Page 1 of 51 Registered Post-Ack.- Bridges 1… · (iv) Schedule-B= (+) ... Act for 20 or more...
Transcript of Page 1 of 51 Registered Post-Ack.- Bridges 1… · (iv) Schedule-B= (+) ... Act for 20 or more...
Page 1 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
Registered Post-Ack.-Due”
भारत सरकार / Govt. of India
रेऱ मंत्राऱय / Ministry of Railways
दक्षिण मध्य रेऱवे / South Central Railway
ववजयवाडा मंडऱ / Vijayawada Division
मंडऱ कायााऱय/Divisional Office,
काया शाखा/Works Branch,
ववजयवाडा/Vijayawada,
सं.No.बीB/डबल्य ूW.496/I/4/T.No.08/Bridges/15/T.Bridges ददनाँक/Dt.01-01-2016
To
Sri K. Bali Reddy,
Railway Contractor
Podapadu (V),
Pedakurapadu Mandalam, Guntur Dist
Sir,
ववशय /Sub:-Tender No.08/Bridges/2015 for the Work of “SW-I: Vijayawada Division
“ Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly
replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-
Gudur-Vijayawada section–Removal of infringement on main line duly shifting the existing
Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada
section – Dismantling of existing old aged Foot Over Bridge at Gudur station.”
संदभा/Ref:- Your tender for the above work submitted on 07-12-2015
*** 1. The competent authority has accepted your Tender for the above work for a total value of Rs 43,91,937/-
(Rupees Forty three lakhs, ninety one thousand, nine hundred and thirty seven only) at the following rates.
Rates: (i) Schedule-A=(+) 26 % (Plus Twenty six percent only) on USSR-2010
(ii) Schedule-A-1=(+) 26% (Plus Twenty six percent only) on USSR-2010
(iii) Schedule-A-2=(+) 17% (Plus Seventeen percent only) on USSR-2010
(iv) Schedule-B= (+) 17% (Plus Seventeen percent only) on basic rates
(v) Schedule-B-1 = “At par”(At par only) on basic rates.
2. The work should be completed within 06 (Six) Months from the date of issue of letter of acceptance of tender
with a maintenance period of 06 (Six) Months.
3. The sum of ` 73,880/- submitted vide DD 169138 dt.05.12.15 issued by Corporation Bank/Patibandla, towards
E.M.D ( realized vide Sr.DC/Pay/BZA MCR No. 295539 dt. 17-12-2015) has been adjusted as part amount of
the security deposit. The balance security deposit of Rs. 1,45,717/- shall be recovered at the rate of 10% of the
bill amount till the full security deposit of Rs. 2,19,597/- is recovered.
4. In terms of Special conditions of contract, you shall furnish a Performance Guarantee amounting to 5% of the
contract value i.e., Rs. 2,19,597/- before signing of the agreement. The performance guarantee should be
initially valid up to the stipulated date of completion plus 60 days beyond that. In terms of Special conditions of
contract, you shall submit the Performance Guarantee (PG) within 30 (thirty) days from the date of issue of
Letter of Acceptance (LOA) [excluding the date of LOA]. Extension of time for submission of PG beyond
30(thirty) days and up to 60 days from the date of issue of LOA [excluding the date of LOA] may be given by
the Authority who is competent to sign the contract agreement. However, a penal interest of 15% per annum
shall be charged for the delay beyond 30 (thirty) days, i.e. from 31st day after the date of issue of LOA. The
agreement should be signed within fifteen days after the issue this letter and performance guarantee should also
be submitted within this time of limit before signing the agreement. In case of failure to submit the requisite PG
even after 60 days from the date of issue of LOA, the contract shall be terminated duly forfeiting EMD and
other dues, if any payable against the contract. The failed contractor shall be debarred from participating in re-
tender for that work. Contd-2
Page 2 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
:2:
5. Until a formal agreement is executed, acceptance of the Tender shall constitute a binding contract between you
and the administration.
6. You have to abide by the Contract Labour (Regulations and Abolition Act 1970) and rules, regulations and
amendments thereto that may be followed from time to time are binding on you in respect of this contract. You
have to submit the application in the prescribed form (Form-V) in triplicate for license under Contract
labour (Regulation and Abolition) Act for 20 or more workers and under BOCW Act for less than 20 Workers together with the demand draft towards security deposit and license fee to the undersigned to forward
the same to the concerned Licensing Officer for issue of the license irrespective of the number of labour
employed for the work. The work should not be executed without a valid labour license.
7. Failure to start the work within ten days, the contractor is liable for penal action as per clause 62 of the General
conditions of contract.
Encl:1) Tender schedule with special conditions &
2) Copy of Performance Guarantee
आपका / Yours faithfully,
Divisional Engineer/Bridges
S.C.Railway,,Vijayawada
For and on behalf of the President of India
Copy to: Sr.DFM/BZA for information.
Copy to:, ADEN/BR/South/BZA, SSE/BR/BTTR, SSE/BR/BZA-I & II, for information and necessary action
Copy to: SSE(Drg)/Bridges & OS/WA-Bridges for information and necessary action
Copy to: Asst Labour Commissioner (Ceneral), 5th floor, Central Govt Office Complex, Plot No.G-2, Industrial
Estate, Auto Nagar, Vijayawada-520007 for information.
(TC : ADEN/Track/BZA , ADFM/I/BZA & ADSTE/Tele/BZA– AA: DEN/Bridges/BZA)
Page 3 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
Tender No.08/Bridges/2015
Name of Work : SW-I: Vijayawada Division - Repairs to corroded steel structural components of Foot
Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair
way steps. SW-II: Vijayawada division -Gudur-Vijayawada section – Removal of
infringement on main line duly shifting the existing Foot Over Bridge column on PF No. 1
of Bitragunta station. SW-III: Gudur - Vijayawada section – Dismantling of existing old
aged Foot Over Bridge at Gudur station
Similar nature of work :- Not Applicable
Appx. Value : Rs.36,93,880/-
(Approximate value of tender arrived by addition of at par value of SSR items enhanced with certain estimated
percentage and value of NS items at the basic rates adopted in schedule.)
Estimate Sanctioned No. & date Allocation Value in Rs.
SW-01- B/W.71/I/1502/Plg dt: 17-10-2014 04-340-32 22,23,433
SW-02- B/W.375/V/1290/Plg dt: 27/10/2015 23-5346-03 9,59,083/-
SW-03- B/W/375/V/1291/Plg dt: 29/10/2015 04-340-32 5,11,134
Completion Period 06 (Six) months
Maintenance Period 06 (Six) months)
Name of the
Tenderer/Contractor:- Sri K. Bali Reddy,
Railway Contractor
Podapadu (V), Pedakurapadu Mandalam, Guntur Dist
SCHEDULE 'A'
List of items of works that are covered by USSR 2010 of S.C. Railway
SlNo
SSR No. Description of work SW-1 Qty.
SW-2 Qty.
SW-03 Qty
Total Appx Qty.
Rate in Rs.
Unit Amount in Rs.
1 181030 Demolishing R.C.C. work including cutting and stacking of steel bars and disposal of unserviceable material within 50m lead. (Extra payment for scraping, cleaning and straightening of bars to be made separately)
32.00 5.00 30.00 67.00 744.82 cum 49902
2 041010 + 041012
Providing and laying in position M 20 Grade concrete for reinforced concrete structural elements but excluding cost of centering, shuttering, reinforcement and Admixtures in recommended proportion (as per IS:9103) to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer in charge All work in buildings above plinth level upto floor two level.
26.00 9.00 0.00 35.00 2530.27 cum 88559
Page 4 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SlNo
SSR No. Description of work SW-1 Qty.
SW-2 Qty.
SW-03 Qty
Total Appx Qty.
Rate in Rs.
Unit Amount in Rs.
3 042010 + 042013
Centering and shuttering including strutting, propping etc. and removal of form for :Suspended floors, roofs, landings, balconies, FOB slabs, walkway slabs and access platform
68.00 2.00 0.00 70.00 230.70 Sqm 16149
4 092010 + 092011
Cement concrete flooring 1:2:4 (1cement: 2coarse sand: 4graded stone aggregate) finished with a floating coat of neat cement including cement slurry, but excluding the cost of nosing of steps etc. complete 25mm thick with 12.5mm nominal size stone aggregate
5.50 0.00 0.00 5.50 98.53 Sqm 542
5 211210 + 211214
Painting cleaned bridge plate girders including all scaffolding, shuttering and strutting along with provision of Jhoola / hanging scaffolding where required With two coats Aluminium paints in dual containers conforming to IS : 2339
765.00
300.00 0.00 1065.00 39.15 Sqm 41695
6 181020 + 181021
Demolishing plain cement concrete including disposal of material within 50m lead1:2:4 or richer mix with max. 20 mm coarse aggregate
0.00 1.00 0.00 1.00 510.54 cum 511
7 011010+ 011011
Earth work in excavation as per approved drawings and dumping at embankment site or spoil heap, within railway land, including 5om lead and 1.5 m lift, the lead to be measured from the centre of gravity of excavation to centre of gravity of spoil heap: the lift to be measured from natural ground level and paid for in layers of 1.5m each, including incidental work, as per specifications-in All kinds of soils.
0.00 23.00 3.00 26.00 100.28 CUM 2607
Page 5 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SlNo
SSR No. Description of work SW-1 Qty.
SW-2 Qty.
SW-03 Qty
Total Appx Qty.
Rate in Rs.
Unit Amount in Rs.
8 011070 Extra for every additional lift of 1.5m or part thereof, after the initial 1.5m, for each work in all soils
0.00 11.50 0.00 11.50 9.70 CUM 112
9 012050 Supplying and filling sand in plinth and under floors including watering, ramming, consolidating and dressing complete
0.00 1.50 0.00 1.50 615.03 cum 923
10 031010 +
031012
Providing and laying in position cement concrete of specified proportion excluding cost of cement, centering and shuttering - All works upto Plinth level :1:3:6 (1 cement : 3 sand : 6 graded stone aggregate 40mm nominal size)
0.00 1.50 0.00 1.50 1865.68 CUM 2799
11 041010 +
041011
Providing and laying in position M 25 Grade concrete for reinforced concrete structural elements but excluding cost of centering, shuttering, reinforcement and Admixtures in recommended proportion (as per IS:9103) to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer in charge - All work upto plinth level, including raft foundation of washable aprons, HS tank, pile cap, footings of FOB, and Platform shelter etc.
0.00 9.00 0.00 9.00 2326.70 CUM 20940
12 042010 +
042011
Centering and shuttering including strutting, propping etc. and removal of form for : Foundations, footings, bases of columns, raft foundation of washable aprons, Pile caps, Footings of FOB etc.
0.00 23.00 0.00 23.00 132.50 Sqm 3048
13 092010+092012
Cement concrete flooring 1:2:4 (1cement: 2coarse sand: 4graded stone aggregate) finished with a floating coat of neat cement including cement slurry, but excluding the cost of nosing of steps etc. complete 40mm thick with 20mm nominal size stone aggregate
0.00 1.00 0.00 1.00 136.90 Sqm 137
Page 6 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SlNo
SSR No. Description of work SW-1 Qty.
SW-2 Qty.
SW-03 Qty
Total Appx Qty.
Rate in Rs.
Unit Amount in Rs.
14 183030 Dismantling stone slab flooring/ dado/skirting laid in cement mortar/ lime mortar including stacking of serviceable material and disposal of unserviceable material within 50m lead
0.00 15.00 0.00 15.00 56.02 Sqm 840
15 096070 + 096072
Kota stone slab flooring of size up to 60x60cm over 20mm (average) thick base of 1:4 cement mortar (1cement: 4coarse sand) and jointed with grey cement slurry mixed with pigment to match the shade of the slab including rubbing and polishing complete 25mm thick
0.00 10.00 0.00 10.00 814.55 Sqm 8146
16 021070+021080
Loading/Unloading ballast, kankar, brickbats, stone- chips, shingle, stone boulders, block kankar, pitching stones , rubble stones, laterite, coal, surkhi, dry mortar, sand , moorum, earth, manure or sludge, ashes, lime etc., including lead up to 50m and stacking into/from trucks, trailors or wagons & Leading ballast, kankar, surkhi, lime, sand, ashes, stone- chips, pitching, stone, boulders, soling, stone, rubble stone, brickbats, shingle, dry mortar, laterite or similar materials including picking up and stacking, lead upto 50m
0.00 29.00 0.00 29.00 157.49 Cum 4567
17 021081 Additional lead for every subsequent 50m or part thereof, over 50m and upto 500m over item no. 021080
0.00 290.00 0.00 290.00 27.64 Cum 8016
Page 7 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SlNo
SSR No. Description of work SW-1 Qty.
