ACS understands genset manufacturers’ customers have demanding operational requirements. We have developed a wide range of expertise to provide comprehensive testing facilities to simulate customer operating conditions.
ACS has completed design and construction for production, development, and research genset test cells.
We have managed the design, construction, and commissioning of load banks for genset, locomotive, and aircraft electrical power system testing as well as for reverse power prevention and maintenance of installed gensets for standby power applications. Our experience includes load bank design and installation for facilities designed to test generators up to 5,000kW, including reactive testing. Test programs include multi-voltage and multi-frequency (DC, 50, 60, 400, and 800Hz) solutions using single or multiple outdoor air-cooled load banks.
Additionally, ACS has experience with Hopkinson’s back to back systems to conduct fully reactive load tests without the use of traditional load banks. Regenerative load bank simulation has been executed for a 5,250 KW wind turbine generator testing. This program included utility grid fault simulation in addition to leading and lagging power factor loads.
ACS has designed systems that can be manually controlled from the HMI test screen or remotely controlled from the test cell control and data acquisition system. Our commissioning process assures that we prove out the client’s acceptance criteria, as identified during the design phase of a project.
Headquarters - Madison, WI - USA / Greenville, SC - USA / Troy, MI - USA / TEDA Tianjin, China / Leicester, UK / www.acscm.com / [email protected]
ACS Relevant Experience - Load Banks for Genset Testing and Power Applications
O V E R V I E W
G E N S E T T E S T F A C I L I T I E S
Application Location Power/Capacity Voltage Description
Alternator testing Stamford, UK 3000KW 380V – 13.8KV Hopkinson’s Back to Back Reactive
Genset testing Seymour, IN 5000KW/6250KVA.80pf
480V – 4160V380V-3300V
SimplexResistive/Reactive
Genset development Waukesha, WI 1500KW 208V – 600V Simplex Resistive/Reactive
Genset production test Tianjin, China 3000KW/3750KVA.80pf
190V – 13.8KV SimplexResistive/Reactive
Genset locomotive LaGrange, IL 12000KW(6 units at 2000KW)
208V – 4160V Simplex load bank on a resistive grounding system
Aircraft power systems test Rockford, IL 1500KW/1875KVA.80pf
400V 3-phase 400-800Hz
Quantum Resistive/Reactive
Reverse power prevention Auburn Hills, MI 500KW 480V Simplex Resistive
Genset testing Wuhan, China 3250KW/4000KVA.80pf
190V-690V LANGDIResistive/Reactive
O V E R V I E W
G E N S E T T E S T F A C I L I T I E S
ACS is a single-source provider of fully integrated
facility and equipment solutions, serving the
international engine- and vehicle-testing
markets. The Company specializes in the
comprehensive design, construction, integration,
and commissioning of development and
production test facilities for engine, vehicle, and
components manufacturers.
ACS Services• Single source integrated delivery
• Facility design
• Construction management
• Systems integration
• Equipment specification, selection &
procurement
• Specialized test equipment design &
fabrication
• Instrumentation and controls
• Facility & equipment commissioning
• Data management
• Preventative maintenance
ACS Integrated DeliveryUsing our integrated delivery model, we work as strategic partners with our clients to
align our team’s expertise with the specific needs of the project from the initial planning
stages through commissioning and close out.
ACS expertise spans the complete test facility process of planning and design,
specification and procurement, construction management, and commissioning of
engine and genset test facilities.
Design and Planning ConsiderationsResistive only and reactive & resistive
Hopkinson’s back to back arrangement
Regenerative load bank simulation
Utility coordination and control
Process water-heating load banks
Sound attenuation
Controls – manual and automated
Metering and protective relays
Site considerations – protection of load bank from physical damage
Safety - protect against dangerous voltage
Heat rejection – protect people and facilities
Heat recovery – recover heat in colder climates, water cooled options
Code-required and maintenance testing of standby power generation – cost
benefit of fixed load or portable
Construction ManagementProcurement
Shipping, rigging, setting
Underground conduit design layout and oversight/management of installation
Structural support, concrete pad, design layout
CommissioningMeasurement and data acquisition
Start-up, commissioning
Owner education and training