PARK PROJECTS

Page 3: pARKs ANd LANdsCApING - City of Pasadena

0000012,272,07512,272,075Robinson Park - Recreation Center Renovation Project (78043)1

000003,400,0003,400,000Desiderio Park - Development of New Park (78054)2

700,0000000200,000900,000Installation of Restroom Building at Desiderio Park - ConstructionPhase (78059)

3

0000210,0000210,000Citywide Park Asset Assessment (78080)4

200,0000000596,000796,000Annandale Canyon Open Space Trail Access, Improvements andPark Expansion (78240)

5

1,313,075000100,0001,386,0912,799,166Citywide Sports Facilities Improvements and Installations (78044)6

0000265,000521,000786,000Hamilton Park - Various Projects (78069)7

0000300,0007,267,1237,567,123Restroom Bldgs (Replace or Construct)-Jefferson, McDonald,Allendale, Victory, Grant, Villa, Singer, Eaton-Blanche, Memorial,Hamilton Parks (78038)

8

0000250,0000250,000Court Repairs at Eaton Blanche and McDonald Park - ConstructionPhase (78082)

9

00000100,000100,000Lamanda Park Library Pocket Park - Concept Study and Design(78078)

10

00000200,000200,000Neighborhood Park Development - Union/El Molino - Concept Study(78079)

11

0000200,0000200,000Union St./Oak Knoll Ave. Pocket Park - Concept Study and Design(78083)

12

0000750,0000750,000Installation of Security Lights at Jefferson, Gwinn and SunnyslopePark (78902)

13

454,40000002,745,6003,200,000Central Park - Implement Master Plan (78461)14

840,00000001,000,0001,840,000Villa Parke Community Center Improvements (78061)15

800,00000000800,000Pickleball Courts - Design and Construction16

300,00000000300,000Robinson Park Recreation Center Pool and Pool Building Renovation- Design Phase

17

36,370,364 4,607,4750002,075,00029,687,889Total

FY 2019 - 2023 Capital Improvement Program

Priority

TotalEstimated

CostsDescription

AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and Beyond

Parks and Landscaping - Park Projects

9 - Summary

Page 4: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondRobinson Park - Recreation Center Renovation Project78043

Project No.

1

000001,312,1931,312,193Community Development Block Grant

000001,000,0001,000,000General Fund

000001,182,1251,182,125Housing-Related Parks Program Grant

000002,638,7572,638,757Residential Impact Fee

000006,000,0006,000,000Section 108 HUD Loan

00000139,000139,000Tournament of Roses

12,272,075 0000012,272,075Total

DESCRIPTION: This project provides for substantial demolition and reconstruction of the RecreationCenter's approximately 9,000 square foot multipurpose room, administrative offices, kitchen, open courtyard, restrooms and conference room. This project will also provide for an approximately 4,900 squarefoot addition of fitness and dance rooms, storage and common areas, and an intensive structural upgradeof the Recreation Center's existing 7,300 square foot gymnasium. The completed facility will be fullyaccessible, include energy efficient lighting, technology and security upgrades, drought tolerantlandscaping, and meet LEED Silver design standards.

JUSTIFICATION: This park is one of the most heavily used facilities in the City of Pasadena, servingapproximately 400 users a day. The existing recreation center is a former mortuary building that wasadapted for reuse. The size, layout and functionality of the interior spaces are inadequate, some of therooms are undersized, and the center can no longer meet the needs of the community.

SCHEDULE: Construction will be completed in FY 2019.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with the Public Facilities Element of theGeneral Plan by providing for more efficient development and utilization of public facilities. It is alsoconsistent with Land Use Element Policy 2.2 on Urban Parks by continuing and completing efforts toenhance Robinson Park.

IMPACT ON THE NORTHWEST: This park is located in Northwest Pasadena which is an area that hasbeen targeted for revitalization.

HISTORY: This project was created in 2002 and fully funded in FY 2018.

Robinson Park Community Center

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Robinson Park - Recreation Center Renovation Project78043

9.1 Responsible Department:Public Works Department

Page 5: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondDesiderio Park - Development of New Park78054

Project No.

2

0000030,00030,000Inclusionary Housing Trust Fund

00000500,000500,000Proposition A (Parks) - Cities Excess Funds

000002,870,0002,870,000Residential Impact Fee

3,400,000 000003,400,000Total

DESCRIPTION: This project provides for the development of 3.8 acres of new park land located at theformer Desiderio Army facility. The City acquired the facility in 2013. This location will be a passiveneighborhood park featuring a meadow-type landscape with limited site amenities including playequipment and furnishings.

