P2 Deptford CS SIP

download P2 Deptford CS SIP

of 32

Transcript of P2 Deptford CS SIP

  • 8/3/2019 P2 Deptford CS SIP

    1/32

    Introd

    uction

    Thames Tunnel

    Siteinformationpaper

    1

    Deptford Church StreetAlternative to Borthwick Wharf Foreshore

    Currently, untreated sewage regularly overows into the River Thames from Londons Victorian sewerage systemvia combined sewer overows (CSOs). The proposed Thames Tunnel would intercept these overows through theuse of a new storage and transfer tunnel, which would link west London and Abbey Mills Pumping Station. Thesewage ow would then be transferred to Beckton Sewage Treatment Works via the Lee Tunnel. The reductionin untreated sewage entering the River Thames would bring long-term benets for the environment and users of

    the River Thames. In order to deliver the project we need a number of sites along the route and this documentidenties our current preferred site at Deptford Church Street.

    Key facts

    Local authority: Lewisham

    CSO name: Deptford Storm Relief

    CSO spill volume in an average year: 1,500,000m (equivalent to approximately

    600 Olympic swimming pools)

    Site type: CSO site

    Duration of main construction works: Approximately three and a half years.

  • 8/3/2019 P2 Deptford CS SIP

    2/32

    Deptford Church Street

    2

    Section 1: Introduction and site information

    Related documents:

    Build

    We are proposing to use a site at Deptford Church

    Street for this construction work and to accommodatepermanent structures required to operate the main

    tunnel. The site would be used to connect the existing

    local CSO, known as the Deptford Storm Relief CSO, to the

    main tunnel via a long connection tunnel, known as the

    Greenwich connection tunnel.

    The location of the site is shown in Figure 1A. Deptford

    Church Street (A2209) is to the east of the site, beyond

    which is the Sue Godfrey Nature Reserve and residentialproperties. Coffey Street and St Pauls Church, a Grade

    I listed church are located to the north. To the south

    and west is Crossfield Street and to the south west is St

    Josephs Roman Catholic Primary School. The site is within

    the St Pauls Conservation Area.

    This site information paper sets out our proposals at

    Deptford Church Street. We have also produced projectinformation papers, which cover overarching topics

    relating to the project. Where we consider that a project

    information paper is particularly relevant, we have

    highlighted this in a related documents box. At the end

    of this site information paper is a list of other documents,

    which may be of interest and a glossary of terms.

  • 8/3/2019 P2 Deptford CS SIP

    3/32

    Introduction

    3

    Figure 1A: Deptford Church Street location plan

    N

    CSO discharge into River Thamesapproximately 300 metres to the north

    Deptford StormRelief CSO

    St Josephs RCPrimary School

    Deptford Station

    WavelengthsLeisure Centre

    St Pauls

    Church

    DeptfordCreek

    De

    ptford

    HighStreet

    CoffeyStreetCrossfield Street

    De

    ptfor d

    Chur chSt

    r e e t

    Sue GodfreyNature Reserve

    CreekRoad

    LEWISHAM

    GREENWICH

    Local authority boundary

    Draft limit of land tobe acquired or used

    Existing sewer

    Greenwich PumpingStation site

    Proposed tunnelroute centreline

  • 8/3/2019 P2 Deptford CS SIP

    4/32

    Deptford Church Street

    4

    Related documents:

    Changes

    Q&A Consultation

    Site selection

    How we chose this site

    What we proposed at phase one consultationAt phase one consultation, which was held between

    September 2010 and January 2011, Borthwick Wharf

    Foreshore was identified as our preferred site to intercept

    the Deptford Storm Relief CSO.

    Why we have amended our proposals

    Since January 2011, we have considered the comments

    from phase one consultation, feedback from ongoing

    engagement and undertaken further technical work. This

    has resulted in us re-assessing potential sites to intercept

    the Deptford Storm Relief CSO.

    Two shortlisted sites were identified. The first is land

    adjacent to Bronze Street and the second is Deptford

    Church Street. In June 2011, we held drop-in sessions for

    the community to understand any local issues they may

    have, should there be a site in this location. We reviewed

    all the comments we received and took these into

    account as part of the site selection process.

