PEP- II Linac Accelerator Systems Department The PEP-II B-Factory Accelerator John T. Seeman...
-
date post
19-Dec-2015 -
Category
Documents
-
view
214 -
download
0
Transcript of PEP- II Linac Accelerator Systems Department The PEP-II B-Factory Accelerator John T. Seeman...
PEP- II Linac Accelerator Systems Department
The PEP-II B-Factory Accelerator
John T. SeemanAssistant Director
Particle and Particle-Astrophysics DivisionSLAC
DOE HEP ReviewJune 14, 2005
PEP- II Linac Accelerator Systems Department
Topics
• Highlights of Run 5 of PEP-II
• Run plan through 2008
• How to increase the luminosity to 2.1 x 1034
• Future down work
PEP- II Linac Accelerator Systems Department
The PEP-II Team
•
August 2004
PEP- II Linac Accelerator Systems Department
Beam Lines
PEP- II Linac Accelerator Systems Department
PEP-II arc section
PEP- II Linac Accelerator Systems Department
PEP-II HER RF cavities
PEP- II Linac Accelerator Systems Department
PEP-II Interaction Region Components near BaBar
HER
LER
Collision point
BaBar
PEP- II Linac Accelerator Systems Department
PEP-II Machine Advisory Committee Reviews
• PEP-II Machine Advisory Committee– 1) Jan 4-6, 1995
– 2) August 24-25, 1995
– 3) April 11-13, 1996
– 4) January 6-8, 1997
– 5) November 10-13, 1997
– 6) December 14-16, 1998
– 7) October 9-11, 2003
– 8) April 15-17, 2004
– 9) December 13-15, 2004
– 10) October 5-7, 2005
PEP- II Linac Accelerator Systems Department
Other Program Reviews
• DOE Operations Review in June 2004
• PEP-II End of Run Review August 2004
• PEP-II Restart Validation Review February- March 2005
• SPC May 2005
• DOE Operations Review in late Summer-early Fall 2005
PEP- II Linac Accelerator Systems Department
PEP-II Safety Planning and Restart Plan• Electrical accident at SLAC on October 11, 2004. All
running of accelerators stopped.• Safety training with new procedures October 2004 –
March 2005.• Type A Investigation October-December, 2004.• Corrective Action team: December 2004-January 2005.• Restart Validation Review: February 2005.• “Pre-restart” conditions completed March 2005.• Linac and PEP-II operations start up April 15, 2005.• Power outage: May 18-20.• Beams returned about May 25.• FFTB beam line revalidated June 2, 2005.• FFTB beam started June 3, 2005.
PEP- II Linac Accelerator Systems Department
230 kV Lines
•
PEP- II Linac Accelerator Systems Department
The cable break area
•
230 kV lines
PEP- II Linac Accelerator Systems Department
The tree that fell (100 ft tall)
• Neighbor’s tree
Stanford tree
PEP- II Linac Accelerator Systems Department
•
Power lineloose cables
PEP- II Linac Accelerator Systems Department
•
PEP- II Linac Accelerator Systems Department
String new wires by crane
•
PEP- II Linac Accelerator Systems Department
Summer 2004 PEP-II Improvements
• IR2 south forward shield wall: Backgrounds
• Add another new LER RF station: Higher current
• Add a HER RF station by splitting up a current 4 cavity station into two 2 cavity stations: Higher current
• Two new “Frascati” longitudinal kickers in LER: More stability
• New electrodes for transverse kickers: More stability
• Add fans to all HER bellows: Cool Higher Order Modes (HOMs)
• Alignment work (quadrupole rolls): Smaller vertical emittance
• New LER synchrotron light monitor: Smaller vertical emittance
• IR NEG pump HOM reduction: Better lifetime and backgrounds
• New Support Tube Chiller: Higher currents
PEP- II Linac Accelerator Systems Department
PEP-II Run Schedule
• PEP-II Run 5 started April 15, 2005.• Will collide steadily from April 2005 through July
2006 with a one month break in October 2005.• Next ROD (repair day) about August 3, 2005.• Down in 2006 August through November for
BaBar, PEP-II, and LCLS upgrade work.• Three month down in Summer-Fall 2007 for
LCLS work.• Collide through September 2008.