JUSTIFICATION: The Desiderio property was specifically acquired to provide a neighborhood park for thesurrounding residential area. The creation of this park will add to the City's overall park acreage andprovide neighborhood park recreational opportunities where none currently exist.

SCHEDULE: Construction will be completed in FY 2019.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with one of the core principals of theOpen Space, Recreation and Parks element which is "Pasadena will be a City that actively creates newgreen spaces by promoting creative partnerships with local and regional agencies, as well as privateinstitutions in order to provide access to and development of both traditional and non-traditional parks,cultural and recreational opportunities, and open spaces."

SPECIAL CONSIDERATION: A new restroom was added to the scope of work for this project during theentitlement process. The park restroom project is a separate project and will be designed after communityoutreach on this element is completed (see page 9.3).

HISTORY: This project was created and received initial funding in FY 2014. In FY 2018, the project wasfully funded.

Desiderio Park - Site Rendering

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Desiderio Park - Development of New Park78054

9.2 Responsible Department:Public Works Department

Page 6: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondInstallation of Restroom Building at Desiderio Park -Construction Phase

78059

Project No.

3

00000200,000200,000Residential Impact Fee

700,00000000700,000Unfunded

900,000 700,0000000200,000Total

DESCRIPTION: This project provides for the design and construction of a restroom building at DesiderioPark. Desiderio Park is 3.8 acres of new park land located in southwest Pasadena adjacent to the LowerArroyo at the former Desiderio Army facility. The City acquired the facility in 2013. This location will be apassive neighborhood park featuring a meadow-type landscape with limited site amenities including playequipment and furnishings.

JUSTIFICATION: The Desiderio property was specifically acquired to provide a neighborhood park for thesurrounding residential area. A restroom building will add to the functionality and use of the park.

SCHEDULE: Construction will begin when funding is identified.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with the Green Space, Recreation andParks Element Policy 8.3 by ensuring Neighborhood Parks have adequate facilities, service, and size.Additionally, it is consistent with Policy 10.3 by ensuring Pasadena’s green spaces have a qualityappearance that instills pride in the surrounding neighborhood and the City at large. The project is alsoconsistent with Land Use Element Policy 5.5 by the City's promotion of architectural and designexcellence in buildings, open space and urban design and the discouragement of poor qualitydevelopment.

HISTORY: This project was created in FY 2016 and initially funded in FY 2017. Design was completed inFY 2018.

Desiderio Park - Site Rendering

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Installation of Restroom Building at Desiderio Park - Construction Phase78059

9.3 Responsible Department:Public Works Department

Page 7: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondCitywide Park Asset Assessment78080

Project No.

4

0000210,0000210,000Residential Impact Fee

210,000 0000210,0000Total

DESCRIPTION: This project provides for the development of a park asset assessment protocol and aninitial inventory and conditions assessment of park assets citywide.

JUSTIFICATION: Periodic assessment of various park assets occurs on an as-needed basis or whenpotential projects are proposed to staff. Establishing a regular assessment program will allow staff toidentify, prioritize, and anticipate maintenance and replacement of park components and provide a meansto respond to public suggestion or inquiry.

SCHEDULE: The park asset assessment will begin in FY 2019.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with the Green Space, Recreation andParks Element, Policy 8.3 (Neighborhood Parks have Adequate Facilities, Service, and Size) by evaluatingif parks are offering the facilities and services necessary in their specific location and neighborhood, andPolicy 8.5 (Recreation Needs) by providing recreation facilities for those who live and work in Pasadena.

IMPACT ON THE NORTHWEST: Portions of this project are located in Northwest Pasadena, which is anarea that has been targeted for revitalization.

HISTORY: This project was created and fully funded in FY 2019.

McDonal Park Play Equipment

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Citywide Park Asset Assessment78080

9.4 Responsible Department:Public Works Department

Page 8: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondAnnandale Canyon Open Space Trail Access,Improvements and Park Expansion

78240

Project No.

5

00000150,000150,000Proposition A (Parks) 1992

00000446,000446,000Residential Impact Fee

200,00000000200,000Unfunded

796,000 200,0000000596,000Total

DESCRIPTION: This project provides for trail construction, trailhead improvements, a small parking lot,and accessibility improvements at the Annandale Canyon park. The acquisition of three additional parcelshas expanded the footprint of the park. Other improvements include trail and interpretive signs, and smallsite amenities.

