P2 KEMP SIP

download P2 KEMP SIP

of 36

Transcript of P2 KEMP SIP

  • 8/3/2019 P2 KEMP SIP

    1/36

    Introd

    uction

    King Edward MemorialPark Foreshore

    Currently, untreated sewage regularly overows into the River Thames from Londons Victorian sewerage systemvia combined sewer overows (CSOs). The proposed Thames Tunnel would intercept these overows through theuse of a new storage and transfer tunnel, which would link west London and Abbey Mills Pumping Station. Thesewage ow would then be transferred to Beckton Sewage Treatment Works via the Lee Tunnel. The reductionin untreated sewage entering the River Thames would bring long-term benets for the environment and users of

    the River Thames. In order to deliver the project we need a number of sites along the route and this documentidenties our current preferred site at King Edward Memorial Park Foreshore.

    Thames Tunnel

    Siteinformationpaper

    1

    Key facts

    Local authority: Tower Hamlets

    CSO name: North East Storm Relief

    CSO spill volume in an average year: 780,000m (equivalent to approximately

    312 Olympic swimming pools)

    Site type: CSO site

    Duration of main construction works: Approximately three and a half years.

  • 8/3/2019 P2 KEMP SIP

    2/36

    King Edward Memorial Park Foreshore

    2

    Section 1: Introduction and site informationWe are proposing to use the foreshore of the River

    Thames adjacent to King Edward Memorial Park for this

    construction work, and to accommodate permanent

    structures required to operate the main tunnel. The site

    would be used to connect the existing local CSO, known

    as the North East Storm Relief CSO, to the main tunnel.

    An area within King Edward Memorial Park would also be

    used temporarily for our construction works.

    The location of the site is shown in Figure 1A. Part of

    the site would be located within the foreshore of the

    River Thames, with the remainder of the site located

    within the multi-purpose sports area and park depot

    in the south western corner of King Edward Memorial

    Park. The Thames Path runs along the riverside and is

    located within the site. To the north of the park is The

    Highway (A1203). Free Trade Wharf, an apartment block,

    is located to the east. To the south is Shadwell Basin

    Outdoor Activity Centre and apartment blocks and to thewest is Glamis Road. The site is within the Wapping Wall

    Conservation Area.

    Related documents:

    Build

    This site information paper sets out our proposals at King

    Edward Memorial Park Foreshore. We have also producedproject information papers, which cover overarching

    topics relating to the project. Where we consider that a

    project information paper is particularly relevant, we have

    highlighted this in a related documents box. At the end

    of this site information paper is a list of other documents,

    which may be of interest and a glossary of terms.

  • 8/3/2019 P2 KEMP SIP

    3/36

    Introduction

    3

    Figure 1A: King Edward Memorial Park Foreshore location plan

    N

    Shadwell Basin

    King EdwardMemorial

    Park

    North EastStorm Relief CSO

    Free Trade Wharf

    CableStree

    t

    TheHighway

    Glam

    is Road

    TOWER HAMLETS

    SOUTHWARK

    Local authority boundary

    Draft limit of land to beacquired or used

    Proposed tunnelroute centreline

    Existing sewer

    Existing CSO

  • 8/3/2019 P2 KEMP SIP

    4/36

    King Edward Memorial Park Foreshore

    4

    How we chose this site

    What we proposed at phase one consultationAt phase one consultation, which was held between

    September 2010 and January 2011, we presented King

    Edward Memorial Park Foreshore as our preferred site

    to intercept the existing North East Storm Relief CSO.

    We proposed to directly intercept the existing sewer and

    connect the CSO to the main tunnel within the foreshore

    of the River Thames.

    Why we have amended our proposals

    Since January 2011, we have considered the comments

    from phase one consultation, feedback from ongoing

    engagement and new information; and undertaken

    further technical work. This work led us to review potential

    sites to intercept the CSO and how to connect it to the

    main tunnel.

    Since phase one consultation we have:

    Looked again at the layout of our phase one

    consultation foreshore site and access requirements.

    Re-assessed all potential sites that could be used to

    intercept the CSO.

    Investigated options where the CSO could be

    intercepted within King Edward Memorial Park with

    a separate site being used to connect the CSO to the

    main tunnel.

    As a result of this work, an option could be to use King

    Edward Memorial Park with a site at Heckford Street to

    connect the CSO to the main tunnel. In order to seek

    feedback on this potential preliminary working option,

    in July 2011 we held drop-in sessions for the local

    community to understand the options proposed at King

    Edward Memorial Park Foreshore and Heckford Street. Wereviewed all the comments we received and took these

    into account as part of the site selection process.

    What we are proposing at phase two consultationWe have identified two shortlisted sites where we

    would be able to intercept the CSO and connect to the

    main tunnel within the site. The sites, as shown on

    Figure 1B, are:

    King Edward Memorial Park (site 1)

    King Edward Memorial Park Foreshore

    (our preferred site).When comparing, site 1 King Edward Memorial Park

    with King Edward Memorial Park Foreshore, we concluded

    that King Edward Memorial Park would be less suitable

    because using the park would involve the temporary loss

    of a large area of public open space and would be likely

    to cause more disruption to users of the park.

