ORAL ARGUMENT NOT SCHEDULED No. 18-1129 ......ORAL ARGUMENT NOT SCHEDULED No. 18-1129 (consolidated...

55
ORAL ARGUMENT NOT SCHEDULED No. 18-1129 (consolidated with Nos. 18-1135, 18-1148, 18-1159, 18-1184) IN THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT UNITED KEETOOWAH BAND OF CHEROKEE INDIANS IN OKLAHOMA, ET AL., Petitioners, v. FEDERAL COMMUNICATIONS COMMISSION, AND UNITED STATES OF AMERICA, Respondents. On Petition for Review of an Order of the Federal Communications Commission BRIEF FOR INTERVENORS IN SUPPORT OF RESPONDENTS Joshua S. Turner Ari Meltzer Meredith Singer WILEY REIN LLP 1776 K Street NW Washington, DC 20006 (202)719-7000 [email protected] [email protected] [email protected] Christopher J. Wright E. Austin Bonner HARRIS, WILTSHIRE & GRANNIS LLP 1919 M Street NW | Eighth Floor Washington, DC 20036 (202)730-1300 [email protected] [email protected] Counsel for CTIA The Wireless Association® Counsel for Sprint Corporation USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 1 of 55

Transcript of ORAL ARGUMENT NOT SCHEDULED No. 18-1129 ......ORAL ARGUMENT NOT SCHEDULED No. 18-1129 (consolidated...

  • ORAL ARGUMENT NOT SCHEDULED

    No. 18-1129 (consolidated with Nos. 18-1135, 18-1148, 18-1159, 18-1184)

    IN THE UNITED STATES COURT OF APPEALS

    FOR THE DISTRICT OF COLUMBIA CIRCUIT

    UNITED KEETOOWAH BAND OF CHEROKEE INDIANS IN OKLAHOMA, ET AL.,

    Petitioners,

    v.

    FEDERAL COMMUNICATIONS COMMISSION, AND

    UNITED STATES OF AMERICA,

    Respondents.

    On Petition for Review of an Order

    of the Federal Communications Commission

    BRIEF FOR INTERVENORS IN SUPPORT OF RESPONDENTS

    Joshua S. Turner

    Ari Meltzer

    Meredith Singer

    WILEY REIN LLP

    1776 K Street NW

    Washington, DC 20006

    (202)719-7000

    [email protected]

    [email protected]

    [email protected]

    Christopher J. Wright

    E. Austin Bonner

    HARRIS, WILTSHIRE & GRANNIS

    LLP

    1919 M Street NW | Eighth Floor

    Washington, DC 20036

    (202)730-1300

    [email protected]

    [email protected]

    Counsel for CTIA – The Wireless

    Association®

    Counsel for Sprint Corporation

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 1 of 55

  • –i–

    CERTIFICATE AS TO PARTIES, RULINGS, AND RELATED CASES

    Pursuant to D.C. Cir. Rule 28(a)(1), Intervenors hereby certify as follows:

    A. Parties and Intervenors:

    These cases involve the following parties:

    Petitioners: United Keetoowah Band of Cherokee Indians in Oklahoma;

    Osage Nation; Shawnee Tribe of Oklahoma; Ponca Tribe of Indians of Oklahoma;

    Delaware Nation; Otoe-Missouria Tribe; Sac and Fox Nation; Thlopthlocco Tribal

    Town; Delaware Tribe of Indians; Pawnee Nation; Crow Creek Tribe of South

    Dakota; Omaha Tribe of Nebraska; Seminole Tribe of Florida; Blackfeet Tribe;

    Coushatta Tribe of Louisiana; Fort Belknap Indian Community; Rosebud Sioux

    Tribe; Ute Mountain Ute Tribe; United South and Eastern Tribes, Inc.; and Natural

    Resources Defense Council.

    Respondents: Federal Communications Commission and the United States

    of America.

    Intervenors for Petitioners: National Association of Tribal Historic

    Preservation Officers, National Trust for Historic Preservation, Cheyenne &

    Arapaho Tribes, Apache Tribe of Oklahoma, Mescalero Apache Tribe, Alabama-

    Quassarte Tribal Town, Tonkawa Tribe, Peoria Tribe of Indians of Oklahoma, and

    Edward B. Myers.

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 2 of 55

  • –ii–

    Intervenors for Respondents: CTIA-The Wireless Association and Sprint

    Corporation.

    B. Rulings Under Review: Second Report and Order, In re Accelerating

    Wireless Broadband Deployment by Removing Barriers to Infrastructure

    Investment, 33 FCC Rcd. ___, FCC 18-30 (Mar. 30, 2018), 83 Fed. Reg. 19440

    (May 3, 2018) (“Order”).

    C. Related Cases: Petitions for review are consolidated. Intervenors for the

    Respondents are unaware of any other related cases.

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 3 of 55

  • –iii–

    RULE 26.1 DISCLOSURE STATEMENT

    Pursuant to Federal Rule of Appellate Procedure 26.1 and D.C. Cir. Rule 26.1,

    Intervenors submit the following statements:

    CTIA – The Wireless Association (“CTIA”) is a Section 501(c)(6) not-for-

    profit corporation organized under the laws of the District of Columbia that

    represents the wireless communications industry. Members of CTIA include

    wireless carriers, device manufacturers, and suppliers as well as apps and content

    companies, and other industry participants. CTIA has not issued any shares or debt

    securities to the public, and CTIA has no parent companies, subsidiaries, or affiliates

    that have issued any shares or debt securities to the public. No parent or publicly

    held company owns 10 percent or more of CTIA’s stock.

    Sprint Corporation (“Sprint”) is a publicly traded Delaware corporation

    that provides telecommunications services. Softbank Group Corp., a publicly traded

    Japanese corporation, owns approximately 80 percent of Sprint Corporation’s

    outstanding stock.

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 4 of 55

  • –iv–

    TABLE OF CONTENTS

    Page(s)

    CERTIFICATE AS TO PARTIES, RULINGS, AND RELATED CASES ............. i

    RULE 26.1 DISCLOSURE STATEMENT ............................................................. iii

    TABLE OF AUTHORITIES ................................................................................... vi

    GLOSSARY ............................................................................................................ xii

    INTRODUCTION .................................................................................................... 1

    ISSUES PRESENTED .............................................................................................. 2

    STATUTES AND REGULATIONS ........................................................................ 3

    STATEMENT OF THE CASE ................................................................................. 4

    A. The National Historic Preservation Act and the National

    Environmental Policy Act .................................................................... 4

    B. FCC Implementation of NEPA and NHPA ......................................... 5

    C. The Tribal Consultation Process .......................................................... 7

    D. Small Cells and the Race to 5G ............................................................ 9

    E. The FCC’s Order ................................................................................ 10

    SUMMARY OF ARGUMENT .............................................................................. 11

    STANDARD OF REVIEW .................................................................................... 14

    ARGUMENT .......................................................................................................... 14

    I. The Deployment of small wireless facilities is neither a “major federal

    action” nor an “undertaking.” ....................................................................... 14

    A. The FCC’s Determination That Section 1.1312 Does Not Apply

    To The Deployment Of Small Wireless Facilities Was Both

    Reasonable and Amply Supported by the Record. ............................ 17

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 5 of 55

  • –v–

    1. The FCC Reasonably Determined That The Review

    Process Triggered By Section 1.1312 Is Unnecessarily

    Burdensome. ............................................................................. 18

    2. The FCC Reasonably Determined That Small Wireless

    Facilities Are Unobtrusive and Do Not Raise the Same

    Concerns As Macro Cells. ....................................................... 20

    B. The FCC Properly Determined That, Other Than Section 1.1312

    Review, The FCC Has No Involvement In The Deployment Of

    Small Wireless Facilities. ................................................................... 24

    1. “Undertaking” And “Major Federal Action” Only Apply

    When There Is Federal Control. .............................................. 25

    2. Petitioners Cannot Recast Spectrum Licenses As

    Infrastructure Permits. ............................................................. 28

    II. THE FCC WAS NOT REQUIRED TO CONDUCT ANY NEPA

    REVIEW BEFORE ISSUING THE ORDER. ............................................. 38

    CONCLUSION ....................................................................................................... 40

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 6 of 55

  • –vi–

    TABLE OF AUTHORITIES*

    Page(s)

    Cases

    American Airlines, Inc. v. Department of Transportation,

    202 F.3d 788 (5th Cir. 2000) .............................................................................. 30

    Big Bend Conservation Alliance v. Federal Energy Regulatory

    Commission,

    896 F.3d 418 (D.C. Cir. 2018) .......................................................... 13, 16, 26, 38

    Business & Residents Alliance of East Harlem v. Jackson,

    430 F.3d 584 (2d Cir. 2005) ............................................................................... 30

    Cellco Partnership v. Federal Communictaions Commission,

    357 F.3d 88 (D.C. Cir. 2004) ........................................................................ 14, 17

    Center for Auto Safety v. Peck,

    751 F.2d 1336 (D.C. Cir. 1985) .......................................................................... 21

    Chemical Manufacturers Association v. EPA,

    919 F.2d 158 (D.C. Cir. 1990) ............................................................................ 23

    Citizens Against Rails–to–Trails v. Surface Transportation Board,

    267 F.3d 1144 (D.C. Cir. 2001) .......................................................................... 25

    Community Nutrition Institute v. Young,

    773 F.2d 1356 (D.C. Cir. 1985) .................................................................... 14, 40

    Consumer Electronics Association v. Federal Communications

    Commission,

    347 F.3d 291 (D.C. Cir. 2003) ............................................................................ 21

    CTIA-Wireless Association v. Federal Communications Commission,

    466 F.3d 105 (D.C. Cir. 2006) ...................................................................... 12, 15

    * Authorities upon which we chiefly rely are marked with asterisks.

