PIPE LAYING English7 Mar06

download PIPE LAYING English7 Mar06

of 78

description

Laying of pipelines

Transcript of PIPE LAYING English7 Mar06

  • 7/21/2019 PIPE LAYING English7 Mar06

    1/78

    1

    Pipe laying and service installation manual

    1.

    Introduction

    This manual is made for workers at a construction site.

    So this manual describes the procedure of pipe laying work at the site, points to note, etc.

    But description of this manual is general in Lao P.D.R and does not necessarily correspondto every region.

    Therefore please arrange this manual according to local regulation or local manner, and

    make use of this manual.

    2.

    Flow chart of pipe laying

    The site workers must construct based on design specifications.

    This chapter describes a general flow of construction.

    The site workers must confirm the flow chart and every part of work in all processes and do

    pipe -laying suitably.

    This manual does not describe the work of engineer section. If you learn it, refer to text-book for pipe-laying and service installation (after text book) chapter 1,5,6.

    The choice of a new route.

    The choice of pipe diameter.

    Site studies.

    Land survey.

    Design plan drawing.

    Estimation of construction costs.

    Beginning and end point of works.

    Commencement of work

    Pipe laying plan

    Preliminary survey

    Design

    Engineer

    Section

    Preparation forpipe materials

    Draw out theprocess table

    Preparation for

    materials and equipment

    of earthwork

    Occupancyapplication

    The site construction starting

    Technician

    Section

  • 7/21/2019 PIPE LAYING English7 Mar06

    2/78

    2

    3.

    Drawing out the process sheet

    The site worker must complete his work within the planned budget and construction period

    efficiently.

    Therefore the site worker draws out the process sheet to manage each process.

    The site worker checks the progress of process. If there is a delay, investigate the cause of

    the delay, reconsider the present schedule and try to improve.

    This chapter describes general process table in Lao P.D.R, and explains the contents.

    If you learn it more in detail, refer to textbook chapter 9.

    Measurement

    (Offset of pipeline, pipe laying

    length, earth cover and crossing

    position)

    Earthwork - 1

    Water suspension Measurement (width

    and depth of excavation)

    Pipeline work

    Water filling, water pressure test

    Technician

    Section

    Earthwork - 2

    Water drainage

    Completion of construction

    Measurement (Thickness of

    pavement, Thickness of upperand lower of road bed)

    Completion pipeline drawingEngineer

    Section

    Sand bedding

    Pipe cutting, rubber ring

    attachment, jointing,

    installed valve, etc.

    Sand covering

  • 7/21/2019 PIPE LAYING English7 Mar06

    3/78

    3

    Table-1. Bar Chart process sheet (Sample)

    Contents.

    ! The name of the construction work

    ! The planned construction period

    ! Address of the construction site

    1. Preparation work2. Excavation and back-filling

    3. Pipeline work

    4. Installation of pipe equipment

    5. Connect to existing pipe

    6. Service installation replacement

    7. Road recovery

    8. Clean up and drawing

    9. Completion

    Bar chart construction schedule

    Kind ofequipment

    8

    9

    Air valve 1.0 place

    hydrant 1.0 place

    Installation of pipe

    equipment

    Gate valve(150) 2.0 place

    Plan Actual

    The

    name of theconstruction work

    Theplaned constructionperiod

    Address of theconstruction site

    Type of process

    Item

    1

    Quantity Unit

    m2

    pavement

    Clean up anddrawing

    1.0 set

    Completion

    2

    3

    4

    5

    6

    7 Road recovery Cutting pavement 210.0

    Compaction ofroad bed

    150.0

    m

    Service installationreplacement

    2025 20.0 place

    Connect to existingpipe

    2.0 place

    Pipeline-work K 150 100.0 m

    Excavation andback-filling

    1.0 set

    Remark

    Preparation work 1.0 set

    month

    0 10 20 0 10 20 0 10 20 0 10 20

    August

    0 10 20 0 10 20

    September October November December

    1

    2

    3

  • 7/21/2019 PIPE LAYING English7 Mar06

    4/78

    4

    4.

    Preparation for pipe materials, equipment and worker of earthwork

    The site worker must prepare pipe materials, equipment and worker of earthwork based on

    design plan drawing.

    The site worker orders materials which are hard to be procured in no time, not so as to

    affect progress.

    In general, followings are materials and equipments which earthwork and pipeline workrequire:

    1. Equipments of earthwork truck, backhoe, pick, shovel, pump, etc

    2. Materials of earthwork backfill soil, earth stoppers, etc

    3. Safety equipment safety fence, lighting, construction warning

    sign, safety vest, etc4. Pipe materials pipe, valve, bend, socket, bolt, nut, lubricant,

    glue, etc

    5. Piping tool pipe wrench, monkey wrench, water pliers, joint

    tool, cutting tool, etc

    6. Other broom, clean cloths, etc

    Truck

    Cutter Tamping Machine

    Backhoe

    Equipments of earthwork

  • 7/21/2019 PIPE LAYING English7 Mar06

    5/78

    5

    Dewater pump

    Generator

    Soil

    Asphalt Earth stopper

    Safety equipment

    Shovel

  • 7/21/2019 PIPE LAYING English7 Mar06

    6/78

    6

    PVC pipe PVC fitting

    Steel pipe

    Steel pipefitting

    Valve

    DIP

    Pipe materials

  • 7/21/2019 PIPE LAYING English7 Mar06

    7/78

    7

    Meter Box

    Water! meter

    Branch Saddle

    Corporation cock

    iping tool

    Pipe wrench

    Torque & Ratchet Wrench

    Pipe cutter (Big size) Thread machine

  • 7/21/2019 PIPE LAYING English7 Mar06

    8/78

    8

    5.

    Occupancy application

    The site worker must submit an occupancy application to road administrator.

    In certain cases, it takes a lot of time to get permission takes long time. So you had better to

    submit an application as soon as you can.

    This chapter describes a general occupancy application in Laos.

    Saw

    Grinder

    Pipe cutter (Steel pipe)

    Engine Cutter

    Drill

    (For branch)

  • 7/21/2019 PIPE LAYING English7 Mar06

    9/78

    9

    Table-2-1. Occupancy application (Sample

    in case of Vientiane)

  • 7/21/2019 PIPE LAYING English7 Mar06

    10/78

    10

    Table-2-2. Occupancy application (Sample

    in case of Vientiane)

    Submit document

    1.Application (NPPs application form)

    2.Process sheet or schedule.