    In addition, we have identified three further shortlisted

    sites, where the connection to the main tunnel would bemade at a separate site in conjunction with intercepting

    the CSO within part of King Edward Memorial Park. The

    sites, as shown on Figure 1B, are:

    Heckford Street (site 2)

    Shadwell Basin (site 3)

    Limehouse Basin (site 4).

    We decided that using Site 3 Shadwell Basin andSite 4 Limehouse Basin would be less suitable thanHeckford Street (site 2) because it would be technically

    challenging to undertake the construction works within

    water basins, the sites have poor access and they

    are further away from the CSO. This means a longer

    connection tunnel would be required from one of these

    sites to the CSO in King Edward Memorial Park.

  • 8/3/2019 P2 KEMP SIP

    5/36

    Introduction

    5

    Figure 1B: Preferred and shortlisted sites

    Site 1

    Site 2

    Site 3

    Site 4

    N

    TOWER HAMLETS

    SOUTHWARK

    Preferred site King Edward Memorial

    Park ForeshoreOther shortlistedsite locations

    Local authorityboundary

  • 8/3/2019 P2 KEMP SIP

    6/36

    King Edward Memorial Park Foreshore

    6

    The alignment of the main tunnel varies depending upon

    where the CSO is connected to the main tunnel. Figure

    1C shows how the CSO is connected to the main tunnel

    and the different alignments of the main tunnel for KingEdward Memorial Park Foreshore and Heckford Street.

    When comparing the sites, our conclusion is that, on

    balance, King Edward Memorial Park Foreshore should

    remain our preferred site. We propose to reduce thesize of the construction site in the foreshore of the

    River Thames compared with our proposals at phase

    one consultation, which would reduce the effect on

    the foreshore and adjacent residential area. Office andwelfare buildings would be located in the depot and

    hardstanding areas in the south western part of the

    park. Our proposed temporary construction access has

    moved from the north eastern corner of the park, off The

    Highway (A1203), to Glamis Road. A significant length

    of river frontage adjacent to the Rotherhithe Tunnel

    ventilation shaft will remain accessible throughout the

    construction period, as will the vast majority of the park.

    After the construction works are completed, this accesswould remain and would offer an improved route for

    the Thames Path to be integrated with the park. On

    completion of our work, the park would be enlarged

    due to the extension into foreshore. There would also

    be opportunities to reinstate recreational facilities and

    enhance the park facilities.

    Related documents:

    Q&A Consultation

    Site selection

    Site 2 Heckford Street is a shortlisted site that wouldneed to be used together with a site in King Edward

    Memorial Park. This option is considered less suitable than

    our preferred site because the combination of both sitesand the additional tunnelling works would be likely to

    take longer, cause more disruption to both park users and

    the local community, and put more traffic on local roads.

    The site would result in the disruption and potential loss

    of some businesses in an area where the local authority

    is seeking to protect employment uses. The use of this

    site would also result in greater effects on people living

    and working near this site in comparison to our preferred

    site as it would not be possible to utilise the River Thamesfor movement of materials. Furthermore the tunnels

    would pass below significantly more buildings and the

    connection tunnel would be at much shallower depth.

  • 8/3/2019 P2 KEMP SIP

    7/36

    Introduction

    7

    N

    Figure 1C: Connecting North East Storm Relief CSO to the main tunnel

    TOWER HAMLETS

    SOUTHWARK

    Local authority boundary

    Tunnel centre line(preferred site)

    Tunnel centre line (site 2)

    Existing sewer

    Existing CSO

    Preferred site King Edward Memorial

    Park ForeshoreSite 2 Heckford Street

    Connection tunnel

    Worksite for CSOinterception

    Worksite for shaftconstruction

    Controlled (day time) crossing open unless road requiredby construction activities

  • 8/3/2019 P2 KEMP SIP

    8/36

    King Edward Memorial Park Foreshore

    8

    Section 2: Construction

    Construction activitiesConstruction activities are required to intercept the CSO.We would construct an interception chamber to intercept

    the CSO. A connection culvert would link the interception

    chamber to a drop shaft (approximately 60m deep)

    through which flows would pass into the main tunnel.

    Figure 2A illustrates the below ground infrastructure

    proposed. As the construction works would take place

    within the foreshore of the River Thames, a permanent

    structure projecting into the foreshore is required. Theseactivities would take place within the area indicated by

    the red line in Figure 1A, in four main phases, lasting

    approximately three and a half years in total. The main

    construction activities associated with these phases are

    set out in Table 2.1.

    After completion of the works and site restoration we

    may need to visit the site for short periods to support

    finishing works at the bottom of the drop shaft, which willbe carried out from within the main tunnel and serviced

    from the site at Chambers Wharf. For example, we may

    need to provide ventilation for the workers in the main

    tunnel and a means of emergency escape.

