Owner's Engineer

54
1 1 Farid M. Berry Vice President & Project Director Sargent & Lundy LLC June 25, 2013 Role of the OWNER’S ENGINEER in Technology Assessment, Licensing, Engineering and Construction Technical Meeting on Technology Assessment for Embarking Countries IAEA Headquarters, Vienna, Austria

Transcript of Owner's Engineer

Page 1: Owner's Engineer

11

Farid M. BerryVice President & Project Director

Sargent & Lundy LLCJune 25, 2013

Role of the OWNER’S ENGINEER in Technology Assessment, Licensing, Engineering and Construction

Technical Meeting on Technology Assessment for Embarking Countries IAEA Headquarters, Vienna, Austria

Page 2: Owner's Engineer

22

• Sargent & Lundy

• Owner’s Engineer

– Owners Engineer Roles/Tasks

» Technology Assessment

» Licensing

» Engineering & construction

• Commercial Technical Specification

• Division of Responsibilities (DOR)

• Quality Assurance/Oversight

• Integrated Project Schedule

• Training

• Why Owner’s Engineer?

• Selecting an Owners Engineer

• Summary

Page 3: Owner's Engineer

33

• 122 years of leading global power industry experience

• Headquartered in Chicago, USA

• Exclusive focus on power industry

• Nuclear Quality Assurance Program

– Topical Report which has been reviewed and accepted by the USNRC.

• ISO 9001:2008 Certified Quality System

• 2,600+ staff members

• Ranked in top 5 AE’s Globally in Power by Engineering News-Record.

ProfileProfile

Page 4: Owner's Engineer

44

• Over 600 clients– 150 fossil power clients– 120 nuclear power clients– 40 power delivery service clients– 340 consulting clients

Client BaseClient Base

Page 5: Owner's Engineer

55

Areas of Expertise Include:Areas of Expertise Include:-- Project Concept Development

-- Preliminary Financial Evaluation/Capital Cost Estimating-- Site Selection, Feasibility studies

-- Transmission Impact Studies-- Environmental Evaluation

-- Licensing, Permitting, and Document Preparation-- Detailed Design/EPC Implementation

-- Procurement/Quality Control -- Construction Management

-- Preparation and System Startup Testing-- Operations & Maintenance Consulting

Page 6: Owner's Engineer

66

OwnerOwner’’s Engineers Engineer

Owner's Engineer is a term given to an independent Owner's Engineer is a term given to an independent party representative of the party representative of the OWNEROWNER of a of a constructionconstructionor or engineeringengineering project. project.

Page 7: Owner's Engineer

77

New Nuclear Plant TimelineNew Nuclear Plant TimelineGreenfield SiteGreenfield Site

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8

Feasibility Studies/ Technology Assessment

Select EPC/Technology Contractor

Construction License Issued

Fuel Load

COD

Reactor, Simulator order

Year 9 Year 10

EPC Negotiations LWA Granted

EPC Site Mobilization

Preliminary Rx Technology Selection

Final Site Selection

Licensing

Startup &

Testing

Construction

Page 8: Owner's Engineer

88

OwnerOwner’’s Engineer Roles/Taskss Engineer Roles/Tasks• Site Selection• Technology Assessment/Selection• Licensing support• Engineering, Procurement, Construction (EPC) Commercial

Technical Specification and Bid Assistance• Division Of Responsibilities (DOR)• Contract negotiations support• Develop overall project execution plan • Develop an integrated master project schedule• Identify and quantify project risks and develop a risk mitigation

plan

Page 9: Owner's Engineer

99

OwnerOwner’’s Engineer Roles/Taskss Engineer Roles/Tasks(cont.)(cont.)

• Develop design for site specific activities and owners assigned activities• Develop & update project cost estimate

• EPC experience• Maturity of Design

• Shield building design to meet aircraft impact resulted in cost increase of $900Millions

• Regulatory Environment• Procurement

• Review EPC contractor’s procedures and related documents• Perform audits on behalf of the Owner• Represent Owner in EPC contractor’s procurement activities

Page 10: Owner's Engineer

1010

OwnerOwner’’s Engineer Roles/Taskss Engineer Roles/Tasks(cont.)(cont.)

