OPERATION: SURVEY OF SUBMERGED TURRET PRODUCTION BUOY CLIENT:BLUEWATER SERVICES ... of APL HB Buoy...

15
OPERATION: SURVEY OF SUBMERGED TURRET PRODUCTION BUOY CLIENT:BLUEWATER SERVICES UK Ltd VESSEL: FUGRO SALTIRE LOCATION: ROSYTH-PIERCE OIL FIELD-ROSYTH PROJECT: HB APL BUOY SURVEY Brian Smith, Marine Reps Attendance Report 2 nd Nov 2013

Transcript of OPERATION: SURVEY OF SUBMERGED TURRET PRODUCTION BUOY CLIENT:BLUEWATER SERVICES ... of APL HB Buoy...

OPERATION: SURVEY OF SUBMERGED TURRET PRODUCTION BUOY

CLIENT:BLUEWATER SERVICES UK Ltd

VESSEL: FUGRO SALTIRE

LOCATION: ROSYTH-PIERCE OIL FIELD-ROSYTH

PROJECT: HB APL BUOY SURVEY

Brian Smith, Marine Reps Attendance Report 2nd Nov 2013

1

Table of Contents

1.SUMMARY………………………….…………………………………………………………2

2.PERSONNEL ATTENDING……….…………………………………………………………3

3.VESSEL PARTICULARS……………………………………………………………………4 4.MARINE REPS LOG…………………………………………………………………………5 APPENDIX B PHOTOGRAPHS………………………………………………………………9

2

SUMMARY

1.1. Introduction

2. A Submerged Turret Production (STP) buoy which was floating at a depth of 9m had a

270m pick up rope attached to it with the end floating on the surface with a small lighted

buoy attached. A Tug towing the ‘Haewene Brim’ FPSO ran over the rope and got it

entangled in its propellers. Some of the rope from the Tugs props was recovered but not

all of it. There was a danger that there was still some rope attached to the buoy which

could become entangled in other vessels props.

3. It was decided that a vessel would be required to survey the buoy to determine how

much rope, if any was attached to it. A 111m ROV survey vessel the DSV ‘Fugro Saltire’

was hired to take a workboat (W/B) out to the site and use a small ROV hung over-side of

the W/B for the survey. The ROV saw the buoy which had about 7 to 8m of 115mm rope

floating vertically from the buoy. The W/B was then recovered to the ship. The large ROV

vessel then launched its work class WROV and did a more detailed survey of the buoy.

3.1. Work Observed: The Tug that ran over the buoy rope was well inside the 500m zone

(< than 70m) and all of the rope except the bridal was on the tug’s props. The W/B

was launched by the ships main Knuckle boom crane which had the potential of the

load becoming uncontrollable if the mother vessel began rolling (see photo No5). The

W/B handled the seas well (2m) but had some problem finding the buoy. Once located

there was a lot of movement of the ROV due to the workboats movement in the seas.

3.2. Observations: The DSV vessel managed to make a lee for the workboat and also

positioned itself to reduce rolling to a minimum using the DP. The workboat was

launched and recovered without mishap. The Tidal Forces were insignificant. The

main force was the wind 20kts; this caused a lot of drift on the workboat which the

coxswain had to deal with. The DP current was in line with the wind.

3.3. Conclusions: If the workboat had a radar reflector fitted the DSV could have picked

up the boat much easier on its radar. A GPS on the workboat would have helped in

locating the buoy and remaining on station. Due to the professionalism of the project

crew and the ships crane drivers/crew all operations were carried out in a safe and

seamanlike manner. The DSV’s Man Overboard rescue boat was ready throughout.

3.4. This report is prepared in good faith without prejudice to any or all parties concerned.

Name BRIAN SMITH, Marine Rep

3

2. PERSONNEL ATTENDING

. The following personnel were in attendance.