    Related documents:

    Build

    Managing construction

  • 8/3/2019 P2 KEMP SIP

    9/36

    Construction

    Construction

    9

    Main tunnel

    Drop shaftValve chamber

    Existingoverfowto River Thames

    Interceptionchamber

    Existing sewer

    Connection culvert

    Figure 2A: Illustration showing typical elements of below ground infrastructure

  • 8/3/2019 P2 KEMP SIP

    10/36

    King Edward Memorial Park Foreshore

    10

    Advance works

    Phase 1

    Site setup

    Figure reference Figure 2C

    Typical working hours Varies Standard

    Mainconstructionactivities

    Utilities connected

    Utilities diverted or protected

    Pre-construction landscape works carried out

    Site cleared

    Temporary works in River Thames constructed

    Site facilities and access set up

    Drop shaft excavated and built

    Above and below ground structures constructed

    Mechanical and electrical equipment installed

    Temporary works in the River Thames removed

    Site restored and landscaped

    Temporary site facilities removed

    Table 2.1: Main activities during construction phases

    Our typical working hours are expected to be:

    Standard: 8am-6pm weekdays, 8am-1pm Saturday*

    Extended standard: 6pm-10pm weekdays, 1pm-5pm Saturdays

    Continuous: 24 hours a day, seven days a week**

    Varies: Working hours for advanced works will depend on the nature of the works and will be

    agreed with the local authority

  • 8/3/2019 P2 KEMP SIP

    11/36

    Construction

    11

    Phase 2

    Drop shaft

    construction

    Phase 3

    Construction of

    other structures

    Phase 4

    Completion of

    works and siterestoration

    Figure 2D Figure 2E

    Standard with occasional

    extended standardStandard Standard

    * Standard working hours would also include, subject to agreement with the local authority:

    a short period (up to one hour) before works start and after they have finished to allow our workers to prepare for work and check the site.

    equipment and machinery maintenance could also take place 1pm-5pm Saturday and 10am-4pm Sunday.

    ** The main activities taking place 24 hours a day are below ground or within an enclosure.

  • 8/3/2019 P2 KEMP SIP

    12/36

    King Edward Memorial Park Foreshore

    12

    Site layout and construction phasesFigures 2C, 2D and 2E show how the site might be laid

    out during the construction phases, which are set outin Table 2.1 and Figure 2B. These layouts have been

    informed by the size of the infrastructure proposed,

    the construction methods required and the location

    of neighbouring buildings and structures. They have

    also been developed to minimise effects on the local

    community and environment. Particular factors at this site

    that have influenced the layout are as follows:

    Since phase one consultation, the temporary office andwelfare buildings required to service the construction

    site have been moved from the foreshore of the River

    Thames to the multi-purpose sports area and park

    depot in the south western corner of the park. A smaller

    area of foreshore is now required for the construction

    works, thereby reducing potential effects on river

    ecology, river navigation and river users.

    The access route to the site has been amended since

    phase one consultation. The proposed access at phaseone consultation was from the north of the site, directly

    off The Highway (A1203). We are now proposing to

    access the site from the south west, off Glamis Road.

    The proposed construction access would reduce the

    effects of construction traffic on the strategic highway

    network and provide a safer access to the site via an

    existing traffic light controlled junction.

    In addition the new access road avoids a wildlifemeadow in the eastern part of the park and is also

    located further from the Free Trade Wharf residential

    development and the access to Free Trade Wharf. The

    proposed access route through the park runs parallel to

    the river frontage and offers an opportunity to reinstate

    the Thames Path with improved pedestrian and cycle

    access on completion of the project.

    The site layouts are indicative only, and the contractormay arrange the site in a different way, depending on

    the chosen construction methods, provided that any

    environmental effects are appropriately managed and

    that the main construction activities are undertaken

    within the red line shown in Figure 1A.P1

    P2

    P3

    P4

    Advance

    works

    Year 1 Year 2 Year 3 Year 4

    Figure 2B: Construction timeline showing approximateduration of works in phases (P)

  • 8/3/2019 P2 KEMP SIP

    13/36

    Construction

    13

    Figure 2C: Illustrative phase 1 construction plan

    N

    Jack up bargeservicing piling

    operationsBarge

    Maximum extent ofconstruction site for

    phase 1Site hoarding

    Cofferdam

    Local authorityboundary

    Site support/welfare

    Internal site roadSite access

    Existing Thames Path

    Thames Path diversion

    TOWER HAMLETS SOUTHWARK

    Controlled (day time)crossing openunless required byconstruction activities

    Diversion only required when

    internal site road in use

  • 8/3/2019 P2 KEMP SIP

    14/36

    King Edward Memorial Park Foreshore

    14

    Figure 2D: Illustrative phase 2 construction plan

    Controlled (day time)crossing openunless required byconstruction activities

    Diversion only required wheninternal site road in use

    Drop shaft

    Crane

    Piling rig

    N

    Maximum extent ofconstruction site forphase 2

    Site hoarding

    Cofferdam

    Local authority boundary

    Site support/welfare

    Excavated materialstorage and processing

    Maintenance workshopand storage

    Construction supportInternal site road

    Site access

    Existing Thames Path

    Thames Path diversion

    TOWER HAMLETS SOUTHWARK

    Barge

  • 8/3/2019 P2 KEMP SIP

    15/36

    Construction

    15

    Option for contractorto transport materialsusing barges

    Controlled (day time)crossing openunless required byconstruction activities

    Diversion only required wheninternal site road in use

    Drop shaft

    Cranes

    N

    Maximum extent ofconstruction site forphase 3

    Site hoarding

    Cofferdam

    Local authority boundary

    Site support/welfare

    Excavated materialstorage and processing

    Construction support

    Internal site road

    Site access

    Existing Thames Path

    Thames Path diversion

    TOWER HAMLETS SOUTHWARK

    Figure 2E: Illustrative phase 3 construction plan

    Ki Ed d M i l P k F h

  • 8/3/2019 P2 KEMP SIP

    16/36

    King Edward Memorial Park Foreshore

    16

    Additional works and activitiesThe main construction activities at this site are set out in

    Table 2.1. We would also need to undertake additional

    works and activities, some of which may be located

    outside of the area indicated by the red line in Figure 1A.

