Pds 3d Model Piping Checking

download Pds 3d Model Piping Checking

of 23

Transcript of Pds 3d Model Piping Checking

  • 8/6/2019 Pds 3d Model Piping Checking

    1/23

    Table of Contents

    1. Introduction

    2. General

    3. General Safety

    4. Lines

    5. Valves

    6. Heat Exchangers/Reboilers

    7. Pumps and Compressor

    8. Vessels/Columns

    9. Furnaces/Boilers

    10. Relief System

    11. Electrical

    12. Instrumentation

    13. Civil/Structural

    14. Attachments

    1. INTRODUCTION

    The purpose of this document is to lay down a review procedure to ensure that the desired level of

    quality for the creation of a piping 3D is carried out in the engineering office and that sound design

    criteria for operability, safety and maintenance have been observed.

    This check list may also be used for the recording of the check, appropriate space is left for any

    comments against a checked item in column remarks.

    Additionally the form Internal 3D Model Review (see Attachment 1) and the form Approved 3D Model

    Revisions from Internal 3D Model Review (see Attachment 2) may be used for reporting purposes.

    2. GENERAL

    Check if Interference Checking facility has been run, if so, ask to see a printout of the report.

    Check the 3D model against the latest issue of the plot plans, engineering and utility flow diagrams and

    line tables.

    http://www.red-bag.com/jcms/index.php/test-library#introductionhttp://www.red-bag.com/jcms/index.php/test-library#introductionhttp://www.red-bag.com/jcms/index.php/test-library#generalhttp://www.red-bag.com/jcms/index.php/test-library#generalhttp://www.red-bag.com/jcms/index.php/test-library#safetyhttp://www.red-bag.com/jcms/index.php/test-library#lineshttp://www.red-bag.com/jcms/index.php/test-library#valveshttp://www.red-bag.com/jcms/index.php/test-library#valveshttp://www.red-bag.com/jcms/index.php/test-library#heathttp://www.red-bag.com/jcms/index.php/test-library#heathttp://www.red-bag.com/jcms/index.php/test-library#pumpshttp://www.red-bag.com/jcms/index.php/test-library#pumpshttp://www.red-bag.com/jcms/index.php/test-library#vesselshttp://www.red-bag.com/jcms/index.php/test-library#furnaceshttp://www.red-bag.com/jcms/index.php/test-library#reliefhttp://www.red-bag.com/jcms/index.php/test-library#reliefhttp://www.red-bag.com/jcms/index.php/test-library#electricalhttp://www.red-bag.com/jcms/index.php/test-library#electricalhttp://www.red-bag.com/jcms/index.php/test-library#instrumentationhttp://www.red-bag.com/jcms/index.php/test-library#instrumentationhttp://www.red-bag.com/jcms/index.php/test-library#civilhttp://www.red-bag.com/jcms/index.php/test-library#attachmentshttp://www.red-bag.com/jcms/index.php/test-library#introductionhttp://www.red-bag.com/jcms/index.php/test-library#generalhttp://www.red-bag.com/jcms/index.php/test-library#safetyhttp://www.red-bag.com/jcms/index.php/test-library#lineshttp://www.red-bag.com/jcms/index.php/test-library#valveshttp://www.red-bag.com/jcms/index.php/test-library#heathttp://www.red-bag.com/jcms/index.php/test-library#pumpshttp://www.red-bag.com/jcms/index.php/test-library#vesselshttp://www.red-bag.com/jcms/index.php/test-library#furnaceshttp://www.red-bag.com/jcms/index.php/test-library#reliefhttp://www.red-bag.com/jcms/index.php/test-library#electricalhttp://www.red-bag.com/jcms/index.php/test-library#instrumentationhttp://www.red-bag.com/jcms/index.php/test-library#civilhttp://www.red-bag.com/jcms/index.php/test-library#attachments
  • 8/6/2019 Pds 3d Model Piping Checking

    2/23

    Follow the line up systematically and pay strict attention to details since many accidents are caused by

    seemingly minor items.

