Test Campaigns 1

PACS SVR 22/23 June 2006

Overview of PACS Test Campaigns

Helmut FeuchtgruberMPE

Page 2: PACS SVR 22/23 June 2006 Test Campaigns1 Overview of PACS Test Campaigns Helmut Feuchtgruber MPE.

Test Campaigns 2

PACS SVR 22/23 June 2006

AVM Warm Electronics Tests

• AVM WE Tests from Sep-2002 to Jul-2004Purpose: - OBSW development- Initial warm electronics communication verification- Development of basic instrument operational procedures (switch-on/off, memory load, 1355 link initialization etc.)- Development of EGSE software and operational procedures (memory load, packet recording, bus list switching etc.)

Hardware: DPU AVM1, SPU EM, BOLC sim., DMC AVM

Page 3: PACS SVR 22/23 June 2006 Test Campaigns1 Overview of PACS Test Campaigns Helmut Feuchtgruber MPE.

Test Campaigns 3

PACS SVR 22/23 June 2006

CQM ILT

• Two cryogenic test phases: 19-23 Jul 2004 and 6-Sep to 6-Nov 2004 (EMC: 4/6-Nov 2004)

Instrument Hardware: - DPU AVM1, SPU AVM, BOLC AVM, DMC EM, WIH AVM - CQM FPU

Instrument OBSW: - DPU V7.10, several updates during the tests until V7.68 - SPU V11.1, short trial of V11.3, but roll back to V11.1 - DMC V5.006, several updates during the tests until V5.023

Page 4: PACS SVR 22/23 June 2006 Test Campaigns1 Overview of PACS Test Campaigns Helmut Feuchtgruber MPE.

Test Campaigns 4

PACS SVR 22/23 June 2006

EQM IMT

• July/August 2005 3 x Short Functional Tests warm• 19-Sep to 4-Nov in 2 periods (with and without He-

leak)• 7/9-Nov-2005 PACS/SPIRE parallel mode testing • 21/25-Nov-2005 EMC Testing• 7/9-Dec-2005 Straylight Testing• 15-Dec-2005 SFT at ~HeI conditions

Hardware: Refurbished DMC EM, otherwise same as during ILT

OBSW: DMC OBSW V5.025, SPU V11.7, DPU V7.68

Page 5: PACS SVR 22/23 June 2006 Test Campaigns1 Overview of PACS Test Campaigns Helmut Feuchtgruber MPE.

Test Campaigns 5

PACS SVR 22/23 June 2006

FM Pre-ILT

• Since 22-Mar-2006 in several time periods Purpose:

- Development and testing of CUS-based ILT test procedures and operational procedures- Verification of new DPU Boot SW- Dry-run and validation of IST test procedures- OBSW and MIB testing- SPU HLSW development- Support to PCSS development and testing

Hardware: DPU AVM2 & CFM2, DMC EQM, BOLC sim., SPU EM, WIH EQM, FPU simulator (part time)

OBSW: DMC V6.000-V6.005, SPU V12.2, DPU V8.31

Page 6: PACS SVR 22/23 June 2006 Test Campaigns1 Overview of PACS Test Campaigns Helmut Feuchtgruber MPE.

Test Campaigns 6

PACS SVR 22/23 June 2006

Future Test Phases (1)

ILT without FPU:• Continuation of Pre-ILT and integration of PACS FM warm

units into test setup as they become available prior to the cold ILT

ILT with FPU:• SFT warm (before evacuation) • Nominal ILT program (incl. SFT HeI, SFT HeII, entire IST test

procedure and parallel mode test verification)• ILT EMC phase

Hardware: FM warm electronics and FM FPUOBSW: Flight versions

Page 7: PACS SVR 22/23 June 2006 Test Campaigns1 Overview of PACS Test Campaigns Helmut Feuchtgruber MPE.

Test Campaigns 7

PACS SVR 22/23 June 2006

Future Test Phases (2)

• AVM ISTPurpose:- Verification of IST test procedures- Test of system related aspects (TBC)

Hardware: DPU AVM1 (with new boot software), SPU AVM, BOLC AVM, DMC EM, WIH AVM

Software: DPU OBSW V8.xx (TBD during ILT), SPU V12.x (TBD during ILT), DMC V6.xxx

(TBD during ILT and due to DMC EM hardware constraints)

Page 8: PACS SVR 22/23 June 2006 Test Campaigns1 Overview of PACS Test Campaigns Helmut Feuchtgruber MPE.

Test Campaigns 8

PACS SVR 22/23 June 2006

Future Test Phases (3)

Instrument Delivery

• FM ISTPurpose:- Verify that PACS instrument function and performance is preserved at satellite level, before, during and after environmental testing. This includes TV/TB and EMC tests.

• SVT 1&2 (content TBD by ESA/MOC)

Hardware: FM warm electronics and FM FPUSoftware: Flight software, evtl. bugs/SPRs detected during ILT

corrected