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 7 of 55

  • –vii–

    Defenders of Wildlife v. Andrus,

    627 F.2d 1238 (D.C. Cir. 1980) .......................................................................... 26

    EchoStar Communications Corp. v. Federal Communications

    Commission,

    292 F.3d 749 (D.C. Cir. 2002) ............................................................................ 18

    Environmentel, LLC v. Federal Communications Commission,

    661 F.3d 80 (D.C. Cir. 2011) .............................................................................. 38

    Federal Communications Commission v. Fox Television Stations, Inc.,

    556 U.S. 502 (2009) ............................................................................................ 18

    FiberTower Spectrum Holdings, LLC v. Federal Communications

    Commission,

    782 F.3d 692 (D.C. Cir. 2015) ............................................................................ 38

    Free Access & Broadcast Telemedia, LLC v. Federal

    Communications Commission,

    865 F.3d 615 (D.C. Cir. 2017) ............................................................................ 38

    GTE Service Corporation v. Federal Communications Commission,

    782 F.2d 263 (D.C. Cir. 1986) ............................................................................ 20

    Heartwood v. United States Forest Service,

    230 F.3d 947 (7th Cir. 2000) .............................................................................. 39

    *Karst Environmental Education & Protection, Inc. v. Environmental

    Protection Agency,

    475 F.3d 1291 (D.C. Cir. 2007) ................................................................ 5, 12, 25

    *Lee v. Thornburgh,

    877 F.2d 1053 (D.C. Cir. 1989) .................................................... 4, 16, 25, 27, 30

    New York v. Nuclear Regulation Commission,

    681 F.3d 471 (D.C. Cir. 2012) ................................................................ 35, 36, 37

    *Ringsred v. City of Duluth,

    828 F.2d 1305 (8th Cir. 1987) .......................................................... 26, 27, 28, 30

    Sac & Fox Nation of Missouri v. Norton,

    240 F.3d 1250 (10th Cir. 2001) ................................................................ 5, 27, 30

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 8 of 55

  • –viii–

    Save the Bay, Inc. v. United States Corps of Engineers,

    610 F.2d 322 (5th Cir. 1980) .............................................................................. 28

    Sheridan Kalorama Historical Association v. Christopher,

    49 F.3d 750 (D.C. Cir. 1995) .............................................................................. 27

    Sierra Club v. Bosworth,

    510 F.3d 1016 (9th Cir. 2007) ............................................................................ 39

    Sierra Club v. Federal Energy Regulatory Commission,

    827 F.3d 36 (D.C. Cir. 2016) ........................................................................ 33, 36

    Sierra Club v. Penfold,

    857 F.2d 1307 (9th Cir. 1988) ............................................................................ 30

    Sierra Club v. United States Army Corps of Engineers,

    990 F.Supp.2d 9 (D.D.C. 2013) .......................................................................... 37

    SNR Wireless LicenseCo, LLC v. Federal Communications

    Commission,

    868 F.3d 1021 (D.C. Cir. 2017), cert. denied sub nom. SNR

    Wireless LicenseCo v. Federal Communications Commission, 138

    S. Ct. 2674 (2018) ............................................................................................... 14

    Sorenson Communications, LLC v. Federal Communications

    Commission,

    897 F.3d 214 (D.C. Cir. 2018) ...................................................................... 14, 17

    Standing Rock Sioux Tribe v. United States Army Corps of Engineers,

    301 F.Supp.3d 50 (D.D.C. 2018) ........................................................................ 37

    State of New Jersey, Department of Environmental Protection &

    Energy v. Long Island Power Authority,

    30 F.3d 403 (3d Cir. 1994) ........................................................................... 32, 33

    State of South Dakota v. Andrus,

    614 F.2d 1190 (8th Cir. 1980) ............................................................................ 34

    *Sugarloaf Citizens Association v. Federal Energy Regulatory

    Commission,

    959 F.2d 508 (4th Cir. 1992) ............................................... 12, 13, 26, 27, 30, 32

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 9 of 55

  • –ix–

    Taxpayers Watchdog, Inc. v. Stanley,

    819 F.2d 294 (D.C. Cir. 1987) ............................................................................ 37

    Verizon Telephone Companies v. Federal Communications

    Commission,

    292 F.3d 903 (D.C. Cir. 2002) ............................................................................ 14

    Administrative Decisions

    In the Matter of Acceleration of Broadband Deployment by Improving

    Wireless Siting Policies,

    Report and Order, 29 FCC Rcd. 12865 (2014) ................................................... 23

    In the Matter of Amendment of Environmental Rules,

    First Report and Order, 5 FCC Rcd. 2942 (1990) ................................................ 7

    In the Matter of Amendment of Environmental Rules in Response to

    New Regulations Issued by the Council on Environmental Quality,

    Report and Order, 60 Rad. Reg. 2d (P & F)(FCC Mar. 26, 1986) ............. 6, 7, 29

    Amendment of Parts 1, 2, 22, 24, 27, 90 and 95 of the Commission’s

    Rules to Improve Wireless Coverage Through the Use of Signal

    Boosters,

    Report and Order, 28 FCC Rcd. 1663 (2013) ..................................................... 31

    In the Matter of Accelerating Wireless Broadband Deployment by

    Removing Barriers to Infrastructure Inv., Notice of Proposed

    Rulemaking, 32 FCC Rcd. 3330 (2017) ............................................................. 10

    Reassessment of FCC Radiofrequency Exposure Limits & Policies,

    First Report and Order, Further Notice of Proposed Rulemaking,

    and Notice of Inquiry, 28 FCC Rcd. 3498 (2013) .............................................. 40

    In the Matter of the National Environmental Protection Act of 1969,

    Report and Order, 49 FCC.2d 1313 (1974) .......................................................... 5

    Statutes

    5 U.S.C. § 702(2)(A) ................................................................................................ 14

    42 U.S.C. § 4332(C)............................................................................................. 4, 39

    47 U.S.C. § 319(a) ................................................................................................. 5, 6

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 10 of 55

  • –x–

    47 U.S.C. § 319(d) ......................................................................................... 6, 18, 29

    47 U.S.C. § 332(c)(7)(A) ......................................................................................... 21

    47 U.S.C. § 405(a) ............................................................................................. 13, 38

    54 U.S.C. § 300320(3) ............................................................................................... 4

    54 U.S.C. § 302702 .................................................................................................... 7

    54 U.S.C. § 306108 .................................................................................................... 4

    Act of Oct. 15, 1966, Pub. L. No. 89-665 (80 Stat.) ........................................ 4, 6, 26

    Other Authorities

    36 C.F.R. § 800.2(c)(2)(ii)(A), (a)(4) ................................................................ 7, 8, 9

    36 C.F.R. § 800.16(y) .............................................................................................. 25

    40 C.F.R. § 1508.18 ................................................................................................. 25

    47 C.F.R. § 1.1307 ..................................................................................................... 6

    47 C.F.R. § 1.1312(b) ........................................................................................ 12, 15

    47 C.F.R. § 24.11 ............................................................................................... 29, 32

    47 C.F.R. § 27.14(h) ................................................................................................ 35

    47 CFR Part 1, Appx. B, §§ VI.A.5.a & b. .............................................................. 21

    AccentureStrategy, Accelerating Future Economic Value From the

    Wireless Industry (2018) ..................................................................................... 10

    CTIA, The Global Race to 5G (April 2018) ............................................................ 10

    Further Notice of Proposed Rulemaking, and Notice of Inquiry, 28

    FCC Rcd. 3498 (2013) ........................................................................................ 40

    *S. Rep. No. 91-296 (1969) ............................................................................. 4, 5, 26

    Sprint, Sprint Reaches Nationwide LTE Advanced Milestone, (Oct. 31,

    2018) ................................................................................................................... 34

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 11 of 55

  • –xi–

    Verizon, What is Small Cell Technology, (Aug. 3, 2018) ....................................... 34

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 12 of 55

  • –xii–

    GLOSSARY

    CTIA CTIA – The Wireless Association

    Sprint Sprint Corporation

    FCC Federal Communications Commission

    NRDC Natural Resources Defense Council

    ACHP Advisory Council on Historic Preservation

    CEQ Council on Environmental Quality

    EA Environmental Assessment

    EIS Environmental Impact Statement

    NEPA National Environmental Policy Act

    NHPA National Historic Preservation Act

    Order In re Accelerating Wireless Broadband

    Deployment by Removing Barriers to

    Infrastructure Investment, Second Report and

    Order, 33 FCC Rcd. ___, FCC 18-30 (Mar. 30,

    2018), 83 Fed. Reg. 19440 (May 3, 2018)

    TCNS Tower Construction Notification System

    THPO Tribal Historic Preservation Officer

    5G 5th Generation Wireless Services

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 13 of 55

  • –1–

    INTRODUCTION

    For more than 40 years, the FCC has required that certain applicants submit a

    preliminary environmental report to the Commission before constructing

    communications facilities. Although this obligation originally arose under NEPA,

    as technology and the Commission’s licensing processes have changed, the original

    concerns motivating this review have become less relevant. The deployment of

    “small cells” and a switch to geographic licensing rather than site-based approvals

    have eliminated the FCC’s role in deciding where most wireless communications

    infrastructure will be placed. Nevertheless, the agency had continued to subject

    small cells to residual environmental review requirements arising under the FCC’s

    Communications Act public interest authority without ever revisiting the need for

    these mandates or the costs they impose.