  • 7/21/2019 PIPE LAYING English7 Mar06

    11/78

    11

    6.

    Safety control

    The construction starts after all necessary equipments, workers, and documents ofconstruction are prepared.

    First of all, securing safety of the site is very important during construction.

    This chapter describes a general drawing of safety equipment position on road and presents

    some safety equipments with photograph.

    If you learn it more in detail, refer to textbook chapter 8.Fig-1.Safety equipments position

    Safety fence

    Lighting

    Construction

    Site

    Warning signboard

    Safety fence or Safety corn Lighting

    Road

    Construction Machine

  • 7/21/2019 PIPE LAYING English7 Mar06

    12/78

    12

    Safety vest

    Safety corn

    Warning sign board

    7. Earthwork

    The site worker must excavate to lay pipe and backfill after securing safety of the site.

    This chapter describes a general procedure for earthwork with photographs.

    If you learn it more in detail, refer to textbook chapter 3, 4.

  • 7/21/2019 PIPE LAYING English7 Mar06

    13/78

    13

    Earthwork-1

    ! Cutting the pavement Cut the pavement with cutter or pick.

    ! Breaking the pavement Break the pavement with backhoe or shovel.

    ! Excavation Excavate with backhoe or shovel.

  • 7/21/2019 PIPE LAYING English7 Mar06

    14/78

    14

    Notice: In case of the excavating the part of existing pipe or around

    underground facilities, use backhoe up to 50cm above the existing pipes.

    The thickness of 50cm above the existing pipe, use a hand- excavation to prevent

    existing pipes from being damaged

    (b) Since uneven surface on excavation bed gives concentrated load to the laid pipes,

    flatten the bed surface as much as possible.

    (Concentrated load to the laid pipes will be cause of water leakage.)

    (c) Pipe installation height must be properly controlled.

    ( If pipe installation height is not properly controlled, it often leads to air pockets)

    (d)Earth stopper should be used depending on the soil condition of the site.

    ( Refer to textbook chapter 3 2.1)

    ! Dewatering

    Drain water with pump or bucket.

    (It is desirable for using pump.)

  • 7/21/2019 PIPE LAYING English7 Mar06

    15/78

    15

    ! Measurement of excavation

    At the completion of excavation, check the top width, depth and bottom width of its cross

    section.

    Fig-2 Excavation Example for in case of bad

    cross-section

    soil/granite soil

    Take two measurements between

    measuring points.

    (One measuring point 50m, generally)

    Refer to textbook chapter 1 1.2.2 or

    chapter 3 1.2(5).

    Drawing of Excavation cross-section

    B1

    B2

    H

    B1: Top width

    B2: Bottom width

    H :Depth

    Sand bedding

    (10 20cm)

    Pipe

    Sand covering

    ( 20 30cm)

    House sideRoadside

    Distribution

    Pipe

    B1

    B2 Sand bedding

    B3

    Service pipe

    B1

    B2 Sand bedding

    B3

    H1 H2

    H3

    Roadside House side

    Water meter

    Ground Line

    Drain

  • 7/21/2019 PIPE LAYING English7 Mar06

    16/78

    16

    Size of excavation(On H1, H2, H3, B1, B2and B3, See figures shown above.)

    Nominal

    Size (mm)

    H1

    (m)

    H2

    (m)

    H3

    (m)

    B1

    (m)

    B2

    (m)

    B3

    (m)Remark

    Service

    Installation

    13

    Min.

    1.0

    Min.

    0.4

    0.2

    0.3 2025

    30 0.3 0.5

    0.1 0.140

    Distr

    ibutionPipe

    50

    Min.

    1.2

    0.5

    0.60.1 0.1

    75

    100

    150

    2001.2

    1.5

    0.6

    0.8 0.2 0.2250300

    350 1.5 2.0

    0.9

    1.00.3 0.3

    400

    Earthwork-2

    ! Backfilling

    (a) Backfilling-1

    Backfilling of soil with backhoe or shovel.

    (b) Compaction

    Up to pipe top+ 30cm, the backfill should be tamped manually to avoid

    damaging the pipes since mechanical tamping may be harmful.

  • 7/21/2019 PIPE LAYING English7 Mar06

    17/78

    17

    (c) Backfilling-2

    Backfilling of soil with backhoe or shovel.

    Repetition

    (d)Compaction

    Over pipe top+30cm, apply mechanical tamping using a tamper, etc.

    ! Completion of backfill

    ! Road surface recovery

    After natural compaction term (usually 30 days), backfilled surface should be restored

    by wearing coat pavement. As for structure restoration, it should be based on discussion

    with road administrator.

  • 7/21/2019 PIPE LAYING English7 Mar06

    18/78

    18

    Reference :In case of Japanese standard

    After completion of backfill, backfilled surface should be restored temporarily, as following.

    (a)Backfilling of crushed stones (for lower of roadbed)

    Thickness and structure depends on road administrator.

    (b) Compaction

    Compact with mechanical tamping.

    (c) Backfilling of mechanically stabilized crushed stones Thickness and structure depends

    on road administrator.

  • 7/21/2019 PIPE LAYING English7 Mar06

    19/78

    19

    (d)Compaction

    Compact with mechanical tamping.

    8. Pipeline works

    After earthwork-1 finished, the site workers carry out pipeline works.This chapter describes notice of installation of pipe, types of joints, joint connection method

    (PVC, Ductile cast iron pipe) and notice of water filling and follow.

    If you learn it more in detail, refer to textbook chapter 10,11,12.

    ! Handling and storage of pipes and valves.

    (a) Handle pipes and valves with care and avoid giving impact to them, and be careful

    not to damage the coating and lining on pipes.

    (b)Always keep a good condition of the work, and place fences to prevent outsider

    entering storage site.

    (c) If storage site is outdoors, cover pipes and valves with sheet (plastic sheet etc) and

    end of pipe with cap to prevent a foreign matter from entering inside of t pipes.

    (d)Place sleepers or balance log under the pipes.(e)Always apply drags at both ends while stacking.

    (f) While transporting, do not roll or drag pipes.

    (g)At the time of hanging up or down pipes, apply 2 point hanging. Pay attention to the

    center of gravity and use cushion materials so that housing tools do not touch the

    lining parts directly.

    Drag

    Apply sleepers 1meter apart

  • 7/21/2019 PIPE LAYING English7 Mar06

    20/78

    20

    Example

    (h)Rubber parts deteriorate when pipes are exposed to ultraviolet lay, heat, etc. in the

    air. Therefore store them indoors with packing.

