Pert and Cpm2

download Pert and Cpm2

of 41

Transcript of Pert and Cpm2

  • 8/13/2019 Pert and Cpm2

    1/41

  • 8/13/2019 Pert and Cpm2

    2/41

    17-2 Project Management

    Developed in 1950sCPM by DuPont forchemical plantsPERT by U.S. Navy forPolaris missile

    maintenance

  • 8/13/2019 Pert and Cpm2

    3/41

    17-3 Project Management

    The Network Diagram

    Network (precedence)diagram

    Activity-on-arrow (AOA)

    Activity-on-node (AON) Activities

    Events

    Slack is the amount of timean activity can be delayedwithout delaying the project

    maintenance

  • 8/13/2019 Pert and Cpm2

    4/41

    17-4 Project Management

    The Network Diagram (contd)Path

    Sequence of activities that leads from thestarting node to the finishing node

    Critical pathThe longest path; determines expected projectduration

    Critical activities Activities on the critical path

    Slack Allowable slippage for path; the difference thelength of path and the length of critical path

  • 8/13/2019 Pert and Cpm2

    5/41

    17-5 Project Management

    Project Network Activity on Arrow

    1

    2

    3

    4

    5 6

    Locatefacilities

    Order furniture

    Furnituresetup

    Interview Hire andtrain

    Remodel

    Movein

    AOA

  • 8/13/2019 Pert and Cpm2

    6/41

    17-6 Project Management

    Project Network Activity on Node

    1

    2

    3

    5

    6

    Locatefacilities

    Order furniture

    Furnituresetup

    Interview

    Remodel Movein

    4

    Hire andtrain

    7S

    AON

  • 8/13/2019 Pert and Cpm2

    7/41

  • 8/13/2019 Pert and Cpm2

    8/41

    17-8 Project Management

    Time Estimates

    DeterministicTime estimates that are fairly certain

    Probabilistic

    Estimates of times that allow for variation

  • 8/13/2019 Pert and Cpm2

    9/41

    17-9 Project Management

    1

    2

    3

    4

    5 6

    8 weeks

    6 weeks

    3 weeks

    4 weeks 9 weeks

    11 weeks

    1 week

    Movein

    Deterministictime estimates

  • 8/13/2019 Pert and Cpm2

    10/41

    17-10 Project Management

    Routs to reach from 1 to 6

    1) 1-2-4-5-6 (16weeks )

    2) 1-2-5-6 ( 20 weeks )

    3) 1-3-5-6 ( 14 weeks )

  • 8/13/2019 Pert and Cpm2

    11/41

    17-11 Project Management

    1

    2

    3

    4

    5 6

    8 weeks

    6 weeks

    3 weeks

    4 weeks 9 weeks

    11 weeks

    1 week

    Movein

    Deterministictime estimates

  • 8/13/2019 Pert and Cpm2

    12/41

    17-12 Project Management

    Example 1 Solution

    Path Length(weeks)

    Slack

    1-2-3-4-5-61-2-5-61-3-5-6

    182014

    206

    Critical Path

  • 8/13/2019 Pert and Cpm2

    13/41

    17-13 Project Management

    Network activitiesES: early start (As soon as you can start the activity)EF: early finish (As soon you can finish the activity)LS: late start ( For back calculations)LF: late finish ( For back calculations)

    Used to determineExpected project duration

    Slack timeCritical path

    Computing Algorithm

  • 8/13/2019 Pert and Cpm2

    14/41

    17-14 Project Management

    Computing ES, EF, LF, LSSlack (LS-ES)

    Activity duration ES EF LF LS LS-ES1-2 8 0 8 8 0 0

    1-3 4 0 4 10 6 62-4 6 8 14 16 10 22-5 11 8 19 19 8 0

    3-5 9 4 13 19 10 64-5 3 14 17 19 16 25-6 1 19 20 20 19 0

    17 15 P j M

  • 8/13/2019 Pert and Cpm2

    15/41

    17-15 Project Management

    CPM

    EXAMPLES OF CRITICALPATH METHOD

    17 16 P j M

  • 8/13/2019 Pert and Cpm2

    16/41

    17-16 Project Management

    Picnic program

  • 8/13/2019 Pert and Cpm2

    17/41

    17 18 P j t M g t

    Without precedence

  • 8/13/2019 Pert and Cpm2

    18/41

    17-18 Project Management

    Picnic program Activities Time in min

    A PREPARE TEA 20

    B PREPARE FRUITS 5

    C PREPARE SANDWICHES 10

    D PREPARE BASKET 10E DRESS UP 15

    F COLECT BLANKETS 5

    G PREPARE SUIT CASE 20

    H LOAD CAR 10

    I GET GAS 10

    J GET SPARES 15

    K DRIVE 30

    Without precedence

    17 19 Project Management

    HOW TO ARRANGE IT

  • 8/13/2019 Pert and Cpm2

    19/41

    17-19 Project Management

    3

    10

    2

    4

    8

    5

    6

    9

    1

    7

    HOW TO ARRANGE IT

    17 20 Project Management

  • 8/13/2019 Pert and Cpm2

    20/41

    17-20 Project Management

    Picnic program

    Activities Time in min

    A 1,3 PREPARE TEA 20

    B 1,2 PREPARE FRUITS 5

    C 2,3 PREPARE SANDWICHES 10D 3,4 PREPARE BASKET 10

    E 4,6 DRESS UP 15

    F 4,5 COLECT BLANKETS 5

    G 5,6 PREPARE SUIT CASE 20H 6,7 LOAD CAR 10

    I 7,8 GET GAS 10

    J 8,9 GET SPARES 15

    K 9,10 DRIVE 30

    17 21 Project Management

  • 8/13/2019 Pert and Cpm2

    21/41

    17-21 Project Management

    NODE DIAGRAM

    ` A D E H I J K20 10 15 10 10 15 30

    5B 10 C 5 F 20 G

    MAX TIME = 120 MIN.

