1 Palmer, Lisa M From: Sharon Godfrey [[email protected]] Sent: Wednesday, August 14, 2013 8:18 PM To: Palmer, Lisa M Subject: Don't let Duke get away with more pollution from their coal ash waste Aug 14, 2013 North Carolina Department of Environment and Natural Resources Dear Department of Environment and Natural Resources, The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put communities at risk. I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs to start cleaning up the mess that has already been made. Further, I ask that you hold a public hearing on the proposal so the public's voice can be heard. Finally, please take action now and end the delays. Sincerely, Sharon Godfrey 9524 Deer Spring Ln Charlotte, NC 28210-8024 (704) 541-7332

Transcript of Palmer, Lisa M Quality/Surface Water...1 Palmer, Lisa M From: Sharon Godfrey...

  • 1

    Palmer, Lisa M

    From: Sharon Godfrey [[email protected]]Sent: Wednesday, August 14, 2013 8:18 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Sharon Godfrey

    9524 Deer Spring Ln

    Charlotte, NC 28210-8024

    (704) 541-7332

  • 2

  • 3

    Palmer, Lisa M

    From: William & Donna Fisk [[email protected]]Sent: Wednesday, August 14, 2013 5:14 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    William & Donna Fisk

    125 Chimney Glen Dr

    Hendersonville, NC 28739-8840

    (828) 595-2404

  • 4

  • 5

    Palmer, Lisa M

    From: Daphne Cohan [[email protected]]Sent: Wednesday, August 14, 2013 5:09 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Daphne Cohan

    27 Lakeshore Dr

    Weaverville, NC 28787-9404

  • 6

  • 7

    Palmer, Lisa M

    From: Daphne Cohan [[email protected]]Sent: Wednesday, August 14, 2013 5:09 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Daphne Cohan

    27 Lakeshore Dr

    Weaverville, NC 28787-9404

  • 8

  • 9

    Palmer, Lisa M

    From: Cheryl Vecellio [[email protected]]Sent: Wednesday, August 14, 2013 4:50 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Cheryl Vecellio

    252 Wildbriar Rd

    Fletcher, NC 28732-7785

    (727) 421-3896

  • 10

  • 11

    Palmer, Lisa M

    From: Steve Copulsky [[email protected]]Sent: Wednesday, August 14, 2013 4:50 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Steve Copulsky

    6614 Lynn Ave

    Charlotte, NC 28226-8010

    (704) 543-7493

  • 12

  • 13

    Palmer, Lisa M

    From: Renee Reese [[email protected]]Sent: Wednesday, August 14, 2013 4:15 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard. Citizens of our communities feel that safe drinking water is important to the quality of life in our state. Duke's pollution jeopardizes our health.

    Finally, please take action now and end the delays.

    Sincerely,

    Renee Reese

    306 Wendover Heights Cir

    Charlotte, NC 28211-1349

  • 14

    (704) 763-1751

  • 15

    Palmer, Lisa M

    From: ARTHUR Anderson [[email protected]]Sent: Wednesday, August 14, 2013 3:46 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    ARTHUR Anderson

    104 Alexander Ave

    Swannanoa, NC 28778-2502

    (828) 775-9993

  • 16

  • 17

    Palmer, Lisa M

    From: Lorianne Chavez [[email protected]]Sent: Wednesday, August 14, 2013 3:46 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Lorianne Chavez

    4317 Millpoint Rd

    Greensboro, NC 27406-9008

    (865) 566-5195

  • 18

  • 19

    Palmer, Lisa M

    From: George Santucci [[email protected]]Sent: Wednesday, August 14, 2013 3:45 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    George Santucci

    401 Long St

    Jefferson, NC 28640-9505

    3

  • 20

  • 21

    Palmer, Lisa M

    From: Laura Sorensen [[email protected]]Sent: Wednesday, August 14, 2013 3:45 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Laura Sorensen

    40 Green Valley Rd

    Asheville, NC 28806-1428

  • 22

  • 23

    Palmer, Lisa M

    From: Dori Bowman [[email protected]]Sent: Wednesday, August 14, 2013 3:17 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Dori Bowman

    2732 Burnt Mill Rd

    Charlotte, NC 28210-6104

    (704) 556-0491

  • 24

  • 25

    Palmer, Lisa M

    From: Krishna Murphy [[email protected]]Sent: Wednesday, August 14, 2013 2:47 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    OUR CHILDREN are at risk!