1. Marine Rep, Brian Smith, for Bluewater Services Ltd

2. Inspector Client Rep, David Nance, for Bluewater Services Ltd

3. Offshore Project Manager, Gareth Rodgers, KD Marine ltd

4. Offshore Vessel Manager, Graham Haddon, Fugro

5. Master: ‘Fugro Saltire’ Willie Sandtory

4

3. VESSEL PARTICULARS

The Dive Support Vessel (DSV) DP 2 ‘Fugro Saltire’ is a purpose built, deep water ROV vessel. It is equipped with a 150Te AHC knuckle-boom crane designed to deploy full rated load to 3000m (single fall) plus a separate 10T auxiliary subsea crane with 1,000m fall. 150T line fully equipped with man riding capability to SWL 15T Two Fugro FCV3000 150HP ROV systems are deployed via hydraulically operated doors on either side of the integrated ROV hangar via purpose built Heave Compensated (AHC) Launch & Recovery Systems (LARS) designed to minimize the effects of vessel motion. There is also the option of mobilizing a Lynx OBSROV system onto the back deck of the vessel. A working moonpool measuring 7.2 x 7.2m is situated immediately aft of the hanger area overlooked by a large Deck Operations Room. The full reach of the 46m x 22m timbered main deck is designed for deck loading of 10T/m2 and offers the flexibility to both carry substantial construction spreads and deck cargos and provide a platform with excellent seakeeping allowing the deployment of substantial subsea loads using the 150T main crane. Dimensions LOA 111.00m; LBP 100.20m Breadth 24.00m Draught 7.5m (maximum); 6m (50%DW) Machinery Main Power Plant 4 x Rolls Royce Bergen Diesel each driving Marelli Generators Total Power 15,750 kW / 16.800 kVA, 60Hz Auxiliary 1 x Mitsubishi/Stamford, 685kVA Main Propulsion Diesel-Electric : 2 x ducted CPP main propellers with variable frequency electric drive, Bow thrusters 2 x Tunnel; Super Silent, variable pitch, 1 x Retractable Azimuth, variable pitch, Stern thrusters 2 x Tunnel pitch controlled Speed Service 16 knots Endurance 60-90 days Deck/Machinery Deck area 1030m² , nominal Free timbered area : 960m² Deck loading 10T/m² throughout Deck crane Hydramarine 150T AHC, man riding capability to SWL 15T Single Fall Hook Travel: 3000m Load Capacities (SWL): 150Te @ 10m ; 75Te @ 20m ; 25Te@35m Whip Line (Aux Winch) : 10Te @ 36m ; Hook Travel : 450m Auxiliary crane Hydramarine 10Te @ 15m ; Hook Travel : 1000m Subsea Helideck Type Sikorsky S61 / S92 D-Value : 22.2m (22.2m Diameter); Max. landing load : 12,800kg; Control and Navigation DP system Simrad Dual Redundant K-POS DPII Dual DGPS; DPS 200 1 x Fugro Starpack DGPS DP references 2 x HiPAP500, Fanbeam, Seapath 200, RADius Communications Satellite Dual KU-Band / C-Band systems Max Capacity 2.5Mbit/s (KU, N.Sea) MF/HF Furuno FS 2570 VHF Furuno FM 8800S / FM 2721

5

4. MARINE REPRESENTATIVE’s LOG

ATTENDANCE LOG

Job No: J110 Project: HB APL BUOY SURVEY

Our Ref: Locations: Rosyth – Pierce Oil Field - Rosyth

Reason for attendance: Marine Rep on board the Fugro Saltire

November/2013:

Day: Date: Remarks

Monday 25/11/13

06:40 Buses from home to Bluewater Services UK Ltd, Badentoy Industrial Estate, Portlethen, Aberdeen, AB12 4YD, +4 4 (0)1224 403300

08:10 Arrived in office, gave Geoff Westmoreland the ‘Fugro Saltire’ Vessel Assurance File

08:15 Attended the conference call from the Bluewater office to FPSO Haewene Brim (HB)

09:00 Attended the conference call from the Bluewater office to Shell UK

10:10 Taxi from Bluewater office to Rosyth

12:30 Getting security clearance to enter Rosyth Royal Dockyard

13:20 On board the ‘Fugro Saltire’

