P2 Acton SIP

download P2 Acton SIP

of 32

Transcript of P2 Acton SIP

  • 8/3/2019 P2 Acton SIP

    1/32

    Thames Tunnel

    Siteinformationpaper

    1

    Currently, untreated sewage regularly overows into the River Thames from Londons Victorian sewerage systemvia combined sewer overows (CSOs). The proposed Thames Tunnel would intercept these overows through theuse of a new storage and transfer tunnel, which would link west London and Abbey Mills Pumping Station. Thesewage ow would then be transferred to Beckton Sewage Treatment Works via the Lee Tunnel. The reductionin untreated sewage entering the River Thames would bring long-term benets for the environment and users of

    the River Thames. In order to deliver the project we need a number of sites along the route and this documentidenties our current preferred site at Acton Storm Tanks.

    Introd

    uction

    Acton Storm Tanks

    Key facts

    Local authority: Ealing

    CSO name: Acton Storm Relief

    CSO spill volume in an average year: 310,000m (equivalent to approximately

    124 Olympic swimming pools)

    Site type: CSO and main tunnel reception site

    Duration of main construction works: Approximately three and a half years.

  • 8/3/2019 P2 Acton SIP

    2/32

    Acton Storm Tanks

    2

    Section 1: Introduction and site informationWe are proposing to use parts of our existing pumping

    station and storm water tanks site (Acton StormTanks) for this construction work and to accommodate

    permanent building and structures required to operate

    the main tunnel. The site would receive the main tunnel

    from Carnwath Road Riverside and connect the existing

    local CSO, known as the Acton Storm Relief CSO, to the

    main tunnel.

    The location of the site is shown in Figure 1A. The site

    includes six large open storm tanks, pumping station andlandscaped areas within our existing operational site. The

    site also includes Canham Road. To the north west, north

    east, south and east of the site are residential properties.

    These include the Factory Quarter development and

    properties on Emlyn Gardens and Greenend Road. A

    mixed use industrial estate is located to the north west

    and a number of commercial premises to the north of

    Canham Road.This site information paper sets out our proposals at

    Acton Storm Tanks. We have also produced project

    information papers, which cover overarching topics

    relating to the project. Where we consider that a project

    information paper is particularly relevant, we have

    highlighted this in a related documents box. At the end

    of this site information paper is a list of other documents,

    which may be of interest and a glossary of terms.

    Related documents:

    Build

    How we chose this siteCSO

    What we proposed at phase one consultation

    Through our site selection process, we identified three

    possible shortlisted sites to intercept the Acton Storm

    Relief CSO. At phase one consultation, which was

    held between September 2010 and January 2011, wepresented these sites:

    Former Hospital, Netheravon Road South

    Car park, Welstead Way

    Acton Storm Tanks.

    Acton Storm Tanks was identified as our preferred site

    at phase one consultation. We proposed to use a long

    connection tunnel to connect the CSO to the main tunnel.

    What we are proposing at phase two consultation

    We have considered the comments from phase one

    consultation, feedback from ongoing engagement and

    new information; and undertaken further technical work.

    Redevelopment of the Former Hospital site is now well

    advanced so it is no longer a potential CSO site.

    We still consider that Acton Storm Tanks should be our

    preferred site because it is in our ownership and is on the

    line of the CSO which means we can directly intercept it.

  • 8/3/2019 P2 Acton SIP

    3/32

    Introduction

    3

    Figure 1A: Acton Storm Tanks location plan

    N

    Acton StormRelief CSO

    WendellPark

    Canham Road

    ActonStormTanks Cobbo

    ldRoad

    AlliedWay

    GreenendRoad

    Stanley

    Gardens

    CSO discharges into River Thames approximately 1500metres south, adjacent to Chiswick Eyot

    Warp

    leWay

    EALING

    HAMMERSMITH &

    FULHAM

    HOUNSLOW

    Local authority boundary

    Draft limit of land tobe acquired or used

    Proposed tunnelroute centreline

    Existing sewer

    Factory Quarter

    EmlynGardens

  • 8/3/2019 P2 Acton SIP

    4/32

    Acton Storm Tanks

    4

    Main tunnel

    What we proposed at phase one consultationIn addition to sites to intercept the CSOs, we require sites

    to build the main tunnel at:

    each end of the main tunnel in west and east London

    suitable intervals along the route of the main tunnel

    locations where the type of geology that the main

    tunnel goes through changes.