    Mark on the engineering flow diagram all the lines, fittings and instrumentation which have been

    checked.

    Make sure that when a modification, addition, elimination or reduction is considered, that is suits its

    purpose, is practical and also economical. When is doubt consult others.

    Use this procedure for a number of items which can not be shown on diagrams. Please note that the

    checklist does not pretend to be complete and under no condition it shall overrule sound judgment.

    Check that the color code has been used correctly.

    Check if construction can build the unit(s) economically as designed.

    Check that start up and shutdown problems have been considered and drain and let-down facilities have

    been provided.

    Check the accessibility for operation, maintenance with mobile equipment and inspection.

    Check location of future equipment.

    Check location of drop out areas.

    Check platforms and ladders.

  • 8/6/2019 Pds 3d Model Piping Checking

    3/23

    Check that access ways and roads provide ample head room for vehicles, mobile equipment, etc.

    required for efficient and safe construction, operation and maintenance of the plant.

    The policy of access to valves, blinds, manways, instruments, etc. shall been established during 3D

    model creation. Check 3D model for consistency of approach.

    Package units are not normally modelled in detail and are usually show as a block. Ensure adequate

    space is available for access and for removal of components of package unit.

    Check location of particularly noisy equipment, valves, etc. in relation to the frequency of visits by

    operating and maintenance personnel to the area.

    Check the space required around fired heaters for soot blowing and decoking and clearance for burner

    removal.

    Check that air fine coolers can be installed or handled during maintenance of plant by means of a mobile

    crane.

    Check that adequate clearance and maintenance access is provided for plug removal tube cleaning,

    motors, V-belts, fans.

    The 3D model shall also indicate junction boxes, cable trays and trunks, switch gears and power

    stations, control room, local panels, analyzer houses.

    Check at final stage the package units, if vendor information has been included in the 3D model (use

    certified vendor drawings of lay out and detailed piping showing all instruments and local panel).

  • 8/6/2019 Pds 3d Model Piping Checking

    4/23

    3. GENERAL SAFETY

    Check that fire hydrants are not positioned at the ends of, or in the line with the ends of, horizontal

    vessels.

    Check elevated equipments and platforms for the proper escape routes. Ensure unobstructed and short

    escape routes at grade.

    Check that ladders and staircases have been installed on the outside of structures. Are staircases

    provided with turnaround landings?

    Does escape traffic have to pass through structures? Check companies and/or governmental regulations

    for safety.

    Check that remote shutdown and valve closing devices are installed at safe locations. Check that

    equipment concerned can be seen from these locations.

    Check for chimney gasp between platforms and/or table tops.

    Check that safety showers and eye baths are located near equipment containing aggressive chemicals

    (e.g. caustic, ADIP, MEA, HCl, h4SO4, etc.).

    Check accessibility of the unit for mobile fire-fighting equipment and rescue work.

    Avoid head bumpers, shin splitters and tripping hazards.

  • 8/6/2019 Pds 3d Model Piping Checking

    5/23

    Check that emergency/smothering steam header block valves are at safe distance from protected

    equipment (e.g. in hydrogen service or near fired heaters). A steam header block valve station could be

    fire shielded, if required, by brick or concrete wall.

    Make sure that operators manipulating drain valves can see the emerging affluent. The required level

    gauges shall be visible and funnels must be provided.

    Check that water trapped in goosenecks cannot be displaced by hydrocarbons.

    Check that utility stations have been provided, including those at the main operation platforms, e.g. for

    the connection of steam lances.

    Check barometric seal height of vacuum for liquids other than water. Ensure that the liquid can be

    drained as well. Important for the design of the structure elevation.

    Check that platforms have been provided at places where work is expected between maintenance stops.

    Check that steam exhaust cannot cause personnel hazards either from spraying droplets of hot water or

    causing icy or wet surfaces.

