Transcript of Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with...
![Page 1: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/1.jpg)
Optimizing the utilization of your
multi-disciplinary resources
How to balance skills capacity with demand in a volatile multi–project
environment
Barry Muir
Managing Director
![Page 2: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/2.jpg)
The challenge
‘To continuously optimize the utilization of geographically dispersed, multi-disciplinary workforces,
…where each project has its own timeline, priority and competency requirements’
Steve Major, Petrofac
![Page 3: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/3.jpg)
Striking the right balance
The consequences of too much or too little spare resource are equally unpalatable
Re-assess whenever a change occurs in demand or supply
Improving Productivity reduces the challenge
![Page 4: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/4.jpg)
Striking the right balance
‘If fee earners could increase their billable time by 10 minutes per day, the average ACE member would generate 2.3% extra revenue.
Assuming no increase in costs/overheads are incurred, that could raise profits by 33%’
Association of Consulting Engineers Benchmarking, 2011
![Page 5: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/5.jpg)
Agenda
The challenge
What do you need to know?
What needs to be in place?– Roles– Processes
How well do you score?
Successfully bridging the gap
![Page 6: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/6.jpg)
1. What do you need to know?
Forecast demand v capacity – Where are the bottlenecks and under utilization?– Scenarios to show the impact of project awards & change
Productivity & Utilization– How effectively are our teams working?
Track outstanding requests for resource.– Managing the resource allocation process
Resource performance on each project – Is the resource plan still realistic?
![Page 7: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/7.jpg)
Forward loading 1
![Page 8: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/8.jpg)
Forward loading 2
![Page 9: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/9.jpg)
Forward loading 3
![Page 10: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/10.jpg)
Forward loading 4
![Page 11: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/11.jpg)
Scenarios
![Page 12: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/12.jpg)
Productivity
![Page 13: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/13.jpg)
Outstanding requests 1
![Page 14: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/14.jpg)
Outstanding Requests 2
![Page 15: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/15.jpg)
Resource performance on each project
Could requireanother 40 days!
![Page 16: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/16.jpg)
If individual plans are unrealistic…..
![Page 17: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/17.jpg)
2. What needs to be in place?
Key Roles
Demand management
Resource allocation
Progress tracking
![Page 18: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/18.jpg)
2.1 Key Roles
Line managers – – maintaining the supply
Project managers – Defining the demand
Senior managers– Assign priorities and resolve disputes
![Page 19: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/19.jpg)
2.2 Demand management
Change comes from:– New projects and proposals– Client delays free up resources unexpectedly– Changes in project scope, or poor estimating– Key resources leave
Require scenarios to:1. Assess the impact – new bottlenecks or underutilization
2. Explore alternatives….whilst preserving the live data
![Page 20: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/20.jpg)
Impact of changesRe-baseline the plan, as necessary
![Page 21: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/21.jpg)
2.3 Resource allocation
Track each assignment1. Requested
2. Proposed
3. Accepted/declined
4. Confirmed
5. Date changes
Many variations:– the dating agency approach
![Page 22: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/22.jpg)
2.4 Tracking effort & progress
Actual performance will affect the resource plan
So, measure the performance of resource effort – Establish performance baseline – the project budget– Track actual effort – timesheets– Assess progress – value of work done
Re-estimate to completion– Can performance to date be improved?
![Page 23: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/23.jpg)
Earned value
Schedule variance = Budget – Earned value
Cost variance = Earned Value – Actual Effort
Schedule Variance
Cost Variance
![Page 24: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/24.jpg)
Forecast to completionbased on continuance of actual cost & schedule performance
Could requireanother 40 days!
![Page 25: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/25.jpg)
3. What needs to be in place?
Roles & responsibilities of the key stakeholders.
Demand management - assessing the impact of new projects and other changes
Resource allocation process
Tracking effort & assessing progress on each project.
![Page 26: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/26.jpg)
4. How well do you score?
Projects often centrally registered, with financial parameters defined
Multiple spreadsheets for resource planning, often department or regionally based
Resource allocation process is often poorly defined, inconsistent procedures & communication
Roles and responsibilities can be inconsistent in large organizations
Tracking effort often done, measuring progress less so.
![Page 27: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/27.jpg)
5. Bridging the gap
Build on what’s in place– Minimise cost, risk & disruption
Review business processes
Appropriate software tools
![Page 28: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/28.jpg)
The potential rewards
Cost savings– If the improved quality of Information gains only
2% productivity improvement ….
– Annual cost savings could exceed £1,000 per resource:• £100k for 100 resources• £1 million for 1,000 resources
Impact on profit levels
Improved performance on individual projects
![Page 29: Optimizing the utilization of your multi-disciplinary resources How to balance skills capacity with demand in a volatile multi–project environment Barry.](https://reader036.fdocuments.in/reader036/viewer/2022062720/56649efd5503460f94c10e46/html5/thumbnails/29.jpg)
Any Questions ?