    Prior to identifying the precise location of the main tunnel

    sites, we established the broad areas within which they

    would be needed. One of the main tunnel sites is required

    in the Hammersmith Bridge area, which is where the main

    tunnel would have ended.

    At phase one consultation, Hammersmith Pumping

    Station was our preferred site in this area to receive

    the main tunnel from Barn Elms and drive the long

    connection tunnel to Acton Storm Tanks.

    Why we have amended our proposals

    Since January 2011, we have considered the comments

    from phase one consultation, feedback from ongoing

    engagement and new information; and undertaken

    further technical work. This work led us to review possible

    sites within the western end of the main tunnel and ourtunnelling strategy, which considers how sites might be

    linked together to construct the main tunnel.

    Since phase one consultation, a new planning application

    for mixed use development has been submitted, covering

    the area around the Hammersmith Pumping Station

    site. Planning permission is expected to be granted and

    construction is likely to start in the near future. The

    proposals for mixed use development mean that therewould be insufficient space to accommodate a main

    tunnel site at the Hammersmith Pumping Station site.

    Therefore, we needed to find an alternative site to receive

    the main tunnel.

    We also reviewed our tunnelling strategy and concluded

    that the long connection tunnel, which would transfer

    flows from Acton Storm Tanks to the main tunnel, needs

    to be a similar diameter to the main tunnel. Therefore

    we propose to extend the main tunnel to enable a direct

    connection to the Acton Storm Relief CSO.

    As a result of these changes, the broad search area for

    the main tunnel site at the western end of the tunnel has

    changed, to the Acton Storm Tanks area.

    Given the proposed change of use of Acton Storm Tanks,

    in July 2011 we held drop-in sessions for the community

    around the site to understand any local issues, should

    there be a main tunnel reception site at this location. Wereviewed all the comments we received and took these

    into account as part of the site selection process.

    What we are proposing at phase two consultation

    We have identified four shortlisted sites to receive the

    main tunnel from Carnwath Road Riverside, as shown in

    Figure 1B. These are:

    Commercial units, Stanley Gardens (site 1)

    Acton Park Industrial Estate (site 2)

    Industrial units, Allied Way (site 3)

    Acton Storm Tanks (our preferred site).

  • 8/3/2019 P2 Acton SIP

    5/32

    Introduction

    5

    Figure 1B: Preferred and shortlisted sites

    Preferred site Acton Storm Tanks

    Other shortlisted site

    locations for main tunnel site

    Local authority boundary

    N

    EALING

    HOUNSLOW

    Site 1

    Site 3

    Site 2

    HAMMERSMITH &FULHAM

  • 8/3/2019 P2 Acton SIP

    6/32

    Acton Storm Tanks

    6

    Related documents:

    Changes

    Q&A Consultation

    Site selection

    Carnwath Road Riverside

    HammersmithPumping StationHPS

    CRR

    In considering our tunnelling strategy options, there were

    a number of factors we had to take into account. Based

    on current information, we concluded that Acton Storm

    Tanks would be less suitable as a main tunnel drive site.This was mainly due to the fact that this site is not near

    the River Thames, so there would be no opportunity to

    use the river to remove excavated material and to deliver

    of construction materials to site. It was however judged

    suitable as a main tunnel reception site.

    Acton Storm Tanks is our preferred site to receive themain tunnel from Carnwath Road Riverside for a number

    of reasons. It is brownfield site, it is in our ownership andthe site is large enough to accommodate all the main

    works.

    Site 1 Commercial Units, Stanley Gardens, Site 2 Acton Park Industrial Estate and Site 3 IndustrialUnits, Allied Way are shortlisted sites. All these sites areless suitable because they would result in both temporary

    and permanent loss of employment land and possibly

    affect a number of community uses within these areas.We do not own these sites, so we would need to acquire

    the land. In terms of tunnelling options, these sites could

    be used as main tunnel sites, but we would still need a

    site at Acton Storm Tanks to intercept the CSO.