    Check that steam rings are foreseen at flanges in overhead lines of thermal cracking units and for lines

    in hydrogen service.

    Be alert for equipment supported on continuous platforms when sections of these platforms are

    supported on structures subject to different thermal expansion.

  • 8/6/2019 Pds 3d Model Piping Checking

    6/23

    Check that continuously operating vent stack are higher than the highest nearby structure (within a safe

    distance).

    Check the location of liquid relief valves, since its actual height influences the required set pressure.

    Check the location of toxic gases (h4S, VCM etc.) monitoring points if applicable.

    Check that drains of light hydrocarbons (propane, butane) are protected against freezing (e.g. double

    valves).

    Check that firewalls have been located correctly.

    Check that levers of plug-and ball valves are not hampering operators on walkways or platforms, levers

    shall move in the same plane as the piping lay out.

    Check that steam for purging of lines and equipment (e.g. snuffing steam, emergency steam) is dry,

    provide automatic trap stations with drain assembly upstream of last block valve in steamline.

    Check that process ventlines are routed and oriented to safe locations, (3 meter above highest

    platform), watch nearest platforms and prevailing wind direction.

    Check location of manholes with platforms and ladders in respect to safe escape route.

    In case of location of water cooled equipment at high elevated platforms, check if the normal cooling

    water pressure is suitable for this duty, otherwise a booster pump shall be installed.

  • 8/6/2019 Pds 3d Model Piping Checking

    7/23

    To prevent vacuum in equipment located at high elevations, due to siphon operation of the fluid, install a

    vacuum breaker to suck in air or a process gas.

    4. LINES

    Check that piping entering and leaving the unit is logically grouped together.

    Check that valves, blinds, flushing/drain and instrument connections are properly located. Check

    especially so called manifolds and large control valves. Check in cases where spades are used ISO

    spectacle blinds, that piping system are flexible enough to insert these spades.

    Check that piping subject to thermal expansion is anchored at plot limits.

    Check elevation of overhead piping and horizontal clearance of access and/or walkways.

    Check that start-up/circulation lines are short.

    Check that dead ends have been avoided. Check if system can be flushed and drained.

    Check that vapor lines (inclusive steam) branch off from the top of main lines. Prevent pockets in vapor

    lines. Keep lines sloping to a drum or install drainpoints (driplegs).

    Check that piping subject to thermal expansion is flexible enough. Are supports adequate?

    Check if nozzles and branches on expanding piping are not installed near obstructions, support beams,

    etc. (to avoid ripping off). Are these lines properly anchored. Are stresses on equipment nozzles within

    limits.

  • 8/6/2019 Pds 3d Model Piping Checking

    8/23

    Check for pockets in vapor lines where condensation may occur. Has external heating been applied on

    those pockets which can not be avoided?

    Check that long lines attached to small bore nipples are properly supported to prevent breakage due to

    vibration.

    Check that lines do not pass through table top, but run alongside. If impossible group lines together

    passing via a sleeve.

    Check that dead end sections have been avoided (e.g. in water lines).

    Check that piping has been designed to permit easy drainage, venting, flushing, testing, maintenance,

    insulation, painting.

    Check position of eccentric reducers. Normally straight side on bottom of horizontal lines except in pump

    suction lines where vapor pockets may cause calibration in the pump.

    Check that compressor suction lines slope toward knockout drum.

    Check that small bore cooling water lines branch off from top of the header. (This to prevent plugging).

    Check that stripping steam lines are short and horizontal or sloping from the last valve.

    Ascertain that two phase flow vertical piping has been checked for flow stability.

    Check that hydraulic (water) hammer conditions have been checked.

  • 8/6/2019 Pds 3d Model Piping Checking

    9/23

    Check that all lines have been properly numbered.

    Check that high temperature and special material lines have been stress analyzed.

    Check that gas is prevented from entering cooling water system.

    Check absorber gas feed inlets for pockets near the inlet to avoid absorbent in the gas line.