• Perform design reviews on behalf of the Owner of vendor documents (e.g., drawings, calculations, specifications, constructor/vendor document submittals, etc…)

• Support Owner with reviewing EPC contractor costs, schedule, and progress

• Support the owner with plant testing and startup• Provide construction support: oversight, engineering, licensing,

procurement and commissioning. • Support design activities/interface with operating units• Independent engineer evaluation• Training • Miscellaneous support (Deployment, etc…)

Page 11: Owner's Engineer

1111

Technology AssessmentTechnology Assessment

Page 12: Owner's Engineer

1212

Technology AssessmentTechnology Assessment• Suitability for available sites• Amount of power needed • Reliability / Availability• Costs

– Capital– O&M

• Risks associated with each technology– Technical (First-of-Kind issues)

» Passive vs, active– Licensing– Schedule

Page 13: Owner's Engineer

1313

Technology Assessment (continued)Technology Assessment (continued)• No reliance on AC power for safety systems• Reduced reliance on operator actions• Large margin to safety limits

• Fewer Active components - less capital / O&M Costs• Modular construction

• Better predictability of cost and schedule• Etc…

Page 14: Owner's Engineer

1414

LicensingLicensing

Page 15: Owner's Engineer

1515

LicensingLicensing• IAEA General Guidance for the Licensing Process

– Pre-Construction SAR (PCSAR)– Pre-Operation SAR (POSAR)– Station SAR (SSAR)

• US NRC (10 CFR 50 and 52)– 10 CFR 52- Single process

» Early Site Permit (ESP)• Approval to secure one or more sites for future use

» Combined Construction and Operating License (COL)• ITAAC unchartered

– 10 CFR 50- Two step process» Separate construction and operating license

• OE support: License application, RAI’s, Analysis, etc…

Page 16: Owner's Engineer

1616

EPC Commercial Technical SpecificationEPC Commercial Technical Specification

Page 17: Owner's Engineer

1717

EPC Commercial Technical Specification EPC Commercial Technical Specification Requirements OverviewRequirements Overview

• Relationship to EPC Contract

– Will be a Supplement to EPC contract

– Includes technical requirements

» Owners requirements

» Country local and regional requirements

» Industry Lessons Learned

» Regulatory requirements

Page 18: Owner's Engineer

1818

• Goal = Issue Commercial Technical Specification that delivers a State of the Art Plant to the owner

– Emphasis on nuclear industry Lessons Learned to date

» 60 year design life

» Industry requirements (EUR/URD)

» Specific operating experience

» INPO/WANO operating experience

» S&L design experience

– Augment the Proven Technology (DCD)

– Specify critical design and procurement requirements

EPC Commercial Technical Specification EPC Commercial Technical Specification Requirements Overview (ContRequirements Overview (Cont’’d)d)

Page 19: Owner's Engineer

1919

– Adds value relative to requirements affecting:» Plant operations

» Reliability

» Availability

» Maintenance

» ISI/IST

» ALARA

» Design philosophy

» Design margin

» Construction and transition from construction to operation

» Outage optimization

EPC Commercial Technical Specification EPC Commercial Technical Specification Requirements Overview (ContRequirements Overview (Cont’’d)d)

Page 20: Owner's Engineer

2020

• EPC Commercial Technical Specification Structure– Parallels US NRC NUREG-0800 (Standard Review Plans)– Additional sections added for:

» Regulatory (Country specific)» Cooling Media» Site Infrastructure - Barge Facility, Haul Road, etc…» Initial Site Development» Final Site Development » Fukushima Impact/Requirements» Misc. Sections

EPC Commercial Technical Specification EPC Commercial Technical Specification Requirements Overview (ContRequirements Overview (Cont’’d)d)

Page 21: Owner's Engineer

2121

Design Departures

EPC CommercialTechnical

Specification

EPC CommercialEPC CommercialTechnical Technical

SpecificationSpecification

Lessons Learned from the 1970s and

1980s on LWRs

Industry Codes, Standards, Regulatory

Industry Experience, EUR,

URD, EPRI, WANO, INPO,

etc..