  • 8/3/2019 P2 Acton SIP

    7/32

    Construction

    7

    Section 2: Construction

    Construction activitiesConstruction activities are required to intercept the CSO.To enable this, we would demolish the two northernmost

    storm tanks and construct an interception chamber within

    the storm tank facilities to intercept the CSO flows. A

    connection culvert would link the interception chamber

    to a drop shaft (approximately 31m deep) through which

    flows would pass into the main tunnel.

    The drop shaft would receive the tunnel boring machine

    from Carnwath Road Riverside, which would be

    dismantled and removed from the site. The drop shaft

    would also be used to install the secondary lining into

    the main tunnel. Figure 2A illustrates the below ground

    infrastructure proposed. These activities would take place

    within the area indicated by the red line in Figure 1A, in

    five main phases, lasting approximately three and a half

    years in total. The main construction activities associated

    with these phases are set out in Table 2.1.

    Figure 2A: Illustration showing typical elements of below ground infrastructure (existing storm tanks not illustrated for clarity)

    Drop shaft

    Main tunnel

    Valve chamber

    Existing sewer

    ExistingoverfowtoRiverThames

    Interception chamber

    Existingoverfowsewer

    Connection culvertConstruction

  • 8/3/2019 P2 Acton SIP

    8/32

    Acton Storm Tanks

    8

    Advanceworks

    Phase 1

    Site setup

    Figure reference Figure 2C

    Typical working hours Varies Standard

    Maincons

    tructionactivities

    Utilities connected

    Utilities diverted or protected

    Site cleared

    Site facilities and access set up

    Drop shaft excavated and built

    Tunnel boring machine removed from shaft and disassembled

    Above and below ground structures constructed

    Internal (secondary) tunnel lining constructed

    Mechanical and electrical equipment installed

    Site restored and landscaped

    Temporary site facilities removed

    Table 2.1: Main activities during construction phases

    Our typical working hours are expected to be:

    Standard: 8am-6pm weekdays, 8am-1pm Saturday*

    Extended standard: 6pm-10pm weekdays, 1pm-5pm Saturdays

    Continuous: 24 hours a day, seven days a week**

    Varies: Working hours for advanced works will depend on the nature of the works and will be agreed

    with the local authority

    * Standard working hours would also include, subject to agreement with the local authority: a short period (up to one hour) before works start and after they have finished to allow our workers to prepare for work and check the site.

    equipment and machinery maintenance could also take place 1pm-5pm Saturday and 10am-4pm Sunday.

    ** The main activities taking place 24 hours a day are below ground or within an enclosure.

  • 8/3/2019 P2 Acton SIP

    9/32

    Construction

    9

    Phase 2

    Drop shaft

    construction

    Phase 3

    Construction

    of otherstructures

    Phase 4

    Secondary

    lining

    Phase 5

    Completion of

    works and siterestoration

    Figure 2C Figure 2D Figure 2D

    Standard Standard Continuous Standard

    Related documents:

    Build

    Managing construction

  • 8/3/2019 P2 Acton SIP

    10/32

    Acton Storm Tanks

    10

    Site layout and construction phasesFigures 2C and 2D show how the site might be laid out

    during the construction phases, which are set out in Table2.1 and Figure 2B. These layouts have been informed by

    the size of the infrastructure proposed, the construction

    methods required and the location of neighbouring

    buildings and structures. They have also been developed

    to minimise effects on the local community and

    environment. Particular factors at this site that have

    influenced the layout are as follows:

    The construction access arrangements for the site havebeen amended since phase one consultation. Access

    would now be located on Canham Road to further

    reduce the effects of construction on the residents of

    Warple Way.

    Since phase one consultation the construction site has

    been moved to the northern end of the Acton Storm

    Tanks site, which is farthest from nearby residential

    properties on Warple Way.

    The site layouts are indicative only, and the contractor

    may arrange the site in a different way, depending onthe chosen construction methods, provided that any

    environmental effects are appropriately managed, and

    that the main construction activities are undertaken

    within the red line shown in Figure 1A.

