace: Y

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: T-301B

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    9 Shear Wave

    UT

    120Scan 50% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 29/12/2004 Online

    External

    Deterioration

    2 VI-EXT 30100% Coverage 02/04/2009 02/04/2009 OnLine DVI/01

    Internal Corrosion 2 UT 12Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 25% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    25/10/2008 25/10/2008 OnLine UT/01 Original frq is 0. it 's

    recommended from the

    ICP to Inspect annually

    for 3 years. Then

    detemine corrosion rate

    based on the 3

    inspections.

    11 July 2011 Page 47 of 176

  • 7/28/2019 Piping Exam Spec

    48/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-303 Pipework from: HC-03019

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    16-HC-03007-C1

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: E-0301

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    9 Shear Wave

    UT

    120Scan 50% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 29/12/2004 OnLine

    External

    Deterioration

    6 VI-EXT 60100% Coverage 02/08/2009 01/08/2014 OnLine DVI/01

    Internal Corrosion 6 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 25% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    21/10/2008 20/10/2013 OnLine UT/01

    11 July 2011 Page 48 of 176

  • 7/28/2019 Piping Exam Spec

    49/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-303-1 Pipework from: E-0301 shell

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    16-HC-03008-C1

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: D-0302

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    9 Shear Wave

    UT

    120Scan 50% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 29/12/2004 OnLine

    External

    Deterioration

    9 VI-EXT 60100% Coverage 02/08/2009 01/08/2014 OnLine DVI/01

    Internal Corrosion 15 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    10/10/2008 09/10/2013 OnLine UT/01

    11 July 2011 Page 49 of 176

  • 7/28/2019 Piping Exam Spec

    50/176

  • 7/28/2019 Piping Exam Spec

    51/176

  • 7/28/2019 Piping Exam Spec

    52/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-304 Pipework from:

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    16-HC-03009-C1; 1.5-V-03194-C1; 16-HC-05001-C1; 1-V-05053-C1; 2-AM-05002-C2; 2-AM-05003-C2; 12-HC-05049-C1

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: F-0501

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    9 Shear Wave

    UT

    120Scan 50% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 29/12/2004 OnLine

    External

    Deterioration

    9 VI-EXT 60100% Coverage 16/02/2009 15/02/2014 OnLine DVI/01

    Internal Corrosion 15 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    11/09/2008 10/09/2013 OnLine UT/01

    11 July 2011 Page 52 of 176

  • 7/28/2019 Piping Exam Spec

    53/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-304-1 Pipework from: F-0501

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    2-AM-HC-05005-A2; 2-AM-HC-05004-A2; 2-AM-03575-HA2

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: PL-306A

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    14 Shear Wave

    UT

    120Scan 25% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 29/12/2004 OnLine

    External

    Deterioration

    8 VI-EXT 60100% Coverage 01/01/1995 31/12/1999 OnLine DVI/01

    Internal Corrosion 14 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/08/2008 31/07/2013 OnLine UT/01

    11 July 2011 Page 53 of 176

  • 7/28/2019 Piping Exam Spec

    54/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-306A Pipework from: T-0301A

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    12-AM-03028-F0; 12-AM-03030-D0; 12-AM-03541-HD0; 6-HC-03655-HDO; 16-V-03656-HDO; 6-V-03658-HDO; 2-AM-03597-HDO; 2-AM-03697-HDO; 12-V-03699-HDO; 12-V-03663-HDO

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: D-0303A

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    9 Remove ins

    and dye pen

    120Chloride Stress Corrosion Cracking expected

    on Circuit - consult with Materials Engineer.

    01/01/2003 29/12/2012 Shutdown DP/01

    External

    Deterioration

    6 VI-EXT 60100% Coverage 01/06/2009 31/05/2014 OnLine DVI/01

    Internal Corrosion 6 UT 47Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 25% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/2003 12/12/2006 OnLine UT/01

    11 July 2011 Page 54 of 176

  • 7/28/2019 Piping Exam Spec

    55/176

  • 7/28/2019 Piping Exam Spec

    56/176

  • 7/28/2019 Piping Exam Spec

    57/176

  • 7/28/2019 Piping Exam Spec

    58/176

  • 7/28/2019 Piping Exam Spec

    59/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-308B Pipework from: D-0303A/B

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    0.75-AM-03523-HD0; 0.75-AM-03671-HD0; 12-AM-03244-D0; 12-AM-03534-HD0; 1-AM-03335-A2; 1-AM-03411-A2; 1-AM-03392-D0; 4-AM-03616-HD0; 1-AM-03685-HD0; 4-AM-03676-

    HD0; 0.75-AM-03523-HD0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: E-0302B/D

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    9 Remove ins

    and dye pen

    120Chloride Stress Corrosion Cracking expected

    on Circuit - consult with Materials Engineer.