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French

    Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Krishna Murphy

    49 Vance Ave

    Black Mountain, NC 28711-6400

  • 26

    (828) 549-8076

  • 27

    Palmer, Lisa M

    From: Janet Black [[email protected]]Sent: Wednesday, August 14, 2013 2:46 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Janet Black

    2149 Pisgah Hwy

    Candler, NC 28715-7141

  • 28

  • 29

    Palmer, Lisa M

    From: Emily Kendrick [[email protected]]Sent: Wednesday, August 14, 2013 2:46 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Emily Kendrick

    5 Pelzer St

    Asheville, NC 28804-2109

  • 30

  • 31

    Palmer, Lisa M

    From: jonathan vess [[email protected]]Sent: Wednesday, August 14, 2013 2:45 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    jonathan vess

    600 Merrimon Ave

    Apt 14b

    Asheville, NC 28804-3482

  • 32

    (828) 279-4761

  • 33

    Palmer, Lisa M

    From: jonathan vess [[email protected]]Sent: Wednesday, August 14, 2013 2:44 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    jonathan vess

    600 Merrimon Ave

    Apt 14b

    Asheville, NC 28804-3482

  • 34

  • 35

    Palmer, Lisa M

    From: Joe Zinich [[email protected]]Sent: Wednesday, August 14, 2013 2:44 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    You have have stated Duke's unlawful pollution caused by the lagoons "poses a serious danger to the health, safety and welfare of the people of North Carolina" and "serious harm to the

    water resources of the State."

    Then enforce the law and protect our families and communities from more toxic pollution.

    DENR and Duke Energy proposed settlement fails to stop the pollution from coal ash ponds.

    Continuing to study the illegal pollution won't clean it up and continues to put communities at risk. You already know it's unlawful and dangerous!

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French

    Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be heard.

    Finally, please take action now and end the delays.

    Sincerely,

  • 36

    Joe Zinich

    306 Mountain Laurel

    Asheville, NC 28805-9764

  • 37

    Palmer, Lisa M

    From: Teela Waggoner [[email protected]]Sent: Wednesday, August 14, 2013 2:20 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Teela Waggoner

    95 Barnard Ave

    Asheville, NC 28804

    Sincerely,

  • 38

    Teela Waggoner

    95 Barnard Ave

    Asheville, NC 28804-3223

  • 39

    Palmer, Lisa M

    From: Richard Fireman [[email protected]]Sent: Wednesday, August 14, 2013 2:19 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Richard Fireman

    374 Laughing River Rd

    Mars Hill, NC 28754-6281

    (828) 206-8877

  • 40

  • 41

    Palmer, Lisa M

    From: Greg Hils [[email protected]]Sent: Wednesday, August 14, 2013 2:18 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Greg Hils

    222 S Hillside St

    Rutherfordton, NC 28139-2834

  • 42

  • 43

    Palmer, Lisa M

    From: Mary Stafford [[email protected]]Sent: Wednesday, August 14, 2013 2:18 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Mary Stafford

    42 Merion Dr

    Asheville, NC 28806-1617

  • 44

  • 45

    Palmer, Lisa M

    From: Mary Stafford [[email protected]]Sent: Wednesday, August 14, 2013 2:18 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 14, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Mary Stafford

    42 Merion Dr

    Asheville, NC 28806-1617

  • 46

  • 47

    Palmer, Lisa M

    From: Shirley Moder [[email protected]]Sent: Tuesday, August 13, 2013 9:18 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 13, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Shirley Moder

    117 Willow Tree Ln

    Mt Holly, NC 28120-9260

  • 48

  • 49

    Palmer, Lisa M

    From: Jimmy Dean [[email protected]]Sent: Tuesday, August 13, 2013 5:45 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 13, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Jimmy Dean

    122 Hampshire Dr

    Mooresville, NC 28115-8501

    (704) 975-0266

  • 50

  • 51

    Palmer, Lisa M

    From: Beth Henry [[email protected]]Sent: Tuesday, August 13, 2013 5:16 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 13, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    It makes me very sad that, once NGOs indicated intent to sue Duke, DENR filed suit apparently for the sole purpose of entering a terribly weak settlement with Duke. Are the folks at DENR

    afraid for their jobs if they don't kowtow to Duke Energy?