    (i) Make sure rubber rings not to touch any oil or solvent while storing or handling.

    (j) Do not place bolts/nuts directly on the ground after opening the package.

    ! Notice of pipe installation

    (a) Confirmation of pipe laying position (earth cover, crossing position) in the design

    drawing.

    (b) Confirmation if the pipes do not have scars, cracks and other faults.

    (c) In case of hanging down the pipe, if earth stoppers such as wooden piles are put out

    temporarily, after reinforcing and confirming safety, hang down the pipe carefully.

    (d)Since uneven surface on excavation bed gives concentrated load to the laid pipes to

    damage them, flatten the bed surface as much as possible.

    If necessary, bed the sand or sleeper.

    (e)After cleaning the inside of pipe, install the pipe accurately based on design drawing

    using spirit level.(f) While installing the pipe, bed the good quality sand on side and bottom of the pipe

    and tamp to prevent the pipe from moving.

    (g) When installation of pipe is suspended by sunset, cover the end of pipe with the

    wooden cap to prevent soil or spring water from entering inside of the pipes.

    (h)Using straight pipes for bend part leads to reduction of room for joints to expand or

    contract. Therefore such installation style should be avoided.

    (i) The sequence of pipe installation is from the lower to the higher point and direction

    of faucet is height.

    (j) Confirmation of safety. (Especially, if the inside of excavation is safety or not.)

    Cushion material

    Tight the wire rope always

    through the eyeLess than 60

  • 7/21/2019 PIPE LAYING English7 Mar06

    21/78

    21

    ! Characteristics of each pipe material

    (a) Ductile cast iron pipe

    Merits Demerits

    Strong and durable Comparatively heavy

    Tough and impact resistant Anti-escapement measures are necessary at

    fittings

    Because of flexible joints, the pipe will

    follow the ground movements in an

    earthquakes

    Damage to the internal or external

    anti-corrosion surfaces may lead to

    corrosion

    A variety of linings is available

    (b) Steel pipe (Features as distribution pipe)

    Merits Demerits

    Strong and durable Installation of welded joints requires skilled

    workers and special tools

    Tough and impact resistant Measures are required to protect against

    electric corrosion

    The pipes can be one fixed line by

    welded joints so that they will follow the

    ground movements in an earthquakes

    Damage to the internal or external

    anticorrosion surfaces may lead to corrosion

    A variety of linings is available

    (c) Galvanized steel pipe (Features as service pipe)

    Merits Demerits

    Strong, resistant to external injury Natural of easily rusting

    lower cost Drastic dropping of strength caused by

    rusting

    (d) Polyvinyl chloride pipe (PVC)

    Merits Demerits

    Featuresasdistributionpipe

    Highly corrosion-resistant Reduction of impact resistance at lower

    temperatures

    Light-weight and easy to install Susceptible to certain organic solvents,

    heat, and ultraviolet rays

    Easily connected Consideration should be given to the

    long-term strength, fatigue strength, and

    creep strength

    Internal surface roughness does not

    change

    Damage to the surface may reduce the

    strength

    Anti-escapement measures are necessary

    at fittings

    as Corrosion resistant, acid-resistant,

    alkalinity-resistant

    Weak in high temperatures, inadequate in

    temperatures over 60oC

  • 7/21/2019 PIPE LAYING English7 Mar06

    22/78

    22

    Merits Demerits

    Resistant to electric corrosion Weak against ultra-violet rays and

    freezing, and therefore, unsuitable for

    outdoor-exposed piping

    Inside smooth with no scale, no

    contamination

    Thermal expansion is more than metal

    pipes. Light and easy to both handle and

    construct

    Weak against organic solvents

    Inexpensive

    Easy to construct

    ! Types of joints

    This section describes a general joints used in Laos.If you learn it more in detail, refer to

    attachment material.

    (a) PVC pipe (Polyvinyl chloride pipe)

    (i)Flexible Type (RR type) RRRubber ring

    Fig-3 Cross section of Flexible Type (RR type)

    (ii) Fixed Type (TS type) TSTaper socket

    Fig-4 Cross section of Fixed Type (TS type)

    Rubber ringS i ot

    Marking of insertion depth

    Socket

    Spigot

    Marking of insertion depth

  • 7/21/2019 PIPE LAYING English7 Mar06

    23/78

    23

    (iii) Dresser type(Expansion joint)

    Fig-5 Cross section of

    dresser typeexpansion joint

    (b) Ductile cast iron pipe

    (i)Mechanical A-typeFig-6 Cross section of Mechanical A-type

    (ii)Mechanical K-type

    Fig-7 Cross section of Mechanical K-type

    Bolt/Nut

    Faucet

    SpigotRubber RingPush Ring

    Rubber Ring

    Bolt/Nut

    FaucetRubber Ring

    SpigotRubber RingPush Ring

    Bolt/NutFlan e

    S i otS i ot

    Rubber RinSleeve

    Rubber Rin

  • 7/21/2019 PIPE LAYING English7 Mar06

    24/78

    24

    (iii) T-type

    Fig-8 Cross section of T-type

    (c) Flange type of each material

    Fig-9 Cross section of Flange type

    Rubber Ring Spigot

    Faucet

    Rubber Ring

    Bolt/NutHub type

    RF type RF type RF type GF type

    RF type gasket

    Flange surface

    GF type gasket

  • 7/21/2019 PIPE LAYING English7 Mar06

    25/78

    25

    ! Joint connection method

    This section describes a general joints used in Laos.

    (a)PVC- Flexible Type (RR type)

    (i) Necessary tool as following

    saw clean clothfile or grinder

    meter stick

    brush marker

    lubricant

    (From maker specification)

    (ii)Mark the pipeMark the pipe where it is

    to be cut.

  • 7/21/2019 PIPE LAYING English7 Mar06

    26/78

    26

    (iii) Cutting pipeCut the pipe with a finely toothed saw along the marking.

    Removal extra of pipe edge.

    (iv) ChamferingChamfer with a file or grinder certainly.

    Chamfering drawing

    15 / 2

    2

  • 7/21/2019 PIPE LAYING English7 Mar06

    27/78

    27

    Table-3 t- size (Reference)

    (v)Cleaning

    Clean the outer parts of the pipe on the area which is going to be inserted and therubber ring groove.

