Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal...

54
Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International Conference on Seismology and Earthquake Engineering 16-18 May 2011, Tehran, Iran

Transcript of Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal...

Page 1: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Performance of buildings in the February 2011 Christchurch

Earthquake

Associate Prof Rajesh DhakalUniversity of Canterbury

Christchurch, NZ

Sixth International Conference on Seismology and Earthquake Engineering

16-18 May 2011, Tehran, Iran

Page 2: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

URM Buildings: General Observations

Extensive damage to URM buildings in general Many URM buildings in the city flattened Most of the remaining buildings very severely

damaged Few well constructed URM buildings in the

western suburbs were subjected to moderate shakings and suffered repairable damage

In the CBD, very few (unretrofitted) URM buildings will exist in future.

Some examples of typical URM building damage/collapse follow

Page 3: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.
Page 4: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.
Page 5: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.
Page 6: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Many buildings were about to collapse (short duration effect)

Page 7: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

In-plane wall/pier failure

Page 8: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Gable wall failure

Page 9: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Parapet Failures

Page 10: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Anchorage Failure

Page 11: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Out-of-plane wall failure

Page 12: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Vulnerability of cavity construction

Out-of-plane failures (Cavity walls)

Page 13: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Poor quality of mortar

Many tested samples 1.0-1.5 MPa compression strengthΤ = C + µ N

Page 14: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Poor quality of diaphragm timber

Page 15: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Inadequate Cavity Wall Ties

Page 16: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Pounding of URM Buildings

Acknowledgement: Several slides in this section are provided by Gregory Cole, University of Canterbury

Page 17: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Pounding Survey statistics

≥ ≥ ≥ ≥≥

Page 18: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Typical masonry pounding damage

Page 19: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

URM pounding damage mechanism

Page 20: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Diagonal damage path due to pounding

Page 21: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.
Page 22: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Buildings in a row with little separation

Page 23: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Example: Pounding damage

Page 24: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Example: Pounding damage

Page 25: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Example: Pounding damage

Page 26: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Example: Pounding damage

Page 27: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Inadequate building flashing details

Page 28: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Performance of Retrofitted URM

Buildings

Acknowledgement: Several slides in this section are provided by A/P Jason Ingham, University of Auckland

Page 29: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Some well-anchored walls did well

Page 30: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Damage to anchored walls

Page 31: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Steel strong backs generally performed well

Page 32: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Steel Frames: Generally did well

Page 33: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Steel Frames: Some suffered damage

Failed frame to wall connections mounted perpendicular to wall

Page 34: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Wall confined by steel plates

(cracks visible, but not wide)

Page 35: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Shotcrete

In general shotcreted masonry walls performed well.

Minor cracking seen in some walls.

Page 36: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Floor Diaphragms Retrofit

Page 37: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Successful parapet strengthening

Page 38: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Unsuccessful Parapet Strengthening

(require protection at corners)

Page 39: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Unsuccessful Parapet Strengthening

Wall detached from struts

Page 40: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Performance of Old RC buildings

Designed for smaller strength (compared to now) Subjected to large acceleration (higher than

current design level) Lacked ductility (specially the pre-1980 buildings) Mostly not retrofitted As expected, damaged severely

Page 41: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

CTV Building (117 dead)

Page 42: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Hotel Grand Chancellor (Demolished)

Page 43: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Performance of Modern RC buildings

Subjected to large acceleration (higher than current design level)

Inherent ductility As expected, most buildings damaged But no collapse (post 1990) Most buildings can be reused after repair

(bonus?) In general, performance better than expected

Page 44: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Example: Clarendon Tower

Page 45: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Dislodging of precast stair from landing

Page 46: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Dislodging of precast stair from landing

Page 47: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Vertical acceleration effect

Page 48: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Issues related to performance of modern buildings

Staircase in many buildings collapsed (change of current practice needed)

Precast floor (issues with interaction between floor and beam elongation)

Irregularity of buildings (irregular buildings performed poorly)

Foundation: Not adequate for the soft soil underneath

Compression failure of columns: high vertical acceleration

Page 49: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Non-structural damage

Page 50: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Non-structural performance

Structural performance: no surprises Non-structural performance: DISAPPOINTING Ceiling: Very few buildings with ceilings intact Facade/Partition: Damaged severely in most buildings Parapets: Most unrestrained parapets fell September earthquake: Minor structural damage (modern

buildings); severe non-structural damage February earthquake: Moderate-severe damage to modern

buildings; Collapse of non-structural elements Clearly, a mismatch between the structural and non-structural

performance Need more focus in future

Page 51: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Non-structural damage could have killed more people

Page 52: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Falling objects could have, too

It is time that we start explicitly aiming for minimisation of NON-STRUCTURAL DAMAGE and DOWNTIME in seismic

design.

Page 53: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Relevance to Iran

1. There are many unreinforced masonry (URM) buildings which can suffer severe damage in moderate shakings and collapse in strong shakings. The brittle failure of URM building components can be fatal.

2. Systematically strengthened/retrofitted URM buildings perform noticeably better. Although they may suffer damage in large earthquakes, they are unlikely to collapse completely; thereby saving lives of inhabitants.

3. Hence, if you want to reduce the life safety threat from these URM buildings, you MUST retrofit them.

4. Be careful, there is a difference between strengthening and retrofitting.

Page 54: Performance of buildings in the February 2011 Christchurch Earthquake Associate Prof Rajesh Dhakal University of Canterbury Christchurch, NZ Sixth International.

Thank You!

Acknowledgements: Jason Ingham, and Gregory Colefor providing some photographs and slides