    The proposed settlement utterly fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution puts communities at risk. If this type of weak action is what

    will be required of DENR under the McCrory administration, I would hope some self-respecting regulators would be quitting in protest soon.

    Please make Duke Energy stop polluting our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs to start cleaning up the mess that has already been made.

    Finally, please hold a public hearing on the proposal so the public can be heard.

    This joke of a settlement gives pundits nationwide even more reason to mock North Carolina.

    Sincerely,

    Beth Henry

  • 52

    3066 Stoneybrook Rd

    Charlotte, NC 28205-3150

    (704) 375-5424

  • 53

    Palmer, Lisa M

    From: Lani Blakeslee [[email protected]]Sent: Tuesday, August 13, 2013 4:46 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 13, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Lani Blakeslee

    103 Cumberland Cir

    Asheville, NC 28801-1719

    (401) 487-0856

  • 54

  • 55

    Palmer, Lisa M

    From: Thomas Harris [[email protected]]Sent: Tuesday, August 13, 2013 4:44 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 13, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Thomas Harris

    118 W Trinity Ave

    Durham, NC 27701-1915

    (919) 682-6971

  • 56

  • 57

    Palmer, Lisa M

    From: Sam Furgiuele [[email protected]]Sent: Tuesday, August 13, 2013 10:10 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 13, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Sam Furgiuele

    169 Gragg St

    Boone, NC 28607-3562

    (828) 264-7110

  • 58

  • 59

    Palmer, Lisa M

    From: Nora Gottlieb [[email protected]]Sent: Tuesday, August 13, 2013 12:12 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 12, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Nora Gottlieb

    4908 Forestville Rd

    Raleigh, NC 27616-9683

    (919) 266-2073

  • 60

  • 61

    Palmer, Lisa M

    From: Chanah Wizenberg [[email protected]]Sent: Monday, August 12, 2013 7:08 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 12, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Chanah Wizenberg

    5004 Avenida Del Sol Dr

    Raleigh, NC 27616-4562

    (508) 651-7933

  • 62

  • 63

    Palmer, Lisa M

    From: Charles Wussow [[email protected]]Sent: Monday, August 12, 2013 7:08 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 12, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Charles Wussow

    4 Mayflower Dr

    Asheville, NC 28804-3809

  • 64

  • 65

    Palmer, Lisa M

    From: Rachel Ashton [[email protected]]Sent: Monday, August 12, 2013 1:05 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 12, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Rachel Ashton

    106 Stillwater Dr

    Swansboro, NC 28584-8640

  • 66

  • 67

    Palmer, Lisa M

    From: Elizabeth Manley [[email protected]]Sent: Monday, August 12, 2013 2:18 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 12, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Elizabeth Manley

    PO Box 522

    Southern Pnes, NC 28388-0522

    (910) 690-8699

  • 68

  • 69

    Palmer, Lisa M

    From: Marc Parker [[email protected]]Sent: Monday, August 12, 2013 12:48 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 11, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Marc Parker

    123 any st.

    Fletcher, NC 28732

    (828) 555-5555

  • 70

  • 71

    Palmer, Lisa M

    From: Freddy Atwood [[email protected]]Sent: Sunday, August 11, 2013 2:48 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 11, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Do your job. I don't pay taxes for DENR to allow anyone or any company to poison me and my

    family and my community. DO YOUR JOB AND FIX THE PROBLEM. No more slap on the wrist. Cleaner coal is possible. Make the possible happen.