    Nominal Size (mm) 55 65 80 100 150 200 250 300

    t(PVC 5)(mm) 1.8 0.2 2.2 0.2 2.5 0.2 3.2 0.25 4.6 0.3 5.4 0.35 6.6 0.4 7.8 0.45

  • 7/21/2019 PIPE LAYING English7 Mar06

    28/78

    28

    (vi) Rubber Ring AttachmentMount the rubber ring.

    Shape a rubber ring into heart, Mounting is easy.(As following drawing)

    (vii)Marking of insertion depth

    Rubber ring

    Notice: Dont mistake direction of rubber ring.

    Marking of insertion depth

    L

  • 7/21/2019 PIPE LAYING English7 Mar06

    29/78

    29

    Table-4 L- size (Reference)

    (viii)Spreading of lubricantApply the pipe lube.(Do not apply the pipe lube to the ring groove)

    Table-5 Lubricant consumption(

    Reference)

    Nominal Size (mm) 55 65 80 100 150 200 250 300

    L (mm) 75 95 110 135 155 170 195 220

    Nominal Size (mm) 55 65 80 100 150 200 250 300

    Lubricant consumption(g) 3 4 5 10 20 25 30 35

  • 7/21/2019 PIPE LAYING English7 Mar06

    30/78

    30

    (ix) Jointing

    Place the pipe to be jointed into one straight.

    Insert it to marking of spigot with the lever, the puller or hand.

    Insert with the lever Insert with the puller

    (x)InspectionCheck with a check gauge to

    ensure that the rubber ring is

    located properly.

    Check gauge

    Wooden panel

  • 7/21/2019 PIPE LAYING English7 Mar06

    31/78

    31

    (b) PVC- Flexible Type (TS type)

    (i) Necessary tool as followingsaw clean cloth file or grinder brush marker

    solvent cement(maker specification)

    puller or lever(if necessary)

    (ii) Cutting pipe and ChamferingChamfer the angle, burr or ridge (flare) caused by cutting with file.

  • 7/21/2019 PIPE LAYING English7 Mar06

    32/78

    32

    (iii)Marking of insertion depthMake alignment mark for connection.

    (iv) CleaningRemove any moisture or oil sticking to the pipe surface where the cement is to be

    applied with clean cloth.

    (v)Spreading of solvent cementApply the solvent cement to the socket interior and the pipe end surface slightly all

    over and uniformly.

  • 7/21/2019 PIPE LAYING English7 Mar06

    33/78

    33

    (vi)Jointing

    Immediately insert the pipe into the socket until it bottoms at alignment mark.

    Turn the pipe or filling 1/4 turn during connection (but not after the pipe is bottom )

    to distribute the cement evenly.Leave the connected pipe to stand alone for approximately 15 seconds.

  • 7/21/2019 PIPE LAYING English7 Mar06

    34/78

    34

    (vii) Completion

    Wipe the remaining cement off with a cloth, then let the solvent harden for 5 minutes

    before put into use.

    (c) Dresser typeexpansion joint

    (i) Necessary tool as followingmarker ratchet wrenchclean cloths

    (ii) Cleaning and set the flange,

    rubber ringRemove any moisture or oil

    sticking to the pipe surfacewith clean cloth.

    Set the flanges and rubbers

    ring on spigots straightly.

    (Make sure it Flange and rubber

    ring in the right direction.)

    (iii)Set the sleeve and marking of insertion depthSet the sleeve

    on one spigot.Make alignment mark

    for connection.

    L

    L /2

    Marking Sleeve

    Set straightly

    Set straightly

  • 7/21/2019 PIPE LAYING English7 Mar06

    35/78

    35

    Table-6 L- size (Reference)

    (iv) Jointing

    Insert the one spigot into the sleeve.

    (iv)Fitting the rubber ring and the flange

    Fit the rubber ring until Fit the Flange until sleeve.

    marking line.

    (v) Fitting the bolt/nut and tightening

    Be sure not to tighten

    one more than the others.

    Nominal Size (mm) 80 100 150 200 250 300

    L (mm) 70 80 90 100 100 100

    10mm

    SleeveMarking

    SleeveRubber ringSleeve

    Flange

  • 7/21/2019 PIPE LAYING English7 Mar06

    36/78

    36

    (d) Ductile cast iron pipe( A, K type)

    (i) Necessary tool as followingratchet wrench clean cloths

    torque wrench brush

    lubricant

    (maker specification)

    (ii) Pipe fitting

    Make sure the maker-mark is placed at the top.

    Dig a temporary hole at the bottom to make tightening of the bottom part easy.

    (iii)Pipe cleaning

    Wipe outside the spigot from the edge to white line.

  • 7/21/2019 PIPE LAYING English7 Mar06

    37/78

    37

    Wipe inside the faucet, especially the contact surface of rubber ring with cloth.

    Clean inside and outside surface of the push ring.

    (Sand, oil and other foreign matter should be removed)

    Set the push ring on the spigot.

    Make sure it faces in the right direction.

  • 7/21/2019 PIPE LAYING English7 Mar06

    38/78

    38

    (iv)Clean the rubber ring and place the rubber ring on the spigot.

    Wipe the rubber ring with cloth.

    Fit the rubber ring onto spigot.

    (use lubricant on the outside surface of the spigot to help fitting the rubber ring)

  • 7/21/2019 PIPE LAYING English7 Mar06

    39/78

    39

    Make sure the rubber ring faces in the The rubber ring should be placed about

    right direction. 20cm far from the end of the spigot.

    A-type

    K-type

    (v)Application of lubricant

    Apply a lubricant to surface of the spigot and the rubber ring.

    (A solution of 70% water and 30% soap can be used as the lubricant.Apply a lubricant to thoroughly between the edge of pipe and a white line.

    Never use a grease or petroleum oil.

    Apply a lubricant to the internal surface of the faucet

    Spigot

    and rubber ring

    20cm

    20cm

  • 7/21/2019 PIPE LAYING English7 Mar06

    40/78

    40

    Faucet

    (vi) Connecting faucet and spigot

    insert the spigot(faucet) to the faucet(spigot)

    For pipes with less than 600mm diameter, two lines marked on spigot. Adjust the first

    one to the edge of the faucet.

    (vii) Fitting the rubber ring

    Push the rubber ring by maintaining even clearance on both the spigot side and faucet side.

    Be careful not to damage the rubber.

  • 7/21/2019 PIPE LAYING English7 Mar06

    41/78

    41

    A-type

    K-type

    (viii) Setting the push ring

    Adjust the bolt holes of the pipe to the holes of push ring.