SW-2 Qty.
SW-03 Qty
Total Appx Qty.
Rate in Rs.
Unit Amount in Rs.
18 109230 Supply and Installation, including lifting to all heights as required, trapezoidal/ corrugated sheeting system in galvalume colour coated steel having cover width of 1000mm, 35mm crest at apitch of 250mm stiffened with 8mm deep intermittent corrugations or profiling approved by engineer-in-charge. sheet should be made from base metal having 0.52mm(±0.02mm) thickness in steel of grade 345 as per ASTM A 792M, . coated with alloy of aluminium & Zinc to grade AZ150 (min. alloy mass 150 gsm total both sides) with colour coating having complete dip tank pre-treatment process with chromate conversion (Cr +3) as main pre-treatment followed by PU primer (permaprime grade) of min. 5 micron DFT on each surface; finished with special polyester paint to grade EPG-20 of minimum 20 microns DFT on exposed surface and 5 micron in grey shade on unexposed surface. fixing shall be done with self-tapping screws meeting requirement of class-3 of AS 3566 with EPDM washers at suitable intervals as per site requirement and as directed by engineer-in-charge complete work.
0.00 17.00 0.00 17.00 543.10 Sqm 9233
19 109260 +
109261
Providing & fixing of coloured galvalume plain sheet flashings at ridges / apex junctions of roofing cladding, cover / corner / barge pieces etc. in required shape, colour duly fixed with stitching screws (with EPDM washers etc. as per site requirement - Upto 600 mm width (girth)
0.00 5.00 0.00 5.00 393.99 R.Metre 1970
20 186020 Dismantling steel work and trusses upto 10m span and 5m height in built up sections in angles, tees, flats and channels including all gusset plates, bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50m lead
0.00 3000.00 120000.00
123000.00 1.19 Kg 146370
Page 8 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SlNo
SSR No. Description of work SW-1 Qty.
SW-2 Qty.
SW-03 Qty
Total Appx Qty.
Rate in Rs.
Unit Amount in Rs.
21 186040 Extra over item 186020 & 186030 for dismantling trusses, rafters, purlins etc. of steel work for additional span length of one metre or part thereof beyond 10m
0.00 2000.00 21000.00 23000.00 0.18 Kg 4140
22 021141 Additional lead for every subsequent 50m or part thereof, over 50m and upto 500m over item no. 021140.
0.00 3.00 0.00 3.00 31.58 MT 95
23 184080 +
184081
Dismantling roofing including ridges, hips valleys and gutters etc. and stacking the material within 50m lead of G.I Sheet
0.00 18.00 200.00 218.00 35.21 Sqm 7676
24 014010 Dressing Surface (average excavation or filling upto 15 cm) including removing vegetation in all kind of soil. Payment against this item is to be made only if it is not included in earth work item
0.00 0.00 800.00 800.00 67.50 10 sqm
5400
25 183010 Dismantling cement concrete / terrazzo flooring and/or underlayer excluding base concrete
0.00 0.00 18.00 18.00 18.37 Sqm 331
26 182010 + 182013
Demolishing brick work including stacking of serviceable material and disposal of unserviceable material within 50m lead In cement mortar
0.00 0.00 3.00 3.00 431.31 cum 1294
27 184080 + 184082
Dismantling roofing including ridges, hips valleys and gutters etc. and stacking the material within 50m lead of Asbestos sheet
0.00 0.00 400.00 400.00 16.57 sqm 6628
28 185030 + 185032
Dismantling wood work in frames, trusses, purlins and rafters/reepers including stacking the material within 50m lead Of sectional area below 40sqcm
0.00 0.00 2.00 2.00 1075.82 cum 2152
29 186050 Extra over item 186030 & 186040 for dismantling trusses, rafters, purlins etc. of steel work for additional height of one metre or part thereof beyond 5m
0.00 0.00 5000.00 5000.00 0.18 Kg 900
30 186060 Extra for marking of structural steel work required to be re-erected
0.00 0.00 500.00 500.00 1.01 Kg 505
31 187010 + 187011
Dismantling and stacking within 50m lead, fencing posts or struts/ rails including all earth work and dismantling of concrete etc. in base ‘T” or ‘L’ iron or pipe, rail or RSJs
0.00 0.00 100.00 100.00 55.55 Each 5555
Page 9 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SlNo
SSR No. Description of work SW-1 Qty.
SW-2 Qty.
SW-03 Qty
Total Appx Qty.
Rate in Rs.
Unit Amount in
Rs.
32 187010 + 187012
Dismantling and stacking within 50m lead, fencing posts or struts/ rails including all earth work and dismantling of concrete etc. in base R.C.C. / Stone
0.00 0.00 20.00 20.00 65.42 Each 1308
33 021150 Leading miscellaneous materials such as iron work, rails, fittings & fastenings, pipes, wooden logs, stones over pitching stone size, RCC/PCC beams / slabs etc and all similar articles (each individual article or bundle being not more than 3.5 metres long in the longest direction) including all loading, unloading and stacking, lead over 500m and upto 10 km. Note : Lead under this item is payable when the same exceeds 500m.
0.00 0.00 97.00 97.00 108.05 MT 10481
34 021160 Leading miscellaneous materials such as iron work, rail, pipes, wooden logs, stones over pitching stone size, RCC/PCC beams / slabs etc and all similar articles (each individual article or bundle being more than 3.5 metres long in the longest direction) including picking up and stacking, lead upto 50m.
0.00 0.00 21.00 21.00 115.11 MT 2417
35 021161 Additional lead for every subsequent 50m or part thereof, over 50m and upto 500m over item no. 021160
0.00 0.00 21.00 21.00 35.63 MT 748
36 211180 + 211183
Providing road crane of different capacity with diff. jib length revolving type for material handling, assembly & erection of girders/slab/RCC Box etc.40 MT capacity with 75 feet jib
0.00 0.00 10.00 10.00 23926.90 day 239269
37 051180 + 051182
Half brick masonry with bricks of class designation 7.5 in foundations and plinth in :Cement mortar 1:4 (1 Cement : 4 coarse sand)
0.00 0.00 30.00 30.00 272.84 Sqm 8185
38 051190 Extra for half Brick masonry in superstructure above plinth level upto floor two level
0.00 0.00 30.00 30.00 46.13 Sqm 1384
39 057100 + 057104
Add or deduct from rates of brickwork when the bricks specified or permitted to be used by Engineer are of Class designation other than 7.5 Deduct for Class designation 3.5
0.00 0.00 3.00 3.00 -655.33 cum -1966
Page 10 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SlNo
SSR No. Description of work SW-1 Qty.
SW-2 Qty.
SW-03 Qty
Total Appx Qty.
Rate in Rs.
Unit Amount in
Rs.
40 111020 + 112022
15 mm cement plaster on the rough side of single or half brick wall of mix -1:6 (1cement: 6 fine sand)
0.00 0.00 64.00 64.00 77.03 Sqm 4930
41 115010 + 115011
White washing with lime to give an even shade New work (three or more coats)
0.00 0.00 64.00 64.00 9.52 Sqm 609
42 031050 + 031051
Providing and laying in position cement concrete of M 20 grade, excluding the cost of cement and of centering and shuttering, as per direction of the Engineer in charge :All works up to Plinth level
0.00 0.00 3.00 3.00 2190.22 cum 6571
(Items Forty two only) Value of schedule-A 715678
Percentage Rate quoted
“in Figures” (+) 26 %
Percentage Rate quoted “in Words”
Plus Twenty Six percent only
Page 11 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SCHEDULE 'A-I' List of items of works that are covered by USSR 2010 of S.C.Railway
SlNo
SSR No. Description of work SW-1 Qty.
SW-2 Qty.
SW-03 Qty
Total Appx Qty.
Rate in Rs.
Unit Amount in Rs.
1 033060 + 033062
Supply and using cement at worksite :"OPC 53 grade"
11.500 7.000 2.000 20.500 4,600.00 Tonne 94300
(Item ONE only) Value of schedule-A-1 94,300
Percentage Rate quoted “in Figures”
(+) 26 %
Percentage Rate quoted “in Words”
Plus Twenty Six percent only
Page 12 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SCHEDULE 'A-II‟ List of items of works that are covered by USSR 2010 of S.C.Railway
SlNo
SSR No. Description of work SW-1 Qty.
SW-2 Qty.
SW-03 Qty
Total Appx Qty.
Rate Unit Amount in
Rs.
1 045010 +045016
Supplying Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete.Thermo-Mechanically Treated bars
3,850 2,900.00 0.00 6,750 50.76 Kg 342630
2 211080 Providing/ fixing/ leaving/ grouting various size HTS bolts / holding down bolts in concrete column or in other structural steel member with proper nuts, bolts, washers /plates as a complete job. Note - Cement used in grouting will be paid separately under relevant item
0.00 200.00 0.00 200 70.01 Kg 14002
(Items Two only) Value of schedule-A-II 3,56,632
Percentage Rate quoted “in Figures”
(+) 17 %
Percentage Rate quoted “in Words”
Plus Seventeen percent only
Page 13 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SCHEDULE B List of items of works that are not covered by USSR 2010 of S.C.Railway
SlNo
SSR No. Description of work SW-1 Qty.
SW-2 Qty.
SW-03 Qty
Total Appx Qty.
Rate in Rs. Unit Amount in
Rs.
1 NS-2010-22
Supplying , farbicating and erecting welded and/or bolted and/or riveted steel work in built up sections, trusses and framed work, girders, staging, racks etc., using RSJ, tees, angles and channels/flats, plates, gussets, round or square bars, cleats, bolts etc., with contractor's own steel including cutting, bending, straightening, drilling, riveting, hoisting, fixing, erecting, welding, bolting etc., with Providing stifeners wherever required as per approved drawing including applying a priming coat of a approved steel primer with all contractor's materials, labour, tools & plants, lead & lift including crossing of tracks if required etc., complete as per specification and as directed by Engineer-in-charge
31.50 11.00 0.50 43.00 58,390.69 MT 2510800
NOTE : 1) Work should be carried out over electrified section. 2) Work has to be executed in the running condition/ under the traffic block. The block will be
made available as per the convenience of the Railway depending on the positions of the trains. The contractor shall note that, no claims will be allowed for delay in getting traffic/power blocks 3) The rate quoted should be inclusive of contractor's nuts, washers, bolts, rivets etc.,
Payment will be made for net quantity of steel fixed in the repairs of Foot Over Bridges. 4).The steel quantity includes M.S. sheet required for shuttering of Gang way/Stair way slabs
wherever required. 5) Rate quoted shall include applying one coat of Zinc chrome primer I.S.104 and one coat of
Red oxide zinc chrome primer to I.S.2074 6) Steel procured should be from the approved firms mentioned in the special conditions 7 ) The painting should be in accordance with the specifications for painting 8) Tenderer/Contractor should note that the prefabricated and assembled sections of Foot
over Bridge/Stair way has to be erected/launched in their final position duly baricading the circulating area/plat form area. 9). Tenderer/Contractor has to make all preliminary arrangements for carryout the repair works
of Foot over bridge/stairway with all contractor’s labour, tools, plant, machinery etc 10). The contractor should note that the adjacent lines, should not be affected/ obstructed
during the erection/execution of work. Traffic on adjacent lines should also be not disturbed during repairs/ erection of FOB (other than nominated lines).
(Items One only) Value of schedule-B 25,10,800
Percentage Rate quoted “in Figures”
(+) 17 %
Percentage Rate quoted “in Words”
Plus Seventeen percent only
Page 14 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SCHEDULE 'B-I' List of items of works that are not covered by USSR 2010 of S.C.Railway
SlNo
SSR No. Description of work SW-1 Qty.
SW-2 Qty.
SW-03 Qty
Total Appx Qty.
Rate Unit Amount in Rs.
