Mindarie Mineral Sands Project: A New Beginning
AJM 14th Annual Mineral Sands Conference
4-5 March 2014 Melbourne, VIC
Patrick Mutz
CEO Murray Zircon Pty Ltd
![Page 2: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/2.jpg)
Murray Zircon Pty Ltd
Copyright Murray Zircon 2
Australia’s newest mineral sands miner.
![Page 3: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/3.jpg)
Copyright Murray Zircon 3
3/4/2014
Murray Zircon in Australia
South
Australia
Murray Zircon was established in June 2011 as a joint venture to
redevelop the Mindarie Mineral Sands Project in South Australia
![Page 4: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/4.jpg)
Copyright Murray Zircon 4
3/4/2014
Mindarie Mineral Sands Project
Adelaide
Mindarie
Mindarie Project is
located 150km east of
Adelaide.
![Page 5: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/5.jpg)
Murray Zircon Pty Ltd
Copyright Murray Zircon 5
Murray Zircon joint venture majority shareholder: Guangdong Orient Zirconic Industry Science and Technology Co., Ltd. (Orient Zirconic), a listed company in China (SHE: 002167).
Joint venture minority shareholder: Initially, Australian Zircon NL, the former owner/operator of the Mindarie Project.
Australian Zircon’s shareholding now owned by private investors.
Murray Zircon also holds an exploration tenement portfolio covering more than 11,000 km² within the Murray Basin in South Australia.
![Page 6: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/6.jpg)
Location of Murray Zircon Exploration Tenements
Copyright Murray Zircon 6
![Page 7: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/7.jpg)
Mindarie Mineral Sands Project
Copyright Murray Zircon 7
Redevelopment of the Mindarie Project was completed in 2012 with wet commissioning in December.
Mining and processing operations more or less reached steady-state and name-plate capacity in October 2013.
The product is heavy mineral concentrate (HMC) which is exported to China for separation into Zircon, Ilmenite and Rutile.
![Page 8: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/8.jpg)
Mindarie Mineral Sands Project
Copyright Murray Zircon 8
Current JORC Reserves are 58.1 million tonnes at 4.3% THM.
15 year mine-life
Active exploration programme.
JORC Resources recently increased by 58% to 270 million tonnes at 2.6% THM.
![Page 9: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/9.jpg)
22/03/2012
Copyright Murray Zircon 9
Murray Zircon Pty Ltd
Orient Zirconic (China)
Orient Zirconic (Australia)
100%
Private Investors
Murray Zircon Pty Ltd
35% 65%
100%
Mindarie Project Exploration Tenements
100%
WIM 150 Project
Joint Venture
Partner
![Page 10: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/10.jpg)
Orient Zirconic (China)
Guangdong Orient Zirconic Industry Science and Technology Co., Ltd (OZC), is one of China’s leading zircon processing companies and is headquartered at Shantou in Guangdong Province (about 480km northeast of Hong Kong).
OZC has the most comprehensive range of zirconium products in the world, including zirconium dioxide, zirconium oxychloride, fused zirconia, zirconia structural ceramic as well as zirconium sponge and other products.
OZC is listed on the Shenzhen Stock Exchange (Code:002167) with a market capitalisation approx. RMB 4.7 Billion (A$850 million*).
Copyright Murray Zircon
10
*Share price and exchange rate on 31/12/2013.
![Page 11: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/11.jpg)
Copyright Murray Zircon 11
3/4/2014
OZC Headquarters & Branch Locations in China
Chaoyang Branch, Liaoning
Headquarters, Shantou, Guangdong
Leiyang Branch, Hunan
Lechang Branch, Guangdong
Yanhong Branch, Shantou, Guangdong
![Page 12: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/12.jpg)
Copyright Murray Zircon 12
3/4/2014
![Page 13: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/13.jpg)
New majority shareholder in March 2013;
Formerly Company Chairman – Mr Chaodian Chen at 30.8%
Now CNNC subsidiary at 15.7%
CNNC (China National Nuclear Corporation ) is the large state-owned enterprise under the direct management of the central government.