    01/01/2003 29/12/2012 Shutdown DP/01

    External

    Deterioration

    6 VI-EXT 60100% Coverage OnLine DVI/01

    Internal Corrosion 9 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 25% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/2003 31/12/2007 OnLine UT/01

    11 July 2011 Page 59 of 176

  • 7/28/2019 Piping Exam Spec

    60/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-309 Pipework from: TK-0302

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    1.5-AM-03896-A2; 10-AM-03123-A2; 16-AM-03074-A2; 16-AM-03075-A2; 16-AM-03076-A2; 16-AM-03120-A2; 16-AM-03517-HA2; 16-AM-03601-A2; 16-AM-03605-A2; 18-AM-03073-A2; 1-

    AM-03132-A2; 1-AM-03133-A2; 1-AM-03511-A2; 1-AM-03512-A2; 3-AM-03099-A2; 2-AM-03700-A2; 1-AM-03614-HA2; 1-V-03222-A2; 1-V-03223-A2; 1-V-03224-A2; 1-V-03225-A2; 1-V-

    03226-A2; 1-V-03227-A2; 1-V-03613-A2; 1-V-03615-HA2; 2-AM-03126-A2; 2-AM-03151-A2; 2-AM-03296-D0; 2-AM-03676-A2; 2-AM-03708-A023; 2-AM-03709-A023; 2-AM-03710-A023; 2-

    AM-03711-A023; 2-AM-03712-A023; 2-AM-03713-A023; 2-AM-O3699-A2; 3-AM-03083-A2; 3-AM-03084-A2; 3-AM-03085-A2; 3-AM-03089-A2; 3-AM-03090-A2; 3-AM-03091-A2; 3-AM-

    03100-A2; 3-AM-03231-A2; 3-AM-03628-A2; 3-AM-03673-A2; 3-AM-03686-HA2; 3-AM-03687-HA2; 3-AM-03688-HA2; 3-AM-03703-HA2; 4-AM-03097-A2; 4-AM-03098-A2; 4-AM-03131-A2;

    6-AM-03081-A2; 6-AM-03082-A2; 6-AM-03095-A2; 6-AM-03096-A2; 6-AM-03121-A2; 6-AM-03122-A2; 6-AM-03154-A2; 6-AM-03516-HA2; 6-AM-03544-HA2; 6-AM-03651-HA2; 6-AM-03652-

    HA2; 6-AM-03665-HA2; 6-AM-03666-HA2; 6-AM-03667-HA2

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: P-0303A/B/C/D

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    4 Shear Wave

    UT

    60Scan 100% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 31/12/1999 Online

    External

    Deterioration

    4 VI-EXT 30100% Coverage 26/10/2009 25/04/2012 OnLine DVI/01

    Internal Corrosion 8 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 25% of Potential locations by Location

    Category.

    01/09/2008 31/08/2013 OnLine UT/01

    11 July 2011 Page 60 of 176

  • 7/28/2019 Piping Exam Spec

    61/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-309-1 Pipework from: P-0303A/B/C/D

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    10-AM-03077-HD0; 10-AM-03078-HD0; 10-AM-03079-HD0; 10-AM-03518-HD0; 12-AM-03068-HD0; 12-AM-03069-HD0; 12-AM-03070-HD0; 12-AM-03514-HD0; 16-AM-03071-HD0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: P-0304A/B/C/D

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    18 VI-EXT 60100% Coverage 26/10/2009 26/10/2014 OnLine DVI/01

    Internal Corrosion 18 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    02/09/2008 02/09/2013 OnLine UT/01

    11 July 2011 Page 61 of 176

  • 7/28/2019 Piping Exam Spec

    62/176

  • 7/28/2019 Piping Exam Spec

    63/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-310A Pipework from: AM-03022

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    12-AM-03023-C2

    Nace:

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: T-0301A

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    14 Shear Wave

    UT

    120Scan 25% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 29/12/2004 Online

    External

    Deterioration

    14 VI-EXT 60100% Coverage 19/05/2009 18/05/2014 OnLine DVI/01

    Internal Corrosion 22 UT 120Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category.

