Overview of presentation · Alexander Sinske, CTO GLS Consulting [email protected] Overview of...
Transcript of Overview of presentation · Alexander Sinske, CTO GLS Consulting [email protected] Overview of...
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 1
Alexander Sinske, CTO GLS [email protected]
Overview of presentationOverview of presentation
Investment planning: Water pipesPrinciples & DefinitionLikelihood of FailureConsequence of FailureRoll-up of resultsCase Study: Overstrand MunicipalityAsset management alignmentLong term investment planningConclusion
Investment planning: Water pipesPrinciples & DefinitionLikelihood of FailureConsequence of FailureRoll-up of resultsCase Study: Overstrand MunicipalityAsset management alignmentLong term investment planningConclusion
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 2
Investment planning: Water pipesInvestment planning: Water pipes
Input- CAPEX- Development planning- Planned replacement and upgrades- Condition assessment
Output- Failure incidents- OPEX- Interruption: Duration x No of consumers = SID - (Service Interruption Delay)- Water loss
Input- CAPEX- Development planning- Planned replacement and upgrades- Condition assessment
Output- Failure incidents- OPEX- Interruption: Duration x No of consumers = SID - (Service Interruption Delay)- Water loss
PrinciplesPrinciples
Pipe replacement prioritization (PRP)Probability of Failure (PF)Consequence (C)PF x C = RISK (in monetary terms)Intervention: Replacement / Refurbishment reduces- Risk- OPEX- SID- Water loss
Pipe replacement prioritization (PRP)Probability of Failure (PF)Consequence (C)PF x C = RISK (in monetary terms)Intervention: Replacement / Refurbishment reduces- Risk- OPEX- SID- Water loss
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 3
PRP: DefinitionPRP: Definition
�������= � ��� � ������
���
�������= � ��� � ������
���
���= ���������������
PRP: Likelihood of failure (LF)PRP: Likelihood of failure (LF)
Typical Contributing Factors- Nominal diameter- Reserve water pressure ratio- Catalogue remaining useful life- Required (forced) upgrade- High failure frequency- DMA zone leakage volume (where available)- Undesired pipe material (e.g. AC)- Assessed Condition (where available)- Pipe material in combination with geology- High corrosion potential for steel pipes- High static-dynamic pressure range
Typical Contributing Factors- Nominal diameter- Reserve water pressure ratio- Catalogue remaining useful life- Required (forced) upgrade- High failure frequency- DMA zone leakage volume (where available)- Undesired pipe material (e.g. AC)- Assessed Condition (where available)- Pipe material in combination with geology- High corrosion potential for steel pipes- High static-dynamic pressure range
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 4
Rating of Likelihood of failure (e.g.)Rating of Likelihood of failure (e.g.)
Reserve Pressure Ratio = Reserve Pressure Ratio =
Property Criteria Rating(<=) (1..5)
Reserve Pressure Ratio 0.25 1
Reserve Pressure Ratio 0.50 2
Reserve Pressure Ratio 0.75 3
Reserve Pressure Ratio 0.99 4
Reserve Pressure Ratio >0.99 5
Rating of Likelihood of failure (e.g.)Rating of Likelihood of failure (e.g.)
Required Upgrade (master plan item)Required Upgrade (master plan item)
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 5
Likelihood of failure – failure frequencyLikelihood of failure – failure frequency
Likelihood of failure – typical weightingLikelihood of failure – typical weighting
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 6
PRP: Consequence of failure (CF)PRP: Consequence of failure (CF)
Typical Contributing Factors- High damage cost to consumer due to water
pressure- High damage cost to consumer due to flow- High repair cost based on pipe cost function- Flooding due to steep geography - Strategic location (e.g. CBD, HOS, IND)- Lack of network redundancy
Typical Contributing Factors- High damage cost to consumer due to water
pressure- High damage cost to consumer due to flow- High repair cost based on pipe cost function- Flooding due to steep geography - Strategic location (e.g. CBD, HOS, IND)- Lack of network redundancy
Rating of Consequence of failure (e.g.)Rating of Consequence of failure (e.g.)