PEP- II Linac Accelerator Systems Department
October Down Tasks• Safety
– PPS recertification– PEP-II NIT lighting– Linac switch gear work– New K1A/B and K10B substations
• Routine maintenance• PEP-II Upgrades
– New x-y BPMs– RF work– IR vacuum chambers
• LCLS installation– Beam pipe through Sector 20 wall– Beam stoppers– Waveguide work– Accelerating section work– Sector 24 stairs installation
PEP- II Linac Accelerator Systems Department
Daily Integration Record with Trickle Injection
710/pb
LER I
HER I
Luminosity
PEP- II Linac Accelerator Systems Department
PEP-II Monthly Peak Luminosity
•
PEP- II Linac Accelerator Systems Department
•
PEP- II Linac Accelerator Systems Department
•
PEP- II Linac Accelerator Systems Department
•
Prediction July 2003
Actual
PEP- II Linac Accelerator Systems Department
•
Prediction April 2005
Actual
Power outage
PEP- II Linac Accelerator Systems Department
PEP-II Issues
• Recent issues:– Positron source coil short
– Positron source vacuum leak
– PEP-II HER arc vacuum chamber water plugs
– PEP-II LER trouble with orbit steering
– PEP-II klystron failure (collector damage)
– Power outage changed conditions
• Present issues:– Changing machine conditions over hours (orbits?)
– Luminosity droop along mini-trains: (wakefields, parasitic collisions, electron cloud, RF loading?)
PEP- II Linac Accelerator Systems Department
Change of specific luminosity over mini-trains
•
Mini-trainsSpecificluminosity
Luminosity
PEP- II Linac Accelerator Systems Department
Luminosity Equation y is the beam-beam parameter (~0.065)
Ib is the bunch current (1 to 3 mA)
n is the number of bunches (~1600) y
* is the IP lattice optics function (vertical beta) (10 mm)
E is the beam energy (3.1 and 9 GeV) Luminosity (1033 cm-2 s-1)
*341017.2
y
byEInxL
PEP- II Linac Accelerator Systems Department
Future luminosity increase factors
Parameter Present Future Luminosity gain ratio
Hardware and work needed
LER current 2450 mA 4500 mA Two RF stations, new IR vacuum chambers
HER current 1550 mA 2200 mA 1.61 Two RF stations, new IR vacuum chambers
y* 10.5 mm 8.5 mm 1.24 HER higher tunes, RF & power supplies work
y 0.065 L 0.043 H
0.070 L 0.055 H
1.17 Tune plane, coupling, & IR work
Total x 2.3
PEP- II Linac Accelerator Systems Department
Overall Parameters and Goals
Parameter Units DesignBest in collision
Future 2007 goal
I+ mA 2140 2450 4500
I- mA 750 1550 2200
Number bunches
1658 1588 1715
y* mm 15-20 11 8.5
Bunch length mm 15 11-12 9
y 0.03 0.043-0.065 0.055-0.07
Luminosity x1033 3.0 9.2 21
Int lumi / day
pb-1 130 710 1300
Over five times design!Over three times design
Twice design
PEP- II Linac Accelerator Systems Department
PEP-II Future Luminosity Parameters
x y x y n I x* y* Lumi x y
Units cm mm nm nm mA m m x1E33
LER now
32 10.5 33 1.55 1616 2450 103 4.0 9.21 0.053 0.065
LER 2007
28 8.5 47 1.80 1720 4500 115 3.9 21.0 0.065 0.070
HER now
33 10.5 60 1.30 1616 1550 139 3.7 9.21 0.052 0.043
HER 2007
28 8.5 66 1.60 1720 2200 136 3.7 21.0 0.063 0.055
PEP- II Linac Accelerator Systems Department
Future PEP-II Improvement Activities
• New transverse digital feedback processors (Summer 2005)
• New RF comb filters (Fall 2005)
• New klystron linearizer (Spring 2006)
• Install LER-5 RF station (Fall 2006)
• Install HER-10 RF station (Fall 2006)
• Upgrade several high-power IR vacuum chambers (Q2, Q4, Q5, Q2 bellows, LER abort spoiler, straight section bellows …) (Fall 2006)
• HER lattice upgrade for lower momentum compaction and shorter bunches (Fall 2006)
PEP- II Linac Accelerator Systems Department
PEP- II Linac Accelerator Systems Department
•
Local Chamber Area
Dots show new chamber locations.