    09/10/2008 07/10/2018 OnLine UT/01

    11 July 2011 Page 63 of 176

  • 7/28/2019 Piping Exam Spec

    64/176

    ( )

  • 7/28/2019 Piping Exam Spec

    65/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-311 Pipework from: E-0305

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    16-HC-03002-C3

    Nace: Y

    Inspection plan

    Line list:

    Material: SA-106 B

    Pipework to: E-0301

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    9 Shear Wave

    UT

    120Scan 50% of potential locations defined in

    the corrosion study. (Date In Service was

    used as last inspection date.)

    01/01/1995 29/12/2004 Online

    External

    Deterioration

    6 VI-EXT 60100% Coverage 13/02/2009 12/02/2014 OnLine DVI/01

    Internal Corrosion 9 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 50% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    04/09/2008 03/09/2013 OnLine UT/01

    11 July 2011 Page 65 of 176

  • 7/28/2019 Piping Exam Spec

    66/176

  • 7/28/2019 Piping Exam Spec

    67/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    68/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-313A Pipework from: AM-03059

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    12-AM-03892-NDO; 18-AM-03059-D0; 12-AM-03056-D0; 12-AM-03057-D0; 12-AM-03619-HD0; 12-AM-03058-D0; 12-AM-03061-D0; 12-AM-03106-D0; 14-AM-03783-ND0; 2-AM-03840-

    ND0; 12-AM-03531-ND0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: H-0301A

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    4 Remove ins

    and dye pen

    60Chloride Stress Corrosion Cracking expected

    on Circuit - consult with Materials Engineer.

    01/01/1995 31/12/1999 Shutdown DP/01

    External

    Deterioration

    4 VI-EXT 30100% Coverage 01/01/1995 01/07/1997 OnLine DVI/01

    Internal Corrosion 18 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 31/12/1999 OnLine UT/01

    11 July 2011 Page 68 of 176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    69/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-313B Pipework from: P-0301D/E/F/H

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    6"-AM-03794-ND0; 6"-AM-03795-ND0; 12-AM-03256-D0; 12-AM-03257-D0; 12-AM-03258-D0; 12-AM-03261-D0; 12-AM-03306-D0; 12-AM-03536-HD0; 12-AM-03623-HD0; 12-AM-03893-

    ND0; 14-AM-03785-ND0; 18-AM-03259-D0; 2-AM-03841-ND0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: H-0301B

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    4 Remove ins

    and dye pen

    60Chloride Stress Corrosion Cracking expected

    on Circuit - consult with Materials Engineer.

    01/01/1995 31/12/1999 Shutdown DP/01

    External

    Deterioration

    4 VI-EXT 30100% Coverage 01/01/1995 01/07/1997 OnLine DVI/01

    Internal Corrosion 18 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 31/12/1999 OnLine UT/01

    11 July 2011 Page 69 of 176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    70/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-317A Pipework from: E-0302A/C

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    12-AM-03062-HD0; 12-AM-03530-HD0; 1-AM-03134-HD0; 1-AM-03210-HD0; 8-AM-03086-D0; 8-AM-03087-D0; 8-AM-03088-D0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: E-0304A

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    14 VI-EXT 60100% Coverage 18/02/2009 17/02/2014 OnLine DVI/01

    External Stress

    Corrosion Cracking

    14 Remove ins

    and dye pen

    60External Stress Corrosion Cracking expected

    on Circuit - consult with Materials Engineer.