1 NS 2010-17
Insertion and removal of Railway's stee cribs ( CC cribs) of nominal size 0.60x0.60x1.80 metre with railways hard wood packing for temporary arrangements/sccaffolding including handiling from and to stacks at nominated locations at site with all contractor's labour, tools plants, machinery , all lead lift etc., complte and as dirceted by the Engineer-in charges at site.
0 300 0 300 54.90 Each 16470
(Item ONE only) Value of schedule-B-1 16,470
Percentage Rate quoted “in Figures”
At par
Percentage Rate quoted “in Words”
At par only
Page 15 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
CONDITIONS
1. The tenderers are required to quote a uniform percentage rate above or below/at par of USSR 2010 of
S.C. Railway, for the items included in the Schedule „A‟, „A-1‟& A-2‟ and „Schedule „B & B-1‟
separately both in figures and words.
2. The quantities furnished in the schedule are approximate and the work will be carried out as directed
by the Engineer-in-charge. The payment will be made for the actual quantities executed.
3. The rate quoted by the contractor will be inclusive of the cost of all the materials, labour, tools &
plant etc., complete including transportation of the same at his own cost including loading and
unloading.
4. The materials to be supplied and used by the Contractor should have specific prior approval of the
Engineer-in-charge and the work should be carried out in accordance with standard specifications
for materials and works of S.C. Railway.
5. Any work shall be executed by the contractor on running track in a workman like manner to the
satisfaction of the Engineer-in-charge. In the event of an accident occurring wholly or partly due to
any act of tantamount to the negligence on the part of the contractor or his labour, the contractor
shall render himself liable for the damages and also legal prosecution if loss of life is involved.
6. The Railway reserves the right to reject or alter any part of the work executed by the contractor
which in the judgment of Rly. does not comply with the requirements of the specification. The
decision of Railway shall be final on conclusive for all proposes.
7. If any other items of works covered by USSR 2010 of S.C. Railway are required to be executed, the
same are to be carried out with the same percentage as quoted by the contractor ( I.e.) above or
below /at par of S.C. Railway, USSR 2010.
8. Potable fresh water is only permitted for all concreting works and other masonry works of these
bridges.
9) General instructions to be followed for usage of cement:
a) The cement proposed to be used for all items of works should confirm to I.S specification 12269 –
1987 of 53 grade. And the agency executing should submit a test certificate for standard
properties of cement.
b) The quantity should be regulated to the actual requirement for each item of work.
c) Consumption register should be maintained by the SE/SSE In charge of the work.
d) Extracts of the consumption register should be enclosed with the bills to ensure the consumption at
par with the requirement.
e) Cement consumption register should be test checked by ADEN periodically.
10) Bar bending schedule should be enclosed along with bills confirming the steel used on the work is
at par with requirement.
11) All MS rods used shall confirm to IS 432-1982.
12) Conservancy cess charges will be recovered from the contractor‟s bills as per Rules in
force.
Page 16 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
13) All rivet steel to comply with IS specification 1148/64.
14) Fabrication of steel work should comply with IRS specification B.I-2001
15) Welding should confirm to IS 9595/96 if so wherever required.
16) The primer coat Zinc chromate primer should confirm to I.S. specification 104-1962 and Zinc
chrome red oxide to specifications I.S. 2074-92.
17) The painting with aluminium should confirm to I.S 2339-63.
18). The painting should be in accordance with the specifications for painting and the paints
proposed to be used on the work should be got tested at CMT/ Lalaguda before use.
19) The steel used for bridges including FOBs shall confirm to specification No. IS.2062-2006 grade
„B‟ for plates & Grade „A‟ for rolled structural members and it is to be ensured that the steel
used for bridge works including FOB shall not be of rerolled variety and should be from stock
yards of SAIL/TISCO/IISCO/VIZAG steel or from any other ISI manufacturing units. The
necessary steel test certificate should be obtained from the SAIL/TISCO/IISCO/VIZAG firms to
the above specifications for the materials to be used for this work.
20) The joints for main structural members such as ISMB/RSJ/Angles are not permitted. The joints
to be provided if any should be according to the specifications and as per approved standard
drawings only.
21) Controlled Cement Concrete: -
1. Specifications of controlled concrete is enclosed vide Annexure „A‟
2. a) The contractor has to submit the design mix for controlled concrete items i.e., M20, M25
and M 35 grades, wherever required and the same has to be got approved by Engineer-in-
charge before starting the work.
b) The contractor has to make his own arrangements for submitting the cement concrete mix
design at his own cost, the rate quoted should include the cost of design mix, casting and
testing including all materials, leads and lifts, labour, tools, plant and machinery.
c) The contractor should prepare at his own cost, standard cubes of concrete at suitable
intervals during concreting operation under the supervision of Engineer-in-charge or his
representative and submit the same to the Railway for testing. The testing will be arranged by
the Railway at the contractor‟s own cost including freight charges for transporting the test
cubes to the testing laboratory.
d) The contractor should use hopper machine for mixing cement concrete for controlled
concrete items. e) The controlled cement concrete should comply I.S. Specifications.
22) “No Work” shall be done above or with in 2 meters from the live OHE with out a “permit-to-
work”. The draft proceedings order (Annexure-B) to be followed where OHE/TRD is in
existence.
23) Painting work should be done under the supervision of competent Bridge engineering staff
only.
Page 17 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
24). To carry out the painting/maintenance works on the girder bridges/Foot over bridges i.e., with
in the vicinity of OHE (less than 2 Meters distance) a memo has to be sent to TRD supervisor of
the jurisdiction by the SSE/SE/BR duly mentioning the time period required to arrange the
„permit to work‟.
25) The accepted rates should be deemed to include all taxes direct or indirect leviable under
Central, State or Local bodies Act or rules, Octori, toll taxes, tools, royalties, seignorages, cess
and similar imposts that may be prevailing from time to time.
26) Insurance for the labour working at site shall be done before commencement of the work and a
copy of the same to the submitted to SSE/Bridges concerned.
27) Safety equipment like helmet, safety belts etc., are to be supplied to the labour working at site.
28) The work should be completed with in Six months after receipt of acceptance letter.
Page 18 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
ANNEXURE-B.
Draft proceeding order to be followed by TRD and Engineering supervisors/ Tenderer
/Contractor with regard to maintenance works for the Bridges:
1. “No Work” shall be done above or with in 2 meters from the live OHE with out a “permit-to-
work”.
2. Use of steel measuring tapes or long metalising wires is prohibited in electrified sections.
3. Painting work should be done under the supervision of competent Bridge engineering staff only.
4. To carry out the painting/maintenance works on the girder bridges, FOBs i.e., with in the
vicinity of OHE (less than 2 Meters distance) a memo has to be sent to TRD supervisor of the
jurisdiction by the SSE/SE/BR mentioning the time period required to arrange the “Permit to
work”.
5. No Engineering (SSE/SE/BR) supervisor should allow the contractor staff or bridge staff to
carryout the works on bridges (Less than 2 meters from OHE) with out obtaining “permit-to-
work” from the authorized person of TRD Official.
6. After obtaining power-block on OHE, the TRD supervisor will then arrange two discharge rods
to OHE on either side of the Bridge work spot, and then issue permit –to-work to engineering
supervisor.
7. After completion of the work, the Engineering supervisor should give a clearance memo to TRD
supervisor and then only the two discharge rods will be removed from OHE and the OHE will be
charged.
8. Care should be taken when labour were engaged by contractor to do the painting on the girder
bridges i.e., they should be allowed to work after obtaining permit to work only.
9. While doing the painting/maintenance /Erection works beyond 2 meters distance to OHE the staff
must be counseled/watched not to come into the danger zone (i.e. below 2 meters distance to
OHE) during the course of working by SSE/SE/BR.
10. Responsible person from the SSE/SE/BR side should be available at the work spot of the Bridge
maintenance/painting works during the “power block” (permit to work) period to avoid any
untoward incidents.
Page 19 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
Special Conditions for dismantling of existing Foot Over Bridge at Gudur station
1. Cranes should be in proper working condition with full capacity.
2. Day for payment of crane charges will be counted from the time actual block work starts.
3. Deployment of No. of cranes on any specific day should be as per the instructions of
Engineer-in-charge. He should complete all the preliminary works required for attending
line block within the specified period as per instructions of engineer-in-charge.
4. Tenderer/Contractor has to make all preliminary arrangements to carryout the dismantling
works of Foot over bridge/stairway with all contractor‟s labour, tools, plant, machinery etc.
5. The contractor should note that the adjacent lines, should not be affected/ obstructed during
the dismantle of FOB work. Traffic on adjacent lines should also be not disturbed during
dismantling of FOB (other than nominated lines)
6. Work has to be executed in the running condition/ under the traffic block. The block will be
made available as per the convenience of the Railway depending on the positions of the
trains. The contractor shall note that, no claims will be allowed for delay in getting
traffic/power blocks.
Page 20 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
Steel special conditions
1. The Tenderers are required to quote a uniform percentage rate above/below/at par over the
estimated rates for the items of works included in the schedule, duly inspecting the bridge
locations and nature of works involved to carryout the repairs and feasibility of working.
2. The quantities furnished in the schedule are approximate, and the payment will be made for
actual quantities executed.
3. The M.S.Angles to be used for the wor shall confirm to I.S. 2062-2006 Grade „A‟ and M.S.
Plates to IS 2062-92 Grade‟B‟ and M.S.Rounds of approved quality and as per specifications.
4. The steel shall be from stockyards of SAIL/TISCO/IISCO/VIZAG steel (or) from any other ISI
manufacturing units rerolled quantity of steel will not be permitted to use for bridgework.
5. Necessary steel test certificate have to be produced to Engineer-in-charge before starting
fabrication.
6. The section is an Electrified track section and necessary safety precautions have to be taken
during the execution. Railway will not entertain any claims on any account.
7. The rates quoted will be inclusive of cost of materials, labour, tools, plant, machinery,
transportation consumables, lead, lift etc., complete.
8. The Contractor has to use his bolts, nuts and washers and M.S.Rivets of required size as per site
requirement in consultation with the Engineer-in-charge.
9. Welding should confirm to IS.9595/96.
10. Fabrication of steelwork shall confirm to IS specification B1-2001.
11. No wastage is permitted. The payment will be arranged for net quantity supplied and fixed at the
bridge.
12. The Tenderers are required to inspect the bridge site before quoting the rates for feasibility to
carry out the work.
13.Any work should be carried out by the contractor on running track in a workman like manner to
the satisfaction of the Engineer-in-charge. In the event of an accident occurred wholly or partly
due to any act tantamount to the negligence on the part of the contractor/his labour the contractor
shall render him self liable for the damages and also legal prosecution if loss of life is involved.
14. The paints used for the work shall confirm to the following specifications, and the samples
should be tested at CMT/LGD.
a).Zinc chromate to IS 104
b).Zinc chromate Red-oxide to IS. 2074.
c) Aluminium to IS.2339.
Necessary test certificates are to be enclosed for the Bills.
15.Conservancy Conservancy cess charges will be recovered from the contractor‟s bills as per Rules
in force.
16. Necessary safety precautions shall be taken as per existing rules in force before taking up the
work for execution
17.The work should be completed with in SixMonths and the Maintenance has to be done for a
period of SixMonths.
Page 21 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
ANNEXURE-„A‟
SPECIFICATIONS OF CONTROLLED CONCRETE:
1. The agency shall indicate the source of supply of materials viz., course aggregate, fine aggregate, steel, ordinary
Portland cement and cement conforming to IS as applicable. All the materials shall conform to relevant standard
specifications.
2. The TOR steel is purchased from TISCO, IISCO, SAIL, Vizag steel plant or any other source approved by the
Engineer-in-charge. The steel shall not be re-rolled variety. The agency shall produce necessary vouchers in original
in support of the purchase of steel and cement from the suppliers along with certificates to relevant standards from
the manufacturers before the commencement of work.