13:50 Vessel has to wait for the high tide to open the lock

14:00 KD Marines FRC and stores containers are loaded on to the ship

15:00 Did an Induction and familiarization on the vessel

17:00 Let go from the dock, waiting on high water for lock opening

19:30 Let go proceeding to Pierce Field

20:00 Passing under the Forth Bridges

20:28 Pilot away, on passage to Pierce Field

Tuesday

26/11/2013

06.45 Toolbox Talk given by the Offshore Project Manager at KD Marine to the project crew

08.45 The standby boat at the Pierce Field was given 30 minutes’ notice of the arrival of the Fugro Saltire

09.20 On DP commence doing DP trials

10.17 There was a general muster of all crew, lifeboat drill

6

Day: Date: Remarks

10.30 Muster finished

11.00 DP Trials complete

11.35 Entered the 500m zone of the ‘Haewene Brim’ APL buoy position

11.45 Standing by at 270m from the buoy position

11.55 Outside the 500m zone

12.00 Weather, Wind NW 24 kts, significant wave height 2.4m Waiting on Weather

15.30 End of daylight

17.00 Waiting on weather. Finished for the day

Wednesday

27/11/2013

06.45 Toolbox talk given by KD Marines Offshore Project Manager to all project crew and the two crane drivers

07:00 Weather, Wind 20kts significant wave height 2.0m

07:00 Vessels Man Over Board boat overside ready for launch

07.15 All project crew on vessels bridge, Captain gives a general safety talk, and the need for good communications between the bridge and the workboat

07.20 Vessel Informed the ‘Grampian Falcon’, vessel Inside the 500m zone

08.00 KD Marines workboat launched over the Starboard side by Stbd main Nuckleboom crane

08.05 Workboat over the APL buoy according to a fix from vessels Radar

08.09 ROV launched from workboat

09.00 Workboat informs that they can see the buoy and a rope

09.02 Start a survey of the buoy, there is approx. 7 to 8 meters of rope floating upright from the buoy bridle

09.50 Workboat back on board

10.00 Call Bluewater office, they asked us to send some still pictures of the buoy

10.10 Called Wullie Beaton of Shell asked him for a PTW for a work class WROV survey of the buoy up to 250m from buoy

11.40 Received a PTW amended

12.05 Work class WROV in water start surveying the buoy, risers and anchor chains

7

Day: Date: Remarks

14.00 Called Bluewater office and told them there was no sign of damage to the buoy or other equipment. Continue with WROV survey of the Birdgaging on No 1 anchor line. Surveying of Risers

15.10 Stop WROV survey, due to no daylight and ROV crew work hours, exit 500m

24.00 Vessel standing by outside 500m zone for daylight, to start work on the a survey of the Mid Water Arches

Thursday

28/11/2013

08:00 Called Bluewater office, told them about the need to move closer to the buoy (50m) he said to contact Shell Rep on the FPSO HB

08:35 Sent email to HB Shell Rep stating that there is no hazard around the buoy and if we could go to 50m from the buoy to conduct a WROV survey of the Mid Water Arches, all OK. Changed the HIRA for the WROV Ops from 250m standoff to 50m.

08:45 Conference call to Bluewater office

08:45 Work Class ROV off deck to survey the Mid Water Arches

09:03 Conference call to HB

09:45 WROV on deck, dive aborted due to increasing weather and sea state

09:55 On passage to Rosyth ETA 10:00 hours Friday 29th Nov

1900 Vessel moving easily

Friday 29/11/13

09:23 Pilot on board

10:24 Lock open vessel passes straight through

10:50 All fast in Rosyth

11:00 KD Marines crew removing their equipment

13:30 Get Taxi which was ordered by KD Marine

15:50 Get out of taxi in Badentoy Park, got lift home

16:20 Arrive home

8

Appendix ‘B’ Photographs

9

PHOTOGRAPH 1

Submerged Turret Production (STP) buoy with damaged bridal

PHOTOGRAPH 2

KD Marines workboat approaching Fugro Saltire Stbd for recovery to deck

10

PHOTOGRAPH 3

Connecting man riding crane hook

PHOTOGRAPH 4

Work-Boat coming on-board

11

PHOTOGRAPH 5

Potential for loss of control

PHOTOGRAPH 6

Landing on deck

12

PHOTOGRAPH 7

Workboat lashed on deck

PHOTOGRAPH 8

Hydramarine AHC, man riding capability to SWL 15T Knuckle-Boom Crane

13

PHOTOGRAPH 9

‘Fugro Saltire’ alongside in Rosyth

PHOTOGRAPH 10

Fugro Saltire alongside in Rosyth

14