    Place a wedge between the push ring and spigot to ensure correct centering.

    (If necessary)

    Wedge

  • 7/21/2019 PIPE LAYING English7 Mar06

    42/78

    42

    (ix)Fitting the bolt/nut and tightening

    Be sure not to tighten one more than the others.

    Even Clearance

  • 7/21/2019 PIPE LAYING English7 Mar06

    43/78

    43

    (x) Check tightness of all bolts and nuts.

    Finally, use a torque wrench to tighten to the standard torque.

    Record the clearance between the faucet and the rubber ring, the condition of rubber ring,

    and tightening torque of the bolt to the check sheet.(Refer to K type joint check sheet)

    Fig-9 Final tightening and use of torque check

    Table-7Torque (kg-m)

    Nominal Diameter (mm) 80 100 600 700 800 900 2,600

    Nominal size of the bolt M16 M20 M24 M30

    Torque(kg-m) 6 10 14 20

  • 7/21/2019 PIPE LAYING English7 Mar06

    44/78

    44

    (xii) Allowable bending angle and allowable displacement

    4m 5m 6m

    75 500 8 35 100 500 10 35 150 500 15 44 200 500 19 44 250 400 19 35 300 320 19 35350 450 31 50400 410 31 43

    450 350

    31

    40500 320 31 35600 250 31 29700 230 32 26800 210 32 22900 200 32 211000 150 33 191100 140 33 171200 130 33 151350 120 33 141500 110 32 121600 130 43 10 13 1650 130 45 10 13 1800 130 48 10 13 2000 130 53 10 13 2100 130 55 10 13 2200 130 58 10 13 2400 130 63 10 2600 130 70 10

    Allowable bending angle

    Nominaldiameter(mm)

    Allowablebending angle

    ()

    Difference (X)

    betweenmeasure of A1

    and A2

    Allowable displacement per one

    pipe(cm)

    (A-type and K-type)

    Allowable

    bending

    angle()

    Using straight pipes for bent parts lead to

    reduction of room for joints to expand or

    contract and thereore, such installation

    style should be avoid. Istead, it is desiable to

    use bent-pipes for bent parts of a pipeline.

    If there is no other choice than connecting

    straight pipes for bent-parts, do so within

    the rage of allowable angles and use more

    than one joint to attain desired piping

    results.

    Place a pipe straightly

    Tighten the bolts to certain tightness

    Bend within allowable bending angle

    Tighten to reach the standard torque.

    A1

    X=A1A2A2Xmm

  • 7/21/2019 PIPE LAYING English7 Mar06

    45/78

    45

    Check sheet for type K joints

    All joints must satisfy following conditions or disassemble and joint again.

    i. The torque is within -20Nm and +30Nm of the specified torque.

    ii. Condition of rubber gasket is good.iii. The difference between max. and min. of the gland-socket clearance a at each joint is within

    3 mm.

    (e) Ductile cast iron pipe(T type)

    (i) Necessary tool as followingclean clothsbrush lubricant(maker specification)

    puller lever(if necessary)

    kg/m

  • 7/21/2019 PIPE LAYING English7 Mar06

    46/78

    46

    (ii)Pipe fitting

    Make sure the maker-mark is placed at the top.

    (iii)Pipe cleaning and rubber ring

    Wipe outside the spigot from the edge to white line.

    Wipe inside the faucet, especially remove the foreign matter such as sand, mud, gravel, dirt

    and paint flakes from the groove using a driver, etc.

    (If there is foreign matter left, water leakage may occur. )

    Clean the spigot

  • 7/21/2019 PIPE LAYING English7 Mar06

    47/78

    47

    Clean the faucet

    Clean the groove

    Clean

    the rubber ring

  • 7/21/2019 PIPE LAYING English7 Mar06

    48/78

    48

    (iv)Fitting the rubber ring

    Insert the rubber ring into the faucet.

    Form a heart-shape with the rubber ring.

    Make sure the rubber ring is correctly

    seated in the faucet.

    FaucetRubber ring

    Rubber ring

    Faucet

  • 7/21/2019 PIPE LAYING English7 Mar06

    49/78

    49

    Confirm the condition of the rubber ring.

    (v)Application of lubricant

    Apply lubricant to the internal surface of the rubber ring, and the outside surface of the

    spigot end

  • 7/21/2019 PIPE LAYING English7 Mar06

    50/78

    50

    (vi)Connection

    Place the spigot in the faucet.

    Make sure the two pipes forms a straight line.

    Lubricant LubricantWhite line

  • 7/21/2019 PIPE LAYING English7 Mar06

    51/78

    51

    The other line should be visible outside

    This white line should be in the faucet

  • 7/21/2019 PIPE LAYING English7 Mar06

    52/78

    52

    Insert with the lever Insert with the Puller

    (vii) Inspection

    Confirm the proper position of the rubber ring all around the socket by inserting a

    check gauge into the gap between the spigot and faucet.

    Record the clearance between the faucet face and the rubber ring, the clearance between

    the faucet face and white line to the check sheet. .(Refer to T type joint check sheet)Check gauge

    Wooden panel

  • 7/21/2019 PIPE LAYING English7 Mar06

    53/78

    53

    (viii)Allowable bending angle and allowable displacement

    4m 5m 6m

    75 500 8 35 100 500 10 35 150 500 15 44 200 500 19 44 250 500 22 44 300 400 21 42350 400 24 42

    400 330 24 37450 300 24 31500 300 26 31600 300 31 31700 230 31 26800 230 35 26900 230 39 261000 200 35 211100 200 38 211200 200 42 211350 200 47 21

    1500 200 52 211600 200 56 14 18 1650 200 58 14 18 1800 200 63 14 18 2000 200 70 14 18

    Allowable bending angle

    Nominaldiameter(mm)

    Allowablebending angle

    ()

    Difference (X)between

    measure of A1

    and A2

    Allowable displacement per onepipe(cm)

    (T-type)

    It is desiable to use bent-pipes for angle-

    pipeing in case of T-type pipes also.

    Apply angled-piping only when there is no

    other choice and within the allowable angles.

    Further, use more than one pipe to divide

    the pipeline into segment which form a

    desired bending shape eventually.Place a pipe straightly

    Bend within allowable bending angle

    Allowable

    bending angle()

    X=A1A2A2

    XmmA1

  • 7/21/2019 PIPE LAYING English7 Mar06

    54/78

    54

    Check sheet

    T-type joint Check sheet

    DateWork Name

    Project

    Joint work process executedby

    ( )

    Chiefof

    pipin

    gwork

    Instructor

    Personin

    chargePiping system Drw. No.