JUSTIFICATION: In 2009, the City of Pasadena purchased approximately 24.3 acres of land known asthe Annandale Canyon Estates for public open space including public access trails. This project willprovide for the trail development allowing the public safe access to this open space area.

SCHEDULE: Planning and design will be completed in FY 2019.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with Green Space, Recreation andParks Element Objective 2 by recognizing the importance to Pasadena of the history, cultural resources,and unique character of the Arroyo Seco, and conserving and enhancing these assets. Also, the project isconsistent with Objective 5 by acknowledging and enhancing Pasadena’s important relationship with theAngeles National Forest and other regional trail systems.

HISTORY: This project was created and initially funded in FY 2010. In FY 2015, three additional parcelswere acquired.

Annandale Canyon Park Area

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Annandale Canyon Open Space Trail Access, Improvements and Park Expansion78240

9.5 Responsible Department:Public Works Department

Page 9: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondCitywide Sports Facilities Improvements andInstallations

78044

Project No.

6

0000018,92518,925Pasadena Community Foundation Grant

0000100,0001,367,1661,467,166Residential Impact Fee

1,313,075000001,313,075Unfunded

2,799,166 1,313,075000100,0001,386,091Total

DESCRIPTION: This project provides for renovations and new installations of sports fields and sportscourts. Field renovations may include soil replacement, drainage and irrigation work, improved turf, andsupporting infrastructure renovations. Court renovations may include paving and fencing refurbishment orreplacement, player and spectator amenities, and supporting infrastructure renovations. Renovations orinstallations are planned for the following facilities:

FieldsBrenner (softball field) - COMPLETED 50,000Villa Parke (softball field) - COMPLETED 246,083Washington (softball field) - COMPLETED 96,083Jefferson (multi-use field) 150,000Victory (4 multi-use fields) 400,000McDonald (multi-use field) 65,000Grant (softball field and fence) 215,000CourtsLa Pintoresca (basketball court, skate park & fence) 95,000Brookside (tennis courts & fence) - COMPLETED 480,000Grant (tennis court fence & basketball court) 242,000Robinson (basketball court) 300,000Brenner (basketball court & fence) 240,000Allendale (tennis court & fence) 100,000Villa Parke (basketball court) 35,000 Eaton Blanche (tennis & basketball courts) 25,000Citywide court painting & misc. refurbishment 60,000

TOTAL 2,799,166

JUSTIFICATION: Over their service life, sports facilities eventually wear to the point where completerefurbishment is necessary and ongoing maintenance efforts are no longer effective to maintain safe,playable conditions. For fields, overly compacted soils result in inconsistent surface slopes that affectsafety and reduce the playability of a field, unhealthy turf due to lack of available nutrients within thecompacted soil, and storm water and irrigation drainage issues such as poor drainage and puddles, whichcontribute to reduced field availability. For courts, paving cracks or heaves over time can affect safety andplayability, fences wear or are damaged beyond reasonable repair, and amenities such as player benches

Brenner Park

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Citywide Sports Facilities Improvements and Installations78044

9.6 Responsible Department:Public Works Department

Page 10: pARKs ANd LANdsCApING - City of Pasadena

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Citywide Sports Facilities Improvements and Installations78044

or spectator seating needs replacement. Also, from time to time, certain recreational sports gain popularityand as a result require a dedicated court or field rather than sharing space with a different sport.

SCHEDULE: In FY 2019, tennis and basketball court repairs at Grant Park will be completed. Design ofrenovations for fields at Jefferson, Victory and McDonald Park and courts at La Pintoresca, Robinson,Brenner, Allendale and Villa Parke will also be completed.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with the Green Space, Recreation andParks Element Policy 6.9 by continuing to improve maintenance of parkland and recreation facilitiesthroughout Pasadena.

IMPACT ON THE NORTHWEST: A portion of this project is located in Northwest Pasadena which is anarea that has been targeted for revitalization.

SPECIAL CONSIDERATION: The total estimated project cost is based on the scope of the project andknown factors at inception. Project cost and schedule can be impacted by site analysis and evaluation ofexisting sub-surface conditions, community input, and commission reviews.

HISTORY: This project was created and received initial funding in FY 2013. Brenner Park softball fieldwas completed in FY 2013. Villa Parke and Washington Park softball fields were completed in FY 2014.The scope of this project changed in FY 2016 to include sports courts and again in FY 2018 to includenew installations. In FY 2018, resurfacing of the tennis courts and repair of the fencing at Brookside Park,and design at Grant, McDonald and Eaton Blanche park was completed.