    01/01/1995 31/12/1999 Shutdown DP/01

    Internal Corrosion 18 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 31/12/1999 OnLine UT/01

    11 July 2011 Page 70 of 176

  • 7/28/2019 Piping Exam Spec

    71/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    72/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-318A Pipework from: D-0304A

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    12-AG-03506-D0; 16-AG-03125-D0; 4-V-03214-D0; 4-V-03215-D0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: PK-1801

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    21 VI-EXT 120100% Coverage 02/03/2009 28/02/2019 OnLine DVI/01

    Internal Corrosion 21 UT 120Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    01/01/1995 29/12/2004 OnLine UT/01

    11 July 2011 Page 72 of 176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    73/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-318B Pipework from: D-0304B

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    12-AG-03506-D0; 16-AG-03325-D0; 4-V-03414-D0; 4-V-03415-D0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: PL-318A

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    21 VI-EXT 120100% Coverage 02/02/2009 31/01/2019 OnLine DVI/01

    Internal Corrosion 21 UT 120Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    01/01/1995 29/12/2004 OnLine UT/01

    11 July 2011 Page 73 of 176

  • 7/28/2019 Piping Exam Spec

    74/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    75/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-319A-1 Pipework from: E-0304A

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    8-AM-03092-D0; 8-AM-03093-D0; 8-AM-03094-D0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: PL-319A

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    18 VI-EXT 60100% Coverage 20/02/2009 20/02/2014 OnLine DVI/01

    Internal Corrosion 18 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    01/01/1995 01/01/2000 OnLine UT/01

    11 July 2011 Page 75 of 176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    76/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-319B Pipework from: PL-319B-1

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    2-AM-03381-A2; 12-AM-03319-A2

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: PL-309

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    4 Shear Wave

    UT

    60Scan 50% of potential locations defined in

    the corrosion study.

    01/01/1995 31/12/1999 Online

    External

    Deterioration

    4 VI-EXT 30100% Coverage 20/02/2009 21/08/2011 OnLine DVI/01

    Internal Corrosion 14 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    09/05/2008 08/05/2013 OnLine UT/01

    11 July 2011 Page 76 of 176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    77/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-319B-1 Pipework from: E-0304B

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    8-AM-03292-D0; 8-AM-03293-D0; 8-AM-03294-D0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: PL-319B

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    18 VI-EXT 60100% Coverage 20/02/2009 20/02/2014 OnLine DVI/01

    Internal Corrosion 18 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category.

    01/01/1995 01/01/2000 OnLine UT/01

    11 July 2011 Page 77 of 176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    78/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

    Equiment ID: PL-320 Pipework from: D-0302

    Const Code : ASME B31.3 Insulated (Y/N): NExam Spec:

    2-HW-03014-A2; 2-HC-03631-C2; 2-HW-03015-A2; 2-HW-03657-HA2

    Nace:

    Inspection plan

    Line list:

    Material: SA-53 B

    Pipework to: PL-306A

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    11 VI-EXT 60100% Coverage 19/10/2009 18/10/2014 OnLine DVI/01

    Internal Corrosion 11 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    05/09/2008 04/09/2013 OnLine UT/01

    11 July 2011 Page 78 of 176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    79/176

    SC O O ( S C C O )

    Equiment ID: PL-321A Pipework from: T-0302A

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    24-AG-03046-D0; 16-AG-03160-D0; 16-AG-03159-D0; 16-AG-03161-D0; 24-AG-03769-D0; 14-V-03767-ND0; 12-V-03818-ND0; 10-V-03819-NDO; 12-V-03768-NDO; 10-V-03213-D0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: E-0303A

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    External

    Deterioration

    8 VI-EXT 60100% Coverage 02/03/2009 01/03/2014 OnLine DVI/01

    External Stress

    Corrosion Cracking

    14 Remove ins

    and dye pen

    60External Stress Corrosion Cracking expected

    on Circuit - consult with Materials Engineer.

    01/01/1995 31/12/1999 Shutdown DP/01

    Internal Corrosion 14 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 31/12/1999 OnLine UT/01

    11 July 2011 Page 79 of 176

  • 7/28/2019 Piping Exam Spec

    80/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    81/176

    ( )

    Equiment ID: PL-321B Pipework from: T-0302B

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    10-V-03413-DO; 10-V-03821-NDO; 12-V-03776-NDO; 12-V-03820-ND0; 14-V-03775-ND0; 16-AG-03359-D0; 16-AG-03360-D0; 16-AG-03361-D0; 20-AG-03247-D0; 24-AG-03246-D0; 24-AG-

    03777-ND0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: E-0303B

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    4 Remove ins

    and dye pen

    60Chloride Stress Corrosion Cracking expected

    on Circuit - consult with Materials Engineer.