    In the Order, the FCC took a fresh look at NEPA and NHPA requirements

    along with any potential public interest benefits of continued environmental review

    under the Communications Act. The Commission found that the costs of subjecting

    small cells to the FCC’s environmental review regulations have become more

    burdensome at a time when rapid and widespread deployment of wireless

    infrastructure is critical to fulfilling consumer demand and winning the race to 5G.

    The Commission also found that the benefits of such review are minimal because

    they rarely identify any significant problem. The agency accordingly determined

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 14 of 55

  • 2

    that there no longer is any public interest justification for maintaining even residual

    review of small wireless facilities. Having exempted small cells from its

    environmental review regulations, the agency went on to find that there is no

    remaining argument that the siting of these facilities involves the federal

    government. Therefore, the Commission concluded, NEPA and NHPA are

    inapplicable to small cell deployment because there is no federal undertaking or

    action at issue when small cells are deployed.

    The FCC’s actions in the Order serve as a long overdue recognition that its

    prior environmental review regulations are out of step with the manner in which

    modern wireless facilities are deployed. The agency’s decisions in the Order are

    thus completely reasonable, if not required. The Commission’s recognition that the

    public interest is not served by burdensome and unnecessary application of these

    regulations is well within its broad statutory authority. Petitioners’ arguments are

    meritless.

    ISSUES PRESENTED

    1. Whether the FCC reasonably determined that it contravenes the public

    interest to apply environmental review regulations adopted pursuant to the FCC’s

    Communications Act authority to the deployment of small wireless facilities.

    2. Whether the FCC reasonably determined that its involvement in the

    deployment of small wireless facilities is so minimal as to not constitute a “federal

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 15 of 55

  • 3

    or federally assisted undertaking” under NHPA or a “major federal action” under

    NEPA.

    3. Whether the FCC was required to conduct NEPA review before issuing

    the Order.

    STATUTES AND REGULATIONS

    All relevant statutes and regulations are set forth in the addendum to the Brief

    for Respondents.

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 16 of 55

  • 4

    STATEMENT OF THE CASE

    A. The National Historic Preservation Act and the National Environmental Policy Act

    NHPA requires federal agencies to “take into account” the effects of “[f]ederal

    or federally assisted undertaking[s]” on historic properties. 54 U.S.C. § 306108.

    Under NHPA, an undertaking is “a project, activity, or program funded in whole or

    in part under the direct or indirect jurisdiction of a Federal agency, including . . .

    those requiring a Federal permit, license, or approval.” 54 U.S.C. § 300320(3).

    Congress intended these provisions to have “a limited reach.” Lee v.

    Thornburgh, 877 F.2d 1053, 1056 (D.C. Cir. 1989). NHPA is aimed solely at

    discouraging federal agencies “from ignoring preservation values in projects they

    initiate.” Id. (emphasis added). It is a procedural statute that exists to ensure that

    when federal agencies act, they consider the effect on historic properties and do not

    run roughshod over local historical concerns. See Act of Oct. 15, 1966, Pub. L. No.

    89-665, (80 Stat.), 915 (emphasizing that NHPA only reigns in actions of the

    “Federal Government”).

    Like NHPA, NEPA has a limited reach. NEPA commands Federal agencies

    to identify and evaluate the environmental effects of proposed “major federal

    actions.” 42 U.S.C. § 4332(C). The statute was intended to “clarif[y] the goals,

    concepts, and procedures which determine and guide the programs and the activities

    of Federal agencies.” S. Rep. No. 91-296, at 6 (1969) (emphasis added). As with

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 17 of 55

  • 5

    NHPA, NEPA is extends only to “the policies, regulations, and public laws of the

    United States” and the “program activities” of Federal agencies; it is not a restriction

    on private conduct. Id. at 6-7.

    Courts have treated “undertakings” under NHPA and “major federal actions”

    under NEPA as coextensive, recognizing that determining what constitutes an

    “undertaking” or a “major federal action” is an objective inquiry that focuses on the

    degree of federal control over a particular deployment. See, e.g., Karst Envtl. Educ.

    & Prot., Inc. v. EPA, 475 F.3d 1291, 1295-96 (D.C. Cir. 2007); Sac & Fox Nation

    of Mo. v. Norton, 240 F.3d 1250, 1263 (10th Cir. 2001).

    B. FCC Implementation of NEPA and NHPA

    The FCC’s implementation of NEPA and NHPA has evolved over time to

    reflect changes in the FCC’s licensing procedures. In 1974, the FCC adopted its

    initial order implementing NEPA. See In the Matter of the National Environmental

    Protection Act of 1969, Report and Order, 49 FCC.2d 1313 (1974) (the “1974

    Order”). At the time, Section 319 of the Communications Act of 1934 required all

    FCC licensees, including carriers, to obtain a construction permit for a specific site

    or physical location before they could obtain a license to operate. See 47 U.S.C.

    § 319(a). The FCC took 500,000 actions annually that authorized construction at

    specified sites of this type. 1974 Order ¶13.

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 18 of 55

  • 6

    To focus its efforts only on actions likely to have a significant effect on the

    environment, the Commission sought to distinguish between “major” actions and

    “minor” ones. Id. The FCC recognized that “[t]he likelihood that [antenna] towers

    will have a significant environmental effect depends on their height and location.”

    Id. ¶31. Accordingly, the Commission decided to “draw a line based on the height

    of the structure and to concentrate routine processing on larger structures, for which

    the probability of significant effect is greater.” Id. ¶32.

    In 1982, Congress amended Section 319 to eliminate the construction permit

    requirement for certain wireless licensees unless the FCC determined that the public

    interest, convenience, and necessity required a permit. See Act of Oct. 15, 1966,

    Pub. L. No. 89-665, (80 Stat.), 915; 47 U.S.C. § 319(d). Shortly thereafter, the FCC

    revised its rules to clarify that only facilities involving sensitive site areas, high

    intensity lighting, or exceeding RF exposure limits would be subject to NEPA’s EA

    requirement. See In the Matter of Amendment of Envtl. Rules in Response to New

    Regulations Issued by the Council on Envtl. Quality, Report and Order, 60 Rad. Reg.

    2d (P & F) ¶11 (FCC Mar. 26, 1986) (“1986 Order”); 47 C.F.R. § 1.1307. The 1986

    Order added a separate section to the FCC’s rules, Section 1.1312, to address

    facilities for which no construction permit was required. Although construction of

    these facilities did not qualify as “actions which may have a significant

    environmental effect,” and thus did not trigger NEPA, the FCC nevertheless required

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 19 of 55

  • 7

    the licensee or applicant to submit information similar to that required for an EA

    before it would issue a license. Id. ¶18.

    Then, in 1990, the FCC amended Section 1.1312 to require pre-construction

    approval in limited circumstances where (i) the facilities were otherwise exempt

    from obtaining construction permits but (ii) the licensee or applicant determined that

    the proposed facility “may have a significant effect on the environment.” See In the

    Matter of Amendment of Envtl. Rules, First Report and Order, 5 FCC Rcd. 2942

    (1990). Id. ¶1.

    C. The Tribal Consultation Process

    NHPA and its implementing regulations distinguish between projects on tribal

    lands and those on non-tribal lands. For projects on tribal lands, tribes must concur

    that the project will have “no adverse effect” on “historical properties” before the

    project may proceed. See 54 U.S.C. § 302702. For projects on non-tribal lands,

    however, tribes serve as “consulting parties,” and may identify concerns, advise on

    identification and evaluation issues, comment on potential effects, and participate in

    the resolution of adverse effects. See 36 C.F.R. § 800.2(c)(2)(ii)(A), (a)(4); id.

    § 800.16(f). Consulting parties are entitled to have their views considered, but their

    concurrence in the outcome is not required. See id. § 800.6(c).

    For projects on non-tribal lands, the tribal consultation process was designed

    to work as follows: (1) tribes indicate the areas where they would like notification

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 20 of 55

  • 8

    of wireless infrastructure projects, in the Tower Construction Notification System

    (“TCNS”); (2) applicants enter proposed projects into the TCNS, which then notifies

    interested tribes; (3) tribes notify the applicant if they would like to consult on the

    project; (4) applicants provide consulting tribes with a Preliminary Submission

    Packet containing substantial information about the project; (5) tribes have an

    opportunity to comment; and (6) the tribes’ comments are included in the final

    Submission Packet, and, where the record so warrants, a finding of concurrence with

    a proposed “no properties” or “no effect” finding. See CTIA/WIA Comments at 9-

    10 (6/15/17) [JA-306-07].