High repair cost (due to location)High repair cost (due to location)
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 7
Consequence of failure – typical weightingConsequence of failure – typical weighting
LF – typical final factor visualizationLF – typical final factor visualization
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 8
CF – typical final factor visualizationCF – typical final factor visualization
PRP – typical final factor visualizationPRP – typical final factor visualization
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 9
PRP: Roll-up of resultsPRP: Roll-up of results
To facilitate interpretation of PRP results, roll-up of results to areas is supported by- Political region- Roll-up area
Roll-up areas typically consist of - Bulk systems for Bulk Pipes- Suburbs for Network Pipes- Street block polygons for Network Pipes
The pipe length weighted average PRP is calculated for each areaA ranking index is calculated (PRP%)
To facilitate interpretation of PRP results, roll-up of results to areas is supported by- Political region- Roll-up area
Roll-up areas typically consist of - Bulk systems for Bulk Pipes- Suburbs for Network Pipes- Street block polygons for Network Pipes
The pipe length weighted average PRP is calculated for each areaA ranking index is calculated (PRP%)
Rolled-up PRP – visualizationRolled-up PRP – visualization
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 10
Case Study: Overstrand MunicipalityCase Study: Overstrand Municipality
PRP Reports- 2010- 2012- 2014
PRP Reports- 2010- 2012- 2014
Overstrand – failure frequency analysisOverstrand – failure frequency analysis
Logged pipe failure important source of information to identify where pipe failures are likely to occur in futurePipe sections might have been replaced, but underlying reason for failure might not have been resolved Future failures are likely to occur again in adjacent sections until total replacement of street block or areas has been done
Logged pipe failure important source of information to identify where pipe failures are likely to occur in futurePipe sections might have been replaced, but underlying reason for failure might not have been resolved Future failures are likely to occur again in adjacent sections until total replacement of street block or areas has been done
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 11
Overstrand – failure frequency analysisOverstrand – failure frequency analysis
Geo-coding process followed to map incidents to modelled pipesTypical values recorded between 0 and 29 incidents/km/aFailures where the correlated pipe was replaced within the same year or after the failures was recorded, were excluded. This assumes that the reason for the failure related to the old pipe was resolved
Geo-coding process followed to map incidents to modelled pipesTypical values recorded between 0 and 29 incidents/km/aFailures where the correlated pipe was replaced within the same year or after the failures was recorded, were excluded. This assumes that the reason for the failure related to the old pipe was resolved
Overstrand PRP – visualizationOverstrand PRP – visualization
PRP values shown for pipes on aerial mapPRP values shown for pipes on aerial map
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 12
Overstrand PRP – visualization detailOverstrand PRP – visualization detail
Detail PRP breakdown shown for pipes on cadastral & contoursDetail PRP breakdown shown for pipes on cadastral & contours
Overstrand PRP – typical final map Overstrand PRP – typical final map
Top 200 pipes which have 3 or more bursts recordedTop 200 pipes which have 3 or more bursts recorded
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 13
First successes: reduction in burstsFirst successes: reduction in bursts
Reduction in pipe bursts recorded in Pringle Bay since 2010 replacementsReduction in pipe bursts recorded in Pringle Bay since 2010 replacements
Analysis of post-PRP replacement areasAnalysis of post-PRP replacement areas
Betty’s Bay 8 for example had highest PRP rankingBetty’s Bay 8 for example had highest PRP ranking
Length-Weighted Meter Pipe Pipe Burst Pipe Burst Pipe Replace CostAreaName PRP Replaced Replacement Count per a/km Count per a/km (2014)
(2012) Pipe Year before Replacement after ReplacementBetty's Bay 1 0.239 415 2013 3.787 0.000 207 998.00R Betty's Bay 2 0.216 570 2013 3.509 0.000 285 684.00R Betty's Bay 3 0.252 1 860 2013 4.839 0.000 1 500 408.00R Betty's Bay 4 0.265 725 2013 4.729 0.000 363 370.00R Betty's Bay 5 0.186 1 780 2013 0.321 0.000 927 017.00R Betty's Bay 6 0.153 420 2012 5.159 0.000 219 324.00R Betty's Bay 7 0.174 185 2012 7.207 0.000 92 722.00R Betty's Bay 8 0.451 495 2012 9.764 1.010 248 094.00R Betty's Bay 9 0.192 650 2012 3.590 0.000 325 780.00R Kleinmond 1 0.222 2 105 2013 1.493 0.000 1 055 026.00R Hermanus 1 0.203 3 395 2012 0.589 0.147 1 742 146.00R Stanford 1 0.220 595 2013 0.240 0.000 298 214.00R Stanford 2 0.250 385 2013 0.000 0.000 329 329.00R Pearly Beach 1 0.158 240 2012 0.000 0.000 120 288.00R Pearly Beach 2 0.142 170 2012 0.000 0.000 85 204.00R Pearly Beach 3 0.172 345 2012 0.725 0.000 172 914.00R Pearly Beach 4 0.174 1 015 2012 0.493 0.000 522 438.00R Pearly Beach 5 0.186 2 050 2012 1.098 0.000 1 027 460.00R TOTAL 0.214 17 400 2012-2013 2.215 0.074 9 523 416.00R