    01/01/1995 31/12/1999 Shutdown DP/01

    External

    Deterioration

    4 VI-EXT 30100% Coverage 01/01/1995 01/07/1997 OnLine DVI/01

    Internal Corrosion 22 UT 120Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 5% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 29/12/2004 OnLine UT/01

    11 July 2011 Page 81 of 176

  • 7/28/2019 Piping Exam Spec

    82/176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    83/176

    Equiment ID: PL-324A Pipework from: T-0302A

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    20-AM-03052-D0; 20-AM-03773-ND0; 4-AM-031772-ND0; 16-AM-03053-D0; 16-AM-03054-D0; 16-AM-03618-HD0; 16-AM-03055-D0; 1-V-03228-D0; 1-V-03229-D0; 1-V-03230-D0; 1-V-

    03621-HD0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: AM-03056

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    4 Remove ins

    and dye pen

    60Chloride Stress Corrosion Cracking expected

    on Circuit - consult with Materials Engineer.

    01/01/1995 31/12/1999 Shutdown DP/01

    External

    Deterioration

    4 VI-EXT 30100% Coverage 01/01/1995 01/07/1997 OnLine DVI/01

    Internal Corrosion 4 UT 0Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 50% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 01/01/1995 OnLine UT/01

    11 July 2011 Page 83 of 176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    84/176

    Equiment ID: PL-324B Pipework from: P-0301D/E/F/H

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    16-AM-03253-D0; 16-AM-03254-D0; 16-AM-03255-D0; 16-AM-03622-HD0; 1-V-03428-D0; 1-V-03429-D0; 1-V-03430-D0; 1-V-03627-HD0; 20-AM-03252-D0; 20-AM-03781-ND0; 4-AM-

    033780-ND0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: T-0302B

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    4 Remove ins

    and dye pen

    60Chloride Stress Corrosion Cracking expected

    on Circuit - consult with Materials Engineer.

    01/01/1995 31/12/1999 Shutdown DP/01

    External

    Deterioration

    4 VI-EXT 30100% Coverage 01/01/1995 01/07/1997 OnLine DVI/01

    Internal Corrosion 8 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 25% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 31/12/1999 OnLine UT/01

    11 July 2011 Page 84 of 176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    85/176

    Equiment ID: PL-330A Pipework from: H-0301A

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    24-AM-03108-D0; 3-V-03216-D0; 36-AM-03064-D0; 24-AM-03782-ND0; 10-AM-03790-ND0; 10-AM-03791-ND0; 36-AM-03771-ND0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: T-0302A

    Damage

    mechanisms

    Insp.

    Priorit

    Insp. Method Freq.

    months

    Extent of Inspection Last insp.

    date

    Next insp.

    Due date

    Availability Guideline Comments

    Environmental

    Cracking

    2 Remove ins

    and dye pen

    60Chloride Stress Corrosion Cracking expected

    on Circuit - consult with Materials Engineer.

    01/01/1995 31/12/1999 Shutdown DP/01

    External

    Deterioration

    2 VI-EXT 30100% Coverage 01/01/1995 01/07/1997 OnLine DVI/01

    Internal Corrosion 19 UT 60Random Corrosion - consult with Materials

    Engineer. As a minimum take the following

    UT's: 10% of Potential locations by Location

    Category. (Date In Service was used as last

    inspection date.)

    01/01/1995 31/12/1999 OnLine UT/01

    11 July 2011 Page 85 of 176

    WRITTEN SCHEME OF EXAMINATION (EXAM SPECIFICATION)

  • 7/28/2019 Piping Exam Spec

    86/176

    Equiment ID: PL-330B Pipework from: H-0301B

    Const Code : ASME B31.3 Insulated (Y/N): YExam Spec:

    10-AM-03792-ND0; 10-AM-03793-ND0; 24-AM-03308-D0; 24-AM-03784-ND0; 36-AM-03266-ND0; 36-AM-03779-ND0; 3-V-03416-D0

    Nace:

    Inspection plan

    Line list:

    Material: SA-312 TP304L

    Pipework to: T-0302B

    Dam