    The anticipated additional works and activities are set

    out in Table 2.2.

    When Type of works What we would do

    Required for

    construction

    phase

    Installation of equipmentto monitor environmental

    matters such as noise,

    vibration and dust.

    The locations of monitoring equipment would be agreed with the

    local authority and relevant landowners.

    Protection works to third

    party structures (such

    as buildings, bridges

    and tunnels).

    We would undertake studies to identify any effects our construction

    work may have on third party structures. The studies may recommend

    particular construction methods or, in very limited instances,

    protection works.

    If protection works are required to the existing sewer, we would

    access the sewer network through existing manholes.

    Diversion of utilities.If utility diversions are required, we would work with utility providers

    to undertake the necessary works.

    Temporary connection

    to utilities (such as

    water, sewer, phone and

    electricity).

    We expect to connect to water, sewer and phone supplies in Glamis

    Road or The Highway (A1203).

    We may need to connect to a power supply in Welclose Square,

    running cables long Cable Street and Glamis Road. However, we are

    still developing a route for electricity supply in discussion with the

    utility provider.

  • 8/3/2019 P2 KEMP SIP

    17/36

    Construction

    17

    Table 2.2: Additional works and activities

    When Type of works What we would do

    Required for

    construction

    phase

    Traffic management works.

    These may need to extend beyond our site and could include

    relocating kerb lines, repainting road lines and modifying traffic

    signals.

    Dredging.

    There is a possibility that as the detailed design is developed we may

    need to undertake dredging to allow barges to get to and from our

    site.

    Protection of river bed.We may need to carry out works to strengthen the river bed to avoid

    scour.

    Landscaping works

    completed in advance of the

    main construction works.

    We would reconfigure and relocate the multi-purpose sports area,

    childrens playground and memorial benches within the park. The

    memorial benches would be moved to a new permanent location as

    shown in Figure 3D. We would dismantle the bandstand and store it

    so that it can be re-erected at the end of construction works. Paving

    and landscaping works to the seating area next to the Rotherhithe

    Tunnel ventilation shaft would also be undertaken.

    Required for

    operational

    phase

    Permanent connection

    to utilities (such as water,

    phone and electricity

    supply) for the operational

    tunnel.

    We expect to connect to utilities in Glamis Road or The Highway

    (A1203).

    Landscaping works.

    The multi-purpose sports area would be reinstated in its existing

    location. We would relocate the childrens playground to a new

    permanent location within the park, as shown in Figure 3E.

    King Ed ard Memorial Park Foreshore

  • 8/3/2019 P2 KEMP SIP

    18/36

    King Edward Memorial Park Foreshore

    18

    Construction transport and accessWe propose to use barges to bring in and take away the

    material used to fill the cofferdam and to take away

    excavated material from the shaft. It is not generally

    practical and cost effective to transport all materials

    to and from the site by barge so we would still need to

    transport some materials by road. We would however

    give the contractor the flexibility to determine the most

    practical and cost-effective means of transporting other

    materials and equipment.

    Each barge would remove approximately 55 lorries from

    the road. Using barges at this site would reduce the

    number of lorry visits to/ from this site by approximately

    55% (saving 12,000 lorry visits over the construction

    period of approximately three and a half years). Table 2.3

    sets out the anticipated average daily number of lorries

    and barges visiting (ie travelling to and from) the site

    during the peak months of each phase, based on moving

    cofferdam fill material by barge.

    Construction traffic would access the site from The

    Highway (A1203), travelling south down Glamis Road and

    turning left into the site from a new entrance on Glamis

    Road. Traffic would leave the site via the same route.

    This access route is shown on Figure 2F. Beyond this,

    construction traffic would use the major road network to

    get to and from its final destination.

    We may need to suspend or relocate some coach parking

    bays on Glamis Road during construction. We may also

    need to make some modifications to the junction of

    Glamis Road and The Highway (A1203) to accommodate

    construction traffic turning into Glamis Road.

    The Thames Path currently runs through the park. Since

    the Thames Path would be located within part of our

    construction site, it would be necessary to temporarily

    divert the Thames Path around part of our site. In order

    for the diverted Thames Path to re-join the existing

    Thames Path, it would need to cross our internal site

    road. Should construction vehicles be using the road,

    a gated access would prevent pedestrians and cyclists

    crossing it. This arrangement would mean that access

    to the seating area next to the Rotherhithe Tunnel

    ventilation shaft, which provides views across the River

    Thames, would be maintained. When the road is in use,

    pedestrians and cyclists would be directed to a diversion,

    which runs through the park as shown on Figures 2C, 2Dand 2E. Based on our current design we do not anticipate

    that any other footpath or road diversions or bus stop

    relocations would be required.