    Measuring point No.

    Nominal diameter,Type of the pipe

    Pipe No. and shapeSchematic drawing

    Joint No.

    CleaningLubricant

    Check at the groove of socket

    The clearance betweenSocket face and rubber

    gasket

    1

    2345

    678

    The clearance between

    Socket face and white line

    1

    23

    45

    678

    Judgment

    *! On each joint, if one of the measuring points is 9mm or larger than other 7 points, the rubbergasket may be twisted. Disassemble immediately for re-assembling.

    (Note)If the nominal diameter is less

    than 300mm, four positions1,3,5,7 should be measured.

    Thickness gaugeSocket groove

    Rubber gasket

    Arrow view

    White lines

    Measuringpositions

  • 7/21/2019 PIPE LAYING English7 Mar06

    55/78

    55

    (f) Flange type (RF type)

    (i) CleaningClean the flange surfaces, bolts, nuts, and gasket to remove foreign matter that may be

    sticking.

    (ii) Installation of the gasket

    Accurately center the gasket relative to the pipe. Temporarily secure it with a thin strip ofadhesive tape (or adhesive) to prevent movement.

    (iii)Contact the flanges surface

    Install several bolts at equally distances around the periphery.

    Contact the flanges surface.

    (iv)Temporary tightening

    Tighten the bolts installed until temporary tightening while taking care not to dislocate

    the gasket and bolt holes.

    Order for temporary tightening

    Gasket

  • 7/21/2019 PIPE LAYING English7 Mar06

    56/78

    56

    (v) Final tightening

    Install the remaining bolts and tighten them all. Order for final tightening

    Until nearing the specified torque,

    tighten a bolt and then retighten

    the previous bolt all the way

    around the periphery so that the

    gasket will be evenly compressed.

    Table 8

    Torque

    (For reference)

    (vi) Checking the tightened joint

    Visually check that the flanges are properly and parallel mated to each other and the

    gasket is not dislocated.

    (g) Flange type (GF type :Flanges on both pipes touch)

    (i) Cleaning

    Clean the flange surfaces, gasket groove, gasket, bolts, and nuts to remove all foreign

    matter.

    (ii) Installation of the gasket

    Set the GF gasket in the gasket groove. Adhesive is not needed at this time. If the

    gasket comes out of the groove, apply cyanoacrylate adhesive at four to six equally distant

    points depending on the pipe diameter.

    Application of adhesive

    Bolt sizeTighten

    torque(kg-m)

    Applicable pipe

    diameter(mm)

    M16 60 75 200M20 90 250300

    M22 120 350400

    M24 180 450 600

    M30 330 700 1200

    Notes:

    1. Do not use the following adhesives as

    they may adversely affect the gasket.

    Acetic acid plastic adhesives

    Synthetic rubber adhesives.2. When an adhesive is used, check that

    the gasket is firmly attached.AdhesiveAdhesive

    View from the above

  • 7/21/2019 PIPE LAYING English7 Mar06

    57/78

    57

    Set the gasket in the groove so that the outer diameter of the gasket is in contact with

    outer diameter of the groove.

    Install in sequence at points 1, 2, and 3.

    (iii)Contact the flanges

    Install several bolts around

    the periphery. Contact the GFand RF flanges straight to

    each other with care not to

    twist the gasket.

    (iv)Temporary tightening

    Order for temporary tightening

    Tighten the bolts installed until

    temporary tightening while taking

    care not to dislocate the gasket

    and bolt holes.

    View from the above

    View from the above

    Straight forward.

  • 7/21/2019 PIPE LAYING English7 Mar06

    58/78

    58

    (v) Final tightening

    Install the remaining bolts and Order for final tightening

    tighten them all. When nearing the specified

    torque, tighten a bolt and then retighten

    the previous bolt all the way

    around the periphery so that

    the gasket will be evenly compressed.

    Refer to Table 8 for torque.

    (vi)Checking the tightened joint

    Insert a clearance gauge between the flange surfaces from the outside at four equal distant

    points around the periphery. It should not be possible to insert a 0.9 mm thick gauge

    between the flange surfaces.

    ! Notice of water filling and follow.

    (a) Place a temporary saddle corporation cock on the pipe.

    (b) When water fill pipe, open the valve slowly with hearing water flowing sound.

    (c)Vent the air in the pipe from a temporary saddle corporation cock.

    (d) Check the water leakage from pipe joint and valve.(e) Drain water and check the water cloud from a temporary saddle corporation cock.

    (f) Check the residual chlorine from a temporary saddle corporation cock.

    Correct location of gasket

  • 7/21/2019 PIPE LAYING English7 Mar06

    59/78

    59

  • 7/21/2019 PIPE LAYING English7 Mar06

    60/78

    60

    9.

    Service installation

    Service equipment refers to service pipes installed by branching from the distribution pipe

    installed by water supplier and auxiliary devices are directly connected to such service pipes.

    For general household use, small caliber service pipes ranging from 13mm to 25mm in

    diameter are used. For factories and larger building, there are service pipes from 30mm to75mm diameter.

    Service devices directly connected to service pipes means such devices are connected to

    service pipes in such a manner that they are not easily removed.

    They are such devices as saddle corporation cocks, curb cocks, water meters, service cock, etc.

    This chapter describes general flow chart of service pipe installation,general branching

    method and notice of service pipe installation.

    If you learn it more in detail, refer to textbook chapter 13.

    ! Flow chart of service pipe installation

    Water use

    The number of people using water

    The number of outlet

    Calculate the total head loss including

    the height of the supply equipment

    Comparison with the pressure head

    provided as the design minimum dynamic

    water pressure at the water distributiontakeoff pipe

    Selection of Water meter size

    Equipments of earthwork

    Materials of earthwork

    Safety equipment

    Pipe materials

    Piping tool

    Earthwork - 1

    Service pipe installation

    Water meter installation

    Design EngineerSection

    Pre aration

    Technician

    Section

    Calculation of designwater consum tion

  • 7/21/2019 PIPE LAYING English7 Mar06

    61/78

    61

    ! Safety control

    Refer to chapter 6.

    ! Earth works

    Refer to chapter 7.

    ! General service pipe installation

    Show an example of standard service equipment used for normal households.