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 14
Analysis of post-PRP replacement areasAnalysis of post-PRP replacement areas
Replacements areas post PRP implementation (Betty’s Bay)Replacements areas post PRP implementation (Betty’s Bay)
Analysis of post-PRP replacement areasAnalysis of post-PRP replacement areas
Length-weighted replacement priority (PRP) before replacementLength-weighted replacement priority (PRP) before replacement
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 15
Analysis of post-PRP replacement areasAnalysis of post-PRP replacement areas
Projected replacement cost (2014 pricing)Adjacent areas considered also for replacementProjected replacement cost (2014 pricing)Adjacent areas considered also for replacement
Analysis of post-PRP replacement areasAnalysis of post-PRP replacement areas
Replace Cost vs Repair Cost break-even point (years) @ R25 000 per typical burstReplace Cost vs Repair Cost break-even point (years) @ R25 000 per typical burst
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 16
Asset management alignmentAsset management alignment
A further step is to provide an aligned technical approach with Asset Management Principles and provide an absolute measure of need of replacement, not just rankingResult can be used to compare different models with each otherFrom existing PRP results, Failure Modes are analysed independently of each other to determine the final corrected Remaining Useful Life (RUL)
A further step is to provide an aligned technical approach with Asset Management Principles and provide an absolute measure of need of replacement, not just rankingResult can be used to compare different models with each otherFrom existing PRP results, Failure Modes are analysed independently of each other to determine the final corrected Remaining Useful Life (RUL)
Asset management alignmentAsset management alignment
The independent Criticality Grade for a pipe is determined from the existing PRP data.Risk Exposure (RE) can for example be defined as Criticality Grade x (RULmax-RUL)(of the worst failure mode)Roll-up of RE and RUL also possible to street blocks
The independent Criticality Grade for a pipe is determined from the existing PRP data.Risk Exposure (RE) can for example be defined as Criticality Grade x (RULmax-RUL)(of the worst failure mode)Roll-up of RE and RUL also possible to street blocks
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 17
RUL correction algorithmRUL correction algorithm
Verification against condition-based RUL bandsVerification against condition-based RUL bands
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 18
Long term investment planningLong term investment planning
Focusses on simulating annual replacements highlighting spending a PRP budget efficientlyMinimize SID: Non-service minutes due to replacements or repairs per total number of connections in areaMinimize predicted number of theoretical failures (OPEX)Optimize CAPEX for condition assessment
Focusses on simulating annual replacements highlighting spending a PRP budget efficientlyMinimize SID: Non-service minutes due to replacements or repairs per total number of connections in areaMinimize predicted number of theoretical failures (OPEX)Optimize CAPEX for condition assessment
Typical outcome: multi-year simulationTypical outcome: multi-year simulation
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 19
Typical outcome: multi-year simulationTypical outcome: multi-year simulation
Typical outcome: multi-year simulationTypical outcome: multi-year simulation
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 20
Typical outcome: multi-year simulationTypical outcome: multi-year simulation
Conclusion & RecommendationsConclusion & Recommendations
PRP provides key input to engineering inspection, refurbishment and replacement processes.PRP should be used for inspection or guide for replacement, not blindly implemented. Pressure management should also be considered in high pressure areas. PRP programme implemented at Overstrandshowing success. Need longer failure record.Asset management alignment as well as long term investment planning provides valuable future extensions to PRP
PRP provides key input to engineering inspection, refurbishment and replacement processes.PRP should be used for inspection or guide for replacement, not blindly implemented. Pressure management should also be considered in high pressure areas. PRP programme implemented at Overstrandshowing success. Need longer failure record.Asset management alignment as well as long term investment planning provides valuable future extensions to PRP
Copyright 2015 - GLS Consulting (Pty) Ltd Printed with permission. 21
- Thank You -- Thank You -