9.6 Responsible Department:Public Works Department

Page 11: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondHamilton Park - Various Projects78069

Project No.

7

0000265,000521,000786,000Residential Impact Fee

786,000 0000265,000521,000Total

DESCRIPTION: This project provides for various improvements at Hamilton Park, a 6.4 acre communitypark built in the early 1950s. It is located on a water reservoir in a single-family residential neighborhoodthat is home to many families with children. The recreation facilities were designed for moderate use levelsthat have continually increased over the years. Recreational facilities include baseball diamonds, tenniscourts, basketball and volleyball courts, a large multi-purpose playing field, and children's play areas.Planned projects for this park include:

Phase IPerimeter pathway around turf area of the park 100,000Activity striping on existing concrete pad 30,000Parking lot improvements 30,000Replacement fence along parking lot edge 30,000Phase IIPicnic area improvements 20,000Replacement tennis court fence 200,000Baseball backstop replacement 276,000Shade covering for existing bleachers 100,000

TOTAL 786,000

JUSTIFICATION: The listed improvements are needed for the following reasons: perimeter path - providean ADA-accessible route to the ballfields and a recreational loop for all users; activity striping - provide avariety of recreational uses in an area of the park not currently utilized; picnic area and parking lotimprovements - provide improved accessibility and needed rehabilitation; fence improvements - replace asection of existing fence to match the design style used elsewhere in the park; tennis court fence -reached the end of its useful life; backstops - worn and inadequate to contain foul balls within the park;and shade coverings for the bleachers - trees cannot be effectively placed because of the reservoir.

SCHEDULE: In FY 2019, construction of phase I and design of phase II will be completed.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with the Public Facilities Element of theGeneral Plan by providing for more efficient development and greater utilization of public facilities. It isalso consistent with the Land Use Element Policy 2.1 on Neighborhood Parks by enhancing parks inresidential areas.

HISTORY: This project was created in FY 2011 and initially funded in FY 2015 as a replacement forproject number 78721 which was created in FY 1993 and initially funded in FY 2007. Prior work for project

Hamilton Park - 3680 Cartwright St.

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Hamilton Park - Various Projects78069

9.7 Responsible Department:Public Works Department

Page 12: pARKs ANd LANdsCApING - City of Pasadena

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Hamilton Park - Various Projects78069

78721 included planning of the ball-field backstops and tennis court fencing, completed in FY 2008 andinstallation of the drainage system, completed in FY 2010. In FY 2019, this project was fully funded.

9.7 Responsible Department:Public Works Department

Page 13: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondRestroom Bldgs (Replace or Construct)-Jefferson,McDonald, Allendale, Victory, Grant, Villa, Singer,Eaton-Blanche, Memorial, Hamilton Parks

78038

Project No.

8

000002,5002,500Private Capital

00000132,236132,236Proposition 12 (Parks)

0000030,50030,500Proposition 40 - Per Capita

0000056,35656,356Proposition A (Parks) 1992

0000300,0006,848,5317,148,531Residential Impact Fee

00000152,000152,000State of CA - Roberti Z-Berg Harris Grant

0000045,00045,000Tournament of Roses

7,567,123 0000300,0007,267,123Total

DESCRIPTION: This project provides for the replacement of restrooms at the parks listed below. Site conditions atsome parks will necessitate additional work beyond replacement of the building.

Hamilton - COMPLETED Jefferson - COMPLETED McDonald - COMPLETED Singer - COMPLETED Villa Parke - COMPLETED Allendale - COMPLETED Memorial - COMPLETED Grant - COMPLETED Eaton-Blanche - COMPLETED Victory

JUSTIFICATION: The existing restrooms are deteriorated, expensive, and difficult to maintain. Thecondition of the facilities is substandard and some of the restrooms do not comply with State and Federalaccessibility regulations.

SCHEDULE: In FY 2019, construction of the restroom at Victory Park and improvements at Victory ParkCommunity Center will be completed.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with the Land Use Element Policy 2.1 onNeighborhood Parks by enhancing parks in residential areas. It is also consistent with the Public Facilitiesof the General Plan by encouraging a high level of maintenance and upgrading of existing facilities toensure public safety.

