Presenter: Patrick Weaver PMI-SP Micro Planning International Asia Pacific Cell:+61 418 53 1111 [email protected]. Micro Planner X Micro Planner X Micro Planner X Micro Planner X- - -Pert Pert Pert Pert V3.5.1 V3.5.1 V3.5.1 V3.5.1 Overview Overview Overview Overview Copyright 2014 Micro Planning International Pty Ltd ABN 41 126 858 553 Construction CPM 2016 Construction CPM 2016 Construction CPM 2016 Construction CPM 2016 6-Jan-16

Transcript of Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert...

Page 1: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Presenter: Patrick Weaver PMI-SPMicro Planning International Asia Pacific Cell:+61 418 53 1111

[email protected].

Micro Planner XMicro Planner XMicro Planner XMicro Planner X----Pert Pert Pert Pert V3.5.1V3.5.1V3.5.1V3.5.1OverviewOverviewOverviewOverview

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

6-Jan-16

Page 2: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 3: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Arrow Diagram

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 4: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Precedence Diagram

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 5: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 6: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 7: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Working Days Gantt

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 8: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Why the Need to Plan Resources?

� In the US and generally within Australia, there is a shortage of skilled tradespersons within the construction industry

� Client’s still want their projects delivered on time and within budget

� Shortages of resources generally cause delays and increases in cost

� So what is the project manager to do?

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 9: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� Need to know what resources are required by your project

� Thus the project manager MUST carry out resource planning

Why the Need to Plan Resources?

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 10: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resource Planning

�When you analyze a project on timing alone, the results show how soon the project can complete and what the deadlines are for each operation.

�Analysis of time does not tell you whether there are enough people to meet this schedule or whether the available machines can cope or how much cash you need.

�Time Analysis calculates when each operation could happen but to find out when each operation should happen, you need

to consider resources.

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 11: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� Note: In calculating task durations some consideration has been made about resource levels

– what we are discussing today is the optimisation of time and resources.

Time Vs Resources

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 12: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Defining Resource Information

�Before you can allocate resources to individual operations and analyze the workloads, you need to know the following information…

• The resources available to the project

• The cost of each resource (optional)

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 13: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resource Profile

�Need to define the name of the Resource and how much is available and when e.g.

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 14: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resource Types

� Having named the Resource need to know

whether it is either

– Normal

– Pool

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 15: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Normal Resources

� Normal resources are those which are available for work each time period (day) as in people

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 16: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Pool Resources

� Pool resources are ones which are actually consumed, e.g bricks

� Which may be replenished at various time periods

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 17: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Utilisation of a Pool Resource

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 18: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Replenishing the Pool Resource

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 19: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resource Usage Method

� Before you enter a quantity, decide whether to specify how many resources are required (as a Rate) or

� whether to enter the Total number of People Days (or machine days, bricks, cash etc.) for the entire duration. (Also known as Level of Effort)

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 20: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Rate or Total (1) ?

� Specifying usage as a Rate means the specified resource quantity will be used at a steady rate, regardless of length of day, week or duration. If the duration changes so does the total resource usage – the resource allocation is variable.

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 21: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� If you specify a Total allocation then a specific amount of work time is spread evenly over the duration.

� As a result, no matter how much the duration changes, the overall allocation does not – it is constant.

� For example, imagine you have an operation that would take 1 person 4 days and you want it done in 2 days…

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Rate or Total (2) ?

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 22: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Rate or Total (3) ?

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 23: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� You could express the work content either as a Rate of 2 people per day, or as a Total of 4 Man Days. At this point, the resource allocation is the same – 2 people per day for 2 days.

Rate or Total (4) ?

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 24: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Rate or Total (5) ?

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 25: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� However! If the duration were greater, say, 4 days then the Rate method uses 2 people per day for 4 days – a total of 8 man days.

� Whereas a Total allocation of 4 man days does not change – allocating 1 person per day for 4 days.

Rate or Total (6) ?

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 26: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resource Analysis

� Resource Analysis is the process by which you examine the availability of resources and figure out when tasks should be scheduled to work within that availability. During this process, the analysis tends to level out the usage of resources.

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 27: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resource Analysis (Cont)

� Resource Analysis produces a schedule of dates for every task in the project showing when they should start and finish and also produces totals for the usage of resources throughout the project.

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 28: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

What Does Resource Analysis do?

The Parallel Scheduling by Resource Analysis could best be described as a bulldozer technique.

Imagine that every task on a project is able to happen at its earliest time – as calculated by Time Analysis. The result could be usage which fluctuates regardless of how many resources are available.

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 29: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Preparing to Resource Schedule

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 30: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

What Does Resource Analysis do (2)?

The availability of resources can be set at a specific

level – like a bulldozer blade.

As the Resource Analysis bulldozer starts up and

moves forward from Time Now, it pushes the peaks

of excess resources into the troughs of unused

resources.

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 31: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

What Does Resource Analysis do (3)?

There will be times when there is too much earthfor the required level to be reached.

There may also be insufficient earth to maintain continuity at the required level.