    What we are proposing at phase two consultationWe have identified three shortlisted sites to intercept the

    CSO, as shown in Figure 1B. These are:

    Borthwick Wharf Foreshore (site 1)

    Land adjacent to Bronze Street (site 2)

    Deptford Church Street (our preferred site).

    Deptford Church Street is our preferred site to intercept

    the Deptford Storm Relief CSO because in comparison to

    our preferred site at phase one consultation, Borthwick

    Wharf Foreshore, this site has relatively good access and

    avoids work in the foreshore of the River Thames.

    Site 1 Borthwick Wharf Foreshore is a shortlisted

    site. It is considered less suitable than our preferred site

    because of the potential effects on residential, visitor and

    business amenity and due to restricted vehicular access

    along Glaisher Street, a private road, which is less suitable

    for heavy good vehicles. Although the use of barges to

    transport material could help to reduce these potential

    effects, lorries would still need to be used to transport

    some materials to and from the site. Furthermore, the use

    of barges at this site would be complicated by the existing

    derelict jetty.

    Site 2 Land adjacent to Bronze Street is a shortlistedsite. It is considered less suitable than other sites because

    it would cause more disruption to Deptford Church

    Street as works would need to be carried out across both

    carriageways.

  • 8/3/2019 P2 Deptford CS SIP

    5/32

    Introduction

    5

    Figure 1B: Preferred and shortlisted sites

    N

    Deptf

    ord

    Creek

    CreekRoad

    BorthwickStreet

    EvelynStreet

    ConvoysWharf

    Site 1

    Site 2

    Preferred site Deptford Church Street

    Other shortlistedsite locations

    Local authorityboundary

    GREENWICH

    TOWERHAMLETS

    LEWISHAM

  • 8/3/2019 P2 Deptford CS SIP

    6/32

    Deptford Church Street

    6

    Section 2: Construction

    Construction activitiesConstruction activities are required to intercept the

    CSO. To intercept the CSO, we would construct an

    interception chamber. A connection culvert would link

    the interception chamber to a drop shaft (approximately

    46m deep) through which flows would pass into the

    Greenwich connection tunnel before connecting into

    the main tunnel. Figure 2A illustrates the below ground

    infrastructure proposed. These activities would take place

    within the area indicated by the red line in Figure 1A, infour main phases, lasting approximately three and a half

    years in total. The main construction activities associated

    with these phases are set out in Table 2.1.

    After completion of the works and site restoration, we

    may need to visit the site for short periods to support

    finishing works at the bottom of the shaft. These would

    be carried out from within the tunnel and serviced from

    the site at Greenwich Pumping Station. For example, wemay need to provide ventilation for the workers in the

    tunnel and a means of emergency escape.

    Related documents:

    Build

    Managing construction

  • 8/3/2019 P2 Deptford CS SIP

    7/32

    Construction

    Construction

    7

    Figure 2A: Illustration showing typical elements of below ground infrastructure

    Drop shaft

    Greenwichconnection tunnel

    Valve chamber

    Existing sewer

    ExistingoverfowtoRiver Thames

    Interception chamber

    Existingoverfowsewer

    Connection culvert

  • 8/3/2019 P2 Deptford CS SIP

    8/32

    Deptford Church Street

    8

    Advance works

    Phase 1

    Site setup

    Figure reference Figure 2C

    Typical working hours VariesStandard with occasional

    extended standard

    Mainconstructionactivities Utilities connected

    Utilities diverted or protected

    Site cleared

    Site facilities and access set up

    Drop shaft excavated and built

    Above and below ground structures constructedMechanical and electrical equipment installed

    Site restored and landscaped

    Temporary site facilities removed

    Table 2.1: Main activities during construction phases

    Our typical working hours are expected to be:

    Standard: 8am-6pm weekdays, 8am-1pm Saturday*

    Extended standard: 6pm-10pm weekdays, 1pm-5pm Saturdays

    Continuous: 24 hours a day, seven days a week**

    Varies: Working hours for advanced works will depend on the nature of the works and will be agreed

    with the local authority

    * Standard working hours would also include, subject to agreement with the local authority:

    a short period (up to one hour) before works start and after they have finished to allow our workers to prepare for work and check the site.

    equipment and machinery maintenance could also take place 1pm-5pm Saturday and 10am-4pm Sunday.