SPECIAL CONSIDERATION: The total estimated project cost is based on the scope of the project and

New Restroom at McDonald Park

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Restroom Bldgs (Replace or Construct)-Jefferson, McDonald, Allendale, Victory, Grant, Villa, Singer, Eaton-Blanche, Memorial, HamiltonParks

9.8 Responsible Department:Public Works Department

Page 14: pARKs ANd LANdsCApING - City of Pasadena

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Restroom Bldgs (Replace or Construct)-Jefferson, McDonald, Allendale, Victory, Grant, Villa, Singer, Eaton-Blanche, Memorial, HamiltonParks

known factors at inception. Project cost and schedule can be impacted by site analysis and evaluation ofexisting sub-surface conditions, community input, and commission reviews. In FY 2018, this projectreceived $45,000 in Tournament of Roses Community Support Gift funds for additional improvements tothe Victory Park Community Center.

HISTORY: This project was created, received initial funding in FY 2004 and was fully funded in FY 2019.In FY 2008, the restroom at Hamilton Park was completed. In FY 2009, the restrooms at Jefferson Parkand McDonald Park were completed. In FY 2010, the restrooms at Singer Park and Villa Parke werecompleted. In FY 2014, the restrooms at Allendale Park and Memorial Park were completed. In FY 2016,the restroom at Grant Park was completed. In FY 2017, the restroom at Eaton-Blanche Park wascompleted.

9.8 Responsible Department:Public Works Department

Page 15: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondCourt Repairs at Eaton Blanche and McDonald Park -Construction Phase

78082

Project No.

9

0000250,0000250,000Residential Impact Fee

250,000 0000250,0000Total

DESCRIPTION: This project provides for the renovation of basketball, tennis and handball courts at EatonBlanche and McDonald Park. Renovations will include: resurfacing and striping; fencing repairs; installingseat wall at basketball courts; and improving drainage at McDonald Park basketball court.

JUSTIFICATION: Over their service life, sports facilities eventually wear to the point where completerefurbishment is necessary and ongoing maintenance efforts are no longer effective to maintain safe,playable conditions. For courts, paving cracks over time and can affect safety and playability, fences wearor are damaged beyond reasonable repair, and amenities such as player benches or spectator seatingneeds replacement. Also, from time to time, certain recreational sports gain popularity and as a resultrequire a dedicated court or field rather than sharing space with a different sport.

SCHEDULE: Construction will be completed in FY 2019.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with the Green Space, Recreation, andParks Element Policy 6.9 by continuing to improve maintenance of parkland and recreation facilitiesthroughout Pasadena.

HISTORY: This project was created and fully funded in FY 2019. The design phase of this project wascompleted as part of project 78044 - Citywide Sports Facilities Improvements and Installations.

Eaton Blanche Park Basketball Court

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Court Repairs at Eaton Blanche and McDonald Park - Construction Phase78082

9.9 Responsible Department:Public Works Department

Page 16: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondLamanda Park Library Pocket Park - Concept Studyand Design

78078

Project No.

10

00000100,000100,000Residential Impact Fee

100,000 00000100,000Total

DESCRIPTION: This project provides for design and improvements to the Lamanda Park Library groundsthat would allow the area to function as a pocket park.

JUSTIFICATION: The Lamanda Park Branch Library is located in East Pasadena in an identified park“gap” area. The library grounds are suitable for use as passive recreational space.

SCHEDULE: Design will be completed in FY 2019.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with Land Use Element Policy 2.8(Equitable Distribution of Community Devices and Amenities) by ensuring that parks and recreationfacilities, community services, and amenities are equitably distributed and accessible throughout the City;Policy 2.13 (Parks) by maintaining existing and developing new parks and recreational facilities withinwalking distance of residents, supporting healthy lifestyles. It is also consistent with Green Space, Parksand Recreation Element Policy 6.8 (Pocket Parks) by identifying and acquiring land for the establishmentof small urban green spaces (pocket parks) in strategic locations within the City. The spaces may beavailable for all types of uses, depending on the unique qualities of the space, the neighborhood location,and the desires of surrounding residents; and Policy 8.2 (Identify “gaps” in Service Areas) by identifyingresidential areas where there are gaps in parks, open space, or recreation services and exercisingcreative means to fill these gaps.

SPECIAL CONSIDERATION: The total estimated project cost will be determined after the concept studyis completed. The final budget can be impacted by site conditions, community input, and commissionreviews.

HISTORY: This project was created in FY 2017 and fully funded in FY 2018.

Lamanda Park Library - 140 S. Altadena Dr.

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Lamanda Park Library Pocket Park - Concept Study and Design78078

9.10 Responsible Department:Public Works Department

Page 17: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondNeighborhood Park Development - Union/El Molino -Concept Study

78079

Project No.