    Sincerely,

    Freddy Atwood

  • 72

    443 Jade Dr

    Clyde, NC 28721-6378

    (828) 627-0407

  • 73

    Palmer, Lisa M

    From: Terry Atwood [[email protected]]Sent: Sunday, August 11, 2013 2:48 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 11, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Do your job. I don't pay taxes for DENR to allow anyone or any company to poison me and my

    family and my community. DO YOUR JOB AND FIX THE PROBLEM. No more slap on the wrist. Cleaner coal is possible. Make the possible happen.

    Sincerely,

    Terry Atwood

  • 74

    443 Jade Dr

    Clyde, NC 28721-6378

    (828) 627-0407

  • 75

    Palmer, Lisa M

    From: Suzanne Glenzy [[email protected]]Sent: Sunday, August 11, 2013 2:48 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 11, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Suzanne Glenzy

    5855 Old Oak Ridge Rd Apt 3105

    Greensboro, NC 27410-8474

  • 76

  • 77

    Palmer, Lisa M

    From: Robert Trowers [[email protected]]Sent: Sunday, August 11, 2013 12:17 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 11, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the current and continuing pollution from coal ash ponds. Continuing to study this illegal pollution won't clean it up

    and continues to put communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard. This request is made for a simple but unfortunate reason. From my vantage point, the DENR does not seem terribly concerned with the public interest or representing it.

    Again, I urge you to take swift and effective action now to end the delays that allow

    continued pollution of our precious North Carolina environment. I further urge you to assess the cost of a complete cleanup of the toxic coal ash and fine Duke Energy accordingly.

    Sincerely,

    Robert Trowers

    1711 W Lakewood Ave

  • 78

    Durham, NC 27707-1130

  • 79

    Palmer, Lisa M

    From: Richard Hollings [[email protected]]Sent: Sunday, August 11, 2013 11:17 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 11, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Richard Hollings

    829 Myrtle Grove Ln

    Apex, NC 27502-6237

    (919) 362-7164

  • 80

  • 81

    Palmer, Lisa M

    From: Maria Boblitz [[email protected]]Sent: Sunday, August 11, 2013 8:17 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 11, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Maria Boblitz

    3503 Virgil Hodges Lane

    Jonesville, NC 28642

  • 82

  • 83

    Palmer, Lisa M

    From: G.H. Powell [[email protected]]Sent: Sunday, August 11, 2013 8:16 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 11, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    G.H. Powell

    PO Box 647

    Paw Creek, NC 28130-0647

  • 84

  • 85

    Palmer, Lisa M

    From: Nikki Taylor [[email protected]]Sent: Saturday, August 10, 2013 6:46 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 10, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Nikki Taylor

    2112 Eastchester Dr

    High Point, NC 27265-1409

  • 86

  • 87

    Palmer, Lisa M

    From: Joann Dare [[email protected]]Sent: Saturday, August 10, 2013 5:46 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 10, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Joann Dare

    43 Upper Roberts Branch Rd

    Weaverville, NC 28787-9606

    (828) 658-8121

  • 88

  • 89

    Palmer, Lisa M

    From: David Nikkel [[email protected]]Sent: Saturday, August 10, 2013 3:46 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 10, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    David Nikkel

    1926 N Pearl St

    Fayetteville, NC 28303-4341

  • 90

  • 91

    Palmer, Lisa M

    From: kAREN TILSON [[email protected]]Sent: Saturday, August 10, 2013 2:47 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 10, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Karen Tilson

    607 Stamey Mtn. Rd.

    Franklin NC

    Sincerely,

  • 92

    kAREN TILSON

    607 Stamey Mountain Rd

    Franklin, NC 28734-5619

  • 93

    Palmer, Lisa M

    From: Robin Lowery Jr [[email protected]]Sent: Saturday, August 10, 2013 2:16 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 10, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Robin Lowery Jr

    1913 Bailey Ave

    Wilmington, NC 28411-7247

  • 94

  • 95

    Palmer, Lisa M

    From: Jane Church [[email protected]]Sent: Saturday, August 10, 2013 12:47 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 10, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    Dear DENR,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal

    ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French

    Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    SINCERELY AND WITH TRUST IN YOUR SOUND, LONG-RANGE THINKING AND LEADERSHIP, Jane Church