    Before the Order, the tribal consultation process was plagued by delays,

    ambiguous procedures, and insufficient guidance regarding tribes’ role in the

    process. CTIA/WIA Comments at 10 [JA-307]. Many tribes consulted on an overly

    broad number of facilities, designating interest in geographic areas hundreds or even

    thousands of miles away from their ancestral homelands, id., and some tribes

    charged carriers exorbitant upfront fees for what they deemed “specialized

    evaluation” of a project. Id. The record includes the example of an application for

    collocation in a high school parking lot that drew an expression of interest from 24

    tribes, resulting in extensive costs and delays, with no countervailing benefit. See

    Crown Castle Comments at 39-40 (6/15/17) [JA-283-84].

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 21 of 55

  • 9

    Problems with the consultation process have seriously hindered the

    deployment of wireless facilities. Prior to the Order, the average time for tribes to

    complete a request for consultation was 110 days, with more than 30 percent of

    requests taking more than 120 days to complete. CTIA/WIA Comments at 6 [JA-

    303]. Meanwhile, only 0.33 percent of tribal reviews (without regard for the type of

    project or the size of the facility involved) resulted in a finding of adverse effect. Id.

    D. Small Cells and the Race to 5G

    Wireless providers are racing to expand their networks to keep up with

    exponential growth in demand for wireless service. As smart devices have become

    ubiquitous, wireless data consumption grew 25-fold from 2010 to 2015, including a

    100 percent increase in 2015 alone. CTIA Comments at 8-9 (3/8/17) [JA-289-90].

    This increase in demand is illustrated by data usage on the Sprint network in and

    around the stadiums during the last few Super Bowls: the total data usage in 2017

    was more than three times greater than 2016, which in turn was eight times greater

    than in 2015. Sprint Comments at 9-10 6/15/17 [JA-382-83].

    To address the growing demand for speed and capacity and to enable a wide-

    range of additional technical enhancements, wireless providers are turning to next-

    generation 5G networks, which offer superior speed and latency performance. 5G

    networks utilize network densification, which employs small cells to reuse the same

    frequency bands more often and in smaller areas than traditional macro cells. See

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 22 of 55

  • 10

    Sprint Comments at 10 [JA-383]. To meet growing demand, wireless carriers will

    need to deploy approximately 300,000 small cells in the next few years.

    AccentureStrategy, Accelerating Future Economic Value From the Wireless

    Industry at 6 (2018). While there will be far more small cells, their individual impact

    will pale next to that of traditional wireless facilities: A typical small cell is the size

    of a shoe box, a pizza box, or a fire extinguisher, and can be mounted on a utility

    pole, streetlight, traffic signal, or building with limited additional equipment on the

    ground. See Sprint Comments at 12 [JA-385]; CTIA, The Global Race to 5G at 13

    (April 2018). By contrast, traditional macro sites require a tall support tower with

    numerous antennas mounted on top, and they frequently require a fenced off ground

    area and one or more equipment cabinets. Sprint Comments at 11-12 [JA-384-85].

    E. The FCC’s Order

    In April 2017, the FCC issued a notice of proposed rulemaking seeking

    comment on ways to remove or reduce impediments to wireless network

    infrastructure investment and deployment. In the Matter of Accelerating Wireless

    Broadband Deployment by Removing Barriers to Infrastructure Inv., Notice of

    Proposed Rulemaking, 32 FCC Rcd. 3330 (2017) (the “NPRM”). The Commission

    committed to take “a comprehensive fresh look at our rules and procedures

    implementing” NEPA and NHPA. Id. ¶23. The NPRM noted that the FCC’s

    complicated environmental and historic review processes “increase the costs of

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 23 of 55

  • 11

    deployment and pose lengthy and often unnecessary delays, particularly for small

    facility deployments.” Id. ¶33.

    On March 30, 2018, the FCC released the Order, which found that there is no

    longer any public interest justification for subjecting deployments of small wireless

    facilities to the Commission’s discretionary environmental review procedures under

    Section 1.1312 and, therefore, that there is no longer even an arguable basis for

    concluding that they are undertakings under NHPA or major federal actions under

    NEPA. The Order also modified certain procedures for NHPA and NEPA review

    of facilities that remain subject to Section 1.1312.1

    After filing petitions for review of the Order, Petitioners filed two emergency

    motions for stay pending judicial review, which the Court denied on August 15,

    2018.

    SUMMARY OF ARGUMENT

    1. The FCC properly determined that the deployment of small wireless

    facilities is neither an “undertaking” under NHPA nor a “major federal action” under

    NEPA. These statutes do not apply every time a federal “license,” “permit,” or

    “approval” is issued. Rather, an agency must exert control or exercise substantial

    discretion over a given project for the activity to qualify as an “undertaking” or a

    1 While Respondent-Intervenors support the entirety of the FCC’s actions in the

    Order, this brief only addresses those actions pertaining to small cells.

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 24 of 55

  • 12

    “major federal action.” See Sugarloaf Citizens Ass’n v. FERC, 959 F.2d 508, 513

    (4th Cir. 1992); Karst, 475 F.3d at 1295.

    The FCC has never concluded that the mere issuance of a license to transmit

    radiofrequencies in a given geographic area is enough to trigger review under NEPA

    and NHPA. The agency has instead long held that its involvement only rises to the

    requisite level of control if a given facility either (i) is subject to the FCC’s tower

    registration and approval process or (ii) may have a significant environmental impact

    and is thus required to undergo an EA under Section 1.1312(b) of the FCC’s rules.

    See CTIA-Wireless Ass’n v. FCC, 466 F.3d 105, 112-18 (D.C. Cir. 2006). Assessing

    the public interest under the Communications Act, the FCC has made a reasoned

    determination that the burdens of subjecting small wireless facilities to the agency’s

    discretionary, residual environmental review outweigh the limited benefits of that

    review. Order ¶¶63-71 [JA-827-31]. For small wireless facilities that are not subject

    to the tower registration and approval process, the effect of excluding them from

    environmental review under Section 1.1312(b) is to remove the federal control or

    discretion over those facilities that arguably triggers NEPA and NHPA.

    Petitioners’ argument that the FCC’s issuance of geographic spectrum

    licenses, standing alone, constitutes federal control or involvement over small

    wireless facilities would constitute a radical expansion of NEPA and NHPA. For an

    “undertaking” or “major federal action” to occur, the FCC must possess “actual

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 25 of 55

  • 13

    power” to control the project. See Sugarloaf, 959 F.2d at 513; Big Bend

    Conservation All. v. FERC, 896 F.3d 418, 423-25 (D.C. Cir. 2018). While the

    Commission has, in the past, found that site-based licensing and discretionary,

    residual environmental review constitute such “actual power,” it has never held that

    the issuance of a geographic spectrum license, standing alone, meets that threshold.

    In fact, a geographic license falls far short; it does not determine what facilities a

    licensee will use to provide service using the licensed spectrum or where those

    facilities will be located. Indeed, parties can and do construct small wireless

    facilities, such as unlicensed Wi-Fi hotspots, without a spectrum license at all. The

    issuance of geographic licenses, therefore, is so attenuated from the actual

    deployment of small wireless facilities that it cannot constitute an “undertaking” or

    a “major federal action.”

    2. There is no merit to NRDC’s argument that the FCC was required to

    conduct a NEPA review before issuing the Order. Procedurally, NRDC’s argument

    is barred because it was not raised below. 47 U.S.C. § 405(a). Even if it was, under

    established precedent, the Order itself was not a major federal action, and the

    Commission was not required to reconsider the environmental effects of wireless

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 26 of 55

  • 14

    facilities. See Cmty. Nutrition Inst. v. Young, 773 F.2d 1356, 1362–63 (D.C. Cir.

    1985).

    STANDARD OF REVIEW

    This Court defers to agency decisions under the Administrative Procedure

    Act, 5 U.S.C. § 702(2)(A), unless they are “arbitrary, capricious, an abuse of

    discretion, or otherwise not in accordance with law.” SNR Wireless LicenseCo, LLC

    v. FCC, 868 F.3d 1021, 1029 (D.C. Cir. 2017), cert. denied sub nom. SNR Wireless

    LicenseCo v. FCC, 138 S. Ct. 2674 (2018) (quoting 5 U.S.C. § 706(2)(A)). This

    review is “deferential,” Sorenson Commc’ns, LLC v. FCC, 897 F.3d 214, 230 (D.C.

    Cir. 2018) (quotations omitted), and a court cannot “substitute [its] judgment for that

    of the agency,” SNR Wireless, 868 F.3d at 1029; see also Verizon Tel. Companies v.

    FCC, 292 F.3d 903, 909 (D.C. Cir. 2002) (applying “highly deferential standard” to

    FCC decisions “in an area of rapidly changing technological and competitive

    circumstances’”) (quoting Sprint Commc’ns Co. L.P. v. FCC, 274 F.3d 549, 556

    (D.C. Cir. 2001)); Cellco P’ship v. FCC, 357 F.3d 88, 93 (D.C. Cir. 2004).

