Overview Webinar - PMI Montgomery County Maryland€¢ Kavya Gupta, PMP • Oliver Yarbrough, PMP...
Transcript of Overview Webinar - PMI Montgomery County Maryland€¢ Kavya Gupta, PMP • Oliver Yarbrough, PMP...
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Overview WebinarV6.0
1
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
• Asad Naveed, PMP, RMP, MEF-CECP• Erjola Mimani, PMP, PSM 1• Greta Blash, PMP, PMI-ACP, PMI-PBA, CSM• Jason Saetrum, PMP, ASQ CSSBB, IASSC ATA, MCP, Project + Certified• Kavya Gupta, PMP• Oliver Yarbrough, PMP• Samuel Odemo, B. Tech, PMP• Steve Blash, MA, PMP, PMI-ACP• Varun Anand, PMP, CSM
• Joseph D. Launi, PMP, Project +
2
Authors of:
What is New in the PMBOK®
Guide 6th Edition –An In-Depth Comparison
Unauthorized Use of this Material is Strictly Prohibited
Author of:What is New in the PMBOK® Guide 6th Edition –
An In-Depth ComparisonSlide Deck
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Agenda1. Introduction
2. Environment in Which Projects Operate
3. Role of the Project Manager
Knowledge Areas Overviews
4. Project Integration Management
5. Project Scope Management
6. Project schedule Management
7. Project Cost Management
8. Project Quality Management
9. Project Human Resources Management
10. Project Communications Management
11. Project Risk Management
12. Project Procurement Management
13. Project Stakeholder Management
3
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Joseph D. Launi, PMP
• 30+ years in project management
• 15 years in project management training and consulting
• Project Management Professional (PMP)® Certification
• Specializing in project management office development and training
PMP is a registered mark of the Project Management Institute 4
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Project Life Cycle
5, Figure 1-5, Pg. 18
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017 6
KNOWLEDGE
AREA
PROCESS GROUPS
INITIATING PLANNING EXECUTING MONITORING &
CONTROLLING
CLOSING
4. Project Integration
Management
4.1 Develop Project charter 4.2 Develop Project management plan 4.3 Direct and Manage Project
Work
4.4 Manage Project Knowledge
4.5 Monitor and Control Project
Work
4.6 Perform Integrated Change
Control
4.7 Close Project or
Phase
5. Project Scope Management 5.1 Plan Scope Mgt.
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project Schedule
Management
6.1 Plan schedule Mgt.
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop schedule
6.7 Control schedule
7. Project Cost Management 7.1 Plan Cost Mgt.
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8. Project Quality
Management
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9. Project Resource
Management
9.1 Plan Resource Mgt.
9.2 Estimate Activity Resources
9.3 Acquire Resources
9.3 Develop Team
9.4 Manage Team
9.6 Control Resources
10. Project Communications
Management
10.1 Plan Communications Mgt. 10.2 Manage Communications 10.3 Monitor Communications
11. Project Risk Management 11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk analysis
11.4 Perform Quantitative Risk analysis
11.5 Plan Risk Responses
11.6 Implement Risk Responses 11.7 Monitor Risks
12. Project Procurement
Management
12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
13. Project Stakeholder Mgt. 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder
Engagement
13.4 Monitor Stakeholder
Engagement
Project Management Process Groups and Knowledge Areas
, Table 1-4, Pg. 25
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017 7
Knowledge Areas PMBOK® 5th Edition PMBOK® 6th Edition
4. Project Integration Management
4.1 Develop Project charter 4.1 Develop Project charter
13. Project Stakeholder Management
13.1 Identify Stakeholders 13.1 Identify Stakeholders
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017 8
Knowledge Areas PMBOK® 5th Edition PMBOK® 6th Edition
4. Project Integration Management
4.1 Develop Project management plan
4.1 Develop Project management plan
5. Project Scope Management 5.1 Plan Scope Management5.2 Collect Requirements5.3 Define Scope5.4 Create WBS
5.1 Plan Scope Management5.2 Collect Requirements5.3 Define Scope5.4 Create WBS