11

00000200,000200,000Residential Impact Fee

200,000 00000200,000Total

DESCRIPTION: This project provides for the design of a 0.8-acre neighborhood park at the northeastcorner of Union Street and El Molino Avenue by converting an existing City parking lot into park space.

JUSTIFICATION: The Union/El Molino site is ideally located to address a park “gap” area in the CentralDistrict and is of sufficient size to create a neighborhood park.

SCHEDULE: Planning will continue in FY 2019.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with Land Use Element Policy 2.8(Equitable Distribution of Community Devices and Amenities) by ensuring that parks and recreationfacilities, community services, and amenities are equitably distributed and accessible throughout the City;and Policy 2.13 (Parks) by maintaining existing and developing new parks and recreational facilities withinwalking distance of residents, supporting healthy lifestyles; and Policy 10.12 (Urban Open Spaces) bypreserving and developing urban open spaces such as landscaped parklets, paseos, courtyards, andcommunity gardens ensuring adequate public access to these opens spaces. The project is alsoconsistent with the Green Space, Parks and Recreation Element Policy 6.8 (Pocket Parks) by identifyingand acquiring land for the establishment of small urban green spaces (pocket parks) in strategic locationswithin the City and Policy 8.2 (Identify “gaps” in Service Areas) by identifying residential areas where thereare gaps in parks, open space, or recreation services and exercising creative means to fill these gaps.

SPECIAL CONSIDERATION: The total estimated project cost will be determined after the concept studyis completed. The final budget can be impacted by site conditions, community input, and commissionreviews.

HISTORY: This project was created in FY 2017 and fully funded in FY 2018.

Parking at El Molino Ave. and Union St.

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Neighborhood Park Development - Union/El Molino - Concept Study78079

9.11 Responsible Department:Public Works Department

Page 18: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondUnion St./Oak Knoll Ave. Pocket Park - Concept Studyand Design

78083

Project No.

12

0000200,0000200,000Residential Impact Fee

200,000 0000200,0000Total

DESCRIPTION: This project provides for the implementation of a 0.3 acre pocket park at the northwestcorner of Union Street and Oak Knoll Avenue.

JUSTIFICATION: This site is ideally located to address a park “gap” area in the Central District and is ofsufficient size to create a pocket park.

SCHEDULE: Planning will begin in FY 2019.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with the Open Space & ConservationElement, specifically the ‘Increase Open Space’ Implementation Measure by developing a pocket park inan urban area. It is also consistent with the Green Space, Recreation and Parks Element, Policy 6.2(Neighborhood Parks) by acquiring a park within walking distance of multi-family housing. In the Land UseElement, the project supports Policy 2.8 (Equitable Distribution of Community Devices and Amenities) byincreasing the opportunity to access a public park, Policy 2.13 (Parks) by developing a new park, andPolicy 21.10 (Neighborhood Parks and Open Space Amenities.) by ensuring this neighborhood has a parkwithin easy walking distance of residents.

SPECIAL CONSIDERATION: The total estimated project cost will be determined after the concept studyis completed. The final budget can be impacted by site conditions, community input, and commissionreviews.

HISTORY: This project was created and fully funded in FY 2019.

East Union Street at North Oak Knoll Avenue

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Union St./Oak Knoll Ave. Pocket Park - Concept Study and Design78083

9.12 Responsible Department:Public Works Department

Page 19: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondInstallation of Security Lights at Jefferson, Gwinn andSunnyslope Park

78902

Project No.

13

0000750,0000750,000Residential Impact Fee

750,000 0000750,0000Total

DESCRIPTION: This project provides for replacement or installation of security lights, including pedestrianlighting, at Jefferson, Gwinn and Sunnyslope Park.

JUSTIFICATION: Existing lighting systems in these parks are old, inefficient and difficult to maintain. Anew lighting system will increase visibility in the parks and reduce maintenance costs and energyconsumption.

SCHEDULE: Construction at each location will begin and be completed in FY 2019.

RELATIONSHIP TO GENERAL PLAN: The project is consistent with the Land Use Element Policy 2.1 onNeighborhood Parks by enhancing parks in residential areas. It is also consistent with the Public FacilitiesElement of the General Plan by encouraging a high level of maintenance and upgrading of existingfacilities to ensure public safety.

HISTORY: This project was created and fully funded in FY 2019. Design of these locations werepreviously completed under project 78901 - Replacement or Installation of Security Lights – VariousLocations.

Park Security Lighting

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Installation of Security Lights at Jefferson, Gwinn and Sunnyslope Park78902

9.13 Responsible Department:Public Works Department

Page 20: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondCentral Park - Implement Master Plan78461

Project No.