January 2014 - OZC announced the acquisition of Zhejiang Zircon Valley Sci &Tech Pty Ltd; one of China’s largest producers of zirconium oxychloride for export.
February 2014 - OZC announced a merger with Hainan Wensheng High-Tech Materials Co., Ltd (Wingsheng or Winsheen); China’s biggest HMC importer and separator.
Copyright Murray Zircon 13
3/4/2014
Orient Zirconic - Recent Developments
![Page 14: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/14.jpg)
Mindarie Project – History
The Mindarie Project was originally developed by Australian Zircon Limited (ASX:AZC) in 2006.
The mine commenced operations in October 2007 following the construction of a Primary Concentrator Plant (PCP) and Mineral Separation Plant (MSP).
In October 2009 the project was placed on care & maintenance.
Copyright Murray Zircon 14
PCP
MSP
![Page 15: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/15.jpg)
Mindarie Project – Redevelopment
As part of its strategy to redevelop Mindarie, Murray Zircon proactively assumed responsibility for all remaining rehabilitation liability over previously mined areas.
Rehabilitation works commenced in August 2011 and were completed in March 2012.
At the same time, the Company initiated refurbishment of the PCP and associated wet plant facilities in October 2011.
The Company also submitted a Program for Environmental Protection and Rehabilitation (PEPR) to the South Australian Department of Manufacturing, Innovation, Trade, Resources and Energy (DMITRE), for approval to resume mining.
Copyright Murray Zircon 15
![Page 16: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/16.jpg)
Rehabilitation Works
Phased Rehabilitation Milestones
Overburden Completed December 2011
Sub-soil replacement Completed February 2012
Top-soil replacement Completed March 2012
Cropping Completed April/May 2012
Aerial Photo: March 2011
Area 1 Area 2
Area 3
Area 6a
Area 4 Area 5
![Page 17: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/17.jpg)
Copyright Murray Zircon 17
3/4/2014
Rehabilitated Land
![Page 18: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/18.jpg)
Mindarie Project – Redevelopment
Through its successful rehabilitation efforts, positive relationships were built with the local community, affected landowners as well as the government through DMITRE.
NET RESULT?
DMITRE approved Murray Zircon’s PEPR application and issues a licence to resume mining in April 2012;
less than 1 year from the formation of the company.
Copyright Murray Zircon 18
![Page 19: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/19.jpg)
Mindarie Redevelopment & Commissioning
Primary Concentrate Plant refurbishment/upgrade activities completed in August 2012.
Mining contract and product logistics contract finalised in September 2012.
A newly purchased Mining Slurry Unit was installed and a new slurry pumping system was completed in November 2012.
Resumption of mining commenced in October 2012 and wet commissioning of the Slurry Unit and PCP began in December.
First HMC product was exported before the end of December.
Copyright Murray Zircon 19
![Page 20: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/20.jpg)
Highlights of Operations
Mining at Mindarie is via dry, open-cut method using scrapers to remove overburden and dozers to mine the ore.
Typical mineral strands in the area are 150-200m wide, 10-20m deep and up to 13km long.
Mining/processing design capacity is 500 dry tonnes per hour ore feed to produce 10-12K tonnes of HMC per month.
Ore is slurried with water at the in-pit Slurry Unit and the slurry is pumped 3-8km to the Primary Concentration Plant (PCP).
At the PCP, the heavy minerals are removed with spiral classifiers to produce a Heavy Mineral Concentrate containing typically 80-90% heavy minerals.
Copyright Murray Zircon 20
![Page 21: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/21.jpg)
Copyright Murray Zircon 21
3/4/2014 Ore mining by dozer push method
Overburden removal with scrapers
Ore
Slurry
Unit
![Page 22: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/22.jpg)
Highlights of Operations
Only Heavy Mineral Concentrate (HMC) is produced at Mindarie.
HMC is transported from Mindarie by truck approximately 200km to the port in Adelaide at 7-10 B-Double trucks per day.
Transport by train is also an option but is not used at this time.