6. Project Time Management (5th Edition)
6. Project schedule Management (6th Edition)
6.1 Plan schedule Management6.2 Define Activities6.3 Sequence Activities6.4 Estimate Activity Resources6.5 Estimate Activity Durations6.6 Develop schedule
6.1 Plan schedule Management6.2 Define Activities6.3 Sequence Activities<Estimate Activity Durations moved to HR>
6.4 Estimate Activity Durations6.5 Develop schedule
7. Project Cost Management 7.1 Plan Cost Management7.2 Estimate Costs7.3 Determine Budget
7.1 Plan Cost Management7.2 Estimate Costs7.3 Determine Budget
8. Project Quality Management 8.1 Plan Quality Management 8.1 Plan Quality Management
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017 9
Knowledge Areas PMBOK® 5th Edition PMBOK® 6th Edition
9. Project HR Management (5th
Edition)9. Project Resource Management (6th Edition)
9.1 Plan Human Resources Management
9.1 Plan Resource Management9.2 Estimate Activity Resources
10. Project Communications Management
10.1 Plan Communications Management
10.1 Plan Communications Management
11. Project Risk Management 11.1 Plan Risk Management11.2 Identify Risks11.3 Perform Qualitative Risk Anal.11.4 Perform Quantitative Risk Anal.11.5 Plan Risk Responses
11.1 Plan Risk Management11.2 Identify Risks11.3 Perform Qualitative Risk Anal.11.4 Perform Quantitative Risk Anal.11.5 Plan Risk Responses
12. Project Procurement Management
12. 1 Plan Procurement Management 12. 1 Plan Procurement Management
13. Project Stakeholder Management
13.2 Plan Stakeholder Management 13.2 Plan Stakeholder Engagement
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017 10
Knowledge Areas PMBOK® 5th Edition PMBOK® 6th Edition
4. Project Integration Management
4.3 Direct and Manage Project Work 4.3 Direct and Manage Project Work4.4 Manage Project Knowledge
8. Project Quality Management 8.2 Perform Quality Assurance 8.2 Manage Quality
9. Project HR Management (5th
Edition9. Project Resource Management (6th Edition)
9.2 Acquire Project Team9.3 Develop Project Team9.4 Manage Project Team
9.3 Acquire Resources9.4 Develop Team9.5 Manage Team
10. Project Communications Management
10.2 Manage Communications 10.2 Manage Communications
11. Project Risk Management 11.6 Implement Risk Responses
12. Project Procurement Management
12.2 Conduct Procurements 12.2 Conduct Procurements
13. Project Stakeholder Management
13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017 11
Knowledge Areas PMBOK® 5th Edition PMBOK® 6th Edition
4. Project Integration Management
4.4 Monitor and Control Project Work4.5 Perform Integrated Change Control
4.5 Monitor and Control Project Work4.6 Perform Integrated Change Control
5. Project Scope Management 5.5 Validate Scope5.6 Control Scope
5.5 Validate Scope5.6 Control Scope
6. Project Time Management (5th Edition)6. Project schedule Management (6th Edition)
6.7 Control schedule 6.6. Control schedule
7. Project Cost Management 7.4 Control Costs 7.4 Control Costs
8. Project Quality Management 8.3 Control Quality 8.3 Control Quality
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017 12
Knowledge Areas PMBOK® 5th Edition PMBOK® 6th Edition
9. Project HR Management (5th
Edition9. Project Resource Management (6th Edition)
9.6 Control Resources
10. Project Communications Management
10.3 Control Communications Management
10.3 Monitor Communications
11. Project Risk Management 11.6 Control Risks 11.7 Monitor Risks
12. Project Procurement Management
12. 3 Control Procurements 12.3 Control Procurements
13. Project Stakeholder Management
13.4 Control Stakeholder Engagement
13.4 Monitor Stakeholder Engagement
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017 13
Knowledge Areas PMBOK® 5th Edition PMBOK® 6th Edition
4. Project Integration Management
4.6 Close Project or Phase 4.7 Close Project or Phase
12. Project Procurement Management
12.4 Close Procurements
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Trends and Emerging PracticesThe PMBOK® is considered a “good practice”. Some of the new information on “other ways” to manage are included in the introductory portions of each Process Groups and Knowledge Areas.
