PHENIX Simulation System1
Software@BNL December 7, 1999
Simulation: Simulation: Status and MilestonesStatus and Milestones
Tarun Ghosh, Indrani Ojha, Charles Maguire
@ Vanderbilt University
December ‘99 Software Review Meeting
PHENIX Simulation System2
Software@BNL December 7, 1999
Presentation PlanPresentation Plan Scope of Simulation
Current Status
High Level Summary for Day 1 Readiness
Human Resources
Relative Priorities of Tasks Remaining
Milestones before Day 1
Activities after Day 1
PHENIX Simulation System3
Software@BNL December 7, 1999
Scope of SimulationScope of Simulation Manage global event generator software
CVS repository for all to check out Contact with theorists to obtain latest and best event generators:
HIJING, VNI, Ultra-RQMD, … Interface event generator output into program PISA99
First had a ZEBRA-formatted interface (old BNL version) Moving to a ROOT-formatted interface (for event browsing)
Support PWG developed signal generators We don’t write them, but we do interface them to PISA99
Manage GEANT simulation for PHENIX PISA99 Support interface between PISA99 and PHOOL Support the evaluation of the reconstruction
Correlation of GEANT information with event algorithm results
PHENIX Simulation System4
Software@BNL December 7, 1999
Current StatusCurrent Status At work since 1992
PISA used worldwide on almost every known Unix platform Concentrating on Linux since 1998 Converted to ROOT-formatted output in Summer-Fall 1999 Interfaced successfully to PHOOL in late 1999
Massive events generation at three times, and now again 10K for internal challenge in 1997 100K for MDC1 and MDC2 in 1998 and 1999 100K proposed internal challenge in 1999-2000
Dispersal mode in 1999-2000 Massive events generation to be done off-site (CC-J, …) User tools for PWGs to do their own events generation
PHENIX Simulation System5
Software@BNL December 7, 1999
High Level Summary of TasksHigh Level Summary of Tasks
What is needed for Day-1 Analysis?
Match simulation geometry to what is on the floorconsistent with a GEANT3 volume description
Access PHENIX geometry database to set up the detector subsystem (replace phnx.par file)
Develop scripts to automate the geometric acceptance and the efficiency simulations
PHENIX Simulation System6
Software@BNL December 7, 1999
Human ResourcesHuman Resources
C. F. Maguire: supervisor responsible for core software in PISA99
Tarun Ghosh: responsible for scripts and tools for users
Indrani Ojha: responsible for event generator interface software
Heavy reliance on subsystem programmers to do their jobs
Formerly had graduate students in-house (doing Ph.D.’s now)and also have had summer undergraduates
Looking forward to another graduate student for simulation support, or one year-duration undergraduate
PHENIX Simulation System7
Software@BNL December 7, 1999
Relative Priorities of Current TasksRelative Priorities of Current Tasks
Highest priority tasks (soonest accomplished) Event mixing for PISA + PISA and for PRDF + PRDF Introduce 3D magnetic field map (post-VRDC) “Publication” of event generator scripts and tools
High priority (accomplished over longer time) Revise geometry description of PISA99 to use database tools Get next generation of event generators (stuck at 1996-97)
Lower priority task (for year 2000) Move out of GEANT3 and into GEANT 4
PHENIX Simulation System8
Software@BNL December 7, 1999
Milestones Until Day 1Milestones Until Day 1
VRDC start on December 15, and go to January 15 PISA99 and PRDF files generation (must freeze libraries before) Approximately 100K events to be processed Will also do signal file mixing as in MDC2 (start December 20)
3D map file in place by February 15 PRDF+PRDF mixing by February 29 (needs subsystem work) Reconfiguration of geometry installation (DB) May 1
Requires the most subsystem programmer interaction Di-lepton generator “cocktail” from Stony Brook group
Interface to PISA99 the work done by Ralf Averback Update PISA99 documentation
ROOT usage, new make file system Specialized scripts for event generation and retrieval
PHENIX Simulation System9
Software@BNL December 7, 1999
Milestones After Day 1Milestones After Day 1
GEANT4 consideration CERNLIBS may become more problematic with age Need to monitor how well GEANT4 is doing in real world Switchover must not damage analysis of Year 1 data Target date of completion to GEANT4 is not yet known
Fast Monte Carlo Facilitation Simulation group to provide Fast MC options in PISA99 Development of Fast MC modules is PWG responsibility Testing of Fast MC against slow MC is PWG responsibility
Simulation to maintain library of slow MC outputs to compare