    Check that piping with instrument connections has been laid so that these connections are easily

    accessible. Check if necessary platforms and walkways have been provided.

    Check anchoring of piping discharging to atmosphere. Pay special attention to screwed piping.

    Check that vacuum equipment steam jets has been hooked up directly to the steam mains, i.e. without

    any intermediate connections which may suck in air. This is not applicable for vacuum pumps.

    Check (for the same reason) that venting of the gas compressor suction piping has been avoided.

    Check all coordinates on piping for correct configuration and clearances.

    Check that service stations have been properly located. Design also for winterizing (water/steam/air in

    one insulated box).

    Check for rotary equipment that suction and discharge piping are properly supported.

    Check clearance between piping and structural steel with fireproofing.

  • 8/6/2019 Pds 3d Model Piping Checking

    10/23

    Check that thermosiphon reboilers have been located such that minimum pipe distances and equal vapor

    distribution are achieved.

    Check required straight piping runs to distributor piping in distillation columns. Only in vertical plains are

    bends allowed within this straight run.

    If a vent is required on an exchanger for periodically purging of noncondensable vapors, this vent valve

    shall be accessible, vent plus line shall be shown on 3D model.

    Check piping arrangements on shell and tube side of exchangers carefully for correct flow of fluids and

    proper operation of exchangers.

    If symmetrical piping hook up is required to exchangers, airfines or double suction of pump, check this

    carefully.

    Keep length of suction piping to pumps to a minimum and prevent pockets.

    Check location of break flanges on piping at shell and tube exchangers and aircoolers to facilitate bundle

    removal.

    Check that number of passes in a heater are shown and if necessary check that piping is symmetrical.

    Check that location of isolating valves and valves of snuffing steam and emergency steam are at 15

    meter distance from the heater at grade and accessible.

    Avoid dead legs in heavy fuel oil lines and waste gas lines.

  • 8/6/2019 Pds 3d Model Piping Checking

    11/23

    In case of steam jacketed sulphur lines provide T-pieces or cross pieces at the end for cleaning the

    sulphur lines by rigging.

    Check location of relief valves and their good accessibility for servicing.

    Check location of local panels for safe operation and good accessibility.

    5. VALVES

    Check that valves in overhead pipe tracks have been avoided to the maximum extent.

    Check that chain operated valves have been avoided where possible.

    Check that all valves are installed with the steam installed with the stem pointing upwards or

    horizontally.

    Check that hand wheels are easily accessible for operation and yet not obstructing walkways or

    platforms.

    Check also steams, especially in open position.

    Check that valves for emergency operations are workable grade level.

    Check that valves that need frequent attention are easily accessible.

    Check valves in vertical lines for possible water traps.

    Check when reduced port valves are installed, that piping is self draining on both sides of the valve.

    Check that hot oil block valves are well accessible in view of fire risk.

  • 8/6/2019 Pds 3d Model Piping Checking

    12/23

    Check that control valve assemblies are located at ground level or on first platform (except when

    required otherwise for process reasons).

    Check that installation of valves outboard of elevated platforms has been avoided.

    Check that valves or double block and bleeders have been installed in utility connections to process

    equipment and lines.

    Check that spring loaded and/or extra block valves have been used where valves may freeze-up when

    draining or sampling.

    Check that process vents and drains are shown.

    Check location /installation of check valves in ditch. lines of pumps or near connection of lines, for

    example connection of condensate lines from traps to condensate collecting header near to the header.

    Check levers of plug-or ball valves, these shall not obstruct walkways, platforms etc. Levers shall move

    in the same plane as the piping lay out.

    6. HEAT EXCHANGERS/REBOILERS

    Check that piping arrangement is acceptable with respect to the removal of shell and channel covers as

    well as the withdrawal of tube bundles.

    Check whether bundles can be pulled and lowered safely from platforms and stacked arrangements

    (obstructions, hydrants).