S&L Nuclear New Build Design, etc.

Project Specific Details

Technology Design

Licensing Requirements,

Local and Regional

Requirements

QA/QC Requirements

Inputs to EPC Commercial Technical SpecificationInputs to EPC Commercial Technical SpecificationOperating

Experience

Page 22: Owner's Engineer

2222

CONTENTS of the

EPC Commercial Technical Specification

Requirements

Technical Requirements (ContTechnical Requirements (Cont’’d)d)

Page 23: Owner's Engineer

2323

1. General Plant Description and Design Philosophy2. Site Characteristics 3. Design of Systems, Structures, and Components4. Reactor5. Reactor Coolant System and Connected Systems6. Engineered Safety Features7. Instrumentation and Controls8. Electrical Systems and Equipment9. Auxiliary Systems10. Steam and Power Conversion

Technical Requirements (ContTechnical Requirements (Cont’’d)d)

Page 24: Owner's Engineer

2424

11. General Radwaste Protection

12. Radiation Protection

13. Conduct of Operations

14. Initial Test Program

15. Accident Analysis

16. Technical Specification

17. Quality Assurance

18. Human Factors Engineering

Technical Requirements (ContTechnical Requirements (Cont’’d)d)

Page 25: Owner's Engineer

2525

19. Severe Accidents

20. Cooling media and Related Facilities

21. Site Infrastructure- Barge Facility, Haul Road, etc…

22. Initial Site Development

23. Final Site Development

24. Unit 1 Transition from Construction to Operation

25. Items Critical to Quality

Technical Requirements (ContTechnical Requirements (Cont’’d)d)

Page 26: Owner's Engineer

2626

26. Construction Oversight, Construction Optimization Including Construction Command Center

27. Procurement Plan, Requirements and Oversight

28. Risk Analysis and Mitigation

29. Fukushima Impact/Requirements– Hazards (Flooding and Seismic)

– Mitigating Strategies for Beyond Design Basis Events

– Etc…

30. Training and Training Facilities

Technical Requirements (ContTechnical Requirements (Cont’’d)d)

Page 27: Owner's Engineer

2727

Division of ResponsibilitiesDivision of Responsibilities

Page 28: Owner's Engineer

2828

DORDOR Site Infrastructure

Power Block

Licensing

Permitting

Security

Etc…

Page 29: Owner's Engineer

2929

Quality Assurance/Vendor OversightQuality Assurance/Vendor Oversight

Page 30: Owner's Engineer

3030

Quality Assurance/ Vendor OversightQuality Assurance/ Vendor Oversight Quality Assurance/Quality Control

– Develop and Implement QA/QC Program for an independent assessment of the effectiveness of programs and processes related to design, procurement, construction, maintenance and operationactivities, as well as the effectiveness of human performance inimplementing program and process requirements

– Objective:

» Ensure that the programs and processes deliver high quality project work. This should account for safety culture, including the establishment of a safety-conscious work environment, QA, industrial safety, radiological safety and problem identification and resolution

Page 31: Owner's Engineer

3131

Quality Assurance/ Vendor OversightQuality Assurance/ Vendor Oversight Quality Assurance/Quality Control Approach

– QA/QC is integrated in design, construction and procurement

– Utilize Commercial Grade Dedication requirements

» Technical requirements

» Quality requirements

» Acceptance Method

– Verify each level of the procurement chain - audit suppliers often

– Establish an inspection frequency and scope

– Emphasize QA and technical requirements through performance-based inspections

Page 32: Owner's Engineer

3232

Quality Assurance/ Vendor OversightQuality Assurance/ Vendor Oversight

Quality Assurance/Quality Control Approach (continued)– Assess effective implementation of manufacturing and fabrication

processes to provide assurance of product quality

– Establish and maintain document control and records management systems early

– Establish a corrective action program

– Emphasize root cause analysis and/or extent of condition as required to ensure that any proposed corrective action addressesthe underlying QA performance drivers