    ** The main activities taking place 24 hours a day are below ground or within an enclosure.

  • 8/3/2019 P2 Deptford CS SIP

    9/32

    Construction

    9

    Phase 2

    Drop shaft

    construction

    Phase 3

    Construction of

    other structures

    Phase 4

    Completion of

    works and siterestoration

    Figure 2C Figure 2D

    Standard with occasional

    extended standardStandard Standard

  • 8/3/2019 P2 Deptford CS SIP

    10/32

    Deptford Church Street

    10

    Site layout and construction phases

    Figures 2C and 2D show how the site might be laid out

    during the construction phases, which are set out in Table2.1 and Figure 2B. These layouts have been informed by

    the size of the infrastructure proposed, the construction

    methods required and the location of neighbouring

    buildings and structures. They have also been developed

    to minimise effects on the local community and

    environment. Particular factors at this site that have

    influenced the layout are as follows:

    The drop shaft has been located as centrally as possiblewithin the site to maximise distance from sensitive

    receptors such as the Grade I listed St Pauls Church, St

    Josephs Roman Catholic Primary School, and the Grade

    II listed viaduct.

    We have designed a construction access to this site

    that includes a one way system. This would be safe

    for pedestrians and vehicles on surrounding roads and

    footpaths and provide a controlled access for vehicles

    entering and leaving site. It would also help ensure

    safety on site by reducing the need for vehicles to turn

    within the site.

    The site layouts are indicative only, and the contractor

    may arrange the site in a different way, depending onthe chosen construction methods, provided that any

    environmental effects are appropriately managed, and

    that the main construction activities are undertaken

    within the red line shown in Figure 1A.

    P1

    P2

    P3

    P4

    Year 1 Year 2 Year 3 Year 4

    Advan

    ce

    works

    Figure 2B: Construction timeline showing approximate

    duration of works in phases (P)

  • 8/3/2019 P2 Deptford CS SIP

    11/32

    Construction

    11

    Figure 2C: Illustrative phases 1 and 2 construction plan

    Cranes

    Drop shaft

    Piling rig

    CrossfieldStreet

    N

    GREENWICH

    Maximum extent ofconstruction site forphases 1 and 2

    Site hoarding

    Local authority boundary

    Site support/welfare

    Excavated materialstorage and processing

    Maintenance workshopand storage

    Construction support

    Internal site road

    Site access

    Existing footpath tobe diverted

    Footpath diversion

    CoffeyStreet

    LEWISHAM

  • 8/3/2019 P2 Deptford CS SIP

    12/32

    Deptford Church Street

    12

    Figure 2D: Illustrative phase 3 construction plan

    Crane

    Drop shaftCrossfieldStreet

    Piling rigTwo way

    traffic flow

    N

    CoffeyStreet

    GREENWICH

    LEWISHAM

    Maximum extent ofconstruction site for

    phase 3Site hoarding

    Local authority boundary

    Site support/welfare

    Excavated materialstorage and processing

    Maintenance workshopand storage

    Construction support

    Internal site road

    Site access

    Existing footpath tobe diverted

    Footpath diversion

  • 8/3/2019 P2 Deptford CS SIP

    13/32

    Construction

    13

    Additional works and activities

    The main construction works at this site are set out in

    Table 2.1. We would also need to undertake additionalworks and activities, some of which may be located

    outside of the area indicated by the red line in Figure 1A.

    The anticipated additional works and activities are set

    out in Table 2.2.

    When Type of works What we would do

    Required forconstruction phase

    Installation of equipment to

    monitor environmental matterssuch as noise, vibration and dust.

    The locations of monitoring equipment would be agreed with

    the local authority and relevant landowners.

    Protection works to third party

    structures (such as buildings,

    bridges and tunnels).

    We would undertake studies to identify any effects our

    construction work may have on third party structures. The

    studies may recommend particular construction methods or,

    in very limited instances, protection works.

    If protection works are required to the existing sewer, we

    would access the sewer network through existing manholes.

    Diversion of utilities.If utility diversions are required, we would work with utilityproviders to undertake the necessary works.

    Temporary connection to utilities

    (such as water, sewer, phone and

    electricity supply).

    We expect to make a connection to water, sewer and phone

    supplies in Coffey Street or Deptford Church Street (A2209).