3. The agency shall submit samples of course/fine aggregate along with necessary cement, required for mix design. The
Engineer-in-charge at site shall forward the samples to a reputed concrete laboratory for carrying out mix design
duly specifying the various parameters as per IRS bridge code, provision and correction slips and Engg. Standard
order No: 11/2000 and RDSO‟s A&C slip no. 8, dt. 15/22-02-2006 The following parameters shall be specified for
the mix design by the Engineer-in-charge.
a) Grade of concrete required as per IRS bridge code.
b)Type of cement sent for mix design.
c) Minimum and maximum cement content prescribed as per the environment condition prescribed in the IRS
concrete bridge code 1997. Corrections slip No: 8 dt. 15/22-02-2006. The environment condition to be decided as
per Engg. Standing order No: 11 dt: 23-10-2000/7-11-2000.
d) Maximum water cement ratio to be adopted as per environmental condition. The agency shall arrange for mix
design at their own cost including movement of materials to laboratory. During the execution of work if there is any
change in the materials forming concrete, mix design shall be carried out again and work to be carried out
accordingly.
The following are extracts of IRS concrete bridge code 1997, Correction slip No: 8 dt. 15/22-02-2006
Amend the following clauses as follows.
i) Clause 5.1.1: Table 2 is revised as under.
Table 2: Grades of Concrete (Clause 5.1)
Grade
Designation
Specified Characteristic
compressive strength at
28 days (N/mm2)
M10 10
M15 15
M20 20
M25 25
M30 30
M35 35
M40 40
M45 45
M50 50
M55 55
M60 60
Page 22 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
ii) Clause No.5.2.2.1: Table is revised as under.
Grade of
concrete
(N/mm2)
Modulus of Elasticity
(KN/mm2)
M10 18
M15 22
M20 25
M25 26
M30 28
M40 31
M50 34
M60 36
iii) Clause No. 5.3.1:
Following note to be added below table given for workability of concrete.
Suitable plasticizers/admixtures may be used to achieve workability of the order of 150-
200mm.Plasticizers/admixtures should confirm to clause 4.4.
iv) Clause No.5.4.1:
The word “low water cement ratio” appearing in fourth sentence should be replaced by “adequate water
cement ratio.”
v) Clause No.5.4.3:
The Table 4(a) is revised as under: TABLE 4(a) : Maximum water cement ratio: (Clause No.5.4.3:)
Environment
Maximum water cement ratio.
Plain
cement(PCC) Reinforced concrete (RCC)
Prestressed concrete
(PSC)
Mild 0. 55 0. 50 0.45
0. 50 0. 50 0. 40
Severe 0. 50 0. 45 0. 40
0. 50 0. 45 0. 35
Extreme 0. 45 0. 40 0.35
vi) Clause 5.4.4 The Table 4(b) is revised as under: TABLE 4(b): Minimum grade of concrete: (Clause 5.4.4)
Environment Plain concrete (PCC) Reinforced concrete
(RCC)
Prestressed concrete
(PSC)
Mild M- 10 M- 15 M- 35
Moderate M- 10 M- 20 M- 35
Severe M- 15 M- 20 M- 45
Very severe M- 15 M- 25 M- 50
Extreme M- 20 M- 30 M- 50
Page 23 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
The concrete of grades M-10, M-15 & M-20 are normally used in mass concrete work and usually mixed by
volumetric batching also. The mix for this work would be
M-10 1:3:6
M-15 - 1:2:4
M-20 - 1:1.5:3
vii) Clause 5.4.5 Table 4 (c) is revised as under
TABLE : 4 ( c ) :Minimum cementitious material content: (Clause 5.4.5)
Environment
Minimum cementitious material content in Kg/cum
Plain concrete
(PCC)
Reinforced concrete
(RCC)
Prestressed concrete
(PSC)
Mild 210 300 350
Moderate 250 300 400
Severe 250 350 430
Very severe 300 400 440
Extreme 300 400 440
Max. Cementitious material content shall be limited to 500 kg/cum vide No. 5.4. 5.
Note: For under water concrete 10 % extra cement should be added over and above the normal cement
content of the concrete mix specified above.
viii) Clause 5.4.7
This clause is deleted along with its sub-clauses
ix) Clause 7.1.3.4
Replace this clause by clause as under:
Sufficient spacers shall be provided as shall in the opinion of the Engineer be necessary to maintain
specified concrete cover to the reinforcement and preventing displacement before and during the placement
of the concrete. Spacers should be of such material and designs as will be durable, will not lead to the
corrosion of the reinforcement and will not cause spalling of the concrete cover. Spacer block made from
cement, sand and small aggregate should match the mix proportions of the concrete as far as is practicable
with a view to being comparable in strength, durability and appearance. The use of the pieces of wood, tile
or porous material will not be allowed for this purpose.
Page 24 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
x) Clause 7.1.3.5
This clause is deleted
xi) Clause 7.1.5 is replaced as below
Protective coatings: in order to offer adequate resistance against corrosion, reinforcement bars may be
provided with suitable protective coatings depending upon the environment conditions. In aggressive
environments (Severe, Very severe and extreme) application of cement slurry coatings after removal of rust
and other loose materials from the surface of the reinforcement bar will generally be sufficient. However,
specialist literature may be referred to in extreme exposure condition.
xii) Clause 15.9.2.3:
This clause is deleted.
Clause No. 15.9.2.4 and 15.9.2.5 should be read as 15.9.2.3 and 15.9.2.4 respectively.
4. The following are the extracts of Engg. Standing order No: 11 issued by S.C.Railway dt. 23-10-2000/7-
11-2000.
i). Moderate: - All the bridges situated in area which are not exposed to severe rain or witch are
continuously under water of where concrete is in contact with non aggressive soil/ground water will fall
under this category. All sections of this Railway which are not listed under severe category below are
classified under moderate category.
ii) Severe:- Structures which are situated in area which are exposed to severe rain, alternate wetting and
drying or occasional freezing or severe condensation and also in locations where the concrete is exposed to
aggressive sub soil ground water or situated in coastal environment.
The following sections of this railway have been identified to be classified under severe category.
a) Londa - Vasco-da-gama ---- Hubli Division.
b) Gudur -Visakhapatnam.
c) Gudur-Machilipatnam. ---- Vijayawada Division.
d) Bhimavaram-Narsapur.
e) Samalkot- Kakinada
i) Industrial areas as decided by the concerned Divisional Engineers, where corrosive action is severe.
ii) Very severe and extreme:- Classification of particular bridge in these categories of environment will
depend on case basis as per the actual physical location and as decided by the Chief Bridge Engineer or
concerned Chief Engineer/ construction.
All the requirements specified in the correction slip No:1 for the above categories should be strictly
followed in accordance with the correction slip.
5. The agency shall keep minimum two Nos. of concrete pin vibrators of 25/40mm size in good working
order during concrete operation. At no point of time, vibration of concrete should suffer for want of power or
for any other mechanical problem any such concreting without proper compaction will be rejected and the
agency shall redo the work at their own cost.
6. The contractor should prepare at his own cost standard cubes of concrete at suitable intervals, during
concreting operations under the supervision of the Engineer or his representative and submit the same to the
Railway for testing. The testing will be arranged by the Railway at the contractors own cost including freight
charges for transporting the test cubes to the testing laboratory.
Page 25 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
7. Protective coatings: In order to offer adequate resistance against corrosion reinforcement bars shall be
provided with suitable protective coating for bridges depending upon the environment conditions. The
recommended
TABLE (d) : Protective coatings:
Aggressive Environment
(severe)
Severe, very severe and (Extreme) Non aggressive environment
(Mild and Moderate)
Important and Major bridges Minor bridges and structures All structures
Cement polymer composite
coating (or) Fusion bonded
Epoxy coating.
Cement polymer composite
coating (or) Indicated cement
slurry coating.
Truncatevinlubited cement
slurry coating.
Note: The binding wire should also be coated and no GI binding wire without coating will not
be permitted.
Page 26 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SAFETY PRECAUTIONS TO BE TAKEN AT WORK SITE.
1.1. The Contractor shall not allow any road vehicle belonging to his or his suppliers etc. to ply in railway
land next to the running line. If for execution of certain works, viz., earthwork for parallel railway
line, supply of ballast for new or existing railway line etc. road vehicles are necessarily to be used in
railway land next to the railway line, the contractor shall apply to the Engineer-in-charge for granting
permission giving the type and number of individual vehicles, names and license particulars and
permanent addresses of drivers, location, duration and timings for such work/movement. The
Engineer-in-charge or his authorized representative will personally counsel, examine and certify the
road vehicle drivers, contractor‟s flagmen and his supervisors to be deployed on the work, location,
period and timing of the work.
This permission will be subject to the following obligatory conditions:-
i) The Road vehicle will ply only between sunrise and sunset.
ii) Nominated vehicles and drivers will be utilized for work in the presence of at least one flagmen
and one supervisor or his representative certified for such work.
iii) The vehicles shall ply 6 Meters (from Centre of Track) away from track. Any movement
/work at less than 6 Meters and up to minimum 3.5 Meters clear of track center shall only be
done in presence of railway employees authorized by the Engineer-in-charge . No part of road
vehicle will be allowed at less than 3.5 Meters from track center.
iv) The Contractor shall remain fully responsible for ensuring safety and in case of accident, shall
bear the cost of all damages to the equipments and men and also damages to railway and its
passengers.
v) Engineer-in-charge may impose any other condition necessary for a particular work or site.
1.2.1. The Contractor at all times shall adopt safe working methods to ensure safety of structures,
equipments and labour at site of works.
1.2.2. The contractor shall not start any work without the presence of Railway supervisor or his
representative authorized by ADEN-in-charge and Contractor‟s supervisor at site.
1.2.3. The methodology proposed to be adopted by the Contractor is to be approved by Engineer-in-charge
with a view to ensure of safety of trains, passengers and workers and he shall also ensure that the
methods and arrangements are actually available at site before start of the work and the contractor‟s
supervisors and the workers have clearly understood the safety aspects and requirements to be
adopted / followed while executing the work.
1.2.4. There shall be an assurance Register kept at each site, which will have to be signed by both, ie.,
Railway Supervisor or his representative as well as the contractor‟s supervisor as a token of their
having understood the safety precautions to be observed at site.
1.2.5. Survey of site by Supervisor of contractor and Railway‟s Supervisor is to be done to assess
precautions to be taken at site for working of trains and materials required for protection.
Page 27 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
1.2.6. The list of permissible / sanctioned infringements to moving dimensions for the section shall be made
available where work is to be done to execute the works without infringing the moving dimensions.
1.2.7. Competency certificate issued by ADEN-in-charge with the Contractor‟s supervisor at site should be
available in the format given in Annexure-I.
1.2.8. The detailed plans for safe execution of works, duly approved by the Division should be available for
undertaking execution of such works which have bearing on moving dimensions, especially those
works close to the running lines and fixed structures on brides, inside tunnels etc.,
1.2.9 Look-out caution, speed restrictions as well as traffic block shall be ensured where necessary for
execution of works affecting running lines.
1.2.10 Mobile phones or Walky-Talkie sets where necessary should be provided at work sites.
1.3. Precautionary measures to be taken at work site away from the track:-
1.3.1. Trenches and foundation pits should be adequately and securely fenced, provided with proper caution
signs and marked with red lights at suitable intervals during night to avoid accidents. Adequate
protective measures should be taken to see that the excavation operations do not affect or damage
adjoining existing buildings.
1.3.2. Proper precautions should be taken for safety of persons and adjoining property before undertaking
any blasting operation. Red flags should be prominently displayed around the area to be blasted. All
the people on the work except those, who actually light the fuses, should be withdrawn to a safe
distance of not less than 300 meters from the blasting site. Recommendations given in I.S. 4081:1986
should be followed for safety during various operations involved in the process of blasting.
1.3.3. Suitable scaffold should be provided for workman for all works that cannot be safely done from the
ground or from solid constructions except such works which can be done safely from ladders for a
short period. When a ladder is used, extra labour should be engaged for holding the ladder and if the
ladder is used for carrying materials as well, suitable foot holds and handholds should be provided on
the ladder and ladder should be given an inclination not steeper than 4 to 1 ( Four vertical to one
Horizontal).
1.3.4. Workers employed on mixing asphalt materials, cement and lime mortars should be provided with
protective hand and footwear and protective goggles.
1.3.5. Workers employed in white washing and stacking of cement bags or any materials which are
injurious to the eyes should be provided with protective goggles.
1.3.6. Workers engaged in welding works should be provided with welder protective eye-shields, single
piece cotton cloth and shoes.