    Fig-10 General service pipe

    installation

    Technician

    SectionEarthwork - 2

    Completion of installation

    Branch saddle

    Corporation cock

    Stop Valve (Bronze)

    Distribution

    Elbow 90Nipple

    Union

    Valve Fitting

    Meter Box

    Service Tap

    Pipe

    (GSP)

    Meter

    Interval of more than 30cm

    Pipe (GSP)

    Stop Valve (Bronze)

    Pipe (GSP)

    Pipe (GSP)

    42cm

    50cm

    Pipe

    (GSP)

    26cm16.5cm

    40cm

    GSP=Galvanize steel pipe

    for water supply is blue

    mark because it is the

    medium qualified

  • 7/21/2019 PIPE LAYING English7 Mar06

    62/78

    62

    ! Joint connection method

    This section describes general joints used in Laos! (steel pipe and PVC).

    (a) PVC (RR-type, TS-type)

    Refer to chapter 8 (a), (b)

    (b) Steel pipe (GSP)

    (i) Cutting pipe

    With cutting machine or pipe cutter.

  • 7/21/2019 PIPE LAYING English7 Mar06

    63/78

    63

    (ii)Making taper thread

    With thread machine or dies.(Using cutting oil, which dose not affect the water quality)

    Table-9 Number of thread (Reference)

    Diameter

    (mm)

    Number of thread

    (N)15 11.0

    20 12.0

    25 10.0

    32 11.0

    40 11.0

    50 13.0

    65 15.0

    N

  • 7/21/2019 PIPE LAYING English7 Mar06

    64/78

    64

    Example. Bad threads

    (iii)Treatment on the pipe end

    Deburr the pipe end using a file if necessary.

    (iv)Jointing

    tape a pipe with seal tape. screw a pipe into a fitting by hand

    flat

    Inflection thread One side thread

    Polygon thread

    Seal tape

    File

  • 7/21/2019 PIPE LAYING English7 Mar06

    65/78

    65

    Table-10 Insert Number of thread (Reference)

    screw a pipe into a fitting with pipe wrench.

    Diameter

    (mm)

    Number of thread

    Insert number(L) Remain

    number(M)

    Total

    number(N)screw a pipe

    with manual

    screw a pipe

    with wrench

    15 4.5 1.5 5.0 11.0

    20 5.5 1.5 5.0 12.0

    25 4.5 1.5 4.0 10.0

    32 5.5 1.5 4.0 11.0

    40 5.5 1.5 4.0 11.0

    50 7.0 2.0 4.0 13.0

    65 7.5 2.5 5.0 15.0

    N

    L M

  • 7/21/2019 PIPE LAYING English7 Mar06

    66/78

    66

    (v)Anti-corrosion treatment

    Apply an adequate amount of anti-corrosion agent or sealer to the outer threaded portion of

    the joint (4 5 threads from the inner).

    Repair the outer surface of the pipe using anti-corrosion sealer.

    ! General branching method

    (a) Instrument

    Branch saddle Corporation cocks

    Tools

    Apply an adequate amount of

    anti-corrosion agent or sealer.

    Repair the outer surface of the

    pipe using anti-corrosion sealer.

    scar

    4 5 threads

  • 7/21/2019 PIPE LAYING English7 Mar06

    67/78

    67

    (b) Cleaning

    (c) Mounting the saddle

  • 7/21/2019 PIPE LAYING English7 Mar06

    68/78

    68

    (d) Mounting the corporation cocks to saddle

    (e) Setting the drill

  • 7/21/2019 PIPE LAYING English7 Mar06

    69/78

    69

    (f) Drilling

    ! Connecting pipes of Steel pipe and PVC pipe! (For example)

    ! Meter installationHandle meter with care and avoid giving impact to it

    Prevent a foreign matter from entering inside of meter.

    Check the meter position.

    Check the meter flow direction.

    Check the horizontal installation of meter.

  • 7/21/2019 PIPE LAYING English7 Mar06

    70/78

    70

    This section describes only about water meter installation. But there are various kinds of meter.

    If you learn it more in detail, refer toattachment material.

    ! Notice of service pipe installation.

    This section describes general notice of service pipe installation.

    If you learn it more in detail, refer toattachment material.

    (a)At the place where external forces cause strain in the ground surrounding service pipes or

    where the ground is not firm, the pipes should be flexible enough to absorb the stress and

    prevent damage that leads to water leakage.

    (b)To maintain water quality, the service pipe can not be connected to a pipe or

    equipment that may cause a reverse flow of contaminated water.Example of prohibited piping

    (b) Distributing pipe end connector shall be located more than 30 cm away from the end

    connector of other service installation.

    (c) The end connector diameter of water supplying pipe to distributing pipe shall not be

    Do not connect.

    LiaisonValve

    Tap water

    Service pipe

    Well water or

    industrial water

    Do not connect.

    Cooling tower

    CoolerHeatgeneratingwater

    Service pipe

    Tap water

    Heatradiating

    water

    Liaison

    valve

    Ball tap

    Meter flow direction

  • 7/21/2019 PIPE LAYING English7 Mar06

    71/78

    71

    excessively large as compared to the water consumption rate of the relevant service

    installation.

    ! Determining for the service pipe size(a) Designed water usage

    For the direct connection water service system, the water usage should be determined from

    the instantaneous flow rate expected with the possibility of simultaneous usage of taps. In

    general, it is determined from the relationship between the total number of taps and those

    used simultaneously, (see Table 11 ) or between the number of taps and the usage ratio (see

    Table 12 ). The water delivery by tap-type and size, should be considered and reflected in

    the total water usage (see Table 13 ).

    Table 11 Number ofsimultaneously used taps Table 12 Usage ratios

    Totalnumber of

    taps

    Number ofsimultaneously used

    taps

    Total number oftaps

    1 2 3 4 5 6 7

    Usage ratio 1 1.4 1.7 2.0 2.2 2.4 2.6

    1 1Total number of

    taps

    8 9 10 15 20 30

    2 4 2 Usage ratio 2.8 2.9 3.0 3.5 4.0 5.45 10 311 15 416 20 521 - 30 6

    (b) Guideline for determining the pipe size

    The service pipe should be big enough to ensure the designed water usage at the minimum

    water pressure expected for the distribution pipe and it should also be cost-effective.