    ARGUMENT

    I. THE DEPLOYMENT OF SMALL WIRELESS FACILITIES IS NEITHER A “MAJOR FEDERAL ACTION” NOR AN

    “UNDERTAKING.”

    The FCC properly concluded in the Order that the deployment of small

    wireless facilities is neither a “major federal action” under NEPA nor an

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 27 of 55

  • 15

    “undertaking” under NHPA. The FCC previously determined—and this Court

    affirmed—that wireless facility deployments pursuant to geographic area licenses

    may nevertheless constitute “undertakings” in two sharply limited contexts: (1)

    where facilities are over 200 feet or near airports and are thus subject to the FCC’s

    tower registration and approval process; and (2) where facilities not subject to pre-

    construction FCC authorization (like small wireless facilities) are nevertheless

    required, under Section 1.1312(b), to obtain an environmental assessment prior to

    deployment. See CTIA, 466 F.3d at 112-18; 47 C.F.R. § 1.1312(b). For small

    wireless facilities that are not subject to the FCC’s tower registration and approval

    process, the only possible basis for concluding that they are “undertakings” is if they

    are subject to environmental review under the FCC’s “limited approval authority”

    set forth in Section 1.1312(b). See CTIA, 466 F.3d at 112-18; Order ¶¶36-38 [JA-

    817-19]. Where the FCC chooses to exercise its Section 1.1312 public interest

    authority to require NEPA-like environmental review, the agency arguably becomes

    sufficiently intertwined in wireless facility deployments so as to trigger NEPA and

    NHPA. See id. ¶51 [JA-823-24]. But when it decides that environmental review is

    contrary to the public interest, as it has with small cells, their deployment is a private

    rather than federal undertaking.

    The FCC revisited its “limited approval authority” in the Order, reasonably

    concluding under its Communications Act public interest mandate that there is no

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 28 of 55

  • 16

    justification for subjecting small wireless facilities to discretionary, residual

    environmental review under Section 1.1312. Order ¶59 [JA-826]. The agency

    relied on a robust record detailing the harms associated with subjecting such

    deployments to Section 1.1312’s onerous requirements. See id. ¶¶60-81[JA-826-

    38].

    By amending Section 1.1312 to exclude small wireless facilities from

    environmental review, the FCC eliminated the sole predicate federal involvement

    that could arguably have met the standard for “undertakings” and “major federal

    actions” and, thus, there is no basis to subject such deployments to NEPA or NHPA

    review. See id. ¶¶58-59 [JA-826]. For personal wireless services, the Commission

    issues licenses for the use of certain bands of spectrum in defined geographic areas

    (sometimes spanning several states), but it does not approve specific sites or

    facilities. Longstanding precedent confirms that the Commission’s limited role in

    these services (if any) fails to rise to the level of federal entanglement required to

    find that small cell deployments are “undertakings” or “major federal actions.” See

    Lee, 877 F.2d at 1058; Big Bend, 896 F.3d at 423-25. Indeed, this Court has

    repeatedly confirmed that NEPA and NHPA must be read narrowly to avoid

    federalizing a broad swath of projects and saddling federal agencies with limitless

    review obligations. See Lee, 877 F.2d at 1058.

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 29 of 55

  • 17

    A. The FCC’s Determination That Section 1.1312 Does Not Apply To The Deployment Of Small Wireless Facilities Was Both

    Reasonable and Amply Supported by the Record.

    In the Order, the FCC, acting pursuant to its statutory mandate, concluded that

    (1) encouraging the deployment of small wireless facilities will effectuate the

    purposes of the Communications Act by promoting rapid deployment of 5G

    networks to meet the explosive demand for wireless services; and (2) the public

    interest does not support applying Section 1.1312 to small wireless facilities. The

    FCC relied on a robust record demonstrating that small wireless facilities do not

    cause adverse effects to tribal sites or historic properties. Myriad stakeholders

    submitted comments supporting the Order’s conclusions, confirming that the FCC

    had ample bases on which to determine that the public interest would not be served

    by subjecting small wireless facilities to Section 1.1312 review.

    Petitioners do not dispute that the FCC has authority to adopt, repeal, or

    modify rules under its public interest authority. Instead, Petitioners contest the

    FCC’s reasons for exercising that authority, asserting that the Order’s exclusion of

    small wireless facilities from the scope of Section 1.1312 is arbitrary. See

    Keetoowah Br. at 35-36. These claims are subject to a “highly deferential” standard

    of review that Petitioners cannot overcome. Sorenson, 897 F.3d at 230; Cellco

    P’ship, 357 F.3d at 93. Petitioners attempt to shift their heavy burden to the FCC by

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 30 of 55

  • 18

    arguing that the Order amounts to a policy reversal lacking justification. See

    Keetoowah Br. at 34-35. But the Commission had never squarely addressed whether

    the public interest is served by applying Section 1.1312 to small wireless facilities,

    a fact that Petitioners do not dispute. Order ¶61 [JA-826]. Moreover, to the extent

    the Order constitutes a change in position, the FCC has properly acknowledged and

    explained its change, and such determination is entitled to highly deferential review.

    See FCC v. Fox Television Stations, Inc., 556 U.S. 502, 514-15 (2009).

    1. The FCC Reasonably Determined That The Review Process

    Triggered By Section 1.1312 Is Unnecessarily Burdensome.

    In analyzing for the first time whether applying Section 1.1312 to small

    wireless facilities is in the public interest, the FCC reasonably concluded, based on

    a robust factual record, that Section 1.1312 imposes unnecessary burdens in the

    context of small wireless facilities. This Court must uphold the Order so long as the

    Commission made factual findings supported by substantial evidence, considered

    the relevant factors, and “articulate[d] a rational connection between the facts found

    and the choice made.” EchoStar Commc’ns Corp. v. FCC, 292 F.3d 749, 752 (D.C.

    Cir. 2002) (quotations omitted). There is no question that the Order meets this

    standard.

    The Order is consistent with Congress’ directive that the Commission should

    not impose unnecessary regulatory burdens on wireless facilities deployment. When

    Congress adopted Section 319(d) of the Communications Act, eliminating

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 31 of 55

  • 19

    Commission approval requirements for wireless communications facilities and

    precluding construction permit requirements, it intended to facilitate wireless

    infrastructure deployment by reducing the agency’s involvement in the buildout of

    individual facilities. Order ¶63 [JA-827]. It was thus eminently reasonable for the

    FCC to conclude that, as to small wireless facilities, replacing the construction

    permit approval process with review under Section 1.1312 “risks replicating the

    harmful effects that Congress expressly sought to eliminate.” Id.

    Petitioners do not challenge the FCC’s finding that small wireless facilities

    will be necessary to support 5G services. Order ¶64 [JA-827-28]. Rather,

    Petitioners contend that the costs of tribal consultation do not impede the deployment

    of small cells. See Keetoowah Br. at 16-17. But Petitioners offer no support for

    their contention aside from the mere assertions that “carriers are multi-billion dollar

    companies with significant revenue streams” and abusive fees are not widespread.

    Id. at 17-18.

    By contrast, the FCC considered the extensive evidence in the record of the

    “substantial, rising, and unnecessary costs for deployment” that stem directly from

    subjecting small wireless facilities to Section 1.1312 review and the substantial delay

    that review imposes on deployment. Order ¶¶11-15; 68-71 [JA-809-11; 828-31].

    The Order cites specific data in the record regarding the costs to Sprint of completing

    environmental assessments, id. ¶68 [JA-828-29], the substantial cost to Verizon as a

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 32 of 55

  • 20

    percentage of total project costs, id. ¶69 [JA-829-30], and expected increases in these

    costs corresponding to accelerated deployments, id. The Order also cites

    uncontroverted data from AT&T that the cost of complying with review

    requirements would fund over 1,000 additional small cell sites, and that eliminating

    these requirements would reduce deployment timelines by 60-90 days. Id.

    Similarly, the FCC considered evidence from Sprint that the $23 million it had

    already spent on historic reviews could have funded an additional 657 new sites and

    that, with reforms to tribal review fees, Sprint could construct 13,408 new sites for

    what 10,000 sites previously cost. Id. ¶14 [JA-811]. With such overwhelming

    evidence, the Commission’s conclusion that the review process is unnecessarily

    burdensome hardly can be considered arbitrary. See GTE Serv. Corp. v. FCC, 782

    F.2d 263, 273 (D.C. Cir. 1986) (affirming FCC conclusion supported by ample

    evidence in the record).

    2. The FCC Reasonably Determined That Small Wireless

    Facilities Are Unobtrusive and Do Not Raise the Same

    Concerns As Macro Cells.