    Year 2 Year 3 Year 4

    P1

    P2

    P3

    P4 P5

    Year 1

    Advance

    works

    Figure 2B: Construction timeline showing approximate

    duration of works in phases (P)

  • 8/3/2019 P2 Acton SIP

    11/32

    Construction

    11

    Figure 2C: Illustrative phases 1 and 2 construction plan

    Drop shaft

    Cranes

    N

    Maximum extent ofconstruction site forphases 1 and 2

    Site hoarding

    Local authority boundary

    Site support/welfare

    Excavated materialstorage and processing

    Maintenance workshopand storage

    Construction support

    Internal site road

    Site access

    EALING

    HOUNSLOW

    HAMMERSMITH &FULHAM

    Canham

    Road

    Warp

    leWay

  • 8/3/2019 P2 Acton SIP

    12/32

    Acton Storm Tanks

    12

    Figure 2D: Illustrative phases 3 and 4 construction plan

    Dropshaft

    Cranes

    Crane

    N

    Maximum extent ofconstruction site forphases 3 and 4

    Site hoarding

    Local authority boundary

    Site support/welfare

    Maintenance workshopand storage

    Construction support

    Internal site road

    Site access

    EALING

    HOUNSLOW

    Canham

    Road

    Warp

    leWay

    HAMMERSMITH &FULHAM

  • 8/3/2019 P2 Acton SIP

    13/32

    Construction

    13

    Additional works and activitiesThe main construction activities at this site are set out in

    Table 2.1. We would also need to undertake additionalworks and activities, some of which may be located

    outside of the area indicated by the red line in Figure 1A.

    The anticipated additional works and activities are set

    out in Table 2.2.

    When Type of works What we would do

    Required forconstruction

    phase

    Installation of equipment to monitor

    environmental matters such as noise,

    vibration and dust.

    The locations of monitoring equipment would be agreed with

    the local authority and relevant landowners.

    Protection works to third party

    structures (such as buildings, bridges

    and tunnels).

    We would undertake studies to identify any effects our

    construction work may have on third party structures. The

    studies may recommend particular construction methods or,

    in very limited instances, protection works.

    Temporary connection to utilities

    (such as water, sewer, phone and

    electricity supply).

    We expect to connect to water, sewer and phone supplies

    within the site.

    We expect to connect to a electricity supply in Emlyn Road.

    This would require minor temporary construction works

    within Cobbold Road.

    Traffic management works.

    These may need to extend beyond our site and could include

    relocating kerb lines, repainting road lines and modifying

    traffic signals.

    Required for

    operational

    phase

    Permanent connection to utilities

    (such as water, phone and electricity

    supply) for the operational tunnel.

    We expect to connect to utilities from within the site.

    Table 2.2: Additional works and activities

  • 8/3/2019 P2 Acton SIP

    14/32

    Acton Storm Tanks

    14

    Construction transport and accessWe would transport materials to and from the site by

    road. We intend to use most of the excavated material

    to infill two of the existing storm tanks, which would

    minimise the number of lorries visiting the site. Table 2.3

    sets out the anticipated average daily number of lorries

    visiting (ie travelling to and from) the site during the peak

    months of each phase.

    There are two possible site access options for construction

    traffic. Construction traffic could access the site from

    Old Oak Lane (A400), turn right on to The Vale (A4020)

    and left onto the southbound Warple Way, turn right

    into Canham Road and turn left into the site via a new

    temporary entrance off Canham Road. Alternatively,

    construction traffic could access the site from Hanger

    Lane (A406), travelling along Uxbridge Road/The Vale

    (A4020) and then following the same route to the site

    along Warple Way and Canham Road.

    Construction traffic would leave the site via the same

    entrance and turn left onto Canham Road, before

    travelling northbound along Stanley Gardens to the

    The Vale (A4020), from which it is possible to use either

    Hanger Lane (A406) or Old Oak Lane (A400). These

    access routes are shown on Figure 2E. Beyond this,

    construction traffic would use the major road network to

    get to and from its final destination.

    There may be a minor footpath diversion around the

    site. We may need to suspend or relocate some on-streetparking bays on Warple Way (north of Canham Road),

    Stanley Gardens and Canham Road during construction.

    We may also need to make minor modifications to the

    kerb line at each end of Canham Road to accommodate

    the movement of construction vehicles around these

    corners. Based on our current design, we do not anticipate

    that any road diversions or bus stop relocations would be

    required.