1.3.7. Stone breakers should be provided with protective goggles, leg-guards and protective clothing and
they should be seated at sufficiently safe distance from each other.
1.3.8. A fully equipped First-Aid Box should be maintained at site by the Agency with at least one person
fully trained to give First-Aid.
1.3.9. Inflammable articles such as Petrol, oil etc., should be stored separately from other materials and all
prescribed precautions as per the Indian Explosive Act should be taken.
Page 28 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
1.3.10. In the Bridge work, Track works, repairs to tunnel and demolition of structures through contractual
Agency, the safe working and ensuring safety of workman employed should be specifically laid down
in the contract itself.
1.4. Precautionary measures to be taken at work site in vicinity of track:-
1.4.1. Drivers of trains must be served with caution order to look out for any obstruction at the place of
work.
1.4.2. Arrangements should be made to protect the track in case of emergency at work site.
1.4.3. Before the start of the work, the land strip adjacent to the running track where road vehicle /
machinery is to ply for the work shall be demarcated by lime in advance at the appropriate distance
from the centre of existing track in consultation with the Railway Supervisor[Annexure-IV(A)].
Sketch showing the location of marking and barricading along the full length of the work area should
be done as per the sketch given in [Annexure-IV (B)]. This will enable the workmen posted at the
site and also the lorry drivers to have clear guidelines on the movement of vehicles.
1.4.4. Movement of Lorries near the track should be prohibited during night. In case it is unavoidable
adequate protective measures including lighting must be ensured in the complete work area for the
safety of the Public and Passengers. Also additional staff shall be posted as necessary for night
working.
1.4.5. Work should not be allowed to progress without the prior approval of the Engineer-in- charge in case
movement of vehicles close to the track is involved.
1.4.6. Machines and vehicles should ply 6 meters (from Track centre) in case movement at less than 6
meters away from the track is inescapable, it should be permitted in the presence of Railway
employee authorized by the Engineer-in-charge.
1.4.7. Contractor‟s representative should be issued a certificate by ADEN to the effect that they have
acquired sufficient knowledge about the safety precautions that are needed to be followed while
working near the track.
1.4.8. The worksite shall be suitably demarcated to keep public and passengers away from work area.
Necessary sign boards such as Work in progress etc. shall be provided at appropriate locations to
warn the Public / passengers.
1.4.9. Check lists given in Annexure-II and III shall be used to ensure that all the requisite measures have
been taken before start of work and work in progress.
1.4.10. All temporary arrangements required to be made during execution of work shall be made in such a
manner that moving dimensions do not infringe. Necessary checks shall be exercised by Site in-
charge from time to time.
Page 29 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
WORKING OF CONTRACTOR’S VEHICLES AT SITE
1 When the contractor’s vehicles are to be worked closer to 6m but not less than 3.5m from center line of the running track (Annexure-VA)
i) Drivers of vehicle shall be briefed about safety and precautions to be taken while moving/working close to traffic. ii) Demarcation of the land shall be done by bright coloured red ribbon/nylon rope of 12mm thick suspended on 75cm
high wooden/bamboo posts at a distance of 3.5m from center line of nearest running track as shown in (Annexure-IVC)
iii) Contractor shall ensure the road vehicle/Machinery ply in a way so that these do not infringe the line of demarcation.
iv) Presence of an authorized Railways representative shall be ensured before plying of vehicles or working machinery.
v) Railway supervisor shall issue suitable caution order to drivers of approaching train about road vehicles plying or machinery working close to running tracks. The train drivers shall be advised to whistle freely to warn about the approaching train. Whistle boards shall be provided wherever considered necessary.
vi) Lookout men shall be posted along the track at a distance of 800m from such locations, which will carry red flag and whistles to warn to the road vehicles/machinery users about the approaching trains.
vii) On curves where visibility is poor, additional lookout men shall be posted. viii) In unusual circumstances, where operator apprehends infringement to track while working truck/machinery near
running track, following action shall be taken: a) The contractor /supervisor/vehicle operator immediately advise the situation to Railway official and assist him in
protecting the track. b) Protection shall be done for other emergencies.
2. When the contractor’s vehicles are to be worked close to 3.5m from center line of running track: i) Plying of vehicle or working of machinery closer to 3.5m of running track shall be done under protection of track.
Traffic block shall be imposed wherever considered necessary. The site shall be protected as per the sketch given in (Annexure-VB) and the provisions of Para No. 806 & 807 of P-way Manual as the case may be.
ii) Presence of a Railway supervisor shall be ensured at work site. iii) Railway supervisor shall issue suitable caution order to drivers of approaching train about road vehicles plying or
machinery working close to running tracks. The train drivers shall whistle freely to warn about the approaching train.
3. Parking of vehicles or construction machinery: i) No vehicle or construction machinery shall be parked in unmanned condition on a gradient sloping towards running
track. ii) Even on level ground or gradients sloping away from the track, vehicles or construction machinery shall be parked
in unmanned conditions at a minimum distance of 6m from nearest track center in fully braked condition. In addition to brakes, suitable wedges shall also be applied on all the wheels.
4. TRAINING Training in safe working methods for both along and on the track should be imparted to supervisors /operators of the work executing agencies. Such training may be imparted at zonal/divisional training schools for required duration as deemed fit, with a view to ensure that the field staff engaged in such works get acquainted with the safety precautions that are needed to be taken while executing the works.
Page 30 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
ANNEXURE - I
COMPETENCY CERTIFICATE
Certified that Shri………………………………………………….
P.Way supervisor of M/s. …………………………… has been
Examined regarding P.Way working on ………………………….
Work. His knowledge has been found satisfactory and he is capable of
Supervising the work safely.
ASSISTANT ENGINEER
Page 31 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
ANNEXURE – II
CHECK LIST (BEFORE STARTING THE WORK)
Name of the work : ………………………………………………………………………………
Location …………………………………………………………………………………………
Duration of the work : From …………………………… To …………………………………
Sl. No
Details Yes No
1 Contractor’s supervisor identified / Selected. Who is going to be site in-charge?
2 Training imparted to contractors supervisor & Certificate issued?
3 Work site inspected by Constructions supervisor / other department’s supervisors along with contractor’s supervisor?
4 Precautions to be taken identified and listed?
5 Plan of work, drawn out by contractor’s supervisor in consultation with Railway’s supervisor?
6 Plan of work, brought to the knowledge of open line AEN/IOW & PWI?
7 Before start of the work, proper lime marking / barricading had done at site of work?
8 Men deputed for protection of track along with safety equipments?
9 Caution order issued for the train drivers in case work is being done within 6mts of centre of running track?
10 Drivers of vehicles/machinery being used have been identified?
11 Drivers of vehicles/machinery briefed about the safe working?
12 Sufficient lighting provided at site of work for night working?
13 Infringements checked?
14 Sectional (Open line) AEN/PWI/IOW have satisfied themselves regarding safety arrangements?
15 Availability of Walkie –Talkie sets for communication?
Signature of construction/ Other departments Supervisor
Date:
Signature of Open line’s Supervisor.
Page 32 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
ANNEXURE – III CHECK LIST
( WHILE WORK IN PROGRESS )
Name of the work : ………………………………………………………………………………
Location …………………………………………………………………………………………
Duration of the work: From …………………………… To …………………………………
Date of inspection ……………………………………………………
Sl.No
Details Yes No
1 Does the contractor’s supervisor have the certificate?
2 Does the knowledge of contractor’s supervisor on safety of track & work site is up to the mark?
3 Is the Railway’s supervisor of Construction Organization/other departments available at site?
4 Is knowledge of Railway’s supervisor O.K.?
5 Is lime marking/barricading done?
6 Are adequate safety precaution taken?
7 Are communication facility (Walkie – Talkie sets) available at site?
8 Are only identified drivers driving the vehicles/machinery?
9 Is whole work site safe for working of men/vehicles & trains?
10 Are adequate lighting arrangements done at site?
11 Are adequate protection equipment available at site?
12 Is caution order to trains being issued?
13 Are train drivers following the enforced temporary speed restriction?
14 Has work permit been taken for working in Electrified territory/Station yards (P &C areas)
Designation
Page 33 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
ANNEXURE – IV
(A)Marking of Line with Lime
3500mm
150 mm wide white line with lime
Vehicle / trucks can ply in this` area
B) Provision of Barricading
3500mm
Barricading
Luminous tape/Red Colour Nylon Rope 12 mm thick
Post (Bamboo / Steel / Concrete)
1200mm
3500mm 3500mm 3500 mm
C) Elevation of Barricading
Page 34 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
ANNEXURE –V
A) Plying of Vehicles/Machinery between 3.5 mts. to 6.0 mts from centre of track
3500mm
Contractor‟s supervisor Railway‟s supervisor
150 mm wide white line with lime
6000mm
B) Plying of Vehicles / Machinery within 3.5 mts from center of track
DN LINE
Banner flag in day time / HS lamps in night
detonators
UP LINE
1200 metres
3500mm
detonators
Contractor‟s supervisor Railway‟s supervisor
Page 35 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SPECIAL CONDITIONS FOR BUILDING WORKS.
1. For any other items not specially shown in the schedule of rates appended to the tender document, the
Divisional Engineer, will offer rates as shown for the relevant zone in the USSR 2010 subject to the same
percentage adjustment accepted in the contract being applicable to the additional items.
2. The quantities shown in the tender schedule are approximate and will be operated in full or part at the
discretion of the Engineer in charge. Payment will be made based on the actual items operated.
3. All items included in the tender schedule should be carried out in accordance with the Standard
Specifications.
i) For materials and works up to date corrections there to of S C Railway
ii) All materials to be supplied and used by the contractor in connection with this for should have
prior specific approval of the Engineer in charge and should be in accordance with the
specifications for materials and works of SC Railway
iii) Details of fittings and fastenings required for wooden doors, cup-boards and ventilators,
etc., should be of approved quantity and should have prior approval of the Engineer in charge
and should be in accordance with the Standard Specifications for Materials and works of SC
Railway.
4. The tenderers are required to study all the drawings.
i) Referred to in the tender thoroughly before quoting the rates.
ii) The Railway reserves the right to change their drawings during the execution of
works and the contractor should execute the work as per the revised drawings. No extra
payment nor claim will entertained on that account. Payment will be made to the contractor
for the work actually done at the accepted rates of agreement.
5. Details of ducts, chassis, etc., that may be required to be provided for wiring, etc., will be indicated
during progress of the work.
6. Tenderers/Contractors will arrange to provide them in walls, floors, RCC slabs, etc., wherever
necessary as directed by the engineer in charge without any extra claim any pipes, conducts or hooks,
required for electrical shall be placed by the tenderer/contractor at any position indicated without any
extra claim. The pipe conducts hooks, etc., bends to the required slopes will be supplied by the
Railway at the site of work.
Page 36 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
7. The contractor is required to safe guard the steel issued to him and to use the same on the work in
accordance with actual requirement as approved by the Engineer as may be indicated in the relevant
drawings or specification. Short lengths of rods should also be utilized to the extent possible by over
lapping the joints.
i) Materials supplied by the Railway on its own cost, left over on completion of the work will be
the property of the Railway and should be returned to the depot/godown as directed by the
Engineer in charge. In case, it is noticed that on completion or termination of work, the
consumption of the materials had been found to be in excess of the quantities laid down and the
contractor is unable to account fully, the materials issued either due to neglect in safe custody or
to any other reasons, covered at twice the issue rates. The issue rate should be the rate of
prevailing at the time of last issue of the materials concerned. While computing the quantities,
the wastage will be allowed in accordance with the previsions stipulated there for in the
conditions of the contract.
8. All works should be maintained after completion for a period of six months for Engineering works
and the contractor should make good any defects, imperfection of faults, poor wood work etc., at his
own cost, during the maintenance period and defects like cracks, wards should be made good by the
contractor at his own cost inclusive of effected masonry work etc., while rectifying wood work.
9. Electrical energy that may be required for operating the plant, will be supplied by the Railway wherever
feasible at the discretion of the Railway on payment of the charges as required by the Electrical
department. The contractor will have to make his own arrangements for taking the connection from the
nearest Railway electrical source of supply.