  • 8/6/2019 Pds 3d Model Piping Checking

    13/23

    Check stacked heat exchangers for the possibility of oil spills on hot equipment beneath it, especially

    during maintenance work.

    Check accessibility to exchangers for maintenance, bundle removal/cleaning, etc.

    For a thermosiphon check reboiler check the elevation difference between draw-off pan and reboiler for

    driving force

    If a vent is required on the exchanger for periodically purging of noncondensable vapors, this vent valve

    shall be accessible. Vent also to be shown on 3D model

    Cold fluid enters the exchanger at the bottom and leaves it from the top

    Check crane access to airfin coolers for maintenance or construction.

    Check symmetrical piping hook-up to several bundles in an airfin cooler or to exchangers in parallel

    operation. Dead legs in capped headers shall be kept to a minimum or be avoided, use elbow ISO tees

    at the end of the header. Pockets in outlet piping of aircooled or water cooled condensers must be

    avoided as well as in the hot vapor bypass lines.

    7. PUMPS AND COMPRESSOR

    Check that flow in suction piping is as smooth as possible

    Check that high points in pump suction lines have been avoided

    Check that valving around pumps is logical and operable

  • 8/6/2019 Pds 3d Model Piping Checking

    14/23

    Check volumes which must be drained when a filter or a pump needs to be opened

    Check that pumps can be safely and easily handled for maintenance

    Pay special attention to spading-off possibilities

    Check that priming facilities are adequate

    Check that facilities have been provided for gradual heating prior to start

    Check hookup of suction line on double suction pump. Piping layout to be as follows for side inlet:

    Straight length from suction flange until bend to be 3D (D = diameter nozzle pipe), no reducer

    allowed.

    In vertical pipe reducer, strainer and valve can be installed.

    For top inlet straight length = 5D if suction line runs in length direction of pump motor and 3D

    if suction line runs in same plane as pumps impeller(s). Upstream of the bend in the suctionline the strainer, valve etc. can be installed.

    Check that pump operating under vacuum are provided with high point vents, which are connected via a

    vent line to the top of suction vessel

    For a vertical pumps no straight length is required.

    If pump handle liquids with temperatures above auto-ignition, this pumps shall be located in safe-areas

    (not underneath pipe rack) and widely spaced from other pumps. Good accessibility for fire fighting is

    required and above pumps a sprinkler system shall be installed

    Piping to compressors. Pockets shall be prevented, lines shall be slope to suction drum and suction line

    shall mostly be steamtraced. Check vendor drawings carefully

  • 8/6/2019 Pds 3d Model Piping Checking

    15/23

    Check all flushing, cooling, quenching requirements of pumps and compressors

    Check that sufficient space is available for removal of filters from strainers

    Suctions lines of pumps to be of minimum length

    Check NPSH of pumps

    If two pumps are parallel operating the piping hookup at suction and discharge side shall be

    symmetrical.

    On reciprocating compressors safety valves must be located upstream of the discharge block

    valve.

    8. VESSELS/COLUMNS

    Check location of vents as well as direction of outcoming streams

    Check positions of drain nozzles. Keep them clear from areas where heavy equipment such as fork lift

    trucks may work

    Check that manways are within reach of hoisting equipment

    Check that instrument tappings and local instruments are readily accessible

    Check that the lines can follow the expansion when heating up/ cooling down. Pay special attention to

    supports on hot respectively cold structures. Check free movement of platforms

    Check that staircases, platforms, ladders etc. are logically located

  • 8/6/2019 Pds 3d Model Piping Checking

    16/23

    Check that the layout of platforms , ladders, piping, relief sets, etc. is in accordance with the specified

    basis for wind and earthquake load calculations

    Check location and elevation of all piping- and instrument nozzles against requisition of equipment and

    drawing

    Check that spectacle blinds or spades are installed (indicated) at the nozzles for pressure test or

    isolation purposes. Normally required with columns

    Stripping steam to the columns shall be dry; install KO pot at grade provided with automatic steam traps

    and drain valve and provide a minimum distance insulated steamline in vertical run without pockets to

    the steam inlet nozzle of the column.