14

0000072,00072,000Private Capital

000002,673,6002,673,600Residential Impact Fee

454,40000000454,400Unfunded

3,200,000 454,40000002,745,600Total

DESCRIPTION: This project provides for the implementation of improvements as indicated in the MasterPlan for Central Park. The major elements of the plan include:

• Walkway and path replacement at various locations throughout the park - COMPLETED• Renovation and enlargement of the children's play area - COMPLETED• Installation of lighting - COMPLETED• Replacement of the existing restroom - COMPLETED• Improvements and building restoration to El Centro de Accion building including ADA upgrades -COMPLETED• A formal garden/plaza• Landscaping and irrigation• Improvements to the south bowling lawn and potential removal of the north bowling lawn• Site amenities including picnic areas, trash receptacles, benches, tables and drinking fountains

JUSTIFICATION: The improvements proposed by the 2006 Master Plan reflect recommendations of thecommunity, master plan oversight committee and the City Council to make an attractive urban park thatretains its historical elements and acts as a venue for cultural events.

SCHEDULE: No work has been identified in FY 2019.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with the Cultural and RecreationalElement of the General Plan by increasing the range of recreational facilities and services as a means ofimproving the quality of life for Pasadena residents. It is also consistent with the Land Use Element Policy2.2 on Urban Parks by continuing and completing efforts to enhance Central Park.

HISTORY: This project was created and received initial funding in FY 1991. The walkway and pathreplacement was completed in FY 2005. The installation of lighting was completed in FY 2008. Therenovation and enlargement of the children's play area was completed in FY 2014. The replacement of anexisting restroom was completed in FY 2017. In FY 2018, renovations and ADA upgrades at El Centro deAccion were completed.

Central Park - 275 S. Raymond Ave.

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park ProjectsCentral Park - Implement Master Plan

78461

9.14 Responsible Department:Public Works Department

Page 21: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondVilla Parke Community Center Improvements78061

Project No.

15

00000750,000750,000General Fund

40,0000000040,000Private Capital

00000250,000250,000Residential Impact Fee

800,00000000800,000Unfunded

1,840,000 840,00000001,000,000Total

DESCRIPTION: This project provides for various improvements to the Villa Parke Community Center. Theimprovements include, but are not limited to, east entrance upgrades, additional parking area, renovationof gymnasium and auditorium floor, and locker room repairs.

JUSTIFICATION: Improvements to the Villa Parke Community Center will allow for the continued use ofthe facility and better serve the needs of the community.

SCHEDULE: Design will begin in FY 2019.

RELATIONSHIP TO GENERAL PLAN: The project is consistent with Green Space Element Objective 14(Recreation Programming For Health and Fitness) by providing a range of activities to promote health andfitness among all Pasadenans. The project is also consistent with the Public Facilities Objective 2 by moreefficient development and utilization of public facilities.

IMPACT ON THE NORTHWEST: This project is located in Northwest Pasadena which is an area that hasbeen targeted for revitalization.

HISTORY: This project was created and received initial funding in FY 2012. In FY 2018, an assessment ofthe facility was completed as part a Citywide Building Assessment project. This assessment will be utilizedto identify current and future maintenance priorities and programming needs. The project was originallytitled "Villa Parke Community Center Boxing Ring and Gymnasium" and was renamed in FY 2019.

Community Center - Design Concept

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Villa Parke Community Center Improvements78061

9.15 Responsible Department:Public Works Department

Page 22: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondPickleball Courts - Design and Construction

Project No.

16

800,00000000800,000Unfunded

800,000 800,00000000Total

DESCRIPTION: This project provides for the design and construction of the first dedicated Pickleballcourts in the City. The location of the permanent courts is to be determined.

JUSTIFICATION: The City has acknowledged the need for permanent dedicated Pickleball courts,however none currently exist. In FY18, a park planning effort was undertaken to identify a preferredlocation for the courts.

SCHEDULE: The project will begin when funding is identified.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with the Land Use Element Policy 4.2 (ADiversity of Places) by recreation facilities that offer a wide range of experiences, as well as the GreenSpace, Recreation and Parks Element, Policy 6.1 (Establish an Integrated Recreation, Park, and OpenSpace System) by acquiring a park within walking distance of multi-family housing, and Policy 8.5(Recreation Needs) by providing recreation facilities for those who live and work in Pasadena.

HISTORY: This project was created in FY 2019 and is currently unfunded.