    Phase 1Site setup

    Phase 2Drop shaft

    construction

    Phase 3Construction ofother structures

    Phase 4Completion ofworks and site

    restoration

    Average daily

    lorry visits13 lorries 19 lorries 22 lorries 7 lorries

    Average daily

    barge visits 2 barges 1 barge none 2 barges

    Table 2.3: Average daily lorry and barge visits during the peak months

    Construction

  • 8/3/2019 P2 KEMP SIP

    19/36

    Construction

    19

    Related documents:

    Transport

    Figure 2F: Proposed access route to the site from the nearest major road

    RotherhitheTunnel

    The HighwayPossible junction

    modifications

    Glamis Road

    GlamisRoad

    Suspensionof coachparking

    A1203

    A101

    Left turn in,right turn out

    TOWER HAMLETS SOUTHWARK N

    Draft limit of land tobe acquired or used

    Internal site road

    Site access

    Local authority boundary

    Transport for London(TfL) road network

    Proposed lorry access toTfL road network

    King Edward Memorial Park Foreshore

  • 8/3/2019 P2 KEMP SIP

    20/36

    King Edward Memorial Park Foreshore

    20

    Management of construction worksOur construction works would be managed in accordance

    with an agreed Code of construction practice (CoCP).For phase two consultation, we have produced a draft

    CoCP Part A: General requirements, informed by CoCPsfrom other major construction projects in London and

    consultation with the local authorities. Through the

    environmental impact assessment process, scheme-

    wide principles to address potential effects on the local

    environment have been identified and integrated into

    the design. The CoCP Part A sets out scheme-wide control

    measures that would be used to minimise potentialeffects during the construction process.

    Issue Our response

    Permanent relocation

    of the childrens

    playground, currently

    located in the south

    western corner of the

    park.

    Prior to the main construction phase, the playground would be relocated within the park.We would work with park users and the London Borough of Tower Hamlets to agree the

    relocation and design of the playground.

    Temporary loss of part

    of the multi-purpose

    sports area and some

    tennis courts, located

    in the south westerncorner of the park.

    During construction, some of the tennis courts would be used to provide a temporary

    replacement multi-purpose sports area. The multi-purpose sports area would be reinstated in

    its existing location and in an improved condition following completion of construction.

    Potential loss of and

    damage to trees within

    the park.

    We have sought to minimise tree loss and damage where possible, and will propose careful

    root protection, pollarding and trimming methods. Proposals for permanent site landscaping

    incorporate the planting of more trees than the number expected to be lost during

    construction. Where possible it is intended that landscaping would be undertaken in advance

    of the main construction works commencing.

    Table 2.4 sets out what we consider to be the key issues

    for this site during construction, and how we are currently

    proposing to address them.

    Related documents:

    Environment

    Construction

  • 8/3/2019 P2 KEMP SIP

    21/36

    Construction

    21

    Issue Our response

    Temporary diversionof the Thames Path,

    restricted access to the

    riverfront and possible

    loss of river views.

    Access to the Thames Path next to the River Thames beside the Rotherhithe Tunnel

    ventilation shaft would be maintained throughout construction. Gated access across the

    internal site road would allow access from the ventilation shaft to the rest of the park when it

    is not being used by construction vehicles. Views over the River Thames would be temporarily

    affected during construction. However, access will be maintained to the river front from parts

    of the park including the new seating area beside the Rotherhithe Tunnel ventilation shaft.

    Possible effect ofconstruction vehicles

    on the capacity and

    operation of the local

    road network.

    Since phase one consultation, site access has been relocated to the south west side of the

    park, off Glamis Road to reduce the effects of construction traffic on the major road network

    and provide safer site access.

    We would manage the effects of road transport through our traffic management plans,

    which will seek to limit the number of vehicle movements and hours of operation, identify

    the most suitable site access points and any necessary highway management arrangements.

    As already set out, we also propose to use barges to bring in and take away the majority

    of material used to fill the cofferdam, which would significantly reduce the number of lorry

    movements from this site over the construction period.

    Temporary suspension

    or relocation of somecoach parking bays on

    Glamis Road.

    The extent and duration of the suspension of any coach bays during construction wouldbe minimised as far as possible. We are investigating options for temporary replacement

    parking provision during construction where necessary.

    Possible effect of

    foreshore construction

    activities on river

    navigation and river

    users of the River

    Thames, including the

    Shadwell Basin Outdoor

    Activity Centre.

    Since phase one consultation, we have reduced the area of temporary cofferdam foreshore

    extension by relocating those construction activities that do not need to be located

    immediately adjacent to the main tunnel site to the areas of hardstanding on the western

    side of the park, near Glamis Road.

    We have undertaken modelling to test the effect that the structure has on the flow of theriver. The modelling has shown the proposed structure to be satisfactory and the Port of

    London Authority and other key stakeholders are satisfied the permanent works have a

    minimum effect on river navigation. A full navigational risk assessment will be undertaken

    for the temporary and permanent works. Existing moorings may have to be temporarily

    relocated.