    Phase 1

    Site setup

    Phase 2

    Drop shaftconstruction

    Phase 3

    Constructionof other

    structures

    Phase 4

    Secondarylining

    Phase 5

    Completion ofworks and site

    restoration

    Average daily

    lorry visits4 lorries 7 lorries 16 lorries 16 lorries 6 lorries

    Table 2.3: Average daily lorry visits during the peak months

    Related documents:

    Transport

  • 8/3/2019 P2 Acton SIP

    15/32

    Construction

    15

    A40

    A406

    A40

    M4

    A3220

    A4020

    Uxbridge Road

    The Vale

    Left turn in, leftturn out

    Suspension of

    parking

    Warple Way

    StanleyGardens

    Old Oak LaneA400

    Canham

    Road

    EALING

    HOUNSLOWRICHMOND UPON

    THAMES

    BRENT

    HAMMERSMITH &FULHAM

    KENSINGTON &CHELSEA

    Draft limit of land tobe acquired or used

    Internal site road

    Site access

    Local authority boundary

    Transport for London(TfL) road network

    Proposed lorry access toTfL road network

    N

    Figure 2E: Proposed access route to the site from the nearest major road

    A t St T k

  • 8/3/2019 P2 Acton SIP

    16/32

    Acton Storm Tanks

    16

    Management of construction worksOur construction works would be managed in accordance

    with an agreed Code of construction practice (CoCP).For phase two consultation, we have produced a draft

    CoCP Part A: General requirements, informed by CoCPsfrom other major construction projects in London and

    consultation with the local authorities. Through the

    environmental impact assessment process, scheme-

    wide principles to address potential effects on the local

    environment have been identified and integrated into

    the design. The CoCP Part A sets out scheme-wide control

    measures that would be used to minimise potentialeffects during the construction process.

    Table 2.4 sets out what we consider to be the key issues

    for this site during construction, and how we are currently

    proposing to address them.

    Related documents:

    Environment

  • 8/3/2019 P2 Acton SIP

    17/32

    Construction

    17

    Issue Our response

    Possible effect of

    construction vehicles

    on the capacity and

    operation of the local

    road network.

    We are investigating opportunities to maximise the use of excavated material from

    the tunnel to fill up the northernmost storm tanks, and as part of the permanent site

    landscaping. This would reduce the volume of construction traffic.

    We have also sought to minimise disruption to the local road network through our site

    layout and design. We would manage the effects of road transport through our traffic

    management plans, which will seek to limit the number of vehicle movements and hours

    of operation, identify the most suitable site access points and any necessary highway

    management arrangements.

    Temporary suspension orrelocation of some on-

    street parking on Canham

    Road, Warple Way and

    Stanley Gardens.

    Use of the existing one way traffic system around the site would minimise the need to

    relocate/replace existing areas of off street car parking. We are investigating options for

    temporary relocation/replacement parking provision during construction where necessary.

    Possible effect of

    noise and vibration on

    neighbouring areas.

    Since phase one consultation, the main tunnel construction site has been moved to

    the northern end of the site, which is furthest from the majority of nearby residential

    properties. The contractor would be required to implement noise and vibration control

    measures at the worksite, which will be set out in the CoCP. Continuous working would onlybe undertaken for a short period of time to carry out tunnel lining.

    Possible effects on local

    air quality and dust

    nuisance in neighbouring

    areas.

    Since phase one consultation, the main tunnel construction site has been moved to

    the northern end of the site, which is furthest from the majority of nearby residential

    properties. Preliminary findings indicate that while there is the potential for dust nuisance

    effects, there are unlikely to be any significant local air quality effects at any of the sites.

    The contractor would put in place air and dust control measures at the worksite, which will

    be set out in the CoCP.

    Table 2.4: Key issues relating to construction

    Related documents:

    Managing construction Transport

    Acton Storm Tanks

  • 8/3/2019 P2 Acton SIP

    18/32

    Acton Storm Tanks

    18

    Section 3: Future use

    This section describes the site after the completion of the

    construction work, ie when the main tunnel is in use the

    operational phase.