    71008 Everard

    Chapel Hill, NC 27517-8572

    UNITED STATES

  • 96

    Sincerely,

    Jane Church

    71008 Everard

    Chapel Hill, NC 27517-8572

    (919) 967-2758

  • 97

    Palmer, Lisa M

    From: Jane Church [[email protected]]Sent: Saturday, August 10, 2013 12:47 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 10, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    Dear DENR,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal

    ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French

    Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    SINCERELY AND WITH TRUST IN YOUR SOUND, LONG-RANGE THINKING AND LEADERSHIP, Jane Church

    71008 Everard

    Chapel Hill, NC 27517-8572

    UNITED STATES

  • 98

    Sincerely,

    Jane Church

    71008 Everard

    Chapel Hill, NC 27517-8572

    (919) 967-2758

  • 99

    Palmer, Lisa M

    From: Joseph Robustelli [[email protected]]Sent: Saturday, August 10, 2013 12:19 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 10, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Joseph Robustelli

    111 Breckenridge Ct

    Hendersonville, NC 28739-8803

    (518) 808-7051

  • 100

  • 101

    Palmer, Lisa M

    From: Marie Whalen [[email protected]]Sent: Friday, August 09, 2013 4:37 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 9, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays. We must stop destroying our valuable resources. Thank you.

    Sincerely,

    Marie Whalen

    39 Magnolia Ave

    Asheville, NC 28801-1723

  • 102

    (828) 255-8039

  • 103

    Palmer, Lisa M

    From: Jeff Deluca [[email protected]]Sent: Friday, August 09, 2013 3:09 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 9, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Jeff Deluca

    721 S Merritt Mill Rd

    Chapel Hill, NC 27516-2880

    (561) 262-7046

  • 104

  • 105

    Palmer, Lisa M

    From: Audrey Tillinghast [[email protected]]Sent: Friday, August 09, 2013 1:34 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 9, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Audrey Tillinghast

    5337 Cucumber Branch Rd

    Snow Camp, NC 27349-9565

  • 106

  • 107

    Palmer, Lisa M

    From: Tyler Harmon-Townsend [[email protected]]Sent: Friday, August 09, 2013 12:17 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 9, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Tyler Harmon-Townsend

    1533 S Main St

    Winston Salem, NC 27127-2738

  • 108

  • 109

    Palmer, Lisa M

    From: Tracy Dadak [[email protected]]Sent: Friday, August 09, 2013 11:48 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 9, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Tracy Dadak

    17 Black Walnut Ln

    Candler, NC 28715-8377

    (828) 667-5714

  • 110

  • 111

    Palmer, Lisa M

    From: Michael David Loven [[email protected]]Sent: Friday, August 09, 2013 11:11 AMTo: Palmer, Lisa MSubject: I oppose the proposed consent order for Duke’s Asheville and Riverbend facilities.

    I am writing to express my concern with the proposed consent order for Duke Energy’s

    Asheville and Riverbend facilities. The proposed settlement fails to protect North Carolinians and our valuable water resources from toxic coal ash pollution.

    According to DENR’s own statements, Duke’s unlawful pollution is “a serious danger to the

    health, safety and welfare of the people of North Carolina” and “serious harm to the water resources of the State”. Duke should be required to stop the ongoing coal ash pollution as

    soon as possible and move the coal ash to lined, dry landfills away from the river, as is being done by SCE&G at the Wateree Power Station near Columbia, SC.

    I urge DENR to stop delaying and require definitive action to stop Duke’s pollution. DENR

    should also hold at least one public hearing on the proposal so that the public’s voice can be heard on this important matter.

    Thank you.

    Michael David Loven

    800 Eastowne Drive

    Chapel Hill, NC 27514

  • 112

    Palmer, Lisa M

    From: Shirley Conlan [[email protected]]Sent: Friday, August 09, 2013 10:47 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 9, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Shirley Conlan

    10 Creekside Way

    Asheville, NC 28804-1763

    (828) 505-1787

  • 113

  • 114

    Palmer, Lisa M

    From: joe zinich [[email protected]]Sent: Friday, August 09, 2013 10:10 AMTo: Palmer, Lisa MSubject: I oppose the proposed consent order for Duke’s Asheville and Riverbend facilities.