    We expect to connect to electricity from Stowage, running

    cables along Gonson Street, Creekside and Bronze Street,

    however we are still developing a route for power supply in

    discussion with the utility provider.

    Traffic management works.

    These may need to extend beyond our site and could include

    relocating kerb lines, repainting road lines and modifying

    traffic signals.

    Required for

    operational phase

    Permanent connection to

    utilities (such as water, phone

    and electricity supply) for the

    operational tunnel.

    We expect to connect to utilities in Deptford Church Street

    (A2209).

    Table 2.2: Additional works and activities

  • 8/3/2019 P2 Deptford CS SIP

    14/32

    Deptford Church Street

    14

    Construction transport and access

    We would transport materials to and from the site by

    road. Table 2.3 sets out the anticipated average dailynumber of lorries visiting (ie travelling to and from) the

    site during the peak months of each phase.

    Construction traffic would access the site from Blackheath

    Road (A2) travelling northbound along Deptford Church

    Street (A2209), turning left into Crossfield Street and

    right into the site from a new entrance on Crossfield

    Street. Traffic leaving the site would turn right from a new

    entrance on Coffey Street and left onto Deptford ChurchStreet (A2209), then return to Blackheath Road (A2)

    using Creek Road (A200), Norman Road and Greenwich

    High Road (A206). This access route is shown on Figure

    2E. Beyond this, construction traffic would use the major

    road network to get to and from its final destination.

    We may need to suspend or relocate some parking

    bays on Coffey Street and on Crossfield Street during

    construction.

    While the connection to the existing sewer in Deptford

    Church Street (A2209) is constructed (construction phase3) we would need to close the two northbound lanes, as

    shown on Figure 2D. The two southbound lanes would

    provide two way access along Deptford Church Street

    (A2209). The bus lane would be suspended to enable this,

    and buses would need to use the general traffic lanes.

    The northbound bus stop near Coffey Street and the

    southbound bus stop near the railway bridge may also

    need to be moved during this phase and the footpathalong the western side of Deptford Church Street (A2209)

    would be diverted around the site. Based on our current

    design, we do not anticipate that any junction changes

    would be required.

    Phase 1

    Site setup

    Phase 2

    Drop shaftconstruction

    Phase 3

    Construction ofother structures

    Phase 4

    Completion ofworks and site

    restoration

    Average daily

    lorry visits

    2 lorries 24 lorries 13 lorries 5 lorries

    Table 2.3: Average daily lorry visits during the peak months

    Related documents:

    Transport

  • 8/3/2019 P2 Deptford CS SIP

    15/32

    Construction

    15

    Figure 2E: Proposed access route to the site from the nearest major road

    DeptfordChurch Street(A2209)

    Blackheath Road

    Creek Road

    Norman Road

    GreenwichHigh RoadA206

    A200

    A2

    N

    CoffeyStreet

    CrossfieldStreet

    Rightturn out

    Suspensionof parking

    Rightturn in

    LEWISHAM GREENWICH

    Bus stoprelocation

    Draft limit of land tobe acquired or used

    Internal site road

    Site access

    Local authority boundary

    Transport for London(TfL) road network

    Proposed lorry access toTfL road network

  • 8/3/2019 P2 Deptford CS SIP

    16/32

  • 8/3/2019 P2 Deptford CS SIP

    17/32

    Construction

    17

    Issue Our response

    Temporary loss of open space.

    We will consult the London Borough of Lewisham and are considering opportunities

    to improve other open spaces in the local area to compensate for the temporary loss

    of open space during construction.

    Potential loss of and damage to

    trees on site.

    Construction activities at this site would result in the removal of all existing trees

    from Deptford Green. Permanent site landscaping would however incorporate the

    replacement of trees lost during construction with native species. The potential

    for planting to be part of the councils tree planting plan for the area is being

    considered.

    Removal of the wall running

    through the site.

    We will work with the London Borough of Lewisham and English Heritage to

    consider ways to acknowledge the wall within the permanent landscape design and

    planting for the site.

    Temporary closure of the

    northbound lanes of Deptford

    Church Street (A2209) and

    suspension of bus lanes during

    construction phase 3.