Allendale Park

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Pickleball Courts - Design and Construction

9.16 Responsible Department:Public Works Department

Page 23: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondRobinson Park Recreation Center Pool and PoolBuilding Renovation - Design Phase

Project No.

17

300,00000000300,000Unfunded

300,000 300,00000000Total

DESCRIPTION: This project provides for the design of renovations to the pool, pool building andassociated mechanical and electrical systems. The design will include a new pool at current size andconfiguration, a new pool deck and replacement of the existing pool building. The new pool building willinclude accessible shower and restroom facilities, energy efficient lighting and water conserving fixtures.

JUSTIFICATION: This park is one of the most heavily used facilities in the City of Pasadena, servingapproximately 400 users per day. The swimming pool and pool building are in disrepair and due toconsiderable deferred maintenance warrant replacement and upgrades.

SCHEDULE: This project will begin when funding is identified.

RELATIONSHIP TO GENERAL PLAN: This project is consistent with Land Use Element Goal 16(Superior Services) by implementing a superior level of services meeting the needs of Pasadena’s diverseresidents including schools, hospitals, parks, child and senior facilities and programs, libraries, shelters,public auditoriums, health facilities, social clubs and recreation centers. This project is also consistent withLand Use Element Policy 40.3 (Community Services and Infrastructure) by assuring that adequatecommunity services and infrastructure are provided to local residents commensurate with needs. Finally,this project is consistent with Green Space, Recreation and Parks Element Policy 18.3 (AdequateResource Allocation) by providing the resources necessary for the appropriate level of maintenancerequired.

SPECIAL CONSIDERATION: The total estimated project cost is based on the scope of the project andknown factors at inception. Project cost and schedule can be impacted by site analysis and evaluation ofexisting sub-surface conditions, community input, and commission reviews.

IMPACT ON THE NORTHWEST: This park is located in Northwest Pasadena which is an area that hasbeen targeted for revitalization.

HISTORY: This project was created in FY 2017 and is currently unfunded.

Robinson Park Pool - 1081 N. Fair Oaks Ave.

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Park Projects

Robinson Park Recreation Center Pool and Pool Building Renovation - Design Phase

9.17 Responsible Department:Public Works Department

Page 24: pARKs ANd LANdsCApING - City of Pasadena

LANDSCAPE PROJECTS

Page 25: pARKs ANd LANdsCApING - City of Pasadena

00216,000216,000265,000400,0001,097,000Tree Replacement/Planting - Citywide FY 2017 - 2021 (78958)1

1,097,000 00216,000216,000265,000400,000Total

FY 2019 - 2023 Capital Improvement Program

Priority

TotalEstimated

CostsDescription

AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and Beyond

Parks and Landscaping - Landscape Projects

10 - Summary

Page 26: pARKs ANd LANdsCApING - City of Pasadena

Priority TotalEstimated

Costs

Description AppropriatedThroughFY 2018

AdoptedFY 2019

ProposedFY 2020

ProposedFY 2021

ProposedFY 2022

ProposedFY 2023

and BeyondTree Replacement/Planting - Citywide FY 2017 - 202178958

Project No.

1

00000400,000400,000State Environmental Enhancement Mitigation Grant

0000265,0000265,000Street Tree Replacement Deposit

00216,000216,00000432,000Unfunded

1,097,000 00216,000216,000265,000400,000Total

DESCRIPTION: This project will provide for the replacement, planting and watering of public treescitywide.

JUSTIFICATION: In order to continually replenish the City’s public tree vacancies and increase the urbanforest canopy, trees need to be planted annually. This project will allow City staff to apply for grant fundingto help finance the planting and watering of trees that need to be replaced.

SCHEDULE: In FY 2019, approximately 600 trees will be planted.

RELATIONSHIP TO GENERAL PLAN: The project is consistent with Public Facilities Element Objective 6by maintaining a high level of design quality in all public buildings, streets and open spaces. The project isalso consistent with Conservation Element Goal 2.0 by providing a physical environment which contributesto and enhances the quality of life; and Objective 2.4 by retention of Pasadena's image and heritage ofmature trees and plant life.

IMPACT ON THE NORTHWEST: A portion of this project is located in Northwest Pasadena which is anarea that has been targeted for revitalization.

HISTORY: This project was created and initially funded in FY 2017.

Tree Planting

FY 2019 - 2023 Capital Improvement ProgramParks and Landscaping - Landscape Projects

Tree Replacement/Planting - Citywide FY 2017 - 202178958

10.1 Responsible Department:Public Works Department