    1 3 6 9 108

    52

    74

    17 22 Project Management

  • 8/13/2019 Pert and Cpm2

    22/41

    17-22 Project Management

    NODE DIAGRAM

    CRITICAL PATH 1-3-4-5-6-7-8-9-10

    1 3 6 9 108

    52

    74

    17-23 Project Management

  • 8/13/2019 Pert and Cpm2

    23/41

    17-23 Project Management

    CPM

    EXAMPLE CONSTRUCTIONOF A ROOM

    17-24 Project Management

    http://www.animationlibrary.com/a-l/?n=image.php3&image_id=8434
  • 8/13/2019 Pert and Cpm2

    24/41

    17-24 Project Management

    ACIVITIES TIME IN DAYS

    A 1-3 FOUNDATION 2

    B 1-2 BRICKS COLLECTION 1

    C 2-3 CEMENT COLLECTION 1

    D 3-4 FIRST DPC 3

    E 4-6 CURING 2

    F 4-5 BRICKS COLLECTION 1

    G 5-6 CEMENT COLLECTION 1

    H 6-7 2 ND DPC 2

    I 7-9 CURING 2

    J 7-8 BRICKS COLLECTION 1

    K 8-9 CEMENT COLLECTION 1

    L 9-11 WALLS 5

    M 10-11 EARTH FILLING 1

    N 11-13 ROOF 21

    O 11-12 DOOR AND WINDOW 5

    P 12-16 SERVICES 15

    Q 13-14 PLASTERS 2

    R 14-16 FLOORS 15

    S 14-15 WHITE WASH 2

    17-25 Project Management

    Optimization MSc

    maintenance

  • 8/13/2019 Pert and Cpm2

    25/41

    17 25 Project Management

    NODE DIAGRAM

    1

    10

    43

    1552

    1696 7 11

    8

    13 14

    12

    Optimization MScmaintenance

    17-26 Project Management

  • 8/13/2019 Pert and Cpm2

    26/41

    17 26 Project Management

    17-27 Project Management

  • 8/13/2019 Pert and Cpm2

    27/41

    17 27 Project Management

    17-28 Project Management

  • 8/13/2019 Pert and Cpm2

    28/41

    17 28 Project Management

    17-29 Project Management

  • 8/13/2019 Pert and Cpm2

    29/41

    j g

    17-30 Project Management

  • 8/13/2019 Pert and Cpm2

    30/41

    j g

    FIND OUT THE CRITICAL PATH

    17-31 Project Management

  • 8/13/2019 Pert and Cpm2

    31/41

    j g

    PERT

    Program

    Evaluation andReviewTechnique

    17-32 Project Management

    http://www.animationlibrary.com/a-l/?n=image.php3&image_id=12345
  • 8/13/2019 Pert and Cpm2

    32/41

    j g

    Probabilistic Time Estimates

    Optimistic timeTime required under optimal conditions

    Pessimistic time

    Time required under worst conditions

    Most likely time

    Most probable length of time that will be required

    17-33 Project Management

  • 8/13/2019 Pert and Cpm2

    33/41

    Probabilistic Estimates

    Activity

    start

    Optimistic

    time

    Most likely

    time (mode)

    Pessimistic

    time

    to tptm te

    17-34 Project Management

  • 8/13/2019 Pert and Cpm2

    34/41

    Expected Time

    te =to + 4tm +tp

    6

    te = expected timeto = optimistic timetm

    = most likely timetp = pessimistic time

    17-35 Project Management

  • 8/13/2019 Pert and Cpm2

    35/41

    Variance

    2 = (tp to)2

    36

    2 = varianceto = optimistic time

    tp = pessimistic time

    17-36 Project Management

  • 8/13/2019 Pert and Cpm2

    36/41

    Example

    3-4-5d

    3-5-7e

    5-7-9f

    2-4-6b

    4-6-8h

    Optimistictime Most likelytime Pessimistictime

    17-37 Project Management

  • 8/13/2019 Pert and Cpm2

    37/41

    Path Probabilities

    Z = Specified time Path mean

    Path standard deviation

    Z indicates how many standard deviationsof the path distribution the specified time

    is beyond the expected path duration.

    17-38 Project Management

  • 8/13/2019 Pert and Cpm2

    38/41

    17

    Weeks

    Weeks

    Weeks

    Weeks

    10.0

    16.0

    13.5

    1.00

    1.00

    a-b-c

    d-e-f

    g-h-i

  • 8/13/2019 Pert and Cpm2

    39/41

    17-40 Project Management

  • 8/13/2019 Pert and Cpm2

    40/41

    Advantages of PERT

    Forces managers to organize

    Provides graphic display of activities

    IdentifiesCritical activities

    Slack activities 1

    2

    3

    4

    5 6

  • 8/13/2019 Pert and Cpm2

    41/41