    Table 2.4: Key issues relating to construction

    King Edward Memorial Park Foreshore

  • 8/3/2019 P2 KEMP SIP

    22/36

    King Edward Memorial Park Foreshore

    22

    Issue Our response

    Possible effect of noiseand vibration from

    construction activities

    on neighbouring areas.

    Since phase one consultation, we have relocated the construction site access point to Glamis

    Road on the west of the site, to reduce effects on the nearest residential properties. The

    contractor would also be required to implement noise and vibration control measures at the

    worksite, which will be set out in the CoCP.

    Possible effects on

    local air quality and

    dust nuisance in

    neighbouring areas.

    Preliminary findings indicate that while there is the potential for dust nuisance effects, there

    are unlikely to be any significant local air quality effects at any of the sites. The contractor

    would put in place air and dust control measures at the worksite, which will be set out in the

    CoCP.

    Possible effects on

    foreshore habitat and

    river wildlife within the

    River Thames.

    Since phase one consultation, we have reduced the area of temporary cofferdam foreshore

    extension to reduce potential effects on ecology. Ecological surveys are also being

    undertaken to identify possible effects arising from construction activities. The contractor

    would put in place various control measures at the worksite to minimise these effects as far

    as possible. These will be set out in the CoCP.

    Table 2.4: Key issues relating to construction

    Related documents:

    Managing construction

    Transport

    Future use

  • 8/3/2019 P2 KEMP SIP

    23/36

    Future

    use

    23

    Section 3: Future use

    This section describes the site after the completion of theconstruction work, ie when the main tunnel is in use the

    operational phase.

    Design

    Since phase one consultation we have progressed the

    design for the permanent use and appearance of the

    structures at King Edward Memorial Park Foreshore. The

    design of the permanent proposals follows our scheme-

    wide principles and takes into account comments made

    and ongoing engagement with the London Borough of

    Tower Hamlets and other technical consultees.

    Our permanent works which are formed within a structureextending into the foreshore of the River Thames need to

    incorporate functional elements, which are required for

    the operation of the tunnel. These include:

    Underground structures with ground level access covers

    including: a CSO drop shaft with an internal diameter

    of approximately 20m, connection culverts, interception

    chamber, valve chamber and a passive filter chamber.

    Two main ventilation columns up to 5m high.

    Two small diameter ventilation columns to the

    interception chamber up to 6m high.

    Maintenance vehicle access.

    An electrical and control kiosk.

    Table 3.1 sets out the site specific issues that have

    influenced our permanent design proposals and how we

    have addressed them in our proposed design.

    King Edward Memorial Park Foreshore

  • 8/3/2019 P2 KEMP SIP

    24/36

    King Edward Memorial Park Foreshore

    24

    Issue Our response

    Effect on Rotherhithe Tunnel Careful siting of foreshore extension and permanent works to avoid infringing intothe protected zone of the Rotherhithe Tunnel.

    Accommodation of Cole Stairs

    and Bell Wharf CSOs (two

    existing local CSOs that do not

    need to be intercepted as part

    of the Thames Tunnel project

    based on the assessment

    undertaken by theEnvironment Agency).

    Careful siting of foreshore extension and permanent works to ensure that the

    two further CSOs not being intercepted remain operational either side of the new

    structure. Avoiding interference with these CSOs ensures that they do not need to

    be incorporated into the works and therefore the size of construction site required is

    minimised.

    Effect on King Edward

    Memorial Park.

    The proposed above ground structures have been reduced in size since phase

    one consultation, as a result of the modified scheme-wide ventilation strategy. In

    addition the proposed electrical and control kiosk has been relocated to the eastern

    perimeter of the park. Removing this structure from the foreshore extension makes it

    less visible and avoids interrupting views of the River Thames.

    A number of architectural design developments have taken place to ensure that thearchitectural design of the above ground structures and the foreshore extension is

    sympathetic to the park.

    The new foreshore structure would extend the area of the park as it will be designed

    to blend with the existing green space.

    Effect on the setting of the

    Grade II listed Rotherhithe

    Tunnel ventilation shaft andcharacter of the Wapping Wall

    Conservation Area.

    The majority of the proposed permanent works on this site would be below or at

    ground level to avoid any significant effect on the setting of the listed buildings or

    character of the Conservation Area. Landscaping for the extended and reinstatedareas of the park would be designed in consultation with the relevant stakeholders to

    ensure that the character of the Conservation Area is preserved and enhanced.

    Future use

  • 8/3/2019 P2 KEMP SIP

    25/36

    25

    Issue Our response

    Effects on river navigation

    and hydraulics.

    We have reduced the size of the foreshore area required for permanent works sincephase one consultation by moving the shaft closer to the river wall and re-profiling

    the foreshore extension to minimise effects on river flows.

    Preliminary modelling has indicated that the proposed design is acceptable in terms

    of river flow.

    The proposals have been discussed with the Port of London Authority and other key

    stakeholders to develop a layout that has a minimal effect on river navigation.

    Loss of foreshore habitat and

    effects on ecology within the

    River Thames.