    During construction, two-way traffic along Deptford Church Street (A2209) would

    be maintained by using the two southbound lanes. Bus services would continue to

    run along this route by using the general traffic lanes, although there may be some

    delay to journey times. The traffic management plan for the site would ensure that

    lane alterations are managed safely and with minimal disruption.

    Temporary suspension or

    relocation of some on-street

    parking on Coffey Street and

    Crossfield Street.

    The extent and duration of the suspension of any on-street parking during

    construction would be minimised as far as possible. We are investigating options for

    temporary replacement parking provision during construction where necessary.

    Possible effect of noise and

    vibration from construction

    activities on neighbouring areas.

    The contractor would be required to implement noise and vibration control

    measures at the worksite, which will be set out in the CoCP.

    Possible effects on local air

    quality and dust nuisance in

    neighbouring areas.

    Preliminary findings indicate that while there is the potential for dust nuisance

    effects, there are unlikely to be any significant local air quality effects at any of

    the sites. The contractor would put in place air and dust control measures at the

    worksite, which will be set out in the CoCP.

    Table 2.4: Key issues relating to construction

    Deptford Ch rch Street

  • 8/3/2019 P2 Deptford CS SIP

    18/32

    Deptford Church Street

    18

    Section 3: Future use

    This section describes the site after the completion of the

    construction work, ie when the main tunnel is in use the

    operational phase.

    Design

    The design of the permanent use and appearance of the

    structures at Deptford Church Street follows our scheme-

    wide principles and takes into account comments raised

    during ongoing engagement with the London Borough ofLewisham and other technical consultees.

    Our permanent works need to incorporate functional

    elements, which are required for the operation of the

    tunnel. These include:

    Underground structures with ground level access covers

    including: a CSO drop shaft with an internal diameter

    of approximately 17m, connection culverts, interception

    chamber, valve chamber and a passive filter chamber.

    Four main ventilation columns up to 6m high.

    A small diameter ventilation column to the interception

    chamber up to 6m high.

    Maintenance vehicle access.

    An electrical and control kiosk.

    Table 3.1 sets out the site specific issues that have

    influenced our permanent design proposals and how we

    have addressed them in our proposed design.

    Future use

  • 8/3/2019 P2 Deptford CS SIP

    19/32

    Future

    use

    Future use

    19

    Issue Our response

    Effects on the existing open space

    including trees.

    The site would be returned as an open space once construction works have

    been completed, and we have illustrated the potential for an enhanced space

    to be created for the benefit of the local community. We would work with

    the local community and council during the development of our design and

    construction to work up the detail of the space.

    The majority of the proposed permanent works on this site would be below or

    at ground level, so would not significantly affect the amount of open space

    available at the site.

    All of the existing trees located in the centre of the site would be lost, but highquality tree planting would form part of the enhanced space to be created.

    Effects on the Grade I listed church

    of St Pauls to the north of the

    site, Grade II listed viaduct to the

    south, and character of St Pauls

    Conservation Area.

    The majority of the proposed permanent works on this site would be below

    or at ground level, so are unlikely to have any significant effect on the listed

    buildings or Conservation Area.

    The enhancements that we are to make to the open space would enhance the

    setting of the church and promote peoples enjoyment of it.

    The proposed ventilation columns have been located away from the Grade I

    listed church.

    London Borough of Lewishams

    aspirations for the creation of an

    east-west link across Deptford.

    Lewisham has an aspiration for an east west link across Deptford extending

    from Deptford Creek to Deptford High Street and beyond. As part of the

    proposals for this site, a new east west link across the site is indicated as a

    new pathway across the open space running parallel to the existing pavement

    on Coffey Street proving links between Deptford Church Street (A2209) and

    Deptford High Street.

    Table 3.1: Site specific issues that have influenced our permanent design

    Deptford Church Street

  • 8/3/2019 P2 Deptford CS SIP

    20/32

    Deptford Church Street

    20

    Figure 3A: Photo of the site before the works

    Figures 3A, 3B, 3C and 3D show the current site and

    provide an illustration of our design proposals. Further

    information on the development of our design can be

    found in the Design development report.