    DesignSince phase one consultation we have progressed the

    design for the permanent use and appearance of the

    structures at Acton Storm Tanks. The design of the

    permanent proposals follows our scheme-wide principlesand takes into account comments made and ongoing

    engagement with the London Boroughs of Ealing

    and Hammersmith and Fulham and other technical

    consultees.

    Our permanent works need to incorporate functional

    elements, which are required for the operation of the

    tunnel. These include:

    Underground structures with ground level access covers

    including: a main tunnel shaft with an internal diameter

    of approximately 15m, connection culvert, interception

    chamber and valve chamber.

    A ventilation building containing fans, filters and

    electrical and control equipment.

    Three ventilation columns enclosed within a single

    structure up to 15m high.

    Maintenance vehicle access off Canham Road

    Works to structures associated with the existing storm

    tanks, including: modifications to existing weir overflow

    chamber, a new pipe overflow and overflow connection

    chamber.New pipework which will enable flows to bypass Acton

    Storm Tanks, significantly reducing odours which

    currently arise from the site.

    Table 3.1 sets out the site specific issues that have

    influenced our permanent design proposals and how we

    have addressed them in our proposed design.

    Future use

  • 8/3/2019 P2 Acton SIP

    19/32

    Future

    use

    Future use

    19

    Issue Our response

    The existing storm tanks.

    The two northernmost tanks would be decommissioned and filled in. This is because the

    main tunnel reception shaft would be located here.

    The four remaining tanks would be isolated and flows transferred to the main tunnel

    during CSO spills therefore reducing odours.

    Effect of permanent works

    on residential amenity.

    Since phase one consultation, the main tunnel site has been relocated to the northern

    end of the site, which is farthest from the majority of nearby residential properties.

    Visual effect of the

    permanent works.

    The ventilation building and structure are being designed to respect their existing

    industrial context and built form, with the possible use of brick and sloping roofs, andsetting the building back from Canham Road. We are considering adding interest to the

    design by revealing the ventilation equipment using a glass wall.

    The ventilation structure would accommodate all three ventilation stacks and is located

    west of the building to minimise its effect on its surroundings.

    Narrowness of public

    footpaths in Canham Road.

    It is proposed to widen the existing footpath on the south side of Canham Road

    to accommodate normal use and to offer better access to the nearby crche and

    residential areas.

    New site access.

    Two new vehicle accesses from Canham Road are proposed for access to the building

    and ventilation structure. The accesses would be set back from the existing road edge

    and link into the existing one way system. These accesses would be used infrequently

    for maintenance purposes only. The main site access would remain unchanged.

    Table 3.1: Site specific issues that have influenced our permanent design

    Acton Storm Tanks

  • 8/3/2019 P2 Acton SIP

    20/32

    Acton Storm Tanks

    20

    Figure 3A: Photo of the site before the works

    Figures 3A, 3B, 3C and 3D show the current site and

    provide illustrations of our design proposals. Further

    information on the development of our design can be

    found in the Design development report.

    Related documents:

    Design

    Future use

  • 8/3/2019 P2 Acton SIP

    21/32

    Future use

    21

    Figure 3B: Artists impression of the site after the works are completed

    Acton Storm Tanks

  • 8/3/2019 P2 Acton SIP

    22/32

    Acton Storm Tanks

    22

    Figure 3C: Aerial view of the completed works

    Future use

  • 8/3/2019 P2 Acton SIP

    23/32

    23

    Figure 3D: Layout of site once construction works complete

    Secondary accessfor maintenance of

    ventilation column

    Ventilation columnVentilationbuilding

    Existingfootpath tobe widened

    Northern two storm tanksfilled with excavated materialfrom shaft construction

    Building set backfrom boundary by

    approximately 5m

    New fencing tomatch existing

    Secondary accessfor maintenancevehicles

    New line ofboundaryfencing

    Replacement fencingto be provided

    Main access toActon Storm Tanks

    Canham

    Road

    N

    Grassedarea

    Hardstandingarea

    Area to bereinstated followingconstruction works

    Existingcar parking

    Modificationsto above groundchamber

    Remaining stormtanks to be takenout of use

    Acton Storm Tanks

  • 8/3/2019 P2 Acton SIP

    24/32

    Acton Storm Tanks

    24

    Operation and maintenanceOnce the tunnel is operational, we expect to undertake

    inspection and maintenance of the ventilation and below

    ground equipment approximately once every three to six

    months. This would be undertaken within our site and as

    part of the existing maintenance routine.