    Our proposals for the permanent layout and design of the site have sought to reduce

    the extent of the permanent works within the foreshore to minimise effects on water

    ecology as far as possible.

    Ecological surveys of the River Thames and its foreshore are being undertaken to

    identify possible effects, and design measures will be incorporated where required.

    Construction of the tunnel would also deliver river wide improvements to local water

    quality, which would result in positive effects on river ecology, including habitat

    improvements and reduced fish kills.

    Effect on Thames Path.

    The permanent arrangement for the access route to our site from Glamis Road

    would provide an opportunity to use this as an enhanced Thames Path route for

    pedestrians and cyclists. The current Thames Path off Glamis Road is via a narrow

    and enclosed footway which could be widened and include potential landscaping

    improvements. The design of this route would be informed by the assessments of

    the current use and quality of the park along with ongoing consultation with the key

    stakeholders including the local authority.Table 3.1: Site specific issues that have influenced our permanent design

    King Edward Memorial Park Foreshore

  • 8/3/2019 P2 KEMP SIP

    26/36

    g d a d e o a a o es o e

    26

    Figure 3A: Photo of the site before the works

    Figures 3A, 3B, 3C, 3D and 3E show the current site and

    provide illustrations of our design proposals. Further

    information on the development of our design can be

    found in theDesign development report

    .

    Related documents:

    Design

    Future use

  • 8/3/2019 P2 KEMP SIP

    27/36

    27

    Figure 3B: Artists impression of the site after the works are completed

    King Edward Memorial Park Foreshore

  • 8/3/2019 P2 KEMP SIP

    28/36

    g

    28

    Figure 3C: Layout of the site showing landscape advance works

    Memorial Park benchespermanently relocatedin line with Memorial

    Thames Path divertedaround constructionsite hoarding

    The Highway

    Proposed

    constructionsite

    Glam

    isRoad

    Relocatedchildrensplay area

    Paving and landscapingimprovements to areaaround Rotherhithe

    Tunnel ventilation shaft

    Thames Pathremains open duringconstruction

    Minorreconfigurationof tennis courts

    Advanced treeplanting to improveMemorial Avenue

    Relocated multi-purpose sports area

    N

    Proposedconstruction

    site

    Controlled (daytime)crossing of constructionaccess route open unlessrequired by construction

    activities

    Future use

  • 8/3/2019 P2 KEMP SIP

    29/36

    29

    Figure 3D: Layout of site once construction works complete

    Grassed area aroundrelocated bandstand

    Electrical andcontrol kiosk againstexisting brick wall

    Relocatedbandstand

    Memorial Parkbenches relocated online with Memorial

    Ventilationcolumns

    Seating areaActivity/fitness zone

    Bike stands New gated entrance topark and Thames path

    N

    Footballpitch

    The Highway

    Glam

    isRoad

    Tenniscourts

    Relocatedchildrens play areaFootball pitch access

    Thames Path widenedand improved.Provides maintenanceaccess to shaft

    New North EastStorm ReliefCSO outlet

    Bowlinggreen

    King Edward Memorial Park Foreshore

  • 8/3/2019 P2 KEMP SIP

    30/36

    30

    Figure 3E: Aerial view of the completed works

    Future use

  • 8/3/2019 P2 KEMP SIP

    31/36

    31

    Operation and maintenanceOnce the tunnel is operational, we would need access

    to the site occasionally for inspection and maintenance

    purposes. We expect to visit the site approximatelyonce every three to six months to carry out inspections

    and maintenance of the ventilation and below ground

    equipment. This is likely to involve a visit by staff in a

    small van, and may take several hours.

    Once every ten years, we expect to carry out a major

    internal inspection of the tunnel and underground

    structures. This is likely to involve a small team of

    inspection staff, a small team of support crew and twomobile cranes to lower the team and inspection vehicle

    into the shaft. This is likely to take several weeks, and

    would require temporary fencing around the shaft for

    safety and security while the inspection takes place.

    We may also need to make visits to the site for unplanned

    maintenance or repairs, for example, if there is a

    blockage, or equipment failure. This may require the use

    of mobile cranes and vans. Permanent vehicular accesswould be from Glamis Road.

    Management of operational effectsWe have undertaken technical work, including stakeholder

    engagement, to assess and identify the key issues

    associated with this site once it is operational. Table3.2 summarises these issues and how we are currently

    proposing to address them.

    Issue Our response

    Possible odour effects during

    the operation of the tunnel.

    Odour effects at this site are expected to be negligible because we have developedanAir management plan to minimise possible odour and air quality effects arisingfrom the operation of the tunnel. The technology we are proposing to use at this

    site includes the use of passive below ground carbon filters that will remove possible

    odour before air leaves the ventilation equipment.

    Disturbance from future

    maintenance access.

    Permanent access would be required for maintenance and servicing purposes to

    the shaft and ventilation equipment. Any planned maintenance visits would be

    undertaken during normal working hours and all visits managed to avoid disruption

    to local residents, businesses and users of affected public areas as far as possible.

    Table 3.2: Key issues relating to site operation

    Related documents:

    Odour

    Further information

  • 8/3/2019 P2 KEMP SIP

    32/36

    32

    This section sets out documents which may be of particular interest. Further information on our proposals can be

    found on our website (www.thamestunnelconsultation.co.uk) or is available upon request (call our customer centre

    on 0800 0721 086).