That is the theory, in practice it works like this…

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 32: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

The Time Analysis Schedule of Tasks

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 33: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resourcing After Day 1

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 34: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resourcing After Day 2

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 35: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resourcing After Day 3

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 36: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resourcing After Day 4

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 37: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Splitting

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 38: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Defining Minimum Split

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 39: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Stretching Tasks in Resourcing

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 40: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resourcing after Day 1

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 41: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resourcing after Day 2

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 42: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resourcing after Day 4

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 43: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Full Impact of Stretching Schedule by Day 7

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 44: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Deadlines or Resources?

During Resource Analysis, you may meet a situation in which there are insufficient resources available for an task which has no more float. You are, therefore, faced with a decision – do you delay the task so that the project completion or some other deadline is delayed, or do you overload the available resources?

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 45: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Types of Resource Analysis

The answer comes in the form of two types of Resource Analysis – Deadline Critical and Resource Critical.�

Deadline Critical calculates how many extra resources, if any, are needed to finish the project on time.

Resource Critical calculates how much extra time, if any, is required for the existing resources to complete their allotted workloads.

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 46: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Deadline Critical

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 47: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resource Limited

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 48: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Time and Resource Thresholds

From the previous slides you may have imagined a certain amount of anarchy when the chips are down.

First, during a Deadline Critical analysis, the resources can be overloaded. You may have asked yourself two questions:

1. Can I limit this overloading so that, at least, it is within reason?

2. Is it possible to specify that some resources cannot be overloaded even during Deadline Critical analysis – a kind of selective Resource Critical analysis?

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 49: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Time and Resource Thresholds (2)

During Resource Critical analysis, the project can be delayed beyond its deadline. You may have asked yourself:

Is there any way that I can limit this delay?

The answers to these questions come in the shape ofThresholds…

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 50: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resource Thresholds in Deadline Critical

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 51: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Time Thresholds

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 52: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Unavoidable Split/Overload

When you choose a Resource Critical Resource Analysis, you specify that the resources must not be overloaded and, under certain circumstances, the only way of achieving this may be the interruption of one or more tasks...

... but what happens if these tasks are Non-Split or Consecutive?

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 53: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

The Solid Fixed Block:Imagine that tasks A and B require the same resource and that task B is forced to start on day 3 because of a Fixed Earliest date. A fixed date takes priority over

everything else

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 54: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resource Distribution

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 55: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Deadline Resource Histogram

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 56: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Resource Limited Resource Histogram

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 57: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Cost Forecasting

Cost Analysis

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 58: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Costing Rates

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 59: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

The Cost of Each Task

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 60: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Costing Details

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 61: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Daily Wastage Costs

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 62: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Total Estimated Costs or Cash Flow Profile

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 63: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Comparing Schedule Costs

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 64: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 65: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Updating aUpdating aUpdating aUpdating a Micro Planner XMicro Planner XMicro Planner XMicro Planner X----Pert Pert Pert Pert Project PlanProject PlanProject PlanProject Plan

Reporting Progress on Tasks, Reporting Progress on Tasks, Reporting Progress on Tasks, Reporting Progress on Tasks, Resources and CostsResources and CostsResources and CostsResources and Costs

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 66: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Reporting Progress

� Opened the file, go to the Analysis menu and highlight Progress Details and click.

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 67: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 68: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� Enter the appropriate Time Now date,

� Eg 15-Sep-03

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 69: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� Go to File on the Menu bar and select

� Save As ..

� Eg HOMUpdt1.xpj

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 70: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� Go to the desktop and open the sub project to be progressed

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 71: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� X-Pert shows all the tasks and events which should have started and finished since the last Time Now, with a “cross” or diagonal line through the task box

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 72: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� Double Click on the first event/task to be progressed

� Click on the Progress Button

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 73: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� The progress cells now appear

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 74: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� Enter the actual achieved date for the “Start” event; eg “18Aug03”

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 75: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Progressing Tasks

�Double Click the first task to be progressed

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 76: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� Enter the Task’s “Actual Start and / or Actual Finish Dates”

� Eg Actual Start was 18Aug03 and Actual Finish was 22Aug03

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 77: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� Reporting “Actual Resources Used”

� Click on the Resource Usage button

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 78: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� Click on Actual Usage

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 79: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� Click on “Copy Planned to Actual”

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 80: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� Note that cells are filled for you, with the data originally entered

� Click OK and the progress data is now entered

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 81: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Continue to report progress

�For a Task which has started but not finished, you must report a balance to go or a % Done to date, as shown

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 82: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� Note: A task should not have a balance duration reported if both the started and finished dates have been entered. Also % Done will not be used as reporting percentage work done is rather subjective and the more objective form of estimating time to complete a task is preferred.

� If a task is reported with an Actual Start Date and the rest of the fields are left blank, X-Pert will assume progress has occurred since the reported Actual Start Date and Time Now. Should there be insufficient balance left at Time Now, then the task will be assumed completed

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 83: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

� Run a Analysis to view the results of “Progress”

� eg. Resource Analysis – Deadline Critical

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 84: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 85: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Reporting Progress

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553

6-Jan-16

Page 86: Micro Planner XMicro Planner X- ---Pert Pert Pert … · Micro Planner XMicro Planner X- ---Pert Pert Pert V3.5.1V3.5.1 ... Working Days Gantt Construction CPM 2016 ... Construction

Construction CPM 2016Construction CPM 2016Construction CPM 2016Construction CPM 2016

Thank You

Questions ?

Copyright 2014 Micro Planning International Pty LtdABN 41 126 858 553