    Once every ten years, we expect to carry out a major

    internal inspection of the tunnel and underground

    structures. This is likely to involve a small team of

    inspection staff, a small team of support crew and two

    mobile cranes to lower the team and inspection vehicle

    into the shaft. This is likely to take several weeks, and

    would all be undertaken within our site.

    We may also need to make visits to the site for unplanned

    maintenance or repairs, for example, if there is a

    blockage, or equipment failure. This may require the use

    of mobile cranes and vans.

    Permanent vehicular access would be from the existing

    access gates in Warple Way, with only major maintenanceworks accessing the site from Canham Road.

    Management of operational effectsWe have undertaken technical work, including stakeholder

    engagement, to assess and identify the key issues

    associated with this site once it is operational. Table

    3.2 summarises these issues and how we are currently

    proposing to address them.

    Future use

  • 8/3/2019 P2 Acton SIP

    25/32

    25

    Issue Our response

    Possible odour effects

    during the operation of

    the tunnel.

    Odour effects at this site are expected to be negligible because we have developed anAir management plan to minimise possible odour and air quality effects arising from theoperation of the tunnel. The technology we are proposing to use at this site includes a

    mechanical ventilation system that draws air through the tunnel with fans before cleaning

    the air using carbon filters that will absorb possible odour before air leaves the ventilation

    equipment.

    As part of the proposed works, two of the existing storm tanks would be decommissioned

    and filled in. This would reduce existing odour problems. We are also proposing to isolate

    the remaining four tanks, so they would no longer be required. This would be achieved byconstructing new pipe work along the western perimeter of the site.

    Disturbance from future

    maintenance access.

    The permanent access to our site would remain unchanged and visits would be

    undertaken as part of the existing maintenance routine. As detailed in Table 3.1 two

    additional access points would be made available to ease access from Canham Road.

    Table 3.2: Key issues relating to site operation

    Related documents:

    Odour

    Further information

  • 8/3/2019 P2 Acton SIP

    26/32

    26

    u t e o at o

    This section sets out documents which may be of particular interest. Further information on our proposals can be

    found on our website (www.thamestunnelconsultation.co.uk) or is available upon request (call our customer centre

    on 0800 0721 086).

    Phase two public consultation material

    Project information papers include general information about the Thames Tunnel project. There are 17 project

    information papers, which cover various aspects of the project. Those project information papers that may be of

    particular interest are set out below.

    Icon Title Details

    Build

    Provides information on the different types of sites required for the Thames Tunnel

    project and the typical construction activities that will be undertaken at each site.

    Changes

    Explains how the scheme has changed compared to that presented at phase one

    consultation, including changes to the tunnelling strategy for the main tunnel and

    changes to sites.

    Q&A Consultation

    Sets out the consultation we have undertaken to date on the project, the scope

    of this phase two consultation and how interested parties can respond to thisconsultation.

    DesignContains the design principles which have influenced the permanent appearance of

    our sites once construction work is complete.

    EnvironmentSets out the process the project is following to assess potential environmental effects

    of the Thames Tunnel project.

    Managing

    construction

    Includes information on what measures our contractors will put in place at our sites

    during construction.

    Odour Sets out ourAir management plan and how it will work.

    Options Outlines the various ways to deal with sewage overflows.

  • 8/3/2019 P2 Acton SIP

    27/32

    27

    Phase two public consultation material

    Icon Title Details

    OverflowSets out how Londons sewerage system works and why the capital has an overflow

    problem.

    Route and

    tunnel

    alignment

    Sets out the preferred route of the main tunnel and the reasons for our preference.

    Site selection Sets out the process we followed to find and select our preferred sites.

    Transport Contains information on the different transport options we have considered fordelivering and removing materials from our sites.

    Site information papers provide information that relate to each preferred site along the route of the Thames Tunnel

    project. The following site information papers may be of particular interest.