    Related documents:

    Design

    Future use

  • 8/3/2019 P2 Deptford CS SIP

    21/32

    Future use

    21

    Figure 3B: Artists impression of the site after the works are completed

    DRAFT IMAGE, PLACEHOLDER ONLY

    Deptford Church Street

  • 8/3/2019 P2 Deptford CS SIP

    22/32

    Deptford Church Street

    22

    Figure 3C: Aerial view of the completed works

    Future use

  • 8/3/2019 P2 Deptford CS SIP

    23/32

    23

    Figure 3D: Layout of site once construction works complete

    Seasonal bulbplanting and wildflower meadow

    Densely plantededge to DeptfordChurch Street

    Mownlawn

    CoffeyStreet

    DeptfordCh

    urchStreet

    CrossfieldStreet

    Ventilationcolumns

    New shared surfacetreatment to CoffeyStreet. Links park toChurch grounds

    Removable bollardsfor access formaintenance vehicles

    Footpath

    widened

    Electrical and controlkiosk and integratedinformation board

    Low ornamentalhedges

    Timberseating

    Planters Parking

    Fruit treesFenced informalplay area withscented planting

    Green featurescreen withclimbing plants

    N

    Line of seasonalbulb plantingmarking position

    of wall

    Hardstandingfor maintenance

    access

    Ventilationcolumn

    Deptford Church Street

  • 8/3/2019 P2 Deptford CS SIP

    24/32

    Deptford Church Street

    24

    Operation and maintenanceOnce the tunnel is operational, we would need access

    to the site occasionally for inspection and maintenance

    purposes. We expect to visit the site approximately

    once every three to six months to carry out inspections

    and maintenance of the ventilation and below ground

    equipment. This is likely to involve a visit by staff in a

    small van, and may take several hours.

    Once every ten years, we expect to carry out a major

    internal inspection of the tunnel and underground

    structures. This is likely to involve a small team of

    inspection staff, a small team of support crew and two

    mobile cranes to lower the team and inspection vehicle

    into the shaft. This is likely to take several weeks, and

    would require temporary fencing around the shaft for

    safety and security while the inspection takes place.

    We may also need to make visits to the site for unplanned

    maintenance or repairs, for example, if there is a blockage

    or equipment failure. This may require the use of mobile

    cranes and vans.

    Permanent vehicular access would be from Coffey Street.

    Management of operational effectsWe have undertaken technical work, including stakeholder

    engagement, to assess and identify the key issues

    associated with this site once it is operational. Table

    3.2 summarises these issues and how we are currently

    proposing to address them.

    Future use

  • 8/3/2019 P2 Deptford CS SIP

    25/32

    25

    Issue Our response

    Possible odour effects during

    the operation of the tunnel.

    Odour effects at this site are expected to be negligible because we have developed

    anAir management plan to minimise possible odour and air quality effects arisingfrom the operation of the tunnel. The technology we are proposing to use at this site

    includes the use of passive below ground carbon filters that will remove possible odour

    before air leaves the ventilation equipment.

    Disturbance from future

    maintenance access.

    Permanent access would be required for maintenance and servicing purposes to the

    shaft and ventilation equipment. Any planned maintenance visits would be undertaken

    during normal working hours and all visits managed to avoid disruption to local

    residents, businesses and users of affected public areas as far as possible.

    Table 3.2: Key issues relating to site operation

    Related documents:

    Odour

    Further information

  • 8/3/2019 P2 Deptford CS SIP

    26/32

    26

    u t e o at o

    This section sets out documents which may be of particular interest. Further information on our proposals can be

    found on our website (www.thamestunnelconsultation.co.uk) or is available upon request (call our customer centre

    on 0800 0721 086).

    Phase two public consultation material

    Project information papers include general information about the Thames Tunnel project. There are 17 project

    information papers, which cover various aspects of the project. Those project information papers that may be of

    particular interest are set out below.

    Icon Title Details

    Build

    Provides information on the different types of sites required for the Thames Tunnel

    project and the typical construction activities that will be undertaken at each site.

    Changes

    Explains how the scheme has changed compared to that presented at phase one

    consultation, including changes to the tunnelling strategy for the main tunnel and

    changes to sites.

    Q&A Consultation

    Sets out the consultation we have undertaken to date on the project, the scope

    of this phase two consultation and how interested parties can respond to thisconsultation.

    DesignContains the design principles which have influenced the permanent appearance of

    our sites once construction work is complete.