At the port, HMC is currently loaded into standard shipping containers with liners for export to China.
Bulk shipping is also an option but is not used at this time.
In China the HMC is separated into zircon and various titanium minerals.
OZC’s internal demand for zircon will support full production from the Mindarie project.
Copyright Murray Zircon 22
![Page 23: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/23.jpg)
Copyright Murray Zircon 23
3/4/2014
HMC Storage Pad
![Page 24: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/24.jpg)
Mindarie Project – Value Adding
Vertical integration strategy: secure demand and secure supply;
• Allows opportunity for synergism with downstream processing to maximize the recoverable mineral and value.
Efficient mining and processing operations targeting superior mineral recovery at the lowest possible cost.
Leveraging tightly scheduled ‘moving hole’ mining method to control the mining costs and achieve rapid/effective rehabilitation.
Incorporating automation of pumping and processing facilities to improve production efficiencies and maximise production rate.
Iterative mine optimization to minimise strip ratio and maximise total minable reserves.
Copyright Murray Zircon 24
![Page 25: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/25.jpg)
Copyright Murray Zircon 25
3/4/2014
Mineral Reserves and Resources
% %
Million
Tonnes
Total
Heavy
Minerals
Slimes Zircon
%
Leucoxene
%
Rutile
%
Ilmenite
%
Proved Reserves 24.0 4.4 10.8 23.9 6.3 5.1 62.5
Probable Reserves 34.1 4.2 11.1 19.3 6.5 4.6 66.4
Total Reserves 58.1 4.3 11.0 21.2 6.4 4.8 64.8
% %
Million
Tonnes
Total
heavy
minerals
Slimes Zircon
%
Leucoxene
%
Rutile
%
Ilmenite
%
Measured Resources 39.5 3.6 10.4 21.4 5.8 5.1 64.4
Indicated Resources 126.2 3.1 10.1 17.8 6.6 4.6 66.3
Inferred Resources 5.3 3.3 9.0 17.0 5.1 3.9 67.2
Total Resources - OCT 2012 171.0 3.2 10.1 18.6 6.4 4.7 65.9
NEW Indicated Resources 73.4 1.4 10* 9.0 30.5
NEW Inferred Resources 25.9 2.0 10* 22.7 42.1
Total Resources - OCT 2013 270.3 2.6 10* 16.4 54.0
* - estimated
Classified Resource Estimates at variable total heavy minerals cut-off grades
16.9
11.3
12.7
Classified reserves estimates at variable total heavy minerals cut-off grade
Proportion of source material
within heavy mineral component
Proportion of source material
within heavy mineral component
![Page 26: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/26.jpg)
Copyright Murray Zircon 26
3/4/2014
Typical Mining Equipment
![Page 27: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/27.jpg)
Copyright Murray Zircon 27
3/4/2014 Slurry Pumping Skid
![Page 28: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/28.jpg)
Copyright Murray Zircon 28
3/4/2014 Primary Concentration Plant
![Page 29: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/29.jpg)
Copyright Murray Zircon 29
3/4/2014
Mining Camp
![Page 30: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/30.jpg)
Summary
Through Murray Zircon, Orient Zirconic has made a significant investment in the mining community in South Australia.
Murray Zircon has effectively demonstrated its commitment to secure and uphold its social licence to operate;
Completed past mine rehabilitation liability and successfully built positive and effective community and regulatory relationships.
The company has successfully completed redevelopment and commissioning of the Mindarie Project and is now South Australia’s newest mineral sands miner and the only active mining operation under majority Chinese ownership.
Through its vertical integration strategy, Murray Zircon and Orient Zirconic will strive to be a successful, long-term supplier of zircon and titanium dioxide into the global markets.
Copyright Murray Zircon 30
![Page 31: Patrick Mutz, Murray Zircon Pty Ltd: Mindarie Mineral Sands Project: A new beginning](https://reader035.fdocuments.in/reader035/viewer/2022081800/54c02c184a79591c638b4586/html5/thumbnails/31.jpg)
For further information:
Website: www.murrayzircon.com.au Email: [email protected]