Page 33: Owner's Engineer

3333

Quality Assurance/ Vendor OversightQuality Assurance/ Vendor Oversight Quality Assurance/Quality Control Approach (continued)

– Inspection and test process verifies that the completed project meets specified design basis attributes, including performance features and characteristic

– Historical records of calibrations, audits, testing, maintenance, certifications, etc… need to be maintained as part of the permanent plant records

– Ensure installed material/components meet intended function and operability requirements

– Oversight and inspections of suppliers’ facilities

Page 34: Owner's Engineer

3434

Quality Assurance/ Vendor OversightQuality Assurance/ Vendor Oversight Quality Assurance/Quality Control Approach (continued)

– Counterfeit material can compromise safety related components/systems/structures

» Establish a process to quickly identify counterfeit material• Qualified suppliers

• Oversight and inspections of supplier facilities

• Proper material documentation and traceability

• Material that cannot be traced back to the original source should be considered suspect

• Corrective action program

Page 35: Owner's Engineer

3535

Prevention, Detection, CorrectionPrevention, Detection, CorrectionPROCUREMENT PROCESSEARLY LATER

PREVENT DETECT CORRECT

Page 36: Owner's Engineer

3636

Manufacturing OversightManufacturing Oversight• Develop a Manufacturing Quality Oversight Plan for successful

overview of equipment and component fabrication

Page 37: Owner's Engineer

3737

Manufacturing OversightManufacturing Oversight-- Shop OverviewShop Overview• Field Observation- Example: Transition shell forging

– Normalizing and tempering witness point implemented and signed as acceptable

– Documentation for steel melt, heat analysis, and forging are reviewed and confirm compliance with SA-508 material spec and shop work control documents

– Inspect Shop Quality Process from a technical and programmatic standpoint

Page 38: Owner's Engineer

3838

Manufacturing Oversight Manufacturing Oversight -- Witness Point Trip Witness Point Trip ObservationsObservations

• Equipment calibration documentation acceptable?

• Work control documentation maintained current?

• Procedure requirements correctly reflected in work control documents?

• Heat analysis documents material specification compliance?

• Shop quality control reviews completed as required?

• Impact of risks that can occur during the test:

– Example, Seismic event-Had no effect on operations but no procedure in place to mitigate

Page 39: Owner's Engineer

3939

Integrated Project ScheduleIntegrated Project Schedule

Page 40: Owner's Engineer

4040

Master BaselineSchedule

ProjectSchedule

SubprojectTrainingSchedule

OE Activities Schedule

Start-upDesignSchedule

ProcurementSchedule

SubprojectOwner

Schedule

ConstSchedule

18 MonthPre-ConstSchedule

Owners ActivitiesSchedule

DevelopTraining Program

ImplementTraining

TestingSchedule

Page 41: Owner's Engineer

4141

Level I: Project Summary ScheduleLevel I: Project Summary Schedule

Level III: Publication / Control Level ScheduleLevel III: Publication / Control Level Schedule

Level IV: Supporting DetailsLevel IV: Supporting DetailsSchedule fragments or Schedule fragments or Deliverable listings, quantityDeliverable listings, quantitydata, etc..data, etc..

Level II: Management SummaryLevel II: Management Summary

Level 0: Project Milestone SummaryLevel 0: Project Milestone Summary

Page 42: Owner's Engineer

4242

Integrated Project ScheduleIntegrated Project Schedule--Output Output (Continued)(Continued)

– Around the clock critical path/near critical path to optimize the schedule

» Critical path

» Near critical path

– Parallel activities and resource management

» Parallel paths with manpower and equipment

» Use the largest of the large equipment/modules to optimize tasks

– Contingency planning

Page 43: Owner's Engineer

4343

Training Activities/PlansTraining Activities/Plans

Page 44: Owner's Engineer

4444

Training Activities/PlansTraining Activities/Plans• Training Planning Activities

1. Training Plans » QA» Construction» Technical» Security» Operation» Etc…

2. Training Material Development» Systems, Maintenance, Construction, Radiation Protection,

Engineering, etc…3. Training Implementation

Page 45: Owner's Engineer

4545

Why OwnerWhy Owner’’s Engineer?s Engineer?