PEP- II Linac Accelerator Systems Department
New IP Be bellows design
•
SiC
Cooling
PEP- II Linac Accelerator Systems Department
New Q2 Chamber Forward
•
PEP- II Linac Accelerator Systems Department
Forward Q2 Chamber (HER/LER)
LER leg
HER leg
PEP- II Linac Accelerator Systems Department
•
Straight HOM Bellows -Design Details
GlidCop GlidCop StubStub
Inconel Spring Inconel Spring FingerFinger
GlidCop RF GlidCop RF Shield FingerShield Finger
Welded Welded BellowsBellows
Absorbing TileAbsorbing Tile
2.75” long by .24” wide 2.75” long by .24” wide HOM Trapping SlotsHOM Trapping SlotsModes in the chamber propagate through the slots & are absorbed by the AlNiSiC.
Bellows CavityBellows CavityModes that leak past the RF shield finger and are trapped in this area still see the absorberBeam DirectionBeam Direction
PEP- II Linac Accelerator Systems Department
New Q5 HER Chamber
•
PEP- II Linac Accelerator Systems Department
Q5 HER details
•
PEP- II Linac Accelerator Systems Department
HER Q4 Chambers
Q5R BPMQ4R BPM
27.5 inches14 inches
e-e-
Looking upbeam
BPM Timing BPMs
Electron BPMs
Electron BPMs
Electron BPMs
Electron BPMs
PEP- II Linac Accelerator Systems Department
•
Q4/Q5 Bellows LayoutQ4/Q5 Bellows Layout
Q4 side, 10” Q4 side, 10” flangeflange
Q5 side 12” flangeQ5 side 12” flange
GlidCop GlidCop StubStub
Inconel Spring Inconel Spring FingerFinger
GlidCop RF GlidCop RF Shield FingerShield Finger
Welded Welded BellowsBellows
Cooling – not shownCooling – not shown
Absorbing TileAbsorbing Tile
PEP- II Linac Accelerator Systems Department
IR Q4-Q5 bellows with HOM Absorbers
PEP- II Linac Accelerator Systems Department
Accelerator Physics Studies Needed for 2x1034
• Better understanding of beam-beam effects– Parasitic crossings– Small crossing angles– Higher tune shifts
• Reduce beam aborts– RF trips– Longitudinal instabilities– Transverse instabilities– Better backgrounds
• Better magnetic lattice optics– Lower y*– Reduce beats– Improve luminosity tuning knobs
• Increase LER emittance with wigglers• Continue to improve HOM damping at higher currents• Determine instability growth rates in LER/HER at high currents
– Transverse– Longitudinal– Electron cloud
• Machine-detector interface– Reduce backgrounds in trickle charge– Reduce IP pressure with current
PEP- II Linac Accelerator Systems Department
Expected PEP-II Delivered Integrated Luminosity
End of fiscal yearTotal PEP-II Projection
Delivered
“Yearly change”
Peak
Luminosity
x 1033
FY2004 256/fb 117/fb 9.2
FY2005 338 82 10.5
FY2006 516 178 13
FY2007 722 206 20
FY2008 1097 375 21
Projection May 2005
PEP- II Linac Accelerator Systems Department
Integrated Luminosity Goals
Now
PEP- II Linac Accelerator Systems Department
Conclusions
• Restart Validation Process for PEP-II has been completed.
• Run 5 plan has started.
• PEP-II turn on in Run 5 is going well (in spite of the power outage).
• PEP-II has delivered over 14 fb-1 in Run 5 and over 270 fb-1 since May 1999.
• Trickle injection in both rings all of the time.
• Planned upgrades towards 2.11034 are on track.
• Goal is more than 1 ab-1 in 2008.
• Run and down schedules have been mapped until 2008.