    Carnwath Road Riverside

    Hammersmith Pumping StationHPS

    CRR

    Further information

  • 8/3/2019 P2 Acton SIP

    28/32

    28

    Technical reports

    Theme Icon Title Details

    Interim

    engagement

    Interim engagement

    report

    Provides a summary of the public engagement we

    have undertaken between phase one and phase two

    consultations.

    Phase one

    consultation1

    SUMMARY

    Report on phase one

    consultation:

    summary report

    Provides a summary of the comments made at phase one

    consultation and our responses.

    Phase two

    construction

    information

    Code of construction

    practice Part A:

    General requirements

    (CoCP)

    Sets out control measures to be adopted during the project

    construction period.

    Phase twoenvironmental

    information

    Air management

    plan

    Outlines the methods which we will use to manage odour

    from the main tunnel at all our preferred sites.

    Preliminary

    environmental

    information report

    (PEIR)

    Contains initial assessments on the environmental effects of

    the Thames Tunnel project based on information collected to

    date. Please refer to volume 7 of the non-technical summary

    and volume 7 of the PEIR for more information on this site.

    Phase two schemedevelopment

    Design development

    report

    Provides a general overview of how the scheme design at

    each site has evolved to date. Please refer to chapter 4 for

    more information on this site.

    2

    Phase two scheme

    development report

    Provides an overview of the development of the Thames

    Tunnel project and how each site was chosen. Please refer to

    Appendix A for more information on this site.

    Site glossary

  • 8/3/2019 P2 Acton SIP

    29/32

    29

    g y

    Term Definition

    Carbon filters Filters that remove odours before the air is released from the tunnel.

    Combined sewer A single sewer system that takes both rainwater and domestic and industrial wastewater.

    Combined sewer

    overflow (CSO)

    A structure, or series of structures, that allows sewers to overflow into the river when they

    are full as a result of increased rainfall. Without the overflows, the sewers would back up

    and cause flooding in streets or houses.

    Connection tunnel A tunnel connecting a drop shaft to the main tunnel.

    Draft limit of land to be

    acquired or used

    The extent of land that we may need to use or acquire, or over which rights may be needed

    to carry out works that are essential to the project.

    Drop shaft

    A vertical circular concrete structure, used to drop flows from the high level of the CSO to

    the low level of the main tunnel. It would also be used to provide access to construct the

    connection tunnels.

    Interception chamberA structure, built on an existing combined sewer, which diverts stormwater overflow into the

    main tunnel.

    Main tunnel/connection

    tunnel drive site

    A site that would be used to construct the main tunnel or connection tunnel. The excavated

    material would be removed from the tunnel and the concrete tunnel lining segments wouldbe delivered to the tunnel at the main/connection tunnel drive site.

    Main tunnel/connection

    tunnel reception site

    The tunnel would be constructed from a drive site to a reception site. Once the tunnel

    arrives at the reception site, the tunnel boring machine would be dismantled and removed.

    Main tunnel The tunnel from Acton Storm Tanks to Abbey Mills Pumping Station.

    Operational phase After the completion of the construction work, when the main tunnel is in use.

    Secondary lining A second, internal lining to the tunnel, giving it additional strength.

    Thames Tunnel project

    The Thames Tunnel project comprises a storage and transfer tunnel, from west London to

    Beckton Sewage Treatment Works in east London, and the control of 34 CSOs along the

    Thames Tideway.

    Transport for London

    Road Network (TLRN)

    The network of roads managed by Transport for London. These are the major or strategic

    roads, which have high capacity.

    Tunnel boring machine

    (TBM)

    A machine used to excavate tunnels through a variety of conditions, with a circular

    cross-section.

  • 8/3/2019 P2 Acton SIP

    30/32

  • 8/3/2019 P2 Acton SIP

    31/32

    Acton Storm Tanks

  • 8/3/2019 P2 Acton SIP

    32/32

    32

    Phase two consultation: Acton Storm Tanks

    For further information or to comment on our

    proposals see our website:

    www.thamestunnelconsultation.co.uk

    110-ED-PNC-00000-000068

    Autumn 2011

    It is very important that you understand theinformation we have provided. If you needfurther information in another language,

    braille, large print or audio format pleasecontact us on 0800 0721 086.