    Check that sufficient space is available for column erection activities

    Check that consideration has been given to loading and unloading of catalysts, packing, internal etc.

    9. FURNACES/BOILERS

    Check that piping does not obstruct observation windows, access doors, header box covers, etc

    Check that space is available for tube withdrawal and cleaning

    Check that piping at burners is arranged so that insertion/removal of lighting torches and burner guns is

    not hampered

    Pay special attention to safety of fuel system:

  • 8/6/2019 Pds 3d Model Piping Checking

    17/23

    Check that heavy fuel and LBF system are sufficiently segregated

    Check that provisions are made to adequately prevent liquid fuels from entering steam and gas

    system

    Are locations of flame arrestors, straight pipe length etc. of low pressure and waste gas in

    accordance with specifications?

    Check that emergency/smothering steam valve manifolds are at safe distance. Steam shall be dry.

    Install upstream of manifold at low point a drain valve and automatic steam trap

    Check that dry emergency steam is available

    Check that :

    Branch off nozzles are positioned on top of main

    Steam line are under continuous slope (no pockets)

    Sufficient steam traps and drain points are provided

    Check that fuel and atomizing steam cocks are within hand reach when looking at the burners through

    the observation windows

    Check that the local emergency shutdown switch is at a safe location

    Check that safety logic (for heater start-up and shut-down) is not located below (vertical) furnace.

    Normally such a logic is located in a local panel at safe distance (15 meter) from a fired heater

  • 8/6/2019 Pds 3d Model Piping Checking

    18/23

    One complete burner hookup shall be shown per heater including all instruments and all provisions for

    safe startup, operation and shutdown of the heater with associated equipment (e.g. fans).

    Check final certified vendor drawings for equipment correctness.

    Check prescribed safety distances, e.g. for example:

    12 meter to catch basins

    15 meter to process equipment exclusive airfin coolers

    22 meter to airfin coolers

    Check that the damper can be operated from grade.

    Check that the flue gas oxygen analyzer is located at grade.

    Check heater or boiler location for maintenance and construction accessibility and also for decoking,

    regeneration or soot blowing activities.

    10. RELIEF SYSTEM

    Check that inlet lines to relief valves are self draining into process equipment.

    Is its proper functioning not hampered by the nature of the process fluid? The allowable pressure drop

    across the inlet line of relief valve is limited to 3% of the set pressure (at maximum capacity). If

    pressure drop is too high, the line size shall be increased.

    Check accessibility of the relief valves for maintenance and inspection. Check if relief valves have been

    installed at proper elevations. Distinguish between valves releasing to atmosphere or relief deader.

  • 8/6/2019 Pds 3d Model Piping Checking

    19/23

    Check pressure relief discharging to atmosphere for safe location and direction.

    Check that discharge pipe is drainable. If so, does drain not impinge on other equipment? Have

    measures been taken to avoid freezing of moisture on relief valve seats in low temperature service?

    Check tail pipes for adequate support against reaction forces.

    Check that the tail end of vent pipe is within the action radius of fire extinguishing equipment. If not,

    has a snuffing steam connection been provided?

    Check that length of piping is minimized for safety relief valves discharging into a closed system.

    Check that outlet line from relief is self draining into flare header. Check if connections are made on top

    of the flare header.

    Check that flare lines have no pockets and that they are sloping to the flare knockout drum.

    The back pressure on the relief valves (calculated during the design) shall be checked with the actual

    layout of the flare system.

    Check destination of outlets from 1 x 1 thermal relief valves to atmosphere or grade for safety.

    In case hooked up to the vessel, check if steamtracing is required to prevent plugging.

    Check locking devices of the valves at inlet/outlet of the relief valves.

    Check that valves with Castell lock system (or other system) are properly installed.