10. The cement supplied should conform to I.S. specification 8112 for 43 Grade or I.S. Specification
12269 for 53 Grade before executing the work, the agency should submit a test certificate for Standard
Properties as well as indicating the source of supply and brand of the cement.
.
Page 37 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SPECIAL CONDITIONS OF CONTRACT
1. The rates include all lead and if the materials obtained by rail all freight charges including
loading charges. 2. Sales tax, Royalties and Octroi duties, if any, that may be payable under Provincial
Government Sales Tax Act or Local Bodies Act or rules on any of the material that may be
used or supplied by the contractor will be payable by the contractor. The Railway will neither
pay the taxes or duties nor be bound to compensate the contractor for any amounts paid by him
by way of these taxes or duties.
Sales Tax at 4% on the materials portion of the contract will be deducted from each on account
bill where identifiable. Where the labour and material portion is not clearly identifiable, the
labour element shall be taken as 30%. On the balance 70% of the value of the work, 4% shall
be deducted pro-rata from each “on account bill” towards Sales tax.
Seigniorage charges recoverable from bills:-
Seigniorage charges for supply of earth, mooram, sand and other minerals as fixed by the State
Government and payable to them as revised from time to time during the currency of contract
will be recovered by Railway from the contractors “on account” and “final bills” and remitted
to the state government. The rates quoted by the Tenderer shall be inclusive of these charges.
Claims regarding revision of seigniorage charges and consequent enhancement of the accepted
rate will not be entertained. However, no seigniorage charges / fee shall be recovered from the
bills of the contractor, if the contractor produces documentary evidence e.g. “Transit Passes”
issued by State Govt. Officials in token of having paid seigniorage fee. In such cases, the
genuineness of such documentary evidence produced along with proof of payment of
seigniorage charges, shall be got verified by the Railway from the concerned Mining and
Geology Dept 3. WATER:- A charge of One percent will be made by the Railway for the supply by the
Railway of piped water from existing pipe lines and calculated on the amount of all items of
work (USSR/NS items) appearing in the bills payable to the contractor in respect of which
work such water has been issued to the Contractor and such charges should be deducted from
sums due or payable by the Railway to the Contractor from time to time.
4. In the event of water having to be brought by the Railway to the site of the work in traveling
tanks, the actual freight at Public Tariff rate and all other charges incurred therein including any
demurrage that may be levied shall be payable by the Contractor and deducted from sums due
or payable by the Railways to the Contractor from time to time.
In addition to the charges of one percent referred to above, if additional pipe lines to
those already existing are called for by the contractor, the cost of the same and all charges
incurred by the Railway in their laying including supervision charges will be paid by the
contractor or the contractor provides and lay his own piping at the discretion of Divisional
Engineer.
5. The Railway does not guarantee work under each items of the Master Schedule. For example if
a gate-lodge or gang huts are to be built between stations and the work order issued to the
sectional contractors additional payment on account of lead or freight charges for the materials
that may have to be brought by rail or by road, will not be admissible.
Page 38 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
6. If there arises any discrepancy between the printed Unified Standard Schedule of Rates 2010 as
amended by addendum and corrigendum slips issued from time to time upto date and the
schedule attached to the Tender pertaining to this work, the former shall be treated as
authentative and binding in all purposes.
7. Rubble masonry shall be first sum of Railways Specification No 503 according to South
Central Railway Specification for materials and works. Contractors attention is particularly
invited to dressing of stone as laid down in the Railway‟s specification.
8. The Special conditions supplemented to the conditions of Tender and contracts the General
conditions of contract and the notes appearing under the relevant chapter and sub chapters of
the Unified Standard Schedule of Rates 2010 should be considered as part of the contract
papers where the provisions of these conditions are at variance with General Conditions of
Contract these special conditions.
9. Performance Guarantee (P.G.):-
a. The successful bidder shall have to submit a Performance Guarantee (PG) within 30
(thirty) days from the date of issue of Letter of Acceptance (excluding the date of LOA
Ref: CE/Works/SC Lr.W.148/P/GCC/Vil.II, dt.30.05.2014). Extension of time for
submission of PG beyond 30 (thirty) days and upto 60 days from the date of issue of
LOA may be given by the Authority who is competent to sign the contract agreement.
However, a penal interest of 15% per annum shall be charged for the delay beyond 30
(thirty) days, i.e., from 31st day after the date of issue of LOA (excluding the date of
LOA). In case the contractor fails to submit the requisite PG even after 60 days from
the date of issue of LOA, the contract shall be terminated duly forfeiting EMD and
other dues, if any payable against that contract. The failed contractor shall be debarred
from participating in re-tender for that work.
b. The successful bidder shall submit a Performance Guarantee (PG) in any of the
following forms, amounting to 5% of the contract value:-
(i) A deposit of Cash,
(ii) Irrevocable Bank Guarantee,
(iii) Government Securities including State Loan Bonds at 5 percent below the
market value
(iv) Deposit receipts, Pay orders, Demand Drafts and Guarantee Bonds. These
forms of Performance Guarantee could be either of the State Bank of India or
of any of the Nationalized Banks;
(v) Guarantee Bonds executed or Deposits Receipts tendered by all Scheduled
Banks;
(vi) A Deposit in the Post Office Saving Bank;
(vii) A Deposit in the National Savings Certificates;
(viii) Twelve years National Defence Certificates;
(ix) Ten years Defence Deposits;
(x) National Defence Bonds; and
(xi) Unit Trust Certificates at 5 percent below market value or at the face value
whichever is less.
Page 39 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
Also FDR in favour of Senior Divisional Finance Manager, S. C. Railway, Vijayawada
(free from any encumbrance) may be accepted.
1. The Performance Guarantee shall be submitted by the successful bidder after the Letter
Of Acceptance (LOA) has been issued, but before signing of the contract agreement.
This P.G. shall be initially valid up to the stipulated date of completion plus 60 days
beyond that. In case, the time for completion of work gets extended, the contractor
shall get the validity of P.G. extended to cover such extended time for completion of
work plus 60 days.
1.0 The value of PG to be submitted by the contractor will not change for variation upto
25% (either increase or decrease). In case during the course of execution, value of the
contract increases by more than 25% of the original contract value, an additional
Performance Guarantee amounting to 5%(five percent) for the excess value over the
original contract value should be deposited by the Contractor.
1.1 The Performance Guarantee (PG) shall be released after physical completion of the
work based on the „Completion Certificate‟ issued by the competent authority stating
that the contractor has completed the work in all respects satisfactorily. The security
deposit, however, shall be released only after the expiry of the maintenance period
and after passing the final bill based on „No Claim Certificate‟ from the contractor.
1.2 Whenever the contract is rescinded, the security deposit shall be forfeited and the
Performance Guarantee shall be encashed. The balance work shall be got done
independently without risk and cost of the failed contractor. The failed contractor
shall be debarred from participating in the tender for executing the balance work. If
the failed contractor is a JV or a partnership firm, then every member/ partner of such
a firm shall be debarred from participating in the tender for the balance work either in
his / her individual capacity or as a partner of any other JV / partnership firm.
1.3 The Engineer shall not make a claim under the Performance Guarantee except for
amounts to which the President of India is entitled under the contract (not
withstanding and / or without prejudice to any other provisions in the contract
agreement) and this shall be in the event of:
i) Failure of the contractor to extend the validity of the Performance Guarantee as
described herein above, in which event the Engineer may claim the full amount
of the Performance Guarantee.
ii) Failure of the contractor to pay President of India any amount due, either as
agreed by the contractor or determined under any of the Clauses / Conditions of
the agreement, within 30 days of the service of notice to this effect by Engineer.
iii) The contract being determined or rescinded under provision of the GCC the
Performance Guarantee shall be forfeited in full and shall be absolutely at the
disposal of the President of India
Page 40 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
10. Security Deposit:-
The scale of Security Deposit that is to be recovered from the contractor shall be as follows.
i) Security Deposit should be 5% of the contract value.
ii) The rate of recovery will be at the rate of 10% of the bill amount till the
full Security Deposit is recovered.
iii) Security Deposit will be recovered only from the running bills of the contract and no
other mode of collecting SD such as SD in the form of instruments like Bank
Guarantee, Fixed Deposit Receipt etc., shall be accepted towards Security deposit.
iv) Conversion of Security Deposit into FDR after recovery of full stipulated SD (FA& CAO/SC letter No.AFX/EMD/Policy/ Vol.I dt.26.8.2010 circulated vide
PCE/SC lr. No.W.148/ SCRCA dt.30.9..2010):- If the contractor so desires, the cash
deposits in the form of security deposit may be allowed to be converted into FDRs
(in favour of respective Accounts Officers and on account of contractor), after full
recovery, at the discretion of the Railway, duly collecting necessary charges of
conversion by the Railway Administration.
The security deposit shall be released only after the expiry of the maintenance period and
after passing the final bill based on „No Claim Certificate‟.
After the work is physically completed, security deposit recovered from the running bills of a
contractor can be returned to him if he so desires, in lieu of FDR/irrevocable bank guarantee
for equivalent amount to be submitted by him.
In case of contracts of value Rs.50 crores and above, irrevocable bank guarantee can also be
accepted as a mode of obtaining security deposit.
11. REVISED COMPREHENSIVE CLAUSE 46A OF GCC– PRICE VARIATION
CLAUSE: As per Railway Board Letter No.2007/CE-CT/18/Pt.19 dt.14.12.2012-Price
Variation Clause shall be applicable only for contracts of value (contract agreement
value) Rs.50 lakh and more, irrespective of the contract completion period and
Addendum & Corrigendum Slip (ACS) No.6 to GCC, July 2013; Amendment to Clause
46A.7 (a sub-clause of PVC) to GCC, communicated vide PCE/SC Lr.No.W.148/P/
G.C.C./Vol.II dt.05.06.2014. Amendment to Clause 46A1 (ACS No.2 to GCC, July-2014),
communicated vide PCE/SC Lr.No.W.148/P/G.C.C./Vol.II dt.12.12.2014. Clause 46A-Price Variation clause:
46A.1. Price Variation clause shall be applicable only for contracts of value as prescribed
by the Ministry of Railways through instructions/circulars issued from time to time
and irrespective of the contract completion period. Variation in quantities shall not
be taken into account for applicability of PVC in the contract. Materials supplied
free of cost by Railway to the contractors shall fall outside the purview of Price
Variation clause. If, in any case, accepted offer includes some specific payment to
be made to consultants or some materials supplied by Railway free or at fixed rate,
such payments shall be excluded from the gross value of the work for the purpose
of payment/recovery of price variation.
Applicability of PVC based on original contract value is illustrated as under:
“If estimated value of tender (NIT value) is Rs.55 lakhs; but value of the contract
as per contract agreement is Rs.45 laksh, then PVC shall not apply, even if the
actual final value is Rs.50 laksh or more due to variation in quantities during
execution of the contract. Thus, variation in quantities after signing of contract
agreement is not relevant for deciding whether PVC is applicable to a contract or
not”.
Page 41 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
46A.2. The Base Month for „Price Variation clause‟ shall be taken as month of opening of
tender including extensions. If any, unless otherwise stated elsewhere. The quarter
for applicability of PVC shall commence from the month following the month of
opening of tender. The Price Variation shall be based on the average Price Index
of the quarter under consideration.
46A.3. Rates accepted by Railway Administration shall hold good till completion of work
and no additional individual claim shall be admissible on account of fluctuations
in market rates, increase in taxes/any other levies/tolls etc., except that
payment/recovery for overall market situation shall be made as per Price Variation
Clause given hereunder.
46A.4. Adjustment for variation in prices of material, labour, fuel, explosives detonators,
steel, concreting, ferrous, non-ferrous, insulators, zinc and cement shall be
determined in the manner prescribed.
46A.5. Components of various items in a contract on which variation in prices be
admissible , shall be Material, Labour, Fuel, Explosives, Detonators, Steel,
Cement, concreting, Ferrous, Non-ferrous, Insulator, Zinc, erection etc., However,
for fixed components, no price variation shall be admissible.