    I am writing to express my concern with the proposed consent order for Duke Energy’s

    Asheville and Riverbend facilities. The proposed settlement fails to protect North Carolinians and our valuable water resources from toxic coal ash pollution.

    According to DENR’s own statements, Duke’s unlawful pollution is “a serious danger to the

    health, safety and welfare of the people of North Carolina” and “serious harm to the water resources of the State”. Duke should be required to stop the ongoing coal ash pollution as

    soon as possible and move the coal ash to lined, dry landfills away from the river, as is being done by SCE&G at the Wateree Power Station near Columbia, SC.

    I urge DENR to stop delaying and require definitive action to stop Duke’s pollution. DENR

    should also hold at least one public hearing on the proposal so that the public’s voice can be heard on this important matter.

    Thank you.

    joe zinich

    306 mountain Laurel

    Asheville, NC 28805

  • 115

    Palmer, Lisa M

    From: Joan Walker [[email protected]]Sent: Friday, August 09, 2013 9:55 AMTo: Palmer, Lisa MSubject: I oppose the proposed consent order for Duke’s Asheville and Riverbend facilities.

    I am writing to express my concern with the proposed consent order for Duke Energy’s

    Asheville and Riverbend facilities. The proposed settlement fails to protect North Carolinians and our valuable water resources from toxic coal ash pollution.

    According to DENR’s own statements, Duke’s unlawful pollution is “a serious danger to the

    health, safety and welfare of the people of North Carolina” and “serious harm to the water resources of the State”. Duke should be required to stop the ongoing coal ash pollution as

    soon as possible and move the coal ash to lined, dry landfills away from the river, as is being done by SCE&G at the Wateree Power Station near Columbia, SC.

    I urge DENR to stop delaying and require definitive action to stop Duke’s pollution. DENR

    should also hold at least one public hearing on the proposal so that the public’s voice can be heard on this important matter.

    Thank you.

    Joan Walker

    63 Washington Ave.

    Asheville, NC 28804

  • 116

    Palmer, Lisa M

    From: Kathy Kaufman [[email protected]]Sent: Friday, August 09, 2013 9:48 AMTo: Palmer, Lisa MSubject: I oppose the proposed consent order for Duke’s Asheville and Riverbend facilities.

    I am writing to express my concern with the proposed consent order for Duke Energy’s

    Asheville and Riverbend facilities. The proposed settlement fails to protect North Carolinians and our valuable water resources from toxic coal ash pollution.

    According to DENR’s own statements, Duke’s unlawful pollution is “a serious danger to the

    health, safety and welfare of the people of North Carolina” and “serious harm to the water resources of the State”. Duke should be required to stop the ongoing coal ash pollution as

    soon as possible and move the coal ash to lined, dry landfills away from the river, as is being done by SCE&G at the Wateree Power Station near Columbia, SC.

    I urge DENR to stop delaying and require definitive action to stop Duke’s pollution. DENR

    should also hold at least one public hearing on the proposal so that the public’s voice can be heard on this important matter.

    Thank you.

    Kathy Kaufman

    1305 Lucy Lane

    Chapel Hill, NC 27516

  • 117

    Palmer, Lisa M

    From: Diane Swift [[email protected]]Sent: Friday, August 09, 2013 9:47 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 9, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Diane Swift

    208 Navaho Dr

    Hendersonville, NC 28739-6038

    (828) 595-9063

  • 118

  • 119

    Palmer, Lisa M

    From: Charlie Godwin [[email protected]]Sent: Friday, August 09, 2013 8:48 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 9, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Charlie Godwin

    204 Hughey Dr

    Gastonia, NC 28056-8477

    (704) 825-5887

  • 120

  • 121

    Palmer, Lisa M

    From: Stefanie Tanwar [[email protected]]Sent: Thursday, August 08, 2013 11:16 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 8, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Stefanie Tanwar

    1401 Rutledge Ave

    Charlotte, NC 28211-2929

    (828) 302-7375

  • 122

  • 123

    Palmer, Lisa M

    From: Mark King [[email protected]]Sent: Thursday, August 08, 2013 4:57 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 8, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Mark King