14
• Methodology: system of practices, techniques, procedures, and rules used by those who work in a discipline. The PMBOK® is not a methodology but a guide.
• Tailoring allows for consideration of the unique nature of projects.
• Tailoring allows for the PMBOK® to be used as a guide to address competing constraints of scope, schedule, cost, resources, quality and risk.
Tailoring
Taken from: "What is New in the PMBOK Guide® 6th Edition - An In-Depth
Comparison," Pg. 8
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Considerations for Agile/Adaptive Environment
The use of various aspects of agile, iterative and adaptive approaches for projects is increasing. This includes development methods, techniques, outputs and other activities and practices. Some agile terminology and techniques have been integrated into specific PMBOK® Guide processes. This section provides specific approaches that are associated with various agile environments to help practitioners recognize and integrate these practices into their projects where it makes sense to do so.
15Taken from: "What is New in the PMBOK Guide® 6th Edition - An In-Depth
Comparison," Pg. 8
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Process Categories
16Taken from: "What is New in the PMBOK Guide® 6th Edition - An In-Depth
Comparison," Pg. 8
Lessons Learned
Each process has been categorized by of three descriptions:
• Processes used once or at predefined point in the project• Processes that are done periodically as needed• Processes that are done continuously throughout the project
“Manage Project Knowledge” is a new process to reflect the importance of how knowledge and information is shared.
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Tools and Techniques
17Taken from: "What is New in the PMBOK Guide® 6th Edition - An In-
Depth Comparison," Pg. 9
To support the importance of project tailoring, many tools and techniques are grouped together based on their purpose. The groups include:
• Data gathering• Data analysis• Decision making• Communications• Interpersonal and team skills• Communication skills
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Project Business Documents and Pre-Project Work
18, Pg. 30
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Project Success Measures
19, Pg. 34-35
• Completing the project benefits management plan;• Meeting agreed upon financial measures (Net Present Value, Return on Investment,
Internal Rate of Return, Payback Period, and Benefit Cost Ratio);• Meeting business case nonfinancial measures;• Completing movement of an organization from current to future state;• Fulfilling contract terms and conditions;• Meeting organizational strategy, goals, and objectives;• Achieving stakeholder satisfaction;• Acceptable customer/end-user adoption;• Integration of deliverables into the organization’s operating environment;• Achieving agreed-upon quality of delivery;• Meeting governance criteria; and• Achieving other agreed-upon success measures or criteria (e.g., process throughput).
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Project Business documents
20, Pg. 29
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017 21
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Project Influences
22, Pg. 48
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Influences of Organizational Structures on Projects
23, Pg. 47
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017 24
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Definition of a Project Manager
25, Pg. 52
Project manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Project Manager’s Sphere of Influence
26, Pg. 53
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Project Manager Competences
27, Pg. 56-57
Other Qualities and Skills of a Leader
• Dealing with people• Visionary• Optimistic• Collaborative• Managing relationships and conflict• Communicating effectively• Respectful• Honest• Life-long learner
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Leadership v. Management
28
• Managing: directing another person to get from one point to another using a now set of expected behaviors.
• Leadership: working with others through discussion or debate in order to guide them from one point to another.
Taken from: "What is New in the PMBOK Guide® 6th Edition - An In-Depth
Comparison," Pg. 30
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017
Leadership Styles
29, Pg. 65-66
• Laissez-faire• Transactional• Servant Leader• Transformational• Charismatic• Interactional
Taken from: "What is New in the PMBOK Guide® 6th Edition - An In-Depth
Comparison," Pg. 30-31
Personality
• Authentic• Courteous• Creative• Cultural• Emotional
• Intellectual• Managerial• Political• Service Oriented• Social• Systematic
Taken from A Guide to the Project Management Body of Knowledge,
(PMBOK Guide) – Sixth Edition, 2017 30
Contact Us for More Information!We offer a full PMBOK 6th Edition Overview Saturday Mornings as well as other project management courses to help you meet your Talent Triangle
requirements.