46A.6. The percentages of labour component, material component, fuel component etc.,
in various types of Engineering Works shall be as under:
Component Percentage Component Percentage
A) Earthwork contracts:
Labour
component
50% Other material
components
15%
Fuel
component
20% Fixed
component*
15%
B) Ballast and Quarry Products contracts
Labour
component
55% Other material
components
15%
Fuel
component
15% Fixed
component*
15%
C) Tunnelling Contracts
Labour
component
45% Detonators
component
5%
Fuel
component
15% Other material
components
5%
Explosive
component
15% Fixed
component*
15%
D) Other Works Contracts
Labour
component
30% Fuel component 15%
Material
component
40% Fixed
component*
15%
*it shall not be considered for any price variation.
Page 42 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
46A.7. The Amount of variation in prices in several components (labour material etc., )
shall be worked out by the following formulae:
i) L= W x (LQ-LB) x LC
LB 100
ii) M = W x (MQ-MB) x MC
MB 100
iii) F = W x (FQ-FB) x FC
FB 100
iv) E = W x (EQ-EB) x EC
EB 100
v) D = W x (DQ-DB) x DC
DB 100
vi) S = SW x (SQ-SB)
vii) C = CV x (CQ-CB)/CB
For Railway Electrification works:
viii) T = {(CS – CO) /CO X 0.4136} X Tc
ix) R = { (RT – RO) / RO + ( ZT - ZO ) / ZO x 0.06 } x Rc
x) N = { (PT – PO ) / PO } x Nc
xi) Z = { ( ZT – ZO ) / ZO } x Zc
xii) I = { ( IT – IO ) / IT } x 85
Where
L Amount of price variation in labour
M Amount of price variation in Materials
F Amount of price variation in fuel
E Amount of price variation in Explosives
D Amount of price variation in Detonators
S Amount of price variation in Steel
C Amount of price variation in Cement
T Amount of price variation in Concreting
R Amount of price variation in Ferrous Items
N Amount of price variation in Non-Ferrous Items
Z Amount of price variation in Zinc
I Amount of price variation in Insulator
LC % of Labour component
MC % of Material component
FC % of Fuel component
EC % of Explosive component
DC % of Detonators component
Tc % of Concreting Component
Rc % of Ferrous Component
Nc % of Non-Ferrous Component
Zc % of Zinc Component
Page 43 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
W Gross value of work done by contractor as per on-account bill(s), excluding cost of
materials supplied by Railway at fixed price, minus the price values of cement and
steel. This will also exclude specific payment, if any, to be made to the consultants
engaged by contractors (such payment shall be indicated in the contractor‟s offer)
LB
Consumer Price Index Number for Industrial Workers- All India- Published in RBI
Bulletin for the base period.
LQ Consumer Price Index Number for Industrial Workers- All India-Published in RBI
Bulletin for the average price index of the 3 months of the quarter under consideration.
MB Index Number of Wholesale Prices- By Groups and sub-Groups-All commodities- as
published in the RBI Bulletin for the base period.
MQ Index Number of Wholesale Prices- By Groups and Sub-groups-All commodities- as
published in the RBI Bulletin for the average Price index of the 3 months of the quarter
under consideration.
FB Index Number of Wholesale Prices- By Groups and sub-Groups for Fuel and Power as
published in the RBI Bulletin for the base period.
FQ Index Number of Wholesale Prices- By groups and sub-groups for Fuel and Power as
published in the RBI Bulletin for the average price index of the 3 months of the quarter
under consideration.
EB Cost of explosives as fixed by DGS&D in the relevant rate contract of the firm from
whom purchases of explosives are made by the contractor for the base period.
EQ Cost of explosives as fixed by DGS&D in the relevant rate contract of the firm from
whom purchases of explosives are made by the contractor for the average price index
of the 3 months of the quarter under consideration
DB Cost of detonators as fixed by DGS&D in the relevant rate contract of the firm from
whom purchases of detonators are made by the contractor for the base period.
DQ Cost of detonators as fixed by DGS&D in the relevant rate contract of the firm from
whom purchases of detonators are made by the contractor for the average price index
of the 3 months of the quarter under consideration. SW Weight of steel in tonne supplied by the contractor as per the „on-account‟ bill for the
month under consideration
SQ SAILs (Steel Authority of India Limited) ex-works price plus Excise Duty thereof (In
rupees per tone) for the relevant category of steel supplied by the contractor as
prevailing on the first day of the month in which the steel was purchased by the
contractor (or) as prevailing on the first day of the month in which steel was brought to
the site by the contractor whichever is lower.
SB SAILs ex-works price plus Excise Duty thereof ( in Rs. Per tonne) for the relevant
category of steel supplied by the contractor as prevailing on the first day of the month
in which the tender was opened.
CV Value of cement supplied by contractor as per „on account‟ bill in the quarter under
consideration.
CB Index no. of Wholesale Price of sub-group (of Cement & Lime) as published in RBI
Bulletin for the base period.
CQ Index no. of Wholesale Price of sub-group (of Cement & Lime) as published in RBI
Bulletin for the average price index of the 3 months of the quarter under consideration.
Cs RBI Wholesale Price index for cement and lime for the month which is six months
prior to date of casting of foundation. Co RBI Wholesale Price index for cement and lime for the month which is one month
prior to date of opening of tender.
RT IEEMA Price index for Iron & Steel for the month which is two months prior to date
of inspection of material.
Ro IEEMA Price index for Iron & Steel for the month which is one month prior to date of
opening of tender.
Page 44 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
PT IEEMA Price for Copper wire bar for the month which is two months prior to date of
inspection of material.
Po IEEMA Price for Copper wire bar for the month which is one month prior to date of
opening of tender.
ZT IEEMA Price for Zinc for the month which is two months prior to date of inspection of
material.
Zo IEEMA Price for Zinc for the month which is one month prior to date of opening of
tender.
IT RBI Wholesale Price index for structural clay products for the month which is two
months prior to date of inspection of material.
Io RBI Wholesale Price index for structural clay products for the month which is one
month prior to date of opening of tender. 46A,
8.
The demands for escalation of cost shall be allowed on the basis of provisional
indices made available by Reserve Bank of India. Any adjustment needed to be done
based on the finally published indices shall be made as and when they became
available.
46A.
9.
Relevant categories of steel for the purpose of operating Price Variation formula, as
mentioned in this clause, based on Sails Ex-Works Price Plus Excise Duty thereof,
shall be as under:
Sl.
No.
Category of Steel supplied in Railway
work
Category of Steel produced by SAIL Whose Ex-
works Price Plus Excise Duty would be adopted
to determine Price Variation.
1. Reinforcement bars and other rounds TMT 8mm IS 1786 Fe 415/Fe 500
2. All types and sizes of angles Angle 65x65x6mm IS 2062 E250A SK
3. All types and sizes of plates PM plates above 10-20mm IS 2062 E250A SK
4. All Types and sizes of channels and joists Channels 200x75mm IS 2062 E250A SK
5. Any other section of steel not covered in
the above categories and excluding HTS
Average of price for the 3 categories covered
under SL 1, 2, & 3 above.
46A.10 Price variation During Extended Period of contract.
The price adjustment as worked out above, ie., either increase or decrease shall be applicable up to
the stipulated date of completion of work including the extended period of completion where such
extension has been granted under Clause 17-1 Of the General Conditions of Contract. However,
where extension of time has been granted due to contractors failure under Clause-17B of the
General conditions of Contract, price adjustments shall be done as follows:
a) In case the indices increase above the indices applicable to the last month of original
completion period or the extended period under clause 17-A, the price adjustment for the
period of extension granted under Clause 17-B shall be limited to the amount payable as per the
Indices applicable to the last month of the original completion period or the extended period
under clause 17-A of the General conditions of contract; as the case may be.
b) In case the indices fall below the indices applicable to the last month of original/extended
period of completion under clause 17-A, as the case may be; then the lower indices shall be
adopted for the price adjustment for the period of extension under clause 17-B of the General
Conditions of Contract.
Page 45 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
12. DEDUCTION OF INCOME TAX AT SOURCE
In terms of new Section 194-C inserted by the Finance Act 1972 , in the income tax Act 1961
the Railway shall at the time of arranging payments to the contractor and/or sub contractor(in
the case of sub contractor only when the Railway is responsible for payment of consideration
to him under the contract) for carrying out any work (including supply of labour for carrying
out any work) under the contract be entitled to deduct income tax at source on Income
comprised in the sum of such payments.
The deduction towards income tax to be made at source from the payments due to non-
residents shall continue to be governed by Section 195 of the Income Tax Act 1961.
No Income Tax will be deducted by the Railway on payments made for supply of materials
where such value of supply portion is distinct and ascertainable such as supply of Timber, tiles,
bricks, ballast including track/ballast etc. The deductions towards Income Tax to be made at
source from the payment due to non/residents shall continue to be governed by Section 195 of
the Income Tax Act 1961.
13. LIABILITY OF CONTRACTOR(S) - ANY DAMAGE SUSTAINED BY RAILWAYS
DURING ACCIDENTS ETC., CAUSED DUE TO CONTRACTOR(S) FAILURES, FAULT
OR NEGLIGENCE. Railway will post an Engineer-in-charge who may be SSE/SE/JE or Supervisor of any grade at
site for Technical Supervision of the work. This Engineer-in-charge will be responsible for
safety of the traffic. The work shall be executed by the contractor in a workman like manner to
the satisfaction of the Engineer-in-charge. The Contractor and his labour shall be guided by the
instructions of the Engineer-in-Charge. In the event of any accident occurring at the work site
and it is established during the departmental enquiry by the Railway or by Statutory enquiry of
CRS, that the accident occurred wholly or partly due to any act tantamounting to negligence on
the part of the contractor or his labour in not adhering to the instructions of the engineer-in-
charge, the contractor shall render himself liable for damages and also legal prosecution if loss
of life is involved.
14. Implementation of – the Building and other construction Workers (RECS) Act, 1996
and the Building and other Construction Workers Welfare Cess Act, 1996 in Railway
Contracts. “The Tenderer for carrying out any construction work in Andhra Pradesh (name of State) must
get themselves registered from the Registering Officer under Section-7 of the Building and
other Construction Workers Act, 1996 and rules made thereto by the Andhra Pradesh (name of
State)Government and submit certificate of registration issued from the Registering Officer of
the Andhra Pradesh(name of the State) Government (Labour Department). For enactment of
this act, the Tenderer shall be required to pay cess @ 1% of cost of construction work to be
deducted from each bill, Cost of material shall be outside the purview of cess, when supplied
under a separate schedule item.”
Page 46 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
ANNEXURE- “III”
WORKS CONTRACT CLAUSE-13
1. In case cement, Steel, AC sheet with or without accessories, GI sheets with or without
accessories, glasses or any other materials/items are issued to the contractor(s) either free of
cost or on cost to be recovered for use on the work as stipulated in the agreement the supply
thereof shall be made in stages depending on the progress of the work, limited to the quantity
/quantities computed by the Railway, according to the prescribed specification and approved
drawings as per agreement.
The materials supplied should conform to Railway‟s Specification in all respects should be
in accordance with approved sample.
All such materials supplied to the contractor(s) for the work either free of charge or on
payment as the case may be will be issued to contractor(s) at the Railway depot/godown/goods
shed and will have to be transported by the contractor to the site of work at his cost. All such
materials shall be used by the Contractor for the work in such quantities as are indicated in the
schedule or in the relevant specifications or drawings or as approved by the Engineer, whose
decision thereon shall be final. Wastage or damages of such materials in any manner shall be
totally avoided. The contractor(s) shall be liable to the accountal for all such materials issued
by Railway either free of cost or on payment excluding the permissible wastage which incase
of steel materials should not in any case exceed 1% of the total quantity required for the work
as per the approved drawings. No wastage under other items is permissible. Short lengths of
rods should also be utilized to the extent possible by overlapping joints.
The Cement, Steel, A.C.Sheets with or without accessories, G.I sheets with or without
accessories glasses or any other materials issued in excess of the requirement(s) as above, shall
be returned in perfectly good condition by the contractor(s) to the Railway at the Railway
depot/Godown/Goods shed at________immediately after completion or termination of the
contract. If the contractor fails to return the said materials then the cost of such materials issued
in excess of the requirement as computed by Railway according to the specification and
approved drawings will be recovered from the contractor(s) at twice the prevailing procurement
cost at the time of last issue viz., 2 x (purchases price +5% freight only). This will be without
prejudice to the right of Railway to take action against the contractors under the condition of
the contract for not doing/completing the work according to the prescribed specification and
approved drawings. If it is discovered that the quantity of cement, steel or any other material
used is less than the quantity computed by the Railway, according to specifications and
approved drawings the cost of materials not returned will be recovered at the same rates as
applicable to excess issue of materials, indicated in the preceding para.