    EnvironmentSets out the process the project is following to assess potential environmental effects

    of the Thames Tunnel project.

    Managing

    construction

    Includes information on what measures our contractors will put in place at our sites

    during construction.

    Odour Sets out ourAir management plan and how it will work.

    Options Outlines the various ways to deal with sewage overflows.

  • 8/3/2019 P2 Deptford CS SIP

    27/32

    27

    Phase two public consultation material

    Icon Title Details

    OverflowSets out how Londons sewerage system works and why the capital has an overflow

    problem.

    Route and

    tunnel

    alignment

    Sets out the preferred route of the main tunnel and the reasons for our preference.

    Site selection Sets out the process we followed to find and select our preferred sites.

    Transport Contains information on the different transport options we have considered fordelivering and removing materials from our sites.

    Further information

  • 8/3/2019 P2 Deptford CS SIP

    28/32

    28

    Technical reports

    Theme Icon Title Details

    Interim

    engagement

    Interim engagement

    report

    Provides a summary of the public engagement we

    have undertaken between phase one and phase two

    consultations.

    Phase one

    consultation1

    SUMMARY

    Report on phase one

    consultation:

    summary report

    Provides a summary of the comments made at phase one

    consultation and our responses.

    Phase two

    construction

    information

    Code of construction

    practice Part A:

    General requirements

    (CoCP)

    Sets out control measures to be adopted during the project

    construction period.

    Phase twoenvironmental

    information

    Air management

    plan

    Outlines the methods which we will use to manage odour

    from the main tunnel at all our preferred sites.

    Preliminary

    environmental

    information report

    (PEIR)

    Contains initial assessments on the environmental effects of

    the Thames Tunnel project based on information collected

    to date. Please refer to volume 25 of the non-technical

    summary and volume 25 of the PEIR for more information

    on this site.

    Phase two scheme

    development

    Design development

    report

    Provides a general overview of how the scheme design at

    each site has evolved to date. Please refer to chapter 23 for

    more information on this site.

    2

    Phase two scheme

    development report

    Provides an overview of the development of the Thames

    Tunnel project and how each site was chosen. Please refer to

    Appendix U for more information on this site.

    Site glossary

  • 8/3/2019 P2 Deptford CS SIP

    29/32

    29

    g

    Term Definition

    Carbon filters Filters that remove odours before the air is released from the tunnel.

    Combined sewer A single sewer system that takes both rainwater and domestic and industrial wastewater.

    Combined sewer

    overflow (CSO)

    A structure, or series of structures, that allows sewers to overflow into the river when they

    are full as a result of increased rainfall. Without the overflows, the sewers would back up

    and cause flooding in streets or houses.

    Conservation areaAn area designated by the local authority or English Heritage as having special

    architectural or historical interest.

    Draft limit of land to beacquired or used The extent of land that we may need to use or acquire, or over which rights may be neededto carry out works that are essential to the project.

    Drop shaft

    A vertical circular concrete structure, used to drop flows from the high level of the CSO to

    the low level of the main tunnel. It would also be used to provide access to construct the

    connection tunnels.

    Interception chamberA structure, built on an existing combined sewer, which diverts stormwater overflow into the

    main tunnel.

    Main tunnel The tunnel from Acton Storm Tanks to Abbey Mills Pumping Station.Operational phase After the completion of the construction work, when the main tunnel is in use.

    Thames Tunnel project

    The Thames Tunnel project comprises a storage and transfer tunnel, from west London to

    Beckton Sewage Treatment Works in east London, and the control of 34 CSOs along the

    Thames Tideway.

    Transport for London

    Road Network (TLRN)

    The network of roads managed by Transport for London. These are the major or strategic

    roads, which have high capacity.

  • 8/3/2019 P2 Deptford CS SIP

    30/32

  • 8/3/2019 P2 Deptford CS SIP

    31/32

  • 8/3/2019 P2 Deptford CS SIP

    32/32

    Phase two consultation: Deptford Church Street

    For further information or to comment on our

    proposals see our website:

    www.thamestunnelconsultation.co.uk

    110-ED-PNC-00000-000078

    Autumn 2011

    It is very important that you understand theinformation we have provided. If you needfurther information in another language,

    braille, large print or audio format pleasecontact us on 0800 0721 086.