    Phase two public consultation material

    Project information papers include general information about the Thames Tunnel project. There are 17 project

    information papers, which cover various aspects of the project. Those project information papers that may be of

    particular interest are set out below.

    Icon Title Details

    BuildProvides information on the different types of sites required for the Thames Tunnel

    project and the typical construction activities that will be undertaken at each site.

    Q&A ConsultationSets out the consultation we have undertaken to date on the project, the scope

    of this phase two consultation and how interested parties can respond to this

    consultation.

    Design

    Contains the design principles which have influenced the permanent appearance of

    our sites once construction work is complete.

    EnvironmentSets out the process the project is following to assess potential environmental effects

    of the Thames Tunnel project.

    Managing

    construction

    Includes information on what measures our contractors will put in place at our sites

    during construction.

    Odour Sets out ourAir management plan and how it will work.

    Options Outlines the various ways to deal with sewage overflows.

  • 8/3/2019 P2 KEMP SIP

    33/36

    33

    Phase two public consultation material

    Icon Title Details

    OverflowSets out how Londons sewerage system works and why the capital has an overflow

    problem.

    Route and

    tunnel

    alignment

    Sets out the preferred route of the main tunnel and the reasons for our preference.

    Site selection Sets out the process we followed to find and select our preferred sites.

    Transport Contains information on the different transport options we have considered fordelivering and removing materials from our sites.

    Further information

  • 8/3/2019 P2 KEMP SIP

    34/36

    34

    Technical reports

    Theme Icon Title Details

    Interim

    engagement

    Interim engagement

    report

    Provides a summary of the public engagement we

    have undertaken between phase one and phase two

    consultations.

    Phase one

    consultation1

    SUMMARY

    Report on phase one

    consultation:

    summary report

    Provides a summary of the comments made at phase one

    consultation and our responses.

    Phase two

    construction

    information

    Code of construction

    practice Part A:

    General requirements

    (CoCP)

    Sets out control measures to be adopted during the project

    construction period.

    Phase twoenvironmental

    information

    Air management

    plan

    Outlines the methods which we will use to manage odour

    from the main tunnel at all our preferred sites.

    Preliminary

    environmental

    information report

    (PEIR)

    Contains initial assessments on the environmental effects ofthe Thames Tunnel project based on information collected

    to date. Please refer to volume 23 of the non-technical

    summary and volume 23 of the PEIR for more information

    on this site.

    Phase two scheme

    development

    Design development

    report

    Provides a general overview of how the scheme design at

    each site has evolved to date. Please refer to chapter 20 for

    more information on this site.

    2

    Phase two scheme

    development report

    Provides an overview of the development of the Thames

    Tunnel project and how each site was chosen. Please refer to

    Appendix S for more information on this site.

    Site glossary

  • 8/3/2019 P2 KEMP SIP

    35/36

    35

    Term Definition

    Carbon filters Filters that remove odours before the air is released from the tunnel.

    CofferdamA wall that is constructed within the river around the outside of the working area and then

    pumped dry. The inside of the cofferdam can then be filled to create a safe working area.

    Combined sewer A single sewer system that takes both rainwater and domestic and industrial wastewater.

    Combined sewer

    overflow (CSO)

    A structure, or series of structures, that allows sewers to overflow into the river when they

    are full as a result of increased rainfall. Without the overflow, the sewer would back up and

    cause flooding in streets or houses.

    Connection tunnel A tunnel connecting a drop shaft to the main tunnel.

    Conservation areaAn area designated by the local authority or English Heritage as having special

    architectural or historical interest.

    Draft limit of land to be

    acquired or used

    The extent of land that we may need to use or acquire, or over which rights may be needed

    to carry out works that are essential to the project.

    Drop shaft

    A vertical circular concrete structure, used to drop flows from the high level of the CSO to

    the low level of the main tunnel. It would also be used to provide access to construct the

    connection tunnels.Foreshore Ground uncovered by the river when the tide is low.

    Interception chamberA structure, built on an existing combined sewer, which diverts stormwater overflow into the

    main tunnel.

    Main tunnel The tunnel from Acton Storm Tanks to Abbey Mills Pumping Station.

    Operational phase After the completion of the construction work when the main tunnel is in use.

    Scour Movement of the riverbed materials due to the force of the water.

    Thames Tunnel project

    The Thames Tunnel project comprises a storage and transfer tunnel, from west London to

    Beckton Sewage Treatment Works in east London, and the control of 34 CSOs along the

    Thames Tideway.

    Transport for London

    Road Network (TLRN)

    The network of roads managed by Transport for London. These are the major or strategic

    roads, which have high capacity.

  • 8/3/2019 P2 KEMP SIP

    36/36

    Phase two consultation: King Edward Memorial Park Foreshore

    For further information or to comment on our

    proposals see our website:

    www.thamestunnelconsultation.co.uk

    110-ED-PNC-00000-000086

    Autumn 2011

    It is very important that you understand theinformation we have provided. If you needfurther information in another language,

    braille, large print or audio format pleasecontact us on 0800 0721 086.