    551 Koppers Dr

    Aberdeen, NC 28315-7833

  • 124

  • 125

    Palmer, Lisa M

    From: Renee Tevelow [[email protected]]Sent: Thursday, August 08, 2013 4:56 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 8, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Renee Tevelow

    554 Grande Manor Ct

    Wilmington, NC 28405-4189

  • 126

  • 127

    Palmer, Lisa M

    From: Brett Little [[email protected]]Sent: Thursday, August 08, 2013 3:27 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 8, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Brett Little

    2711 Bennington Rd

    Fayetteville, NC 28303-5235

    (910) 624-5049

  • 128

  • 129

    Palmer, Lisa M

    From: Zac Avant [[email protected]]Sent: Thursday, August 08, 2013 2:28 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 8, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Zac Avant

    4924 Curtiswood Dr

    Charlotte, NC 28213-7010

  • 130

  • 131

    Palmer, Lisa M

    From: Alva Jones [[email protected]]Sent: Thursday, August 08, 2013 2:27 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 8, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Alva Jones

    3900 Marchester Way Apt 3g

    Greensboro, NC 27407-4304

  • 132

  • 133

    Palmer, Lisa M

    From: Kate Fulbright [[email protected]]Sent: Thursday, August 08, 2013 1:46 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 8, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Kate Fulbright

    4924 Curtiswood Dr

    Charlotte, NC 28213-7010

    (423) 619-4673

  • 134

  • 135

    Palmer, Lisa M

    From: Shelley Frazier [[email protected]]Sent: Thursday, August 08, 2013 12:20 PMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 8, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Shelley Frazier

    609 S Boylan Ave # 1

    Raleigh, NC 27603-2131

  • 136

  • 137

    Palmer, Lisa M

    From: Rod Hooker [[email protected]]Sent: Thursday, August 08, 2013 11:50 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 8, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Rod Hooker

    3904 New Holland Dr

    Wilmington, NC 28412-5103

    (910) 859-0029

  • 138

  • 139

    Palmer, Lisa M

    From: Marguerite Dingman, Clerk [[email protected]]Sent: Thursday, August 08, 2013 10:23 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 8, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    Your constituency is the PUBLIC and your duty is to protect our health and welfare. WE are the customers in "customer service."

    Your agency exists to represent OUR interests. What is good for Duke Energy is not always

    what is best for the citizens of North Carolina.

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal

    ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French

    Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

  • 140

    Marguerite Dingman, Clerk

    2014 Ward St

    Durham, NC 27707-1443

    (919) 493-6789

  • 141

    Palmer, Lisa M

    From: Banna Bazzarie [[email protected]]Sent: Thursday, August 08, 2013 10:21 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 8, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Banna Bazzarie

    3549 Dewing Dr

    Raleigh, NC 27616-8957

  • 142

  • 143

    Palmer, Lisa M

    From: Richard Starkweather [[email protected]]Sent: Thursday, August 08, 2013 9:48 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 8, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our groundwater and the French Broad River near the Asheville Coal Plant and Mountain Island Lake near Charlotte. Duke needs

    to start cleaning up the mess that has already been made.

    Further, I ask that you hold a public hearing on the proposal so the public's voice can be

    heard.

    Finally, please take action now and end the delays.

    Sincerely,

    Richard Starkweather

    929 Toxaway Dr

    Hendersonville, NC 28791-1842

    (828) 595-2204

  • 144

  • 145

    Palmer, Lisa M

    From: Judy Starkweather [[email protected]]Sent: Thursday, August 08, 2013 8:20 AMTo: Palmer, Lisa MSubject: Don't let Duke get away with more pollution from their coal ash waste

    Aug 8, 2013

    North Carolina Department of Environment and Natural Resources

    Dear Department of Environment and Natural Resources,

    The proposed settlement between DENR and Duke Energy fails to stop the pollution from coal ash ponds. Continuing to study the illegal pollution won't clean it up and continues to put

    communities at risk.

    I urge you to require that Duke Energy stop the pollution of our g