    The FCC also properly assessed the differences between small cells and macro

    cells, concluding that regardless of whether the public may benefit from Section

    1.1312 review of larger facilities, there are no appreciable benefits from requiring

    such review of small wireless facilities. Order ¶72 [JA-831-32]. The Order’s

    approach to small wireless facilities is in lockstep with the FCC’s approach to other

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 33 of 55

  • 21

    small facilities whose impact is inconsequential, such as consumer signal boosters,

    Wi-Fi routers, and unlicensed equipment, all of which operate pursuant to FCC

    authorizations and are excluded from Section 1.1312. See id. ¶43 [JA-43]. The

    FCC’s assessment of the costs and benefits of its own regulation is entitled to highly

    deferential review. See Consumer Elecs. Ass’n v. FCC, 347 F.3d 291, 304 (D.C.

    Cir. 2003); Ctr. for Auto Safety v. Peck, 751 F.2d 1336, 1342 (D.C. Cir. 1985)

    (recognizing narrow scope of review applicable to agency consideration of “costs

    and benefits of alternative policies”).

    The scope of the Order is limited in five ways, reflecting the reasonableness

    of the FCC’s approach. First, the Order only applies to small wireless facilities,

    which can be no more than three cubic feet in volume and carry associated wireless

    equipment no larger than 28 cubic feet. Order ¶¶75-76 [JA-833-35]. These facilities

    are analogous to those that the Commission has previously excluded from review.

    See Nationwide Programmatic Agreement for the Collocation of Wireless Antennas,

    47 CFR Part 1, Appx. B, §§ VI.A.5.a & b. Second, the Order only applies to

    facilities deployed on structures below a certain height threshold (50 feet or no more

    than 10 percent taller than other structures in the area). Order ¶74 [JA-832-33].

    Third, the Order does not apply at all to facilities deployed on tribal lands. Id. ¶17

    [JA-812]. Fourth, the Order does not alter any reviews conducted by states or

    localities. Id. ¶77 [JA-835-36]; 47 U.S.C. § 332(c)(7)(A). Fifth, the Order does not

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 34 of 55

  • 22

    apply to small wireless facilities subject to the FCC’s antenna structure registration

    process. Id. ¶45 [JA-821].

    The record provides ample support for the FCC’s conclusion that the cost of

    environmental review for the narrow class of facilities covered by the Order far

    outweighs its benefits. Id. ¶81 [JA-838]. Numerous commenters explained that

    reviews of proposed deployments rarely result in a finding of significant

    environmental impact or adverse impact on historic properties. See Crown Castle

    Comments at 34 [JA-278] (noting that Crown Castle has never received a negative

    report or response from a Tribal Nation for a small cell deployment); Sprint

    Comments at 6 [JA-379] (describing no possible adverse effects); Verizon

    Comments at 44 (6/15/17) [JA-413] (only 0.3% of requests for tribal review resulted

    in findings of adverse effect); Texas Historical Commission 6/2/17 ex parte letter at

    1 [JA-128] (stating that 0.25 percent of projects “were found to have an adverse

    effect on historic properties” since 2014, including at least some projects involving

    small wireless facility deployments); Texas Historical Commission 3/15/18 ex parte

    letter at 1 [JA-793] (citing one lone instance of concern associated with a small

    wireless facility deployment). By contrast, the FCC recognized that continuing to

    subject small wireless facilities to Section 1.1312 would have “detrimental effects

    on the roll-out of advanced wireless service.” Order ¶79 [JA-837].

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 35 of 55

  • 23

    Finally, the Petitioners’ characterization of the Order as a policy reversal is

    simply wrong. The Order merely clarifies the application of an existing rule to new

    technologies. The 2014 order cited by Petitioners did not purport to consider

    whether it was in the public interest to subject small wireless facilities to Section

    1.1312. See In the Matter of Acceleration of Broadband Deployment by Improving

    Wireless Siting Policies, Report and Order, 29 FCC Rcd. 12865 ¶84 (2014). Rather,

    the 2014 order took for granted that, because small wireless facilities were subject

    to Section 1.1312 review at the time, their deployment constituted a federal

    undertaking. Id. Accordingly, the question before the Commission in 2014 was not

    whether applying Section 1.1312 to small wireless facilities was in the public

    interest, but, instead whether it was proper to categorically exclude small wireless

    facilities from environmental review. Id. ¶77. While the FCC concluded that the

    record before it—at a time when small cells were much less prevalent—was

    insufficient to justify a categorical exclusion, id. ¶86, it did not conclude that small

    wireless facilities must affirmatively be subject to environmental review, and thus

    did not adopt a policy that, Petitioners erroneously claim, the Order now reverses.

    Cf. Chem. Mfrs. Ass’n v. EPA, 919 F.2d 158, 170 (D.C. Cir. 1990) (finding no

    reversal where agency had not adopted a “settled course of behavior”).

    By contrast, here the FCC made a threshold determination under its organic

    statute that it should not extend Section 1.1312 to small wireless facilities. The effect

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 36 of 55

  • 24

    of that decision was to remove any credible argument that deployment of small

    wireless facilities is an “undertaking” or “major federal action,” rendering moot the

    question whether a categorical exclusion for small wireless facilities is appropriate.

    B. The FCC Properly Determined That, Other Than Section 1.1312 Review, The FCC Has No Involvement In The Deployment Of

    Small Wireless Facilities.

    Carriers have long been free to choose when and where to deploy small

    wireless facilities, subject to lawful state and local regulations, with only the residual

    possibility of limited FCC oversight. By removing small wireless facilities from the

    scope of Section 1.1312, the FCC has reduced its already negligible involvement in

    the deployment of these facilities to zero. Order ¶59 [JA-826]; CTIA, 446 F.3d at

    112-18. Petitioners’ effort to shoehorn aspects of FCC licensing that are only

    tangentially related to the construction of small cells, such as geographic licensing,

    into the requisite federal action are unavailing: The FCC does not finance small

    wireless facility deployments, does not require preconstruction authorization, does

    not license or approve individual facilities, and now plays no role whatsoever in

    siting decisions. Courts have never recognized such a de minimis level of federal

    “involvement” in a project as an “undertaking” or a “major federal action,” and this

    case should be no different.

    Agencies must analyze two issues when deciding whether an activity

    constitutes an “undertaking” or a “major federal action”: (1) does the agency exert

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 37 of 55

  • 25

    control or exercise substantial discretion over the project so as to be under the

    purview of NHPA or NEPA (“federal involvement inquiry”); and (2) if the agency

    is so involved, does the action result in effects on the environment or historic

    properties (“effects inquiry”). See 36 C.F.R. § 800.16(y); 40 C.F.R. § 1508.18;

    Karst, 475 F.3d at 1295. Unless an action qualifies under both the federal

    involvement inquiry and the effects inquiry, it is not subject to NEPA or NHPA.

    Petitioners cannot satisfy either standard. The FCC has no involvement in the

    deployment of small wireless facilities, and even assuming, arguendo, that it was

    involved, small wireless facilities by definition “pose little or no risk” of

    environmental or historic preservation effects. See Order ¶42 [JA-820]; supra,

    Section I.A.2.

    1. “Undertaking” And “Major Federal Action” Only Apply

    When There Is Federal Control.

    Long-standing precedent and common sense dictate that a federal agency

    must exercise control or otherwise show substantial involvement in all aspects of a

    project for the activity to qualify as an “undertaking” or a “major federal action.”

    See Citizens Against Rails–to–Trails v. Surface Transp. Bd., 267 F.3d 1144, 1151

    (D.C. Cir. 2001); Karst, 475 F.3d at 1295. Congress enacted NEPA and NHPA to

    ensure that, when the federal government acts, it remains mindful of historic and

    environmental concerns. See Lee, 877 F.2d at 1058 (“It is their own nest Congress

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 38 of 55

  • 26

    has asked the agencies not to foul.”); Act of Oct. 15, 1966, Pub. L. No. 89-665, (80

    Stat.); S. Rep. No. 91-296, at 6 (1969).

    Because NEPA and NHPA are “look before you leap” directions aimed

    exclusively at the federal government, neither extends to private action. Federal

    control is the hallmark of an “undertaking,” with courts evaluating the agency’s

    degree of discretion, whether federal aid has been given, and whether the overall

    level of federal involvement is sufficient to convert private action into federal

    activity. Ringsred v. City of Duluth, 828 F.2d 1305, 1308 (8th Cir. 1987). At a

    minimum, a federal agency must possess “actual power” to control the project for

    an “undertaking” or “major federal action” to occur. See Sugarloaf, 959 F.2d at 513;

    see also Big Bend, 896 F.3d at 423-25 (declining to require NEPA review where

    “the bulk of” a pipeline project was “not subject to federal jurisdiction”); Defs. of

    Wildlife v. Andrus, 627 F.2d 1238, 1244 (D.C. Cir. 1980) (mere federal “approval”

    of a private act does not create a “major federal action” unless “the federal

    government undertakes some ‘overt act’ in furtherance of” the project).

    Petitioners fail to grapple with this well-established precedent. Instead, they

    assert, without authority, that “undertaking” and “major federal action” should be

    read broadly, to encompass private, small wireless facility deployments over which

    the FCC exercises no control. See Blackfeet Br. at 19-20. This Court has never

    taken such an expansive view.