Page 46: Owner's Engineer

4646

Why OwnerWhy Owner’’s Engineer?s Engineer?

• Owner’s engineer support the owner in a successful planning, oversight, execution and implementation of the project from inception through commissioning.

• Owner’s engineer reduce overall project risk for the owner.

• Owner’s engineer ensures deliverables are in-line with owner’s expectations.

• Owner’s engineer can reduce a project’s overall project cost(capital, operation and maintenance)

• Savings through control of project schedule, defined scope and management, and overall project controls.

• Design optimization that reduce the owner’s lifecycle costs.

Page 47: Owner's Engineer

4747

Why OwnerWhy Owner’’s Engineer?s Engineer?• Owner’s engineer, brought in when project still in

conceptual stage, can help with defining the project size, location, technology selection, configuration, scope, interfaces, and schedule.

• Owner’s engineer, involved from project inception can help, develop a project execution plan and contracting strategy. Owner benefits from having a dedicated engineering advisor who is familiar with all aspects of the project and will help the owner identify opportunities that may otherwise be overlooked while avoiding or minimizing risks.

Page 48: Owner's Engineer

4848

Why OwnerWhy Owner’’s Engineer?s Engineer?

• Some of the activities that an owner’s engineer can provide include:

» Defining and/or reviewing the project scope.

» Developing a detailed DOR.

» Developing project design criteria.

» Assessing and evaluating the budget.

» Conducting feasibility and site selection studies and alternatives analysis.

» Analyzing available technologies and their suitability to the project and owner’s NPP goals.

Page 49: Owner's Engineer

4949

Why OwnerWhy Owner’’s Engineer?s Engineer?

» Preparing integrated project schedules.

» Preparing technical commercial specifications.

» Support with the licensing process, permitting and environmental processes

» Support with EPC contract documents, including RFP (request for proposal) and evaluations.

» Provide detailed design, overall project management, contract administration, and construction oversight.

Page 50: Owner's Engineer

5050

Why OwnerWhy Owner’’s Engineer?s Engineer?» Preparation and/or review of equipment procurement

specifications and ensure suppliers are in compliance with all contract requirements.

» Support development of configuration management control that captures the plant design basis.

» Support owner’s process management, implementation of earned value, project cost reporting and trending.

» Develop of the training program and capacity building

» Support plant commissioning process (system turnover, start-up tests, punch lists, performance testing, etc…).

Page 51: Owner's Engineer

5151

Selecting an OwnerSelecting an Owner’’s Engineer?s Engineer?• Prior experience:

» Design (NI, TI and BOP)» Licensing» Procurement» Quality » NSSS experience» Operation» Oversight» Project Management

Page 52: Owner's Engineer

5252

SummarySummary Strategies for SUCCESS

» GET INVOLVED

» Qualified Owners Engineer

» EPC commercial technical specification

» Integrated DOR

» Integrated project schedule/plan

Page 53: Owner's Engineer

5353

Summary (continued)Summary (continued) Planning through operationDevelop and Monitor an integrated plan that captures information and data for:

» Planning (Site selection, technology selection, Material reservation, etc…)

» Design (Systems, foundations, structures, component/Material specification, etc…)

» Procurement (Technical specifications, Material selection and management, etc…)

» Construction (Construction execution, oversight, Material availability, etc…)

• June 18, 2013- China “Cable was not available, they used bigger size (stronger)”

» Start-up (Training, testing, Material replacement/repair, fuel load, etc…)

» Operation (Maintenance & Material management, outages, etc…)

Page 54: Owner's Engineer

5454

Thank You