  • 8/6/2019 Pds 3d Model Piping Checking

    20/23

    Check that safety relief valves and inlet/outlet lines adequately supported.

    Check that tail pipes of relief valves require weather protection cap.

    Check that the proper type of the relief valve has been specified, for example in waxy service piston

    type in view of plugging.

    In case of 1 x 1 thermal relief valves, the inlet of the relief valve shall be self-draining to the process

    line, the discharge line can be connected to a collecting header which shall be discharging under slope

    without pockets to a vessel. Check if inlet and outlet lines of relief valves shall be steamtraced.

    11. ELECTRICAL

    Check that cable trunkings are properly located and not obstructed by equipment etc.

    Columns of pipe racks are normally used to install junction boxes for both electrical and instrumentation

    purposes.

    Check that orientation and access is not hampered by location of control valve station, steamtracing

    stations, utility stations or other piping lay-outs.

    12. INSTRUMENTATION

    Check that all instruments are on 3D model and have been correctly tagged.

    Check that instrument cable trunkings are properly routed and in accordance with applicable instrument

    drawings.

    Check that local control panels, main junction boxes, etc. are properly located.

  • 8/6/2019 Pds 3d Model Piping Checking

    21/23

    Check location and accessibility for operation and maintenance of all instruments. Mind removable piping

    on both sides of reactors (swing elbow), here special design is required.

    Check straight length of orifice runs.

    Check clearance above external displacers for removal of floats.

    Check platform clearance around level gauges, control valve stations, relief valve station, especially for

    Camflex type control valves with bypass.

    Show all personnel protection, gas detection points (sniffing points).

    13. CIVIL/STRUCTURAL

    Check that all structures with bracing and pipe racks are shown, inclusive fireproofing.

    Check that all plinths for equipment and structures are shown.

    Check that all table tops are shown.

    Check location of analyzer house(s), if fast loop requirements for correct measurements (samples) will

    be met.

    Check that bracing of steel does not form an obstruction.

    14. ATTACHMENTS

    1. Internal 3D Model Review

    2. Approved 3D Model Revisions from Internal 3D Model Review

    3. Definition of Percentage Completion

  • 8/6/2019 Pds 3d Model Piping Checking

    22/23

    Internal Model Review

    attachment not available ??

    Approved Model Revisions From Internal Model Review

    attachment not available ??

    Definition of Percentage Completion

    The following description is a definition of each percentage complete stage of the piping 3D model.

    Company practice normal practice is to make 3D model reviews at 30, 60, 90 and 100% completion.

    Definitions

    BASIC

    Plot Plan Attached to 3D Models

    Battery limits located

    All major equipment located

    Major structure shown

    Major pipe rack shown

    30% Completion

    Comments from Client BASIC 3D model review incorporated

    Large bore critical process lines studies on the 3D model

    Piping studies 15 - 20% complete

    Location of unit access ways for mobile maintenance and fire fighting equipment shown

    Comments from Client for operation and maintenance incorporated

    60% Completion

    Comments from Client 30% 3D model review incorporated

    Ready for Clients comments for operation and maintenance

    All equipment located

    Piping studies 70% completed

    All large bore process lines and utility mains shown

  • 8/6/2019 Pds 3d Model Piping Checking

    23/23

    In-line instruments shown for lines installed

    Instruments on equipment located. Local panels shown

    Main cable trays installed

    All structures (concrete and steel), ladders and platforms shown

    All pipe racks shown

    90% Completion

    Comments from Client 60% 3D model review incorporated

    All piping shown

    Safety showers, eye baths or jump-in baths shown

    Piping studies 100% complete

    Instrumentation, including cable trays 100% complete. Electrical cable trays 100% complete

    All major pipe supports located

    100% Completion

    Clients final comments from 90% 3D model review incorporated

    3D model updated to latest issue of PEFSs, PEUFSs, line tables, arrangement drawings and

    final equipment drawings

    All sprinkler mainheaders shown