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 39 of 55

  • 27

    Instead, this Court has long confirmed that “undertaking” and “major federal

    action” must be read narrowly, to encapsulate “only . . . projects or programs [federal

    agencies] initiate or control through funding or approvals.” Lee, 877 F.2d at 1058

    (emphasis added). In Lee, for example, this Court clarified that NHPA’s reach is

    narrow, holding the statute did not apply to a proposed D.C. correctional facility

    “because the planning and construction of the facility was neither funded nor

    dependent on approval by a federal agency.” Id. at 1058. Likewise, in Sheridan

    Kalorama Historical Association v. Christopher, this Court cautioned against

    adopting overly capacious interpretations of NHPA’s terms that would “read all

    limitations out of the Act.” 49 F.3d 750, 756 (D.C. Cir. 1995) (concluding that the

    failure to disapprove a building proposal “did not render the project” an

    “undertaking”).2

    Other Circuit Courts agree with this approach. See, e.g., Ringsred, 828 F.2d

    at 1308 (8th Cir.); Sugarloaf, 959 F.2d at 515 (4th Cir.); Norton, 240 F.3d at 1262-

    63 (10th Cir.). In Ringsred, for example, the Eighth Circuit held that the Secretary

    of Interior’s approval of contracts related to a private parking ramp “were so

    incidental” to the project that neither NHPA nor NEPA applied. Ringsred, 828 F.2d

    2 Petitioners wrongly claim that Sheridan interprets “undertaking” “broadly,”

    Keetoowah Br. at 25, but Sheridan explicitly rejects a broad theory of “undertaking,”

    cautioning against “extending the reach of § 106 beyond the grasps of its terms.” 49

    F.3d at 756.

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 40 of 55

  • 28

    at 1308. Although the Secretary’s approval of the contracts “did give him ‘a factual

    veto power’” over the project, the court concluded that the Secretary’s control over

    the ramp was “not significant enough to establish a major federal action.” Id.; see

    also Save the Bay, Inc. v. U.S. Corps of Eng’rs, 610 F.2d 322, 327 (5th Cir. 1980)

    (“a private project does not become a ‘major Federal action’ merely because of some

    incidental federal involvement”).

    The FCC has no involvement in small wireless facility deployment, let alone

    “control” of these private actions. As in Ringsred, “[n]o federal action is a legal

    condition precedent” to the deployment of small wireless facilities. Id. at 1308.

    Where Section 1.1312 review is not required, carriers may deploy small wireless

    facilities without any FCC approval at all. The deployment of such facilities cannot

    be considered an “undertaking” or a “major federal action” under any reading.

    2. Petitioners Cannot Recast Spectrum Licenses As

    Infrastructure Permits.

    Without Section 1.1312, Petitioners are left to spin an alternate narrative of

    FCC involvement: That the FCC’s issuance of broad geographic area spectrum

    licenses is enough to federalize the deployment of small wireless facilities. See

    Keetoowah Br. at 24; NRDC Br. at 12-13. But this radical reimagining of NEPA

    and NHPA’s scope relies on a misapprehension of the authority conveyed by

    geographic area spectrum licenses. It also ignores long-standing precedent

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 41 of 55

  • 29

    confirming that government involvement of the type involved in spectrum licensing

    is of no moment.

    Spectrum licenses grant the right to use spectrum, not the right to deploy or

    build infrastructure. See Order ¶85 [JA-839-40]. A geographic area spectrum

    license does no more than authorize wireless operations on specific frequencies in a

    given geographic area,3 and gives the FCC no role in individual deployment

    decisions. See id. Instead, the choice of where and when to deploy any particular

    wireless facility, including a small wireless facility, lies with the licensee and does

    not require an FCC license, permit, or any other form of FCC approval any more

    than a person’s decision of where to place a WiFi router in her home. See id.; see

    also 47 U.S.C. § 319(d) (precluding construction permits for wireless

    communications facilities); 47 C.F.R. § 24.11 (declaring that applications for

    individual wireless sites “are not required and will not be accepted” in conjunction

    with geographic area licenses); 1986 Order ¶12 (recognizing the role of local, state,

    regional, or local land use authorities).

    3 The Order distinguishes between geographic area licenses, which grant

    licensees blanket authority to transmit on specific frequencies in a given geographic

    area, and site-by-site licenses, which grant licensees authority to transmit on specific

    frequencies at specific sites. See Order ¶36 [JA-817-18]. Small wireless facilities

    subject to the site-by-site licensing regime must continue to comply with

    environmental and historic preservation review. Id. References to “spectrum

    licenses” and the FCC’s “spectrum licensing authority” herein thus relate only to

    geographic area licenses.

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 42 of 55

  • 30

    Courts have repeatedly rejected claims that this kind of peripheral federal

    involvement can transform the project into an “undertaking” or a “major federal

    action.” See, e.g., Lee, 877 F.2d at 1058 (construction of D.C. correctional facility

    not an “undertaking” where project not subject to federal control or approval);

    Sugarloaf, 959 F.2d at 513-15 (certification of incinerator too “ministerial” to be an

    “undertaking”); Norton, 240 F.3d at 1263 (acquisition of land not a “major federal

    action” where agency exercised “no discretion” over project); Am. Airlines, Inc. v.

    Dept. of Transp., 202 F.3d 788, 803-04 (5th Cir. 2000) (decision allowing increased

    flights not a “major federal action” because agency lacked “significant discretion”);

    Ringsred, 828 F.2d at 1308. Absent substantial federal involvement in all aspects of

    a project, agency action is merely “marginal” and does not trigger review. Sierra

    Club v. Penfold, 857 F.2d 1307, 1314 (9th Cir. 1988); see also Bus. & Residents All.

    of East Harlem v. Jackson, 430 F.3d 584, 592 (2d Cir. 2005) (a federal agency must

    have power to “approve or otherwise control” a project for it to fall within NHPA’s

    scope).

    The FCC likewise has never viewed geographic area spectrum licensing as

    providing the federal nexus required to convert the deployment of facilities into

    “undertakings” and “major federal actions.” Order ¶84 [JA-839]. Similar

    technologies, like signal boosters, also operate on FCC licensed spectrum but have

    never been subject to NEPA or NHPA. Deployed in homes and businesses across

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 43 of 55

  • 31

    the country, signal boosters use antenna technology to amplify cell signals between

    mobile devices and wireless networks. Like small cells, they operate pursuant to

    geographic area spectrum licenses. See Amendment of Parts 1, 2, 22, 24, 27, 90 and

    95 of the Commission's Rules to Improve Wireless Coverage Through the Use of

    Signal Boosters, Report and Order, 28 FCC Rcd. 1663 (2013). Yet the FCC has

    never considered the authorized use of signal boosters pursuant to a spectrum license

    as sufficient to transform the deployment of those facilities into “undertakings” or

    “major federal actions.” Order ¶84, n.170 [JA-839]. Nor could it; as here, the FCC’s

    tangential involvement in authorizing spectrum use is not enough to federalize the

    deployment of signal boosters.4 By contrast, the FCC has historically treated its site-

    specific licensing decisions as sufficient to trigger NEPA and NHPA. See Order

    ¶36 [JA-817-18].

    Geographic area spectrum licenses are not, as Petitioners suggest, a legal

    prerequisite to deploying wireless infrastructure. See Keetoowah Br. at 24-30.

    Instead, geographic area spectrum licenses are only necessary to provide wireless

    service using specified frequencies. Order ¶85 [JA-839-41]. But while a spectrum

    license may be required to operate a small wireless facility, neither a geographic

    4 The same is true of microwave news gathering trucks, with masts up to around

    50 feet tall, and certain licensed satellite dishes. These facilities would not be

    deployed but for FCC authorizations permitting operations on licensed spectrum, yet

    their implementation has never been subject to NEPA or NHPA.

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 44 of 55

  • 32

    area spectrum license nor any other form of FCC approval is required to build a

    particular small wireless site. See id.; see also 47 C.F.R. § 24.11.

    It is well established that “where federal approvals are not legal predicates to

    private actions,” the approvals are neither “major federal actions” nor

    “undertakings.” State of N.J., Dept. of Envtl. Prot. & Energy v. Long Island Power

    Auth., 30 F.3d 403, 417 (3d Cir. 1994); see also Sugarloaf, 959 F.2d at 512-13.

    Private projects, like small wireless facility deployments, are federalized for review

    purposes only if the project “cannot begin or continue without prior approval by a

    federal agency and the agency possesses authority to exercise discretion over the

    outcome.” Sugarloaf, 959 F.2d at 512 (internal quotations and citations omitted).

    Sugarloaf thus held that FERC’s certification of an incinerator as a small power

    facility did not amount to a “major federal action” because the facility legally could

    have been built without the agency’s certification. Id. at 513-14.

    So too here. Wireless service providers or infrastructure owners are not

    legally required to obtain a geographic area spectrum license—or any other form of

    FCC approval—before constructing small wireless facilities. See Order ¶86 [JA-

    841-42]. The issuance of geographic service licenses is typically “remote in both

    time and regulatory reach” from the deployment of small wireless facilities. Id. ¶88

    [JA-842-43]. In fact, many small wireless facilities are deployed by private entities

    that do not hold FCC spectrum licenses at all. See Crown Castle Comments at 3

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 45 of 55

  • 33

    [JA-274]. Private actors make marketplace decisions about deployment plans in light

    of applicable state and local zoning requirements. Id. FCC action is not a “legal

    requirement” for these deployments, and the agency retains no “discretion” over

    them. Long Island Power Auth., 30 F.3d at 417.