2. It shall be the responsibility of the contractor to keep in safe custody any Railway material
plant or equipment issued for the work. The contractor shall at his own expense provide
suitable temporary shed/sheds for this purpose on the Railway land made available by the
Railway free of rent and shall remove the shed/sheds when no longer required in terms of
clause 30 of General conditions of contract.
Page 47 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
3. If due to any reason the Railway is not in a position to make available the Railway land the
Railway Engineer-in-charge of the work may permit the contractor to erect at his own cost
shed/sheds or secure private accommodation outside the Railway premises. In such a case the
contractor may be permitted to take the Railway material required for the works outside the
railway premises and to store in the Shed so erected or private accommodation so secured. It
shall be the responsibility of the contractor to keep the railway material in safe custody and the
same should be kept entire separate from the contractors material and the Railway shall have
liberty to inspect the same from time to time.
4. The code Nos. description and rates given in the schedule are based on the printed USSR -
2010, of S.C.Railway. Any discrepancy noticed during the execution of the work, in the
working rates quantity of cement etc. should be rectified by reference to the printed schedule,
which shall be treated as authoritative and binding on the contract. The relevant notes
applicable to the respective sub chapters will apply to the items of the Tender schedule and
should be considered as having been incorporated in the contract agreement and binding on the
Contractor.
5. For any other items not specially shown in the schedule of rates appended to the tender
document, the Divisional/Executive Engineer will offer rates as shown for the_________ zone
in the South central railway printed USSR - 2010, of S.C.Railway subject to the same
percentage adjustment accepted in the contract being applicable to the additional items.
6. Railway shall not supply from its own quota to the contractors controlled or imported
commodities. Assistance will, however given by recommending to appropriate authorities.
Contractor applications for issue of import licenses and release of controlled commodities if the
Engineer is satisfied that this material is actually required by contractor for carrying out the
work and is not available in the country.
7. VARIATION OF COSTS
Price variation clause is not applicable for contract agreement value upto Rs.50 lakhs.
Time is the essence of contract
8. (a) PERIOD OF COMPLETION: The Railway expects that a resourceful and experienced
contractor should be able to complete the work in all respects within the period as
specified in the Tender Notice and in the Schedule where items of work are
furnished from the date of letter of acceptance of the Tender
(b) Extension of time of completion will be governed by clause 17 of General Conditions
of Contract. However, while granting the extension of time under clause 17(B) of
GCC, a token penalty as deemed fit based on the circumstances of the case can be
imposed on the contractor without prejudice to other rights of Railway
Administration as provided under GCC.
9. MAINTENANCE PERIOD: The work shall be maintained after completion for a period as
specified in the Schedule where items of work are furnished by the contractor and he shall
make good any defects, imperfections, shrinkages or faults which may appear at his own cost.
10. It is HEREBY AGREED that it shall be the duty of the contractor to keep himself informed of
all corrections, and amendments of the said General conditions of contract made up to the date
of the execution of these presents and no objection shall be taken by the contractor on the
ground that he was not aware of such amendments and corrections of the said General
Conditions of Contract or to any of them.
Page 48 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
11. VARIATION IN CONTRACT QUANTITIES:-
The procedure as detailed below shall be adopted for dealing with variations in quantities
during execution of works contracts:
a) The Railway reserves the right to alter the designs and drawings. If due to change of
drawing or design or any other reasons, there be variations, either increase or decrease in
quantities, payment will be made only for the actual quantities executed at the accepted
rates. If there be sufficient cause the Railway may grant extension of the date of
completion suitably. Such circumstances shall in no way affect or vitiate the contract or
alter the character thereof, or entitle the contractor to damages or compensation thereof
except as provided for in this contract.
b) The quantities of each item of work furnished in the Schedule are approximate and are
intended for the guidance of Tenderer/Contractor. In actual execution of work there may
be some increase in the quantities specified. Such variation upto 25% shall in no degree
affect the validity of the contract and it shall be performed by the contractor as provided
therein and be subjected to the same conditions, stipulations and obligations originally
and expressly included and provided for in specifications and drawings and the amount
to be paid there for shall be calculated in accordance with accepted schedule rates.
(1) Prior Finance concurrence is necessary for varying the individual quantities
beyond 25% or where the gross agreement value exceeds 25% of the agreement
value.
(2) Individual NS items in contracts shall be operated with variations of plus or minus
25% and payment would be made as per the agreement rate. For this, no Finance
concurrence would be required.
(3) In case an increase in quantity of an individual item by more than 25% of the
agreement quantity is considered unavoidable, the same shall be got executed by
floating a fresh tender. If floating a fresh tender for operating that item is
considered not practicable, quantity of that item may be operated in excess of
125% of the agreement quantity (100% i.e. the original quantity +25% i.e. quantity
over and above the original quantity) subject to the following conditions.
a) Operation of an item by more than 125% of the agreement quantity needs
the approval of an officer of the rank not less than S.A. Grade:
i) Quantities operated in excess of 125% but upto 140% of the
agreement quantity of the concerned item, shall be paid at 98% of the
rate awarded for that item in that particular tender;
ii) Quantities operated in excess of 140% but upto 150% of the
agreement quantity of the concerned item shall be paid at 96% of the
rate awarded for that item in that particular tender;
iii) Variation in quantities of individual items beyond 150% will be
prohibited and would be permitted only in exceptional unavoidable
circumstances with the concurrence of associate finance and shall be
paid at 96% of the rate awarded for that item in that particular tender
b) The variation in quantities as per the above formula will apply only to the
Individual items of the contract and not on the overall contract value.
c) Execution of quantities beyond 150% of the overall agreement value should
not be permitted and, if found necessary should be only through fresh
tenders or by negotiating with existing contractor, with prior personal
concurrence of FA&CAO/ FA&CAO(C) and approval of General Manager.
Page 49 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
4. The limit for varying quantities for minor value items shall be 100% (as against
25% prescribed for other items). A minor value item for this purpose is defined as
an item whose original agreement value is less than 1% of the total original
agreement value.
5. No such quantity variation limit shall apply for foundation items.
6. As far as SSR/SOR items are concerned, the limit of 25% would apply to the
value of SSR/SOR schedule as a whole and not on individual SSR/SOR items.
However, in case of NS items, the limit of 25% would apply on the individual
items irrespective of the manner of quoting the rate (single percentage rate or
individual item rate).
7. For the tenders accepted at the Zonal Railways level, variations in the quantities
will be approved by the authority in whose powers revised value of the agreement
lies.
8. For tenders accepted by General Manager, variations upto 125% of the original
agreement value may be accepted by General Manager.
9. For tenders accepted by Board Members and Railway Ministers variations upto
110% of the original agreement value may be accepted by General Manager
10. The aspect of vitiation of tender with respect to variation in quantities should be
checked and avoided. In case of vitiation of the tender (both for increase as well as
decrease of value of contract agreement) sanction of the competent authority as per
single tender should be obtained.
11. In cases where decrease is involved during execution of contract:
a. The contract signing authority can decrease the items upto 25% of
individual item without finance concurrence.
b. For decrease beyond 25% for individual items or 25% of contract
agreement value, the approval of an officer not less than rank of S.A.
Grade may be taken, after obtaining „No claim certificate‟ from the
contractor and with finance concurrence giving detailed reasons for each
such decrease in the quantities.
c. It should be certified that the quantities proposed to be reduced will not be
required in the same work at a later stage
d. In the event of any reduction in the quantity to be executed for any reasons
whatsoever, the contractor shall not be entitled to any compensation but
shall be paid only for the actual amount of work done.
e. The contractor is bound to notify the Engineer at least seven days before the
necessity arises for the execution of any item in excess of 25% of the over
all value of the agreement.
12. In case the contractor fails to attend the meeting after being notified to do so or in
the event of no settlement being arrived at, the Railway shall be entitled to execute
the extra works by other means and the contractor shall have no claim for loss or
damage that result from such procedure
Page 50 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
12. Employment of Civil Engineering Graduates/Diploma-holders:
The contractor shall employ the following technical staff during the execution of this work.
i) One graduate engineer when the cost of the work to be executed is Rs.2 Crores and
above.
ii) One qualified diploma holder (over-seer) when the cost of the work to be executed is
more than Rs.25 lakhs but less than Rs.2 Crores. Technical staff should be available at
site whenever required by the Engineer-in-charge to take instructions. In case the
contractor fails to employ the technical staff as aforesaid, he shall be liable to pay a
reasonable amount not exceeding a sum of Rs.40,000/- (forty thousand only) for each
month of default in case of graduate engineer and Rs.25,000/- (twenty five thousand
only) for each month of default in case of diploma holder (over-seer)
(Modification of Cl.26 and introduction of new Cl.26A to IR‟s GCC Ref: Rly. Bd.
Lr.No.2012/CE-I/CT/0/20, dt.10.05.2013.)
The decision of the Engineer-in-charge as to the period for which the required technical staff
was not employed by the contractor and as to the reasonableness of the amount to be deducted
on this account shall be final and binding on the contractor.
iii) Individuals having Diploma in Railway Engineering awarded by IPWE (India) shall also
be considered as qualified Diploma holder Engineers and contractors for track contract
works can employ such individuals at their worksite on Indian Railways.
(Ref: Rly. Bd. Lr.No.2012/CE-I/CT/0/20, dt.12.07.2013.)
Note: The above clause is not applicable for contracts for Welding of Rail joints.
13. Railway Contractors / Extension of Provident Fund Act to the Employees working under
Railway Contractors:-
The Contractor shall comply with the provisions of EPF & MP Act, 1952 and obtain code
number from the concerned authorities whenever workmen employed by him are 20 or more.
He shall also indemnify Railways from and against any claim, penalties, recoveries under the
above Act and Rules. Contractors to get the code number under the EPF so as to enable the PF
Commissioners to extend the social security benefits to the workmen engaged by the Railway
contractors. The first month‟s bill will be released only after code number is taken from the PF
Office and a copy of coverage intimation produced. Subsequently for each month, bills will be
released only on submission of challans & 12 A monthly return copy in proof of remittance of
PF dues for previous month.”
14. Conservancy charges as applicable and as modified from time to time will be recovered
from Contractor‟s running bills.
Page 51 of 51
DEN/Bridges/BZA Signature of Tenderer(s) BZA Divn., SCR, T.No.08/Bridges2015 invited vide Open Tender No.DRM/Works/BZA/21/2015 dt.03-11.2015, date of opening on
.07-12.2015 for the work of “SW-I: Vijayawada Division Repairs to corroded steel structural components of Foot Over Bridges/Vijayawada yard duly replacing existing damaged gang way slab and stair way steps, SW-II:Vijayawada division-Gudur-Vijayawada section–Removal of infringement
on main line duly shifting the existing Foot Over Bridge column on PF No. 1 of Bitragunta station. SW-III: Gudur - Vijayawada section –
Dismantling of existing old aged Foot Over Bridge at Gudur station..”
..”
SPECIAL CONDITIONS
MODIFICATION TO CLAUSE 63 & 64 OF
GENERAL CONDITIONS OF CONTRACT
1. The Provision of Clause 63 and 64 of the General Conditions of Contract will be
applicable only for settlement of claims /disputes, for values less than or equal to
20% of the original value (excluding the cost of materials supplied free by
Railway) of the contract or 20% of the actual value of the work done (excluding the
value of the work rejected) under the contract whichever is less. When
claims/disputes are of value more than 20% of the value of the original contract or
20% of the value of the actual work done under the contract, whichever is less, the
contractor will not be entitled to seek such disputes/claims for reference to
arbitration and the provisions of Clause No; 63 &64 of the General Conditions of
Contract will not be applicable for referring the disputes to be settled through
arbitration
2. The Contractor shall furnish his monthly statement of claims as per Clause 43(1) of
General Conditions of Contract. But the Contractor should seek reference to
arbitration to settle the disputes only once, subject to the conditions as per Para 1
3. The Special conditions shall prevail over the existing Clause 63 & 64 of General
Conditions of contract