    The pipe size should be such that the sum of the height of the tap and the total head loss

    relative to the water usage does not exceed the head of the minimum dynamic water

    Table 13 Water usage by application and

    applicable tap sizes

    ApplicationWater

    usage

    Applicable

    tap sizeNote

    Sink for kitchen 12-40 13-20

    Sink for washing machine 12-40 13-20Wash basin 8-15 13

    Bathtub (Japanese) 20-40 13-20

    Bathtub (Western) 30-60 20-25

    Shower 8-15 13

    Urinal (flush tank) 12-20 13 Usage at onetime (4 to 6seconds):

    2 to 3 liters

    Urinal (flush valve) 15-30 13

    Water closet (flush tank) 12-20 13

    Water closet (flush valve) 70-130 25 Usage at onetime (8 to 12seconds):

    13.5 to 16.5

    liters

    Hand wash basin 5-10 13

    Fire hydrant (smaller one) 130-260 40-50

    Sprinkler 15-40 13-20

    Car wash tap 35-65 20-25For industrial

    use

  • 7/21/2019 PIPE LAYING English7 Mar06

    72/78

    72

    pressure for the distribution pipe. A larger size should be selected with respect to both the

    possible increase in future demand, and the minimum operating pressure for water heaters

    and other devices.

    Care should be taken to prevent an excessive water velocity in service pipes

    (c) Calculation of the total head loss

    (i) Weston's formulaThis formula is applied when pipe size is less than 50mm.

    And material of pipe is PVC, GSP, Stainless steel pipe, and Polyethylene pipe.

    h

    {0.0126

    (0.01739

    0.1087d )/

    v }

    l/d

    v

    2

    /2g

    Q=(

    d

    2

    /4)

    v=Q/A=Q/(d2/4)

    I

    (h/l)

    1000(0/00)

    h: Total head loss( m )

    l : Length of service pipe(m)

    g: Acceleration of free fall( 9.8m/s

    2

    )

    v: velocity in pipe( m/s )

    d: Diameter of pipe ( m )

    I : Hydraulic gradient(0/00)

    Refer to drawing of Weston's formula flow curve(P-48)

    (ii) Hazen-Williams' formula

    This formula is applied when pipe size is more than 75mm.

    v 0.35464CD

    0.63

    I

    0.54

    Q 0.27853CD

    2.63

    I

    0.54

    d 1.6258C

    0.38

    Q

    0.38

    I

    0.205

    (h/l)

    1000 = I

    {10.666

    C

    1.85

    D

    4.87

    Q

    1.85

    }

    1000

    h: Total head loss( m ) l: Length of service pipe(m)v: Velocity in pipe( m/s ) Q: Flow(m

    3

    /s)

    d: Diameter of pipe ( m ) I : Hydraulic gradient(0/00)

    C: Coefficient of Velocity(110)

    Refer to drawing of Hazen-Williams' formula flow curve.(P-49)

    (iii)Conversion of head loss of service device

    Head loss of Service devices, such as saddle corporation cock, water meter, stop valve,

    and service cock are converted into head loss of straight-line pipe.

    Head of designminimumhydrodynamicwater pressure (H)

    Lift head h

    Hydraulic gradient lineTotal head loss

    Surplus head

    h + h < H

  • 7/21/2019 PIPE LAYING English7 Mar06

    73/78

    73

    Refer to following table.

    Table 14Conversion of head loss of service device(Reference)

    Application

    Nominal Size

    Saddle corporation

    cock stop valvewater meter service cock

    13mm 1.5m 4.0m 3.0m

    20mm 2.0m 11.0m 8.0m

    25mm 3.0m 15.0m 8.0m

    40mm 6.0m 26.0m

    50mm 8.0m 35.0m

    (iv)Calculation of the total head loss {(l

    l

    )I} h H

    H : Head of design minimum hydrodynamic

    water pressure (m)

    h : Lift head ( m )

    l

    :

    Length of service pipe(m)

    l

    :

    Head loss of service device(Conversion )(m)

    I : Hydraulic gradient(0/00)

    (v) Example for Calculation

    Case-1

    Nominal Size 20, Pipe length=15m, Flow=0.6/sec, Total head loss(h) =

    h = lI=15(240/1000)=3.6m

    l=15m

    I=240/1000(Get I at drawing of Weston's formula flow curve.)

    Case-2

    Nominal Size 13, Pipe length=35m,

    Distribution pipe pressure=1.0kg/cm2=10m

    Lift head (m)=3.0

    Flow (Q) = /sec

    h = 10.0 3.0 7.0

    I h/l = 7.0 / 35.0 = 200 / 1000

    Get flow at drawing of Weston's formula flow curve

    Q = 0.18/sec

    3.0m

    35.0m

    Distribution pipe

    pressure:1.0kg/cm2

    Distribution pipe

  • 7/21/2019 PIPE LAYING English7 Mar06

    74/78

    74

    How to get I or flow at drawing of Weston s formula flow curve

    Case-1

    Case-2

    (vi)Number of branch for service pipe

    If a service pipe is branched into many service pipes (as following drawing), allowance

    number of branch should be limited to certain numbers according to pressure, diameter

    and so on.

    Refer to the table of number of branch for service pipe (For reference, P-)

    10.

    Postscript

    Description of this manual is for general use in Lao P.D.R.

    Proper construction work is very important to lead to reduce future water leakage accidents.

    On pipe-laying, you should carry out the construction work according to this manual.

    Description of pipe materials is also for ordinary use in Lao also. But in the future, when water

    supply technology progresses in Lao, high quality and high performance materials will be

    required.And as living standard and life-style change in Lao, water use and form will change also.

    This manual is not satisfactory for receiving these changes.

    Therefore please revise this manual timely by yourselves.

    And if you have some questions in this manual or you would like to know other water

    supply equipments that are not included in this manual, please ask WASA (Water Supply

    Authority) or NPNL (Nampapa Nakkhone Luang) .

    0.6

    Flow(/sec)

    I: Hydraulic gradient(0/00)

    240

    20 0.18

    Flow(/sec)

    I : H draulic radient(0/00)

    200

    13

    service pipe 20

    Distribution pipe

    100

    Main service pipe 25

    service pipe 20

    service pipe 13

    Main service pipe 40

  • 7/21/2019 PIPE LAYING English7 Mar06

    75/78

    75

    Drawing of Weston s formula flow curve

  • 7/21/2019 PIPE LAYING English7 Mar06

    76/78

    76

    Hazen-Williams formula flow curve

  • 7/21/2019 PIPE LAYING English7 Mar06

    77/78

    77

  • 7/21/2019 PIPE LAYING English7 Mar06

    78/78