    Nor could the agency “take environmental [or historical] considerations into

    account before acting” to issue spectrum licenses. Id. The physical deployment of

    particular infrastructure occurs in a manner and at locations that the Commission

    cannot foresee, let alone direct, at the time of spectrum licensing. Order ¶85 [JA-

    839-41]. While it is safe to assume that some wireless facilities will be built

    following spectrum licensing, the Commission cannot know when, where, or what

    kind of facilities will be deployed. There is thus “no plausible way” for the FCC to

    meaningfully assess the environmental and historic effects of particular small cell

    deployments. Order ¶89 [JA-843]; see Sierra Club v. FERC, 827 F.3d 36, 46-47

    (D.C. Cir. 2016) (agency need only assess effects that are “sufficiently likely to

    occur that a person of ordinary prudence would take it into account”).

    That principle is amply demonstrated by the development of technology that

    has led to the need for small cell deployment. When geographic wireless licenses

    were first issued, technology at that time required construction of macro sites. To

    meet growing demand, providers now need to deploy more wireless facilities, but

    evolving technology allows these deployments to utilize smaller equipment. These

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 46 of 55

  • 34

    facilities are still being deployed under the aegis of the carrier’s existing FCC

    geographic area license, without the need to return to the agency for modification or

    revision of that license. For example, Sprint’s recent small cell deployments utilize

    its existing 2.5 GHz licenses. See Sprint Reaches Nationwide LTE Advanced

    Milestone, https://newsroom.sprint.com/quarterly-network-update.htm; see also

    AT&T Comments at 5-6 (6/15/17) [JA-260-61] (noting plans to install small cells

    around the country); What is Small Cell Technology,

    https://www.verizon.com/about/our-company/5g/what-small-cell-technology

    (documenting Verizon’s countless recent small cell deployments). The fact that the

    Commission has no control over whether and how carriers roll out these new

    technologies under their existing licenses underscores that geographic spectrum

    licenses do not provide the level of federal authority necessary to constitute a federal

    undertaking or major federal action. See State of S.D. v. Andrus, 614 F.2d 1190,

    1194 (8th Cir. 1980) (issuing a mineral patent is not a “major federal action” under

    NEPA because it is “not a precondition which enables a party to begin mining

    operations”).

    Nor do the performance and construction requirements associated with

    spectrum licenses provide control over small wireless facility deployment. See

    Keetoowah Br. at 26-27. The FCC’s construction requirements ensure that licensed

    spectrum is put to beneficial use by imposing coverage benchmarks upon licensees,

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 47 of 55

    https://newsroom.sprint.com/quarterly-network-update.htmhttps://www.verizon.com/about/our-company/5g/what-small-cell-technology

  • 35

    but they do not require the construction of particular facilities in any specific place.

    For example, Upper 700 MHz C Block licensees must provide coverage to at least

    75 percent of the population in its licensed geographic area by the end of its license

    term. See 47 C.F.R. § 27.14(h). But the FCC’s rules say nothing about how or where

    the licensee may choose to deploy wireless infrastructure.5 As far as the FCC is

    concerned, licensees are free to deploy any mix of communications infrastructure

    they like so long as the minimum construction and coverage requirements are met.

    Licensees can satisfy construction obligations without deploying any small wireless

    facilities, as they have done for over 20 years. Indeed, licensees could theoretically

    meet those obligations without deploying any permanent physical facilities.6 The

    mere fact that the FCC requires licensees to operate on their licensed spectrum does

    not reflect any federal control—or even involvement—in wireless siting decisions,

    particularly as they relate to small cells.

    NRDC cites New York v. Nuclear Regulation Comm’n, 681 F.3d 471 (D.C.

    Cir. 2012), to support its claim that the Order “unlawfully separat[es] the wireless

    services provided by a facility from the facility necessary to provide these services.”

    5 The FCC has no way to know how many small wireless facilities a licensee

    has deployed, let alone where they are located, making NEPA and NHPA review

    implausible.

    6 A carrier could, for example, use mobile cells on wheels to provide service

    throughout their licensed area, or in the future could use aerial platforms to provide

    wireless service in rural areas.

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 48 of 55

  • 36

    NRDC Br. at 12. NRDC misses the point. New York held that a Waste Confidence

    Decision (“WCD”) that would be used by the NRC as “a predicate to every decision

    to license or relicense a nuclear power plant” constituted a major federal action. New

    York, 681 F.3d at 476 (emphasis added). This Court reasoned that the WCD was

    inextricably intertwined with the NRC’s nuclear power plant licensing authority and

    thus qualified as a major federal action. See id. But the FCC’s geographic area

    licenses authorize carriers to use spectrum only and exert no licensing authority over

    small wireless facility deployments. The analogous circumstance would be if the

    NRC licensed entities on a state- or region-wide basis and then exercised no control

    over where, when, or how many nuclear facilities those entities went on to build—

    clearly a very different regulatory regime than this Court considered in New York.

    Thus, NRDC’s “asserted linkage” between small cell deployments and spectrum

    licensing is far “too attenuated” to provide the requisite level of federal involvement

    for an “undertaking” or a “major federal action.” Sierra Club, 827 F.3d at 47

    (requiring a “reasonably close causal relationship” akin to “proximate cause”

    between federal action and its effects).

    Moreover, NRDC’s argument adds nothing to Petitioners’ claim that the FCC

    unreasonably determined that small cell siting does not raise significant

    environmental concerns. In New York, it was undisputed that nuclear reactor siting

    is a major federal action raising environmental concerns, and this Court concluded

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 49 of 55

  • 37

    that the prior WCD was a predicate to those decisions. 681 F.3d at 476. But here,

    where the FCC reasonably concluded that small cell siting does not raise significant

    environmental issues, there is no reason why NEPA should be triggered by a prior

    geographic licensing decision. See supra, Section I.A.

    NRDC mischaracterizes the FCC’s actions here as unlawful “splintering

    tactics,” NRDC Br. at 12. It is true that agencies cannot evade NEPA and NHPA by

    artificially dividing a major federal action into “smaller, less significant actions.”

    Taxpayers Watchdog, Inc. v. Stanley, 819 F.2d 294, 298 (D.C. Cir. 1987). But “[t]he

    rule against segmentation . . . is not required to be applied in every situation.” Id.

    Where, as here, Petitioners can identify no “overarching federal project,” and federal

    permission is required only for the “discrete” and tangential ability to utilize

    spectrum, segmentation claims are misplaced. Standing Rock Sioux Tribe v. U.S.

    Army Corps of Eng’rs, 301 F.Supp.3d 50, 70 (D.D.C. 2018); see also Sierra Club v.

    U.S. Army Corps of Eng’rs, 990 F.Supp.2d 9, 37 (D.D.C. 2013) (noting “general

    reluctance to conclude that federal action with respect to a small portion of a

    pipeline” is sufficient to “federalize the entire project”). Applied as NRDC suggests,

    the anti-segmentation rule would expand NEPA and NHPA beyond recognition and

    federalize the entire wireless network ecosystem. Under this expansive view, the

    construction of carrier stores would arguably require NEPA and NHPA review: But

    for the FCC’s spectrum licenses authorizing a carrier to provide wireless service, the

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 50 of 55

  • 38

    stores would not be built. Although neither courts nor the FCC have ever understood

    the construction of carrier retail stores to be “undertakings” or a “major federal

    actions,” the “but for” test urged by Petitioners here could well lead to this absurd

    result. See Big Bend, 896 F.3d at 423-25 (rejecting a “but for” approach that would

    “improperly” extend NEPA’s reach).

    II. THE FCC WAS NOT REQUIRED TO CONDUCT ANY NEPA REVIEW BEFORE ISSUING THE ORDER.

    NRDC raises additional claims that are incorrect and not properly before this

    Court. NRDC asserts that the Order itself is a “major federal action significantly

    affecting the quality of the human environment” and contends that the FCC failed to

    prepare an EIS as required by NEPA. See NRDC Br. at 10-11. Because this

    argument was not raised below, it is outside the scope of this appeal. See 47 U.S.C.

    § 405(a) (“The filing of a petition for reconsideration shall not be a condition

    precedent to judicial review . . . except where the party seeking such review . . . relies

    on questions of fact or law upon which the Commission… has been afforded no

    opportunity to pass”); Free Access & Broad. Telemedia, LLC v. FCC, 865 F.3d 615,

    619 (D.C. Cir. 2017) (no jurisdiction to review agency analysis if not raised in

    petition for reconsideration); FiberTower Spectrum Holdings, LLC v. FCC, 782 F.3d

    692, 696 (D.C. Cir. 2015) (same); Environmentel, LLC v. FCC, 661 F.3d 80, 83

    (D.C. Cir. 2011).

    USCA Case #18-1129 Document #1770273 Filed: 01/25/2019 Page 51 of 55

  • 39

    In any event, NRDC is mistaken. The FCC’s issuance of the